Time Management. Part 3 Scheduling Fundamentals Activity Definition and Sequencing. Richard Boser

Similar documents
Time Management. Part 5 Schedule Development. Richard Boser

Project Time Management

Project Time Management

PROJECT TIME MANAGEMENT. 1 Powered by POeT Solvers Limited

Introduction to Project Management

Chapter 6. (PMBOK Guide)

The Plan s Journey From Scope to WBS to Schedule

The Project Planning Process Group

Scheduling Glossary Activity. A component of work performed during the course of a project.

Project Time Management

Module 3: The Project Planning Stage

Time Management. Part 2 Work Breakdown Structure (WBS) Review. Richard Boser

Precedence Diagram Method. CSTM 462 Planning & Scheduling

Time Management. Herb Pollard III

Unit 4: Time Management (PMBOK Guide, Chapter 6)

Project Time Management

Chapter 01. PMP work book answers V Exercise 01: Question Answer Question Answer

Chapter 2: Project Time Management

8. Project Time Management

Scheduling. Anne Banks Pidduck Adapted from John Musser

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza

Project Time Management

Project Management Glossary

Featured Paper Satya Narayan Dash By Satya Narayan Dash, PMP, CSM, MCP

Goals of the Unit. spm adolfo villafiorita - introduction to software project management

CRITICAL PATH METHOD (CPM) SCHEDULES

PROJECT TIME MANAGEMENT

Define Activities Sequence Activities Estimate Activity Resources Estimate Activity Durations Develop Schedule Control Schedule

TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain *

Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761

Chapter-6. Developing a Project Plan

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072

SCHEDULING AND TIME MANAGEMENT. Project Management and Leadership 2015D, PhD, PMP

Project Planning and Scheduling

Develop Project Charter. Develop Project Management Plan

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects

CPM-200: Principles of Schedule Management

Project Management Process. Prepared by Jay Knape

CSSE 372 Software Project Management: Software Project Scheduling

How to Craft a World-Class Work Breakdown Structure

Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter

Synergy between PMBOK and MS Project 2007 A Schedule Management Perspective

PROJECT TIME MANAGEMENT

Project Time Management Activity Definition Activity Sequencing Duration Estimating Schedule Development Schedule Control

added to the task, using Project, it will automatically calculate the schedule each time a new resource is added.

Introduction to Project Management ECE 480. Erik Goodman

CSC 443: IT Project Management Midterm 1 exam - Spring semester March 21 st, 2012

The Basics of Best Practices. Elden F. Jones II, MSPM, PMP, CMII

Quick Reference Guide Interactive PDF Project Management Processes for a Project

Chapter 4: Project Time Management

The 10 Knowledge Areas & ITTOs

Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration

Problems, Methods and Tools of Advanced Constrained Scheduling

CPM -100: Principles of Project Management

GPMCEP GLOBAL PROJECT MANAGEMENT, LLC C O U R S E

Managing the Project Schedule

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

Basic CPM Calculations

Learning Objectives. Learning Objectives (continued) Importance of Project Schedules

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza

Project Management. Week 4- Project Planning and Network Diagrams

Project Integration Management

Lecture 6: Project Time Management By: Prof. Lili Saghafi. Information Technology Project Management, Fifth Edition

Project Management Institute (PMBOK 2000) PMP Preparation Worksheet

WORK PROGRAM GUIDELINES

PMP 2013 Exam Prep. Course Overview

EXAM PREP COURSE. Course Overview. Course Objectives. Course Materials Include: Our PMP Exam Prep (Fifth Edition) training program:

Project Planning. Lecture Objectives. Basic Reasons for Planning. Planning. Project Planning and Control System. Planning Steps

Input, Output and Tools of all Processes

MECH 896 Professional Development for MEng Students. Homework Discussion. Scheduling Overview. Winter 2015: Lecture #5 Project Time Management

Making project management indispensable for business results. Project Management 101

Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza

Software Project Management I

Scheduling Best Practices

Information Technology Project Management

Chapter 6: Project Time Management

Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose

ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS

Minnesota Health Insurance Exchange (MNHIX)

Computer Training Centre University College Cork

PMP Exam Prep Training - 5 Days

// Taming an Unruly Schedule Using the 14-Point Schedule Assessment

Agenda. CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016

Expert Reference Series of White Papers. Importance of Schedule and Cost Control

PMP Project Management Professional Study Guide, Third Edition

PMBOK GLOSSARY. Activity Duration Estimating. Estimating the number of work periods which will be needed to complete individual activities.

Introduction to Project Management

Planning of Project Work (IS PM 6. Lecture, 2011 Spring)

Project Management Concepts

Knowledge Area Inputs, Tools, and Outputs. Knowledge area Process group/process Inputs Tools Outputs

Project Management Professional Exam Prep Plus

PMP Exam Preparation Answer Key

Pearson Education Limited 2003

SWEN 256 Software Process & Project Management

Errata. 133 Figure 5-15 Corrected the output for 8.3 Control Quality to read verified deliverables

4. Project management triangle The Project Management Triangle (called also Triple Constraint or the Iron Triangle) is a model of the constraints of

Overview of A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition

Transcription:

Time Management Part 3 Scheduling Fundamentals Activity Definition and Sequencing Richard Boser

Time Management This knowledge area includes the project management processes required to ensure timely completion of all work activities included in the project. Project Management Training Group -- Illinois State University 2

Time Management: Knowledge Process Areas 6.1 - Activity Definition Specific schedule activities required to produce project deliverables. 6.2 - Activity Sequencing Documenting dependencies among schedule activities. 6.3 Activity Resource Estimating Type & quantity of resources required to perform each schedule activity. 6.4 Activity Duration Estimating Number of work periods needed to perform schedule activities 6.5 - Schedule Development Analyzing the activity sequences, durations, resource requirements and constraints to create the project schedule 6.6 - Schedule Control Evaluating and controlling any changes to the project schedule Project Management Training Group -- Illinois State University 3

PMI-isms Related to Time Mgmt Assume you have historical info (Organizational process assets) PM has authority and power. PM s fault if project doesn t meet time and cost goals. Always follow Plan-Do-Check-Act cycle. Scope change must be evaluated for impact to time, cost, quality, risk & customer satisfaction. (See Rita Mulcahy (2005) PMP Exam Prep p. 16) Project Management Training Group -- Illinois State University 4

6.1 Activity Definition Inputs Enterprise environmental factors (PMO) Organizational process assets Scope Statement WBS WBS Dictionary PM Plan Tools & Techniques Decomposition Templates Rolling Wave Planning Expert Judgment Planning component (high-level schedule) Outputs Activity list Activity Attributes Milestone list Requested changes Project Management Training Group -- Illinois State University 5

Activity Definition Tool: Decomposition Project Management Training Group -- Illinois State University 6

Activity List (Activity Definition Outcome) Vendor Selection (Work Package) Agenda for visits Visit schedule Evaluation criteria Team prep and training Report on visits Finalists list Project Management Training Group -- Illinois State University 7

Activity Attribute Matrix (PMBOK p. 130) Activity: Report on visits ID and/or Code: Description: Predecessor: Successor: Logic Relationships: Lead or Lag: Resource Requirements: Assumptions/Constraints: Imposed Dates: Project Management Training Group -- Illinois State University 8

Milestones (Activity Definition Outcome) Zero duration events that mark major progress in work. Start Milestones Finish Milestones (deliverables) Many small milestones improve project control. Use for high level schedule Use for summary level reporting to senior management. Project Management Training Group -- Illinois State University 9

6.2 Activity Sequencing (PMBOK) Inputs Scope Statement Activity List Activity Attributes Milestone List Approved Change Requests Tools & Techniques Precedence (PDM) Diagram Method Arrow Diagram Method (ASM) Schedule Network Templates Dependency Determination Apply Lead & Lag (GERT) Conditional Outputs Project Schedule Network Diagrams Activity List UP Activity Attributes UP Requested Changes Project Management Training Group -- Illinois State University 10

Precedence Diagramming Method (PDM) or Activity-On-Node (AON) Task A ES 1d EF Task B ES 3d EF Task D ES 2d EF Task E ES 1d EF Task G ES 2d EF Task C ES 4d EF Task F ES 4d EF Look carefully as you will create a PD very soon! Project Management Training Group -- Illinois State University 11

Planning by Post-It # Verb Noun Estimated Time: Project Management Training Group -- Illinois State University 12

Activity: Sequencing with Sticky Notes Develop a Precedent Diagram for a surprise birthday party (or alternate). At a minimum, include at least dozen activities. Use only Finish-Start relationships. Use parallel activities when appropriate. You have 15 minutes. Project Management Training Group -- Illinois State University 13

Activity: Debrief Questions How did you decompose the project activities? Bottom-up? Or top-down? How many parallel activities were used? Were there any bottlenecks in your operation? If so, how resolved? How would you shorten the project time? Which activities were not in your control? Challenge activity: Enter in MS Project Project Management Training Group -- Illinois State University 14

Sequencing Tool Precedence Diagramming Method (PDM) Or Activity-On-Node (AON) Task A ES 1d EF Task B ES 3d EF Task D ES 2d EF Task E ES 1d EF Task G ES 2d EF Task C ES 4d EF Task F ES 4d EF Project Management Training Group -- Illinois State University 15

Sequencing Tool Activity on Node (AON) Design Formwork Mobilize Install Foundation Forms & Concrete Erect Steel Procure Steel Four types of dependencies possible. Where are the mandatory dependencies? Are there any discretionary dependencies? Project Management Training Group -- Illinois State University 16

Sequencing Tool Activity on Arrow (AOA) Design Formwork Mobilize Install Foundation Forms & Concrete Erect Steel Excavate Procure Steel Only ONE activity can occur between the same pair of nodes. All finish-start relationships. Dummy activities take no time or effort AND maintain logic. Nodes can serve as milestones. Project Management Training Group -- Illinois State University 17

Sequencing Tool Dependency Logic Dependents Logical Relationships Consecutive / Linear (Finish Start) Concurrent / Parallel D A B C 3 F 2 4 7 2 E 5 Project Management Training Group -- Illinois State University 18

Sequencing Tool Types of Dependencies Mandatory Dependencies Hard logic cannot change Discretionary Dependencies Soft logic- discretion of project manager External Dependencies Supply Chain related outside YOUR control (typically) Project Management Training Group -- Illinois State University 19

Sequencing Tool Dependency Relationships Project Management Training Group -- Illinois State University 20

Sequencing Tool Dependency Relationships Examples: FS Lots of examples. FF (rare) B can t finish before A e.g. Data entry (B) can t finish until Data collection (A) is finished SS Data entry (B) can start once Data collection (A) starts (w/ lag). SF (rare) B can t finish before A e.g. Terminate legacy server Old system discontinued (B) when new system (A) operable. Project Management Training Group -- Illinois State University 21

A dependency requiring that design be completed before manufacturing can begin is an example of a dependency. a. Discretionary b. External c. Mandatory d. Scope Test Yourself Project Management Training Group -- Illinois State University 22

A dependency requiring that design be completed before manufacturing can begin is an example of a dependency. a. Discretionary b. External c. Mandatory d. Scope Test Yourself C: Required or mandatory dependency Project Management Training Group -- Illinois State University 23

Sequencing Tool Lead (Accelerate) SS A 10 5 B 7 Start Start with 5 days head start for A When might lead be used? Project Management Training Group -- Illinois State University 24

Sequencing Tool Lead (Accelerate) FS A 10 5 B 7 Finish Start with 5 days overlap from finish When might lead be used? Project Management Training Group -- Illinois State University 25

Sequencing Tool Lag (Wait) A 10 5 Finish Start with 5 days lag When might lag be used? B 7 Project Management Training Group -- Illinois State University 26

Lead & Lag in MS Project Project Management Training Group -- Illinois State University 27

Technical Constraints that Affect Sequencing FS least risk-prone Use FS if it fits project time frame Discretionary constraints Judgment calls by PM (e.g. SS vs. FS) Unique Attributes Resource availability, location, staffing, etc Project Management Training Group -- Illinois State University 28

Types of Constraints - MS Project Imposed Dates Start no earlier than Start no later than Finish no later than Finish no earlier than Other Types Must start on Must finish on As late as possible Software Default As soon as possible Project Management Training Group -- Illinois State University 29

Sequencing Tool Activity: Dependencies in MS Project Create in MS Project Project Management Training Group -- Illinois State University 30

Network Diagram Applications Show activity dependencies Display workflow and activity sequence Tool for planning, organizing & controlling Determine progress for control & reporting Justify time estimates Plan schedule compression Project Management Training Group -- Illinois State University 31

Quiz #3: Sequencing Activities 1. What is the difference between AOA & AON? 2. Provide examples of mandatory, discretionary, and external dependencies. 3. Name the 4 types of dependency relationships? 4. How does lead differ from lag? 5. What is the default setting for software time constraints? 6. When is a milestone used? Project Management Training Group -- Illinois State University 32

End Activity Definition and Sequencing Questions/Notes Project Management Training Group -- Illinois State University 33