Edvard Grieg Anders Henriksson, Lundin Petroleum Prosjektleder
Lundin Petroleum Asset overview
Lundin Norway AS Established on the NCS in 2004 by the purchase of the DNO portfolio in Norway Core staff from previous Saga Petroleum and DNO 40 licences in total, 22 as operator Daily NCS production of approximately 30 000 boe from the Alvheim and Volund fields Several development projects in the planning phase as operator Brynhild startup 2014 Luno startup 2015
Utsirahøyden Utsirahøyden is an area where Lundin has focus Exploration has been on and off in almost 40 years in this area Several ongoing development projects in this area Edvard Grieg Ivar Aasen Johan Sverdrup Infrastructure: oil, gas, power
Edvard Grieg PL338 is located in block 16/1, about 180 km west of Stavanger Water depth at platform location is 109 m By January 2011 the license consisted of: Lundin Norway AS (operat0r): 50% Wintershall Norge AS: 30% RWE Dea Norge AS: 20% Todays owners: Lundin Norway AS (operatør): 50% OMV Norge AS: 20% Wintershall Norge AS: 15% Statoil Petroleum AS: 15%
Edvard Grieg
Edvard Grieg - Capacities Kapasitet PL338 Kapasitet PL338 + tie-ins Olje (Sm 3 /d) 14 300 20 000 Gassprosessering (MSm 3 /d) 2.5 5 Prod. vann (Sm 3 /d) 13 000 13 000 Vanninjeksjon (Sm 3 /d) 24 000 24 000
Edvard Grieg - Mainlifts H00 + L00 + U00 6665 T P00 5338 T F00 268 T N C00 10645 T FORBORINGSDEKK TOTAL TOPSIDE TØRRVEKT 22668 T Weightreport rev. 14
Jacket EPC Some key data Jacket Contract value 1.2 BN Jacket weight: Pile weight: Bouyancy tanks: 13.400 ton 6.500 ton 1.500 tonnes Temporary drill deck for 20 slots Appurtenances 7 Risers for pipeline connection 10 caissons (7 pump caissons and 3 dump caissons) 16 J tubes 8 for future cables 8 for future risers Delivery date: 01.04.14
Edvard Grieg Pre-drilling
Edvard Grieg UHGP Installeres 2014
Edvard Grieg EGOP «Grane Y» Installation on going
EG platform: High complexity EG platform designed as a Field Centre from day #1 in-license tie-ins: discoveries & prospects final processing + export of oil & gas from Ivar Aasen Specific design challenges Significant differences between reservoirs to be produced Incompatible formation waters Area solutions for oil & gas export + future power from shore
EG main process 3 separators to limit recycle of intermediate components 1x coalescer to reduce water-in-oil to ~0.3% due to salt content 2-stage recompression w/vsd & 2-casing design w/space for extra impellers HP gas compression train 1x 100% train... with «spare» compressors «high» and «low» design flow for gas processing
EG inlet separators Parallel inlet separators primary / secondary / test segregated water treatment Inlet routing flexibility valves: primary/test valves: secondary/test spools: primary/secondary Significant impact on layout Space for future manifolds
Jacket EPC Construction at Verdal Yard Load-Out 1-2 of April
Jacket EPC Construction at Verdal Yard Status 9th. of April
Verdal, April 15th, 1430 hours
The Launch moment! Well testing and by the way, Launch, May 3 rd.
Saturday evening, May 3rd.
Sunday morning, May 4th.
Pile stabbing
Pile hammer
Bouyancy tanks Removal, May 10th.
PDD installation
Finished, May 13th. 0500 hours
Edvard Grieg Topside EPC Contract
Topside EPC Contract May Bi-weekly cut-off
Engineering April 2014 Karl-Petter Løken
Engineering Detail Engineering finished Construction and Follow-on Engineering on-going Engineering manning reduced every month
Edvard Grieg Topside EPC Contract Equipment
Duisburg 29.07.2013
Hengelo 2.08.2013
Hengelo 13.02.2014 Final Inspection Re-compressor and Injection Compressor
ATV
Edvard Grieg Topside EPC Contract Construction
Process Module - Assembly status Three of total four deck floors are installed. The first section for the fourth deck (P40) has arrived from Poland (in the hook)
Process Module Current status of erection program in Egersund. Gas Injection Compressor 1 and 2 Stg. Recompressor Installation of equipments on P30 deck has commenced.
Process Module El. Cabinets in LER and the framework for Raised Access Floor are installed. 1 & 2 stage recompressor and Gas Inj. Compressor skids are installed incl. Noise hoods.
C00 Installation dates
Installation of C32 Mod Section
Installation of C32 Mod Section
Currency connection The light is on!
Lifting of Helideck, May 27th.
EDVARD GRIEG FLOTEL STATUS - MARCH 2014