CEMARS. Certified Emissions Measurement And Reduction Scheme. GPS PE Pipe Systems. Emissions Management and Reduction Plan

Similar documents
SCRA Sustainability Report 2012/13. Changing f or children and young people

Sustainability and Carbon Footprint Reduction

Statement of Carbon Neutrality 2012

SSE s criteria used for GHG emissions reporting

Prudential plc. Basis of Reporting: GHG emissions data and other environmental metrics.

ENVIRONMENT. Aviation. Property. Marine Services. Trading & Industrial. Beverages

ENVIRONMENTAL MANAGEMENT PLAN

Independent review of selected Subject Matter contained in Macquarie Group Limited s 2016 Annual Report

San Antonio College Greenhouse Gas (GHG) Report Fiscal Year 2009

Implementing a Ship Energy Efficiency Management Plan (SEEMP) Guidance for shipowners and operators

Energy Management Strategy

Scope 1 describes direct greenhouse gas emissions from sources that are owned by or under the direct control of the reporting entity;

ECO Stars Fleet Recognition Scheme Improving Local Air Quality Through Operator Engagement

Greenhouse Gas Reporting Criteria

EU Life+ Project: Combining Water and Energy Efficiency. A report by the Energy Saving Trust and Waterwise UK.

ENVIRONMENTAL REPORT

Sample Scope 3 GHG Inventory Reporting Template

Supplier Guidance Document. Energy and Fuel Use Data from Hertfordshire County Council Outsourced Services

Charnwood Borough Council

TNT Australia Pty. Limited A.B.N

Rainwater Harvesting

Carbon Footprint Report

Corporate Carbon Neutral Plan

Carbon Footprint Analysis 2011 H2

Water Efficiency Self-Assessment Guide from

Carbon emissions. A practical guide for fleet operators and drivers. Photography by Bob McCaffrey on Flickr

ASSET & FACILITIES MANAGEMENT CORPORATE ENERGY EFFICIENCY POLICY

Electricity North West Carbon Footprint Report

Carbon Footprint Calculator for Royal Society of Arts

ANNUAL ENVIRONMENTAL REPORT 2009

Key Solutions CO₂ assessment

Our footprint. We believe in our people and support them to champion change. Environmental Awareness. Sustainable Design


IMPLEMENTING ISO 14001:

We make rational and conscientious use of our

Glasgow Life Carbon Management. Final Report

Improving the quality of certification, measurement, verification and validation of conformity assessment results Dr Elsabe Steyn

Guidance on how to measure and report your greenhouse gas emissions

Public Sector Sustainability Report

It s not just about the environment

Greenhouse Gas Protocol Report for IT Mästaren. Assessment Period: Produced on June 10, 2014 by Our Impacts on behalf of U&W

PUBLIC REPORT Water Corporation From 1 July 2006 To 30 June 2011

Electrical infrastructure serving the city of London CITY OF LONDON Corporate Energy Consumption Report

London Underground Environment Strategy

CARBON MANAGEMENT PLAN

Translink Carbon Report 2011/12

How To Understand The Emissions Of Westpac Group

Environmental Operational Reporting and Offset Management Standard

Carbon Footprint Report 2013 Explanatory Document to Carbon Report

Our financing of the energy sector in 2013

Scotland s Climate Change Declaration

UK Government proposals on energy tax changes

carbon footprinting a guide for fleet managers

ALLIED PRINTING SERVICES, INC. CORPORATE SUSTAINABILITY AND ENVIRONMENTAL MANAGEMENT PROGRAM REPORT

Fact sheet. Conversion factors. Energy and carbon conversions 2011 update

Baseline The baseline for reporting is our 2014 performance data.

Carbon Management Plan

How To Tax Company Cars In The Uk

International Standard for Determining Greenhouse Gas Emissions for Cities

Information & Communications Technology

DEME-QHSES-DOC-031 ENERGY MANAGEMENT ACTION PLAN. Uncontrolled if printed. Most recent version is available on the DEME website.

Scope 1 describes direct greenhouse gas emissions from sources that are owned by or under the direct control of the reporting entity;

FACTSHEET: Carbon Accounting for Smaller Entities

Big Yellow Group PLC Basis of Reporting 1st April st March 2014 Corporate Social Responsibility

Energy Saving Fact Sheet Energy Management

PEAK DISTRICT NATIONAL PARK AUTHORITY ENVIRONMENTAL MANAGEMENT ANNUAL PERFORMANCE REPORT 2013/2014

APPENDIX B - PL1 Homes that meet people s needs and aspirations

GUIDELINES FOR VOLUNTARY USE OF THE SHIP ENERGY EFFICIENCY OPERATIONAL INDICATOR (EEOI)

Ethical and environmental policy. Union of Brunel Students

Examples of Good Practice the Freight Forwarding Sector

Solar City Master Plan - Executive Summary

From Carbon Subsidy to Carbon Tax: India s Green Actions 1

2. Environmental indicators

VISIT 2010 Fujitsu Forum Europe 0

Information & Communications Technology

Where does the wine sector sit in terms of Australian climate policy and the global carbon market

ENVIRONMENTAL MANAGEMENT POLICY, OBJECTIVES AND TARGETS

Environmental Performance Data Calculation Standards

AEA group Safety Health and Environmental Report

Carbon Disclosure Project CDP 2009 Small & Medium-sized Enterprises Information Request

CDP7 and OneReport Comparison

CITY OF ORILLIA ENERGY MANAGEMENT PLAN

A GUIDE ON CLIMATE CHANGE FOR PRIVATE EQUITY INVESTORS

2011 Business Carbon Footprint (BCF) Report Commentary & Methodology

Sustainable Plastics with Reduced Carbon Footprint & Reduced Waste

Accounting for ethical, social, environmental and economic issues: towards an integrated approach

The. Brendan P. Sheehan, Honeywell Process Solutions, USA, and Xin Zhu, UOP, a Honeywell Company, USA, explore energy optimisation in plant processes.

Reporting criteria for selected key performance indicators in the 2014 Responsible Business Report

London Freight Plan Data Modelling

Ener ficiency. Corporate Energy and Greenhouse Gas Inventory. Consulting. Squamish-Lillooet Regional District. Prepared For: Prepared by:

Overview of the Heavy-Duty National Program. Need to Reduce Fuel Consumption and Greenhouse Gases from Vehicles

Environmental sustainability BBC Environment Targets: Performance 2014/15

your comfort. our world. DNSS EcoSave A/C remote monitoring and malfunction prediction

CSX Public Safety, Health, and Environmental Management System

IEMA The Importance of Due Diligence Auditing in the transition to a Sustainable Economy Mark Thompson 9 December 2014

Musgrave Energy & Natural Resources Management Policy. Working together to deliver sustainability

Greenhouse Gas Emissions Verification (January 2013 December 2013)

C21 Ecologically Sustainable Development

BS EN Energy Management Systems VICTORIA BARRON, PRODUCT MARKETING MANAGER, BSI

Transcription:

CEMARS Certified Emissions Measurement And Reduction Scheme Emissions Management and Reduction Plan GPS PE Pipe Systems Person responsible: Graham Chadband, Operations Director, GPS PE Pipe Systems Prepared by: Tim French, Quality & Environmental, GPS PE Pipe Systems Dated: 22/04/2013 Version: 1.0 Verification status: Verified For the period: 01/01/2012 to 31/12/2012 Base year: 01/01/2008 to 31/12/2008 EMRP template v2.2, carbonzero Holdings Limited 2012 Page 1 of 13

Reviewed by: Approved for release by: Tim French Quality & Environmental GPS PE Pipe Systems Graham Chadband Operations Director GPS PE Pipe Systems EMRP template v2.2, carbonzero Holdings Limited 2012 Page 2 of 13

Contents 1 Introduction... 4 2 Rationale... 4 3 Top management commitment... 4 4 Person responsible... 4 5 Awareness raising and training... 4 6 Significant emissions sources... 5 7 Targets for emissions reduction... 6 8 Specific emissions reduction projects... 8 9 Unintended environmental impacts... 10 10 Key performance indicators... 10 11 Monitoring and reporting... 11 12 Emissions reduction calculations... 11 13 Performance against plan... 11 Figure 1: Example risk assessment matrix for projects....10 Figure 2: Example of performance against target since base year....12 Table 1: Emission reduction targets.... 7 Table 2: Projects to reduce emissions.... 8 Table 3: Projects to improve data quality.... 8 Table 4: Projects to prevent emissions and reduce liabilities... 9 Table 5: Example GHG inventory results.... Error! Bookmark not defined. EMRP template v2.2, carbonzero Holdings Limited 2012 Page 3 of 13

1 Introduction This report is the annual greenhouse gas (GHG) Emissions 1 Management and Reduction Plan prepared for GPS PE Pipe Systems and forms the manage step part of the organisation s application for CEMARS certification. 2 Rationale GPS PE Pipe Systems is committed to adopting and promoting environmental good practice throughout its business in order to operate in a sustainable manner. GPS is committed to reducing its environmental impacts and continually improving its environmental performance as an integral part of its business strategy and operating methods. Since 2008 GPS has been working with the Prince of Wales May Day Network and the East of England Business in the Community (BITC) in declaring its carbon emissions and making pledges to commit to further reductions. In 2010 GPS received the East of England BITC Carbon Positive Award in recognition of significant reductions in energy usage and waste reduction activities. In 2010 GPS also took part in the Carbon Disclosure Project at the request of a major customer. GPS is also a participant in the Carbon Reduction Commitment Scheme with other UK based Aliaxis companies. Throughout 2012 GPS has continued to work with its major customers in reducing emissions by developing new products and processes. 3 Top management commitment Graham Chadband (Operations Director) has approved this emissions management plan and the company emissions reduction targets. 4 Person responsible The Operations Director has been made responsible for leading the GPS PE Pipe Systems emissions reduction activities and for reporting to the Senior Management Team. 1 Throughout this document emissions means GHG emissions. EMRP template v2.2, carbonzero Holdings Limited 2012 Page 4 of 13

Electricity HGV Freight Milage Gas Diesel Car Mileage Waste to Landf ill LPG Utility Water & Water Treatment Air travel tonnes CO2e 5 Awareness raising and training GPS hold a quarterly Energy Forum with representatives from departments across the business attending. The Forum discusses energy saving initiatives and reviews emissions reduction activities and performance against targets. A yearly Environmental Awareness day is also held for all employees to attend. Investment in training is on-going. All employees go through environmental awareness training as part of their induction. A program of Environmental Awareness Training of Team Leaders has been carried out. Environmental performance is communicated through notice boards and through company newsletters. In 2012 we produced a Corporate and Social Responsibility Report which detailed our environmental commitment and our performance against targets. 6 Significant emissions sources The main sources of GHG emissions are discussed in the emission inventory report and a summary is shown in Figure 1 below. 8,500 8,000 7,500 7,000 6,500 6,000 5,500 5,000 4,500 4,000 3,500 3,000 2,500 2,000 1,500 1,000 500 0 Figure 1: Top GHG emissions sources EMRP template v2.2, carbonzero Holdings Limited 2012 Page 5 of 13

As shown in Figure 1 above, electricity use is the key source of reported GHG emissions in the 2012 reporting period. This accounts for 7,942.66 tco 2 e or 82% of our emissions. Pipe extrusion is an energy intensive process. It accounts for approximately 78% of our electricity usage. Through our Energy Forum we have implimented a number of activities to reduce consumption, primarily by implementing procedures to turn off machines and lighting when not in use. Although these have produced some improvements it is generally accepted that further significant reductions can only be achieved by the intallation of energy efficient processing equipment. The Emissions Management and Reduction Plan includes a program for replacing older extruders with new energy efficient models. To date we have replaced 6 extruders. The Extrusion Area will be the main area of focus for future reduction activities. We are continuing to improve our data collection. For our logistics operation we now have the ability to report mileage data for each delivery. This will improve the accuracy of our second largest emission. We have established 2008 as our baseline against which future targets will be set. 7 Targets for emissions reduction GPS PE Pipe Systems is committed to managing and reducing its emissions in accordance with the Programme requirements. Table 1: provides details of the emission reduction targets to be implemented. These are SMART targets (specific, measurable, achievable, realistic, and time-constrained). Through participation with CEMARS GPS will: Reduce its own greenhouse gas (GHG) emissions and improve its energy efficiency GPS has committed to reduce its own GHG emissions by 5% by 2012 (Scope 1 & 2 emissions) and the intensity of its GHG emissions by 3% by 2016 (both compared to 2008). Introduce services that help customers meet their environmental goals GPS will provide regular Corporate Social Responsibility Reports that will include verified greenhouse gas emissions. Keep the public informed GPS will pledge to regularly update its website to report progress in meeting its emissions targets. Long Term Target GPS PE Pipe Systems has a long term target to reduce emissions attributable to our organisation by 8% of the base year emissions by 2020. EMRP template v2.2, carbonzero Holdings Limited 2012 Page 6 of 13

GHG emission reduction initiative Reduce purchased electricity emissions Target 3% (4%) (5%) Table 1: Emission reduction targets. Baseline (tco 2 e) Target date Metrics/KPI Responsibility Rationale 8,703 31/12/12 Total purchased Special Projects Achievable through consolidation of electricity per annum current projects. (31/12/14) (31/12/16) Reduced purchased gas emissions 3% (4%) (5%) 502 31/12/12 (31/12/14) (31/12/16) Cubic metres of gas used for heating and tool cleaning furnace Energy Achievable through the use of the Factory heating Energy Management System and efficient use of the Fluidised Bed Tool Cleaning Furnace. EMRP template v2.2, carbonzero Holdings Limited 2012 Page 7 of 13

8 Specific emissions reduction projects In order to achieve the reduction targets identified in Table 1: specific projects have been evaluated to achieve these targets. These are detailed below. Table 2: Projects to reduce emissions. Objective Actions Responsibility Reduce purchased electricity Reduce purchased gas Replace 50% of current extruders with energy efficient models rolling programme of 2 replacements per year up to 2016. Extruder barrel insulation preventing heat loss to minimise energy usage for melting polymer granules. Extruder tool insulation reduce heat loss and reduce energy required to heat tooling. Install PIR sensors in Factory Offices, rest areas and all new installations in the Office Block. Review heating management system with regard to operational settings. Review the operation of the tool cleaning furnace to improve efficiency and maximise loading capacity. Special Projects Special Projects Special Projects Maintenance Energy Maintenance Completion date 2016 2017 2015 2012 2011 2012 Table 3: highlights emission sources that contributed to poor data quality in the Emissions Inventory Report and describes the actions that will be taken to improve the data quality in future inventories. Table 3: Projects to improve data quality. Emissions source Freight Mileage Metre Readings Actions to improve data quality Obtain data for weight of load per distance travelled for each delivery (tonnes.km). Formulate monthly report to capture this information. Publish information on monthly logistics KPI. Investigate AMR installation Date of readings to match bills Responsibility Logistics Engineering Completion date 2012 2014 EMRP template v2.2, carbonzero Holdings Limited 2012 Page 8 of 13

The emissions inventory identified various emissions liabilities. Table 4 details the actions that will be taken to prevent GHG emissions from these potential emissions sources. Table 4: Projects to prevent emissions and reduce liabilities Emissions source HFCs Actions to reduce liabilities The company s ISO 14001 certified environmental management system includes a six-monthly assessment of water chiller units and air conditioning systems. Preventive maintenance visits will minimise any leakage of HFCs. Responsibility Maintenance Completion date On-going EMRP template v2.2, carbonzero Holdings Limited 2012 Page 9 of 13

9 Unintended environmental impacts The two projects to reduce emissions have been assessed to identify any impacts on other aspects of the environment. A short description of the reasons behind the choice of indicator is provided below Figure 2. Additional measures will be implemented to ensure that these impacts are minimised. ENVRONMENTAL IMPACTS Resource use Electricity consumption Fuel consumption Water consumption Wastewater discharge Waste to landfill Air, land and water quality Transport congestion Biodiversity Land use Flooding Local economy Reduce Purchased Electricity Reduce Purchased Gas Figure 2: Example risk assessment matrix for projects. Reduce Purchased Electricity Project Resource use will be increased as new extruders would need to be manufactured. Electricity consumption will be reduced as this is the aim of the project. Indirect emissions should also be improved as less electricity will be required. The local economy may be positively affected by the purchase of assess and the on-going supply of services. Reduce Purchased Gas Project A positive effect on resource use should be observed due to the reduction in use of a finite natural resource. A reduction in fuel consumption will be positive as this is the aim of the project. The reduction in fuel use should also have a positive effect on emissions. EMRP template v2.2, carbonzero Holdings Limited 2012 Page 10 of 13

tco2e 10 Key performance indicators The emissions intensity for the organisation as tonnes CO 2 e per M gross turnover during this measurement period (01/01/2012 to 31/12/2012) was as follows: 162.04 tco 2 e / M turnover (for 2012) 185.12 tco 2 e / M turnover (5-year average) The emissions intensity for the organisation as tonnes CO 2 e per tonne product during this measurement period (01/012011 to 31/12/2011) was as follows: 0.38 tco 2 e / tonne product (for 2012) 0.40 tco 2 e / tonne product (5-year average) 11 Monitoring and reporting The progress of all projects will be reported on a quarterly basis. The Project owner will report to the Operations Meeting and to the Senior Management Representative. If deviations from targets or absence of data or incomplete data collection and recording are identified actions will be taken to address these issues in a timely manner. 12 Emissions reduction calculations See reduction calculator 13 Performance against plan Figure 2 below illustrates that GPS has reduced its total Scope 1 and Scope 2 emissions according to plan in years 2, 3, 4 and 5 since the base year (2008). 10,000 9,800 9,600 9,400 9,200 9,000 8,800 8,600 8,400 8,200 8,000 7,800 7,600 7,400 7,200 7,000 Scope 1 & 2-5 Year Average 2008 EMRP template 2009 v2.2, carbonzero 2010 Holdings 2011 Limited 2012 2012 Page 11 of 13 Year Scope 1 & 2 - Actual Target

tco2(e) / M Turnover Figure 3: Example of performance against target since base year. 195.00 190.00 185.00 180.00 175.00 170.00 165.00 160.00 155.00 150.00 145.00 2008 2009 2010 2011 2012 Year Target Actual 5 Year Average Figure 3: Intensity value performance against target since base year. EMRP template v2.2, carbonzero Holdings Limited 2012 Page 12 of 13

Figure 4: Intensity value performance against target since base year EMRP template v2.2, carbonzero Holdings Limited 2012 Page 13 of 13