Taking Advantage of Market Opportunities through Siemens Reference Power Plants. Dr. Daniel Hofmann and Holger-Max Emberger

Similar documents
Operational Flexibility Enhancements of Combined Cycle Power Plants. Dr. Norbert Henkel, Erich Schmid and Edwin Gobrecht

SRS: THE STANDARDIZED REPOWERING SOLUTION FOR 300MW STEAM POWER PLANTS IN RUSSIA. Matthias Fränkle Siemens Power Generation (PG), Germany

SGT5-8000H SCC5-8000H 1S. Experience of Commercial Operation at Irsching 4. ANIMP-ATI, Sesto San Giovanni 26 June 2012

Low Load Operational Flexibility for Siemens G-class Gas Turbines

The SGT5-8000H proven in commercial operation

Siemens Gas Turbines over 100 MW

Power Plants. BENSON Once-Through Heat Recovery Steam Generator. Power Generation

SGT5-4000F Trusted Operational Excellence

The new Gas Turbine Portfolio to meet the market requirements for Distributed Generation

Power Island. Industrial Power Plants. / energy

O&M and Lifecycle Management for CCGT Power Plants Flex Power Services Enhancing a plant s market capability

Steam Power Plants as Partners for Renewable Energy Systems

Fast cycling and rapid start-up: new generation of plants achieves impressive results

The Lodi Energy Center, owned

Improving Flexibility of the Combined Cycle Power Plant Hamm Uentrop to Cover the Operational Profiles of the Future

Design and Test Operation Performance of 1,500 C Class Gas Turbine Combined-Cycle Power Plant:

Siemens Steam Turbine-Generator SST-5000 Series. for combined cycle and subcritical steam applications. Answers for energy.

SGT5-4000F Gas Turbine and Combined Cycle Power Plant Evolution reflecting the changing Market Requirements

Power Generation Service Life Cycle Management for Power Plants

Alain Nifenecker - General Electric Manager Controls Engineering

Application and Design of the ebooster from BorgWarner

New Developments on Industrial Steam Turbines

February Service Division. Unrestricted Siemens AG All rights reserved.

Vogt Power Emission Control Solutions

Senoko Power Station CCP2 performance increase with focus on efficiency. Answers for energy.

THM Gas Turbines Heavy duty gas turbines for industrial applications

Siemens Steam Turbine SST-600

FULL ELECTRICAL LNG PLANTS: HIGHEST AVAILABILITY AND ENERGY EFFICIENCY THROUGH OVERALL SYSTEM DESIGN

CSP-gas hybrid plants: Cost effective and fully dispatchable integration of CSP into the electricity mix

BIOMASS LOOKING FOR EFFICIENT UTILIZATION THE REHEAT CONCEPT. Jaroslav Lahoda Olaf Arndt Walter Hanstein. Siemens Power Generation (PG)

Wärtsilä modular power plant comprised of multiple ICE generating units provides output flexibility.

Pre-designed Steam Turbines

ANCILLARY SERVICES SUPPLIED TO THE GRID: THE CASE OF THISVI CCGT POWER PLANT (GREECE)

How To Power A Power Plant With Waste Heat

Steam Turbine Concepts for the Future Volatile Power Market

Industrial Steam Turbines

Siemens H: uprate and commercial release follow design validation

ON-LINE MONITORING OF POWER PLANTS

Totally Integrated Power SIESTORAGE. The modular energy storage system for a reliable power supply.

Carbon Dioxide Membrane Separation for Carbon Capture using Direct FuelCell Systems

USC Steam Turbine technology for maximum efficiency and operational flexibility. Dr. Rainer Quinkertz Andreas Ulma Edwin Gobrecht Michael Wechsung

Top Technology for Industry, Agriculture, Business and Communities

Siemens Gas Turbine SGT5-4000F. Advanced performance. Answers for energy.

Gas turbine performance and maintenance continuous improvement

Proud to be here, since 1853

Flexible performance, convincing quality economical and future-proof packages

Combined Cycle Control Overview

Systems and services for small hydro power plants

Integrated. for Steam Power Plants

Best Choice BENSON BOILER. Excellent performance features make the Benson boiler the most widely used type of once-through boiler

White paper Combustion engine power plants

Ancillary Services and Flexible Generation

Natural Gas Conversions of Existing Coal-Fired Boilers

Adaptation of the SGT6-6000G to a Dynamic Power Generation Market

PI System O&M Management Tool in Power Generation Industry. 27 October Barış Başer O&M Group Manager

OVERVIEW OF GENERAL ELECTRIC S ADVANCED TURBINE SYSTEMS PROGRAM

Steam turbines for solar thermal power plants. Industrial steam turbines. Answers for energy.

5. State the function of pulveriser. The pulverisers are the equipments which are used to powdered coal.

NO-BREAK KS 7e. Concentrated Energy kva (50Hz) 3000 kva (60Hz) DIESEL ROTARY UNINTERRUPTIBLE POWER SUPPLY SYSTEM

Den Haag and Leiden Repowering

Brochure. Electric generators to power the world

Adapting Gas-Power Generation to New Role in Low-Carbon Energy Systems

HySTAT HYDROGEN GENERATORS

Steam Generator Boilers Compact Steam Boilers. Rapid Start-Up Safe in Operation

CONTENTS. ZVU Engineering a.s., Member of ZVU Group, WASTE HEAT BOILERS Page 2

System Assessment Capabilities for Fossil Fuel Power Stations

GE Energy LMS100. Flexible Power

LPG Burning Gas Turbine for Power Generation

Gas-Fired Power HIGHLIGHTS

EXPERT REMANUFACTURED WIND TURBINE

HEAT RECOVERY OPTIONS FOR DRYERS AND OXIDIZERS

Power Trading and Retail System. empowering. smarter trading. across the energy value chain. Smart energy. Powering progress

Hot billet charging saves millions of energy costs and helps to increase rolling mill productivity considerably.

The Problem Solving of Exhaust Frame Air Cooling System Pressure Low in GE Frame 9 Gas Turbine

Ansaldo Energia: la flessibilità operativa dei cicli combinati coniugata all efficienza energetica

Lifetime Extension for SIEMENS Gas Turbines

THERMAL POWER PLANTS Vol. III - Gas Turbines For Electric Power Generation - H.I.H. Saravanamuttoo GAS TURBINES FOR ELECTRIC POWER GENERATION

Power Generation Industry Economic Dispatch Optimization (EDO)

SOLARPACES: Development of an integrated solar thermal power plant training simulator

HARMATTAN GAS PLANT COMPRESSOR CONVERSION 09-IAGT 306

Performance Monitoring & Optimization

ORC TURBOGENERATOR TYPE CHP - Organic Rankine Cycle Turbogenerator fed by thermal oil, for the combined production of electric energy and heat -

V MW. Your best option for low cost energy production at low and medium wind sites. Federico Gonzalez Vives. Director Technology.

Performance Monitoring For Gas Turbines

OROT RABIN POWER STATION UNITS x 350 MW

RELIABLE PERFORMANCE IN ONE PACKAGE

Outlook on Integrated Gasification Combined Cycle (IGCC) Technology

Skoda Supercritical Steam Turbine 660 MW

R&D in Vattenfall Johan Söderbom

Haliade 150-6MW Experiencia funcional con la nueva generación offshore

Online Monitoring of Gas Turbine Power Plants

Last update: January 2009 Doc.: 08A05203_e

Power Plant Performance Monitoring Using Statistical Methodology Approach

Source: EIA Natural Gas Issues and Trends 1998

Subject: Technology Collaboration for Gas Turbine and its auxiliaries of a 1.5 MW (ISO) rating, suitable for marine (defence) application.

Information Needed for Effective Asset Management

APPLIED THERMODYNAMICS TUTORIAL 1 REVISION OF ISENTROPIC EFFICIENCY ADVANCED STEAM CYCLES

VESI JA ENERGIA VIENTITUOTTEENA. Fortum Miko Olkkonen Senior Executing Manager, Hydro Projects Fortum Power & Heat Oy

Drives and motors. A guide to using variable-speed drives and motors in data centres

BIOPOWER 5 CEX. 1 Wärtsilä 10 January 2012 Presentation name / Author

Transcription:

Taking Advantage of Market Opportunities through Siemens Reference Power Plants Dr. Daniel Hofmann and Holger-Max Emberger 1. Introduction In a market where requirements and the operational environment for plant are changing rather rapidly compared to former years, flexibility is one key driver for business success. Besides the requirement for high performance and high availability to achieve low life cycle cost, flexibility in the plant operations and maintenance are strong drivers. This paper presents two Siemens PG developments for increased flexibility to support our customers in successful competition in the power market. Starting with a short description of the market requirements driving flexibility demand and a rough sketch of the Siemens Reference Power Plant philosophy two exemplary Siemens solutions for flexibility needs are presented. The first solution is shown on a new addition to the RPP portfolio. The SCC5-3000E 1S is a Single Shaft plant in the 300MW range, rounding the Siemens heavy duty power plant portfolio at the lower output end. This plant features unique flexibility regarding maintenance and shows how the requirement for higher power demand in certain times can be balanced with the requirement for increased maintenance intervals. The second solution is increasing the operational flexibility of combined cycle plants by enabling faster start up of the plant. Such the power market demands can be followed more rapidly and economically. Additionally the customer gains access to new opportunities in the ancillary market. 2. Market environment We strengthen our customers - to keep them competitive. This is one of the Siemens principles. For the RPP development this translates into focusing on the customer perspective for development decisions. Therefore the market requirements and the respective influence factors from a customer perspective are the starting point for the economical evaluation. This is done by selecting a geographical target market for a RPP and deriving the market requirements and influencing factors for this market from a plant operators point of view. With the specific influence factors the component and plant layout decisions are verified for their customer benefit. Only options that have a positive customer benefit will be realized and build the backbone of the RPP. In a market study two third of the EU power retail markets are shown to be opened for competition (Lit 1). However in some of those markets large power generation companies rule the competition. In those markets that are open and where a certain diversity of generating capacity and accessibility to the grid is given, e.g. in liquid markets, the requirements on plants are changing to

include flexibility additionally to the 'usual' requirements on performance and availability to consistently achieve economical operation. Flexibility in this context can be described by the capability to follow the market on the supply side (fuel price, fuel availability) and the demand side (hourly, daily or seasonal power revenue, ancillary services). The changing parameters on both, supply and demand side, bear risks for plant owners. Whereas combined cycle power plants in the 90 th were planned as base load plants, today's fuel price volatility and the liberalization drive the duty cycle in many cases into the intermediate or cycling operational regime. A plant solely designed for base duty may not be able to follow those changes in market environment efficiently. Additionally the liberalization provides market opportunities like ancillary products that can add to the revenue stream if the services can be supported by a flexible plant. Having a large combined cycle power plant online faster does increase the flexibility to respond to the requirements and such increases competitiveness for the operator. Description of the improvements in plant start up time for a large heavy duty Siemens combined cycle power plant is one of the flexibility features described in the paper. Flexibility can play an important role not only on the operations side. Flexibility is as well a valuable asset in the field of maintenance. As for the operational flexibility, maintenance flexibility can come in several different facets. One of those is the capability to influence the maintenance intervals depending not only by the duty cycle, but by the power output of the plant. Such the operator can influence the time till the next major outage to shift it where possible to a time of low revenue potential by changing the plant output. This feature is described by the example of an addition to our existing reference plant portfolio, the SCC5-3000E 1S. 3. Extension of RPP portfolio Since the 1990 th Siemens develops the Reference Power Plants (RPP) as a project neutral development of combined cycle or steam power plants. The plant is kept flexible by using a modular design approach with pre-designed modules covering different applications. Thus the plant can easily be adapted to customer or site specific requirements by selection of the respective modules for the most common applications. Upgrades of components or in the BOP area are introduced into the plant design on a continuous base as well as inclusion of lessons learned from executed projects. This feedback loop assures highest design quality. Optimization is done on the life cycle base with the focus on overall plant design. This assures highest customer value by considering the whole plant and the whole life cycle (planning, permitting, erection, commissioning, operation and maintenance) in the layout phase. The RPPs are developed for defined climatic regions mirroring the major markets. However a transfer to other climatic regions can easily be done based on the modular approach. Impact on

plant performance through the reference plant approach vs. a specific layout are small and are far outweighed by the reduced risk and delivery time. The current Siemens heavy duty combined cycle RPP portfolio ranges in the 50Hz market from about 100MW to 800MW per unit. Using multi unit configuration multiples of those outputs can be achieved according to the customer requirements. The SCC5-3000E 1S is an addition to the Siemens portfolio in the lower power output range with a block size of ~300MW. It targets the need for high availability and reliability with good fuel efficiency and long service intervals for a competitive price. As a special feature it can provide flexible service intervals for different plant outputs. SCC5-4000F 2x1 SCC5-3000E 2x1 SCC5-2000E 2x1 SCC5-4000F 1S SCC5-3000E 1S SCC5-1000F 1S 0 200 400 600 800 1000 Power [MW] SCC5-4000F 2x1 SCC5-3000E 2x1 SCC5-2000E 2x1 SCC5-4000F 1S SCC5-3000E 1S SCC5-1000F 1S 48 50 52 54 56 58 60 Efficiency [%] 3.1. New RPP SCC5-3000E 1S 3.1.1. Gas Turbine By identifying the gap in power output between a 100MW unit and the 400MW unit the market potential for a ~300MW unit size is tapped with the selection of the SGT5-3000E as the core for the plant. Different plant concepts and main components were investigated for the LCC impact and the most economical solution selected. The gas turbine as the plant core is a derated version of the well proven SGT5-4000F. The whole design of the SGT5-3000E is based on a common parts approach with the SGT5-4000F. To utilize most of the operational experience and to gain additionally the benefit of larger quantities in parts purchase and logistics, the SGT5-3000E has ~95% identical parts with the SGT5-4000F. To reduce the gas turbine in power, the compressor was adjusted to provide a lower mass flow. The compressor vanes were re-staggered and adjusted. The first stage blade row was slightly modified by maintained stagger angle to increase surge margin especially for high ambient temperatures. To improve turbine efficiency, the row one vane was slightly re-staggered. The casting stock tolerances of this vane are such that the restaggering is done by machining of the same casting as for the SGT5-4000F.

As the turbine inlet temperature was reduced with all other hot gas path components unchanged, the service intervals between major overhauls could be extended to 33,000 EOH (33MAC)for the higher power output and 41,000 EOH (41MAC) for the lower power output setting. This lead to an increase in availability and a reduction in service cost. Much attention was given to cooling air savings for further NOx emission reduction (Lit 2). 41MAC: 41,000 EOH Concept (with standard firing temperature) Major Outage Major Outage Equivalent operating hours (EOH) 0 41,000 82,000 33MAC: 33,000 EOH Concept (with elevated firing temperature) Major Outage Major Outage Major Outage Equivalent operating hours (EOH) 0 33,000 66,000 100,000 *) MAC = MAintenance Concept The capability of the gas turbine to run in different service intervals with different power ratings is proven by the vast experience with the hot gas components from the established SGT5-4000F fleet with higher firing temperatures. The SGT5-4000F has now clocked more than 2 million EOH with the leading unit having more than 70,000EOH to data (Jan. 2006). 3.1.2. Steam Turbine The steam turbine selected for this application is the SST5-900RH, an addition to the Siemens portfolio since the acquisition of the industrial turbine portfolio from Alstom. The turbine is of two casing design with a high pressure and a combined intermediate / low pressure turbine. The application of this turbine ranges from industrial to heavy duty with more than 100 units sold. The HP part is designed as a barrel type and operated at elevated rotational speed to give a much more compact and efficient design. The HP turbine is coupled through a gear to the main shaft. The gear transmits only the power of the HP turbine (<30MW) to keep in a standard gear design envelope. This shaft train setup has already been realized in a combined cycle plant. The IP/LP is a single casing turbine with a modular setup to accommodate different exhaust and extraction variants. The selected configuration is compact and efficient with an axial exhaust to the directly coupled condenser.

3.1.3. Generator A hydrogen cooled Generator has been selected for this plant configuration. The increased efficiency of the hydrogen cooling compared to an air cooled generator makes up for the slightly higher component cost. Additionally low power factors as currently demanded in some markets are supported with a single setup. As standard for our RPPs, the component selection is based on the life cycle cost evaluation and NPV evaluation. With more than 700GW of installed generator capacity, Siemens is one of the most experienced suppliers worldwide. 3.1.4. Plant Design With the target of about 300MW unit size, the individual component selection and the different plant configurations (Multi- or Single Shaft, 2 or 3 pressure, reheat or non reheat) have been evaluated. The configuration with the highest evaluated NPV proved to be the Single Shaft configuration with a three pressure reheat bottoming cycle. The gas turbine is directly coupled to the generator. The steam turbine is coupled via an SSS clutch to enable unrestricted gas turbine start up. For a compact plant layout and highest efficiency, the HP steam turbine power is coupled via the gear between SSS clutch and IP/LP steam turbine. The general plant layout is taken from our proven standardised Single Shaft plant, the SCC5-4000F 1S. Again for high reliability and availability as well as risk reduction, layout, components and design and service philosophies are transferred where applicable and economic. Crane Hot reheat SGT5-3000E SGen5-2000H SST-900 Condenser Cooling water Figure 1 SCC5-3000E shaft train layout

SGen5-2000H Exciter SSS-Clutch Gear SST-900 (IP/LP) SST-700 (HP) Condenser Figure 2 Detail of shaft train with steam turbine setup 3.1.5. Flexible maintenance interval The stresses for the hot gas path components depend amongst other on the operating temperature they are subjected to. By decreasing the firing temperature compared to the SGT5-4000F, the SGT5-3000E service on the hot gas path components can be extended. As the components with the shortest refurbishment or life interval governs the achievable service interval, significant design effort was made to achieve a common usage rate of the components for the different performance ratings. With the appropriate adjustment of the firing temperature the two maintenance concepts with 33MAC and 41MAC are achieved. The performance ratings of the two concepts are shown in Table 1. CC rating SCC5-3000E 1S 33MAC 41MAC Net Power Output, MW 305 289 Net Heat Rate, kj/kwh 6328 6368 Net Efficiency, % 56.9 56.5 NOx Emissions, ppmvd @ 15% O2 15 15 Table 1 Combined cycle performance rating for SCC5-3000E 1S at ISO conditions Up to here, the two concept stand separately for two different business models. Either operating the plant with high performance and service intervals extended to compared to a F-class unit, or with even longer service intervals and derated power output. However the prediction which would be the most favourable operating regime long term is a difficult one in nowadays changing market environment.

The SCC5-3000E 1S plant offers a new solution. The two service concepts can be integrated into a single more flexible one. Depending on the market situation, the plant may be operated with a lower output but longer service intervals is this is the most economical solution. With a change in demand and higher achievable electricity revenues, the plant can run up in power to participate in this beneficial market. This additional performance will come at the cost of slightly higher life consumption. Once the market is back to the former prices, the plant is reduced in output and returns to the extended service interval setting. This gives the plant operator or dispatcher a unique opportunity to react on the market situation by changing the service intervals. The feature can be used in the other direction, e.g. to shift the next outage to the most economical time by operating at a higher or lower power setting. The changes in regime are governed by the selected turbine inlet temperature. Starting from the base of the 41MAC concept, the EOH counter runs faster for the time additional power above the base setting is called. With the return to base setting, the EOH counter returns to the usual count. 300 41MAC Power Limit Power [MW] 250 200 150 100 Power curve (example) EOH counter (example) 33MAC 41MAC 50 Time Figure 3 Exemplary curve of power and EOH counter for flexible maintenance concept Above mentioned flexible maintenance concept has already been sold into the market place for customers benefit on our proven SCC5-2000E plant. The plant is currently build and is scheduled for commercial operation in xxx 4. Fast start up 4.1. Idea A change in fuel price can shift a power plant to higher or lower merit order in the dispatch rank. With the current high in the gas prices, a combined cycle plant planned for base load can be

required to operate in intermediate or daily cycling mode to be economical. The changing market environments can additionally open up other market opportunities like ancillary markets and short term trading. Especially for those operational regimes a fast start up capability enables a plant in standby to participate in a spinning reserve market or in an hour ahead trading scheme. 4.2. Plant requirements The concept is based on the proven Siemens Reference Power Plant design and requires only one real change in plant equipment and modification in plant master control. According to the market requirements most Siemens RPPs were designed as base load plants. With the low number of starts, the requirements on start up time for a hot start were low, 100 minutes were acceptable for a 400MW single shaft plant. The changes in market however change the importance of plant features. The business benefit from a faster start up is significantly different for a cycling plant that starts five times a week (see paper on commercial xxx). The real hardware change necessary to allow a faster start up is the implementation of a BENSON evaporator in the HRSG high pressure section together with a condensate polishing plant (CPP) (Lit 3). The introduction of a BENSON HP stage eliminates thick wall components like the HP drum and allows higher temperature and pressure gradients during start-up compared with a drum type HRSG. This design enables an unrestricted gas turbine start for a wide range of gas turbine ramp gradients including advances currently under development. The implementation of the CPP is necessary to for the water chemistry of a BENSON HRSG and provides the high water quality for all pressure stages. Additionally, the CPP reduces wait time for steam chemistry considerably. With those changes an unlimited ramp up of the gas turbine is feasible. Siemens as the OEM turnkey provider has the experience and knowledge to optimize not only individual components but the whole plant. For the complete picture of start up time optimization not only gas turbine and HRSG needs to be involved but an holistic approach was taken involving all faculties in plant design. With all parties working together further potential was identified by a revised unit start up procedure for hot starts (about 8hrs. downtime). The interaction of gas turbine, steam turbine and BoP was optimized. The result is the so called parallel start up procedure where the gas turbine is started and ramped up with its maximum allowable gradient. The exhaust gas is lead through the HRSG and the first steam is directly used for steam turbine roll off. Due to the condensate polishing plant there is no wait time for steam purity. 4.3. Test / commercialization Such a concept requires an advanced control concept for the water-steam cycle and the steam turbine. The first field test was run with manual control to prove the concept. Now the automated control concept was tested for the first time in a field unit with a start up time from standby to full load of less than 40 minutes for a single shaft 400MW plant.

400 Hot Start Comparison: Normal Start & Advanced Start Load at Generator Terminals [MW] 350 300 250 200 150 100 50 "Advanced Facy" Start Normal Start 0 Time Figure 4 Fast start up test in field unit The new concept is not only applicable for new plants but also available as upgrade package for plants in operation. After analyzing and assessing the existing plant design and equipment, Siemens can define fast start-up features which could be implemented without any disadvantages regarding plant performance and lifetime. Some fast start-up features are already implemented in plants in Spain and Portugal and proven during commissioning and commercial operation. 5. Summary The paper shows two examples of Siemens Reference Power Plant solutions for the increasing requirements for flexibility in our current changing markets. The market environment is changing driven by liberalization and volatile changes in fuel cost and electricity revenues. Additionally the changing markets provide opportunities for new power products. In reaction to the changing market needs, Siemens focuses on further improvement of flexibility of the proven RPP plants. Two of those improvements are described in the paper: Fast start up for cycling plants A new RPP with extended and flexible maintenance intervals Both developments extend the current market expectations.

The start up of a large combined cycle plant in less than 40 minutes is possible in a collaborative effort of all parties involved in plant design and operation and the experience base of Siemens as a turnkey power plant provider. Significantly longer service intervals for base operation of a high efficiency plant with the capability to increase performance by shortening the intervals have the advantage to reduce operating cost while providing extra power when the market situation is advantageous. This capability can be used as well for shifting of the maintenance outage to a more preferable low revenue time. 6. Literature Lit 1 ABS Energy Research, Electricity Deregulation Report Global 2005, Ed 4 2005 Lit 2 50-Hz Heavy Duty Gas Turbines Experience and Evolution, Hans Maghon, Bernd Stöcker, Dietmar Granser; Power Gen Asia 2005 Lit 3 Fast Cycling Capability for New Plants and Upgrade Opportunities, H. Emberger, E. Schmid, E. Gobrecht; Power Gen Asia 2005 Lit 4 Economic Evaluation of Cycling Plants An Approach to Show the Value of Operational Flexibility, H. Emberger, D. Hofmann, C. Kolk, Power Gen Europe 2006