Water Main Testing Specifications

Similar documents
SECTION DISINFECTION OF PIPE AND WATER STORAGE FACILITIES

Repair and Disinfection of Water Mains Water Protection Program fact sheet

For a building with a crawl space, see Figure

SECTION IV - TESTS AND INSPECTIONS PART 1 - GENERAL Testing - General

Water System Disinfection

Practice Tests Answer Keys

SIZING OF WATER PIPING SYSTEM

CLEANING, INSPECTION, AND TESTING OF SEWERS

Section C-1 Pipes and Fittings

Reference Guide for Obtaining Permits and Utility Services For New Construction

MERCER ISLAND FIRE DEPARTMENT FIRE COMMERCIAL SPRINKLER STANDARDS

STANDARD OPERATING PROCEDURES FOR ALL WATERMAIN DISTRIBUTION REPAIR & INSTALLATION

Water Services and Utilities - General Regulations in Ohio

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING

SECTION 3 SANITARY SEWER DESIGN

STANDARD SPECIFICATIONS SECTION CLEANING AND LINING WATER MAINS

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.

Stenner Pump Chlorinator Installation & Start Up Guide

Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

Standard Specifications for Installation and Repairs of Water and Sewer Service Lines

2.0 DESIGN CRITERIA FOR WATER DISTRIBUTION SYSTEMS

CHAPTER. Standpipes and Hose Systems OVERVIEW. Standpipe and Hose Systems Defined

Wastewater Collection Practice Test #3 Page 1 of 15

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

CITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General

APPENDIX A RECOMMENDED RULES FOR SIZING THE WATER SUPPLY SYSTEM

SPRINKLER SYSTEM PLANS AND CALCULATIONS CHECK LIST

Automatic Fire Sprinkler Submittal Requirements

Dechlorination of Potable and Superchlorinated Water

Sample Test Questions

Section SEWER PIPE INSTALLATION AND TESTING

MATHEMATICS FOR WATER OPERATORS

DESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES SITE UTILITIES

CHAPTER 4 WELL COMPLETION AND MAINTENANCE

SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING

One of the fundamental design elements that every

ARTICLE II (2) ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH Purpose and Application.

BLADDER SURGE CONTROL SYSTEM

Specifications For Rehabilitation Hudson #1A Hudson #2 Foster Island Well #41

Sample Test Questions

SANITARY SEWER SPECIFICATIONS

Standard Hydraulic Piping Flushing Procedure

Water Quality Contingency Planning Standard EPB 540B

WATER MAIN CONSTRUCTION TECHNIQUES DEPARTMENT OF PUBLIC WORKS WATER & WASTEWATER DIVISION

SECTION ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section Submittals.

Element D Services Plumbing

ABC & C 2 EP Formula/Conversion Table for Water Treatment, Distribution, & Laboratory Exams

SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA (7300 Short Road, Serene Lakes)

Close-Out Documents... 9

UPPER MOHAWK VALLEY REGIONAL WATER BOARD SERVICE AREA. City of Utica

Chapter 7 Plumbing Connections

812-3 LIMITATIONS: b. No fire hydrant shall be obstructed or used when there is a fire in the area.

SECTION WATER DISTRIBUTION SYSTEM. B. The foreman of the contracting crew must speak fluent English.

Georgia State Amendments to the International Plumbing Code

CHAPTER 10 BOILERS, WATER HEATERS AND PRESSURE VESSELS

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

Design & Construction Standards, Revised January

SECTION HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION

INSTALLATION OF INSITUFORM LINER

AKRON EDUCTORS TROUBLESHOOTING GUIDE OPERATION & THEORY OF EDUCTORS GENERAL OPERATING AND MAINTENANCE INSTRUCTIONS

Sewer Water Pipeline Replacement with CERTA LOK RESTRAINED JOINT PVC PIPE

ARTICLE 1141 Cross Connection Control Program

Presented By: Fred J. Sánchez Water Quality Operations Supervisor

SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION CONCRETE BONDING COMPOUND.

SANITARY GRAVITY SEWER LINE TESTING. B. Section CCTV Inspection of Gravity Sewer Lines

READ ONLY. Adopting Agency BSC SFM. Adopt Entire Chapter Adopt Entire Chapter as amended (amended sections listed below)

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES

I. Introduction. 10 minutes

A. The CONTRACTOR shall provide pipe coating, complete and in place, in accordance with the Contract Documents.

WESTFIELD WATER RESOURCES DEPARTMENT

Beacon Hill Sewer District Standard Specifications

SMALL GAS OPERATOR OPERATION AND MAINTENANCE PLAN

FLUID FLOW Introduction General Description

This will also provide you with the knowledge to insure long life for your Investment

Design Criteria & Service Goals

SECTION 4Aggegate Subbase

Gas Line Sizing. Z Maximum gas demand shall be determined by adding all of the equipment Btu ratings from appliances connected on the system.

MAINTENANCE OF SMALL WATER SUPPLY, SANITATION AND IRRIGATION SCHEMES

POLYURETHANE LINING AND COATING ON PIPE RAW WATER

WATER MEASUREMENT USING TWO INCH (50 mm) DRAIN TESTS

NFPA31FuelOilPiping 1 Revised

Corrosivity of Water Supplies

Revised April (May) 2015

7. Codes of practice for plumbing

CHAPTER 26 PLUMBING CODE

SECTION DUCTILE IRON PIPE AND FITTINGS

Method to Determine PERFORMANCE OF INDIRECT-FIRED WATER HEATERS March 2003 Edition

SECTION 2 POTABLE WATER SYSTEMS 2.1 GENERAL 2.2 SYSTEM DESIGN

SECTION SANITARY SEWER PIPE

Inexpensive Leak Detection for Small Waterworks. Virginia Department of Heath Office of Drinking Water Catalog Number: HTO/005/2015

Distribution System Operation

Problems with Hypo: Best Design Practices for Smooth and Efficient Sodium Hypochlorite Feed Systems Chad Hantelman, City of Bremerton Jeff Zahller,

Conversions between the common units of length used in the Imperial system are listed below 12 in = 1 ft 3 ft = 1 yard 1760 yards = 1 mile

SECTION ASBESTOS CEMENT PIPE REPAIRS, DEMOLITION, AND DISPOSAL

Application for the Construction or Installation of Aboveground Storage Tank (AST) Systems or Associated Underground or Over-water Piping Systems

Louisiana Administrative Code Title 51 Part XIII. Sewage Disposal

Routine Maintenance and Inspection

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

Transcription:

Pressure and Leakage Test A. Testing Procedures Water Main Testing Specifications 1. All pressure leakage testing shall be tested against installed pipe, fittings, valves, joints, and fire hydrants up to nozzles. B. Valve Operations Village of Mundelein Water Division personnel are the only individuals authorized to operate any water valves. C. Taps for Testing Contractor/developer is required to provide one (1)-inch service taps in manholes for test gauges, flushing needs, and for disinfection at each end of the pipe test section. 1. Service tap materials are to be purchased from the Village of Mundelein Water Division. 2. Contractor shall make the tap connection using an approved tapping tool on PVC C- 900 piping, contractor shall provide removed coupon to Village of Mundelein Water Division Inspector. 3. Contractor shall schedule an appointment with the Village of Mundelein Water Division for the witnessing/inspection of all taps. 24-hour notice prior to appointment must be provided to the Village of Mundelein Water Division. 4. Contractor shall remove copper tube with goose neck assembly from manholes upon completion of testing and chlorination procedures. D. Air Removal Before applying the specified test pressure, air shall be expelled completely from the section of piping under test. Air removal will be done in conjunction with the flushing procedures of the water main (see Flushing Requirements.) E. Allowable Leakage No pipe installations will be accepted if the leakage is greater than that determined by the following formula: In inch-pound units, L = SDv P 133,200 (1 of 8)

Where: L = allowable leakage, in gallons per hour S = length of pipe tested, in feet D = nominal diameter of the pipe, in inches P = average test pressure during the leakage test, in pounds per square inch (gauge) In metric units, Where: Lm= SDv P 715,317 LM = allowable leakage, in liters per hour S = length of pipe tested, in meters D = nominal diameter of the pipe, in millimeters P = average test pressure during the leakage test, in kpa These formulas are based on an allowable leakage of 11.85 gpd/mi/in. of nominal diameter at a pressure of 150 psi. When testing against closed metal-seated valves, an additional leakage per closed valve of 0.0078 gal/b/in. of nominal valve size shall be allowed. When hydrants are in the test section, the test shall be made against the main valve in the hydrant. F. Acceptance of Installation 1. Acceptance shall be determined as the basis of allowable leakage or the procedures established by the Village of Mundelein Engineering Department. If any test of laid pipe discloses leakage greater than that specified, repairs or replacements shall be accomplished in accordance with the Specifications. 2. All visible leaks are to be repaired regardless of the amount of leakage. 3. Dye or any other form of colorizing the water will not be introduced into the water main for the purpose of locating leaks. Disinfection of Water Mains Water main disinfection will be in accordance with the State of Illinois Rules and Regulations Title 35, Subtitle F, Chapter 11, Section 652.203 of the Technical Policy Statement. A. Flushing Water Main 1. Sections of pipe to be disinfected shall first be flushed to remove any solids or contaminated material that may have become lodged in the pipe. Fire hydrants in these sections will be flushed using either the two and a half (2 ½)-inches nozzle or the pumper nozzle to develop a velocity of at least two and five-tenths (2 5/10)-feet per second in the main. (2 of 8)

2. All fire hydrants will be flushed and operated in the section of water main to be tested/disinfected. 3. Village of Mundelein Water Division personnel are the only individuals authorized to operate any water valves. 4. All valves that are closed will have a tap with copper tube and goose neck assembly installed in the vault for the purpose of flushing, and disinfecting the water main to the furthest end point of each section being tested. B. Requirement of Chlorine Before being placed into service, all new mains and repaired portion of, or extensions to existing mains shall be chlorinated so that the initial chlorine residual is not less than 50 mg/1 and that a chlorine residual of not less than 25 mg/1 remains in the water after standing 24 hours in the pipe. 1. Liquid Chlorine A chlorine gas-water mixture shall be applied by means of a solution-feed chlorinating device, or the dry gas may be fed directly through proper devices for regulating the rate of low and providing effective diffusion of the gas into the water within the pipe being treated. Chlorinating devices for feeding solutions of the chlorine gas, or the gas itself, must provide means for preventing the backflow of water into the chlorine. 2. Chlorine- Bearing Compounds in Water This method must have prior approval from the Village of Mundelein Water Superintendent before introduction. A mixture of water and high-test calcium hypo chlorite (65-70% Chlorine) may be substituted for the chlorine gas water mixture. The dry powder shall first be mixed as a paste and then thinned to a one (1) percent chlorine solution by adding water to give a total quantity of seven and five-tenths (7 5/10) gallons of water per pound of dry powder. This solution shall be injected in one (1) end of the section of main to be disinfected while filling the main with water in the amounts as shown in the table which follows: Chlorine Requirements to Produce to mg/1 Concentration in 100-feet of Pipe By Diameter Pipe Size In Inches 4 6 8 10 12 100 % Chlorine, Lb. 0.027 0.061 0.108 0.170 0.240 1 % Chlorine Solution, Gals. 0.33 0.73 1.30 2.04 2.88 (3 of 8)

3. Tablet Disinfection This method must have prior approval from Village of Mundelein Water Superintendent before introduction. Since preliminary flushing must be eliminated in using this method, it should be utilized only when scrupulous cleanliness has been used in construction. It shall not be used if trench water or foreign material has entered the main or if the water is below 41 F, or if the piping length exceeds 50 linear feet. Tablets should be placed in each section of pipe, hydrants, hydrant branches, and other appurtenances. Tablets must be at the top of the main and shall be attached by an adhesive approved by the Village Water Superintendent. Tablets in joints between pipe sections, hydrants, hydrant branches, or appurtenances are to be crushed and placed inside the annular space, rubbed like chalk in butt ends of sections to coat them if the type of assembly does not permit crushing. In filling a section of piping with water when using the tablet method water velocity shall be less than one (1)-foot per second. Number of 5-Grain Hypochlorite Tablets Required For a Dosage of 50 MG/L per Length of Pipe Section Pipe Size (Foot) Length of Pipe Section Up to Inches 13 18 20 30 40 2 1 1 1 1 1 4 1 1 2 2 2 6 2 2 3 3 4 10 3 5 7 7 9 12 5 6 10 10 14 B. Point of Application The preferred point of application of the chlorinating agent is at the beginning of the pipeline extension or any valved section of it, and through a corporation stop inserted in the pipe. 1. The contractor will install corporation cocks with a copper tube gooseneck assembly for the purpose of disinfecting and as sample collection point at each branch, dead end, or a location which has a closed valve. Fire hydrants will be disinfected as part of this procedure. 2. At a point not to exceed five (5)-feet downstream from the beginning of the new main the water entering the new main will receive a dose of chlorine fed at a constant rate such that the water will have not less than 25 mg/1 free chlorine. (4 of 8)

3. Water from the existing distribution system shall be made to flow at a constant rate into the new main. 4. The Village of Mundelein Water Division personnel must witness the disinfection process. An appointment with 24-hour prior notice must be scheduled with Village of Mundelein Water Division. 5. In the process of chlorinating newly laid pipe, all valves, fire hydrants, or other appurtenances shall be operated while the pipe line is filled with the chlorinating agent and under normal operating pressures. Disinfection of Water Services (Larger Than Two (2)-Inches) For the purpose of clarifying this section, water service in this section refers to one (1) or more of the following installations that terminate inside of a building under construction. The service line being installed is for the purpose of a combination domestic and fire protection use. The service line being installed is for the purpose of branching into multiple domestic services inside of a meter room. The service line is the section of main being tested from the Village of Mundelein right-of-way valve to a location inside of the building. There are no fire hydrants installed on the service line. A. Meter Rooms/Building Installations 1. The service line will be disinfected to the inside valve of the meter room prior to any branch service being connected. 2. The meter room will have a permanent heating system installed and in working condition prior to the disinfection. 3. One (1) sample point will be provided at the source and one (1) sample point will be provided at the inside valve provided the length of pipe does not exceed 1,000- feet. 4. The contractor will supply a copper tube gooseneck assembly at each of the sample points. 5. The Village of Mundelein in Water Division personnel must witness the disinfection process. An appointment with 24 hours prior notice must be scheduled with Village of Mundelein Water Division. B. Domestic/Fire Service Mains/Meter Room 1. The service line will be disinfected up to the inside valve on both the fire branch and the domestic branch. (5 of 8)

2. The Fire Service Main Branch will have a valve of equal size to the riser section installed prior to chlorination. 3. The building, meter room, or location of the incoming service line will have a permanent heating system installed and in working condition prior to the disinfection. 4. One (1) sample point will be provided at the source and one (1) sample point will be provided at the inside valve provided the length of pipe does not exceed 1,000- feet. 5. The contractor will supply a copper tube goose neck assembly at each of the sample points. 6. The Village of Mundelein Water Division personnel must witness the disinfection process. An appointment with 24 hours prior notice must be scheduled with Village of Mundelein Water Division. Dechlorination Requirements Following chlorination, all treated water shall be thoroughly flushed from the newly laid pipe using the fire hydrant(s) and/or all the copper gooseneck assemblies. The flushing shall replace the highly chlorinated water with water that has a chlorine residual of less than 1mg/1 or equal to the residual from the supply service. Sampling and Testing The discharging of chlorinated water must be expelled to the surrounding ground surface. The contractor/developer must comply with all of the I.E.P.A. Rules, Regulations, and Standards for dechlorinating water as part of the discharging. The contractor/developer is responsible for the equipment and materials to dechlorinate the water at each point it is discharging. The Village of Mundelein Water Division personnel are the only individuals authorized to operate the valves. The Village of Mundelein Water Division personnel must witness the dechlorination procedures when flushing the water mains. An appointment with 24-hour prior notice must be scheduled with Village of Mundelein Water Division. Sample collection for bacterial testing will start immediately after flushing the highly chlorinated water from the system and prior to any portion of the water main being placed into service. Samples will be collected at all sample points designated by the Village of Mundelein Water Superintendent. Sampling procedures must follow the I.E.P.A. Standards for construction of new water mains. (6 of 8)

A. Locations and Spacing 1. Samples will be collected from each dead end, branch lateral, or section of pipe that has a closed valve. Samples will be collected from the copper tube with gooseneck assembly at these points. 2. Samples will be collected from fire hydrants at points not to exceed 1,000-feet of linear water main. 3. A sample will be collected from the copper goose-neck assembly point that is located no further than five (5)-feet downstream from the beginning of the new water main. B. Collection Requirements 1. The contractor is required to collect all samples at the location(s) designated by the Village of Mundelein Water Superintendent. 2. Village of Mundelein Water Division personnel are the only individuals authorized to operate any water valves and must witness all samples at time of collection. 24-hour prior notice must be scheduled with the Village of Mundelein Water Division. 3. The contractor is required to take the collected samples to a certified laboratory approved by the Village of Mundelein Water Superintendent. 4. The Village of Mundelein Water Division has the right to collect quality control samples at the same time contractor collects samples. The charges for the quality control samples will be charged to the contractor. 5. Samples will be collected on consecutive days with at least 24-hours of separation between the collection times. 6. Each sample collected will be tested for quality and must show the absence of coliform organisms. C. Satisfactory Sample Results If all the samples tested meet the Bacterial Quality Standards and are certified as satisfactory by the testing lab: 1. The contractor may have the lab fax the results directly to the Village of Mundelein Water Division; 2. The contractor must provide original copies of the certified results to the Village of Mundelein Water Superintendent within seven (7) business days of the date on the test results; and (7 of 8)

3. The contractor must contact the Village of Mundelein Water Division to schedule an appointment to have the water main placed into service within 72 hours of the satisfactory test results being certified and only as approved by the Water Superintendent. Unsatisfactory Sample Results If any one (1) of the samples tested fails to meet the Bacterial Quality Standards and is deemed unsatisfactory, then all the samples collected on the same date for the tested section of pipe, will be considered unsatisfactory. 1. Unsatisfactory samples from the first day of collection will be discarded. A new first day collection must be scheduled with the second day to be consecutive. 2. Unsatisfactory samples from the second day of collection will be discarded. First day samples will also be discarded and the contractor must schedule new first and second day samples. The contractor will have up to three (3) chances of first day and two (2) chances of second day bacterial testing to obtain satisfactory results on all the samples collected and tested. Meter Room Requirements 3. Should the contractor fail to obtain satisfactory results after the allotted attempts, the water main section being tested is to have the original disinfection procedures repeated until satisfactory results are obtained. (Future Section) Contact Public Works Department in the interim. (8 of 8)