EVALUATING THE LACK OF FLEXIBILITY AGAINST THE BENEFITS OF IN-PIT CRUSHING AND CONVEYING

Similar documents
In-Pit Crushing and Conveying Phil Morriss

Types of Mining - Expert Table

COAL MINING TECHNOLOGY. A Presentation by MANOJ KUMAR SINGH Manager(IE), NCL-HQ, Singrauli(MP) mks_ie@nclhq.nic.

Walking and Working Surface Checklist:

3D Modelling & Mine Planning Software. Comprehensive tools provide a competitive advantage from exploration to rehabilitation.

BENEFITS OF USING MOBILE CRUSHING AND SCREENING PLANTS IN QUARRYING CRUSHED STONE. 1. Introduction. Mario Klanfar*, Darko Vrkljan*

Workplace Incident Fatalities Accepted by the Workers Compensation Board in 2014

Florida Building Code 2004 SECTION 1009 STAIRWAYS AND HANDRAILS

Hydraulic Excavators

Deswik.Sched. Gantt Chart Scheduling

Simple Machines. What are simple machines?

Basements and Deep Building Construction Policy 2014

Geotechnical Management. An Overview on typical system elements

3 Tappan Zee Bridge Rehabilitation Options

CONSTRUCTION TRAFFIC MANAGEMENT PLAN V11, 26/09/12

Working in a quarry guidelines

A new short- and medium-term production scheduling tool MineSight Schedule Optimizer (MSSO)

Stefan Sjöström, SEABB, PAPI UGM Automation ABB Underground mining Mobile Integration. ABB Group May 18, 2015 Slide 1 3BSE

Lödige Goods Passenger Lifts

Base Cabinet with Self-storing Folding Doors and Floor

Software Stability Model for Dump Truck Scheduling

Stacker and reclaimer systems for cement plants

Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains

choice for the application.

Fabrication, Delivery and Installation

Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS

Training Simulators for the Mining Industry

May 24, These Questions and Answers (Q&A) consolidate, clarify, update and replace all prior Q&As regarding this subject

GUIDELINES FOR MINE HAUL ROAD DESIGN

Free Examples of plant layout drawing

Automated Mine Scheduling: What is it and will it help me?

Truck: A :22 PM ton. Maximize payload, maximize profit. LOADRITE X2650 Excavator Scales. transforming the way the world works

Backfill for Bench Stoping Operations

Mine Schedule Implementation Using a Multi-Agent Based System

FIBER OPENING AND BLENDING. AUTEFA Solutions leads the way

Outotec HIGmills; A Fine Grinding Technology

Table 4.9 Storm Drain Inlet Protetion Applicable for

There is no water, surface tension cracks, nor other environmental conditions present that reduce the stability of the excavation.

EQUIPMENT SAFETY EARTHMOVING MATERIAL HANDLING NAVFAC MIDLANT

How To Use Leica Dozernav Plus

The entire document shall be read and understood before proceeding with a test. ISTA 3B Page 1 of 35

How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No May 15, 2013

Road Rehabilitation and Reconstruction Using AutoCAD Civil 3D

Presentation ThyssenKrupp Bulk Materials Handling Dr. Markus Oles

GPS BASED TRUCK DISPATCH SYSTEM (TDS) IN HIGHLY MECHANIZED BAUXITE MINES A CASE STUDY.

USE OF SOLUTION STRATEGY IN OPEN CAST MINING TRUCK DISPATCHING SYSTEM

ADA POST INSPECTION CHECKLIST. Job No. Route County Location

At the completion of this guide you should be comfortable with the following:

OPTIMIZATION OF LOAD HAUL DUMP MINING SYSTEM BY OEE AND MATCH FACTOR FOR SURFACE MINING

APPLICATION OF OPENRISK AT OPEN CAST COAL MINES

BUCKET AND CUTTING TOOTH DEVELOPMENTS FOR THE BUCKET WHEEL EXCAVATORS OF MÁTRA POWER STATION LLC

Pole Lathe and Shave Horse Design

DGMS (Tech.) (S&T) Circular No. b_ of 2016 Dhanbad, datedcwdy/2016. Subject: Standards of illumination in opencast coal mines

Christa s Lost Lessons Simple Machines

Candelaria and Ojos del Salado Chile

Patrik Westerlund & Marcello Sanchez, SEABB, PAPI UGM Automation ABB Underground mining Mobile Integration

ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS

Conveyor Belt Group. Flexowell -belts for safe and efficient steep inclined and vertical conveying

Focus on learning key. 1 NIHL impacts. Exercise. Discuss. Introduction

The Manitoba Water Services Board SECTION Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

Corrugated Packaging 101

Partnerships Implementing Engineering Education Worcester Polytechnic Institute Worcester Public Schools

ASSET MANAGEMENT GUIDE FOR PROJECT DESIGN FORMAT

TABLE OF CONTENTS. INTRODUCTION... 5 Advance Concrete... 5 Where to find information?... 6 INSTALLATION... 7 STARTING ADVANCE CONCRETE...

Manual Handling- The Whole Story!

High Capacity Hot Air Dryer

NEW BLUE LINE CONNECTIONS

Expertise in heavy loads. ThyssenKrupp freight elevators.

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.

Safety Applications for GPS Systems in the Mining Industry

KITCHENS. Tip PAGE 1 FITTING YOUR KITCHEN GUIDE. How to mark out a kitchen. Tools required for installing a kitchen STEP ONE STEP TWO STEP THREE

Wren Kitchens Installation Tips Carefully check your kitchen delivery Measuring out and marking up Fitting the base cabinets...

Container design and types

Operating Concept and System Design of a Transrapid Maglev Line and a High-Speed Railway in the pan-european Corridor IV

42U/45U 28" Wide Rack Installation & Service Guide

Mining with Paste Fill

TOOLS FOR SELF RELIANCE REFURBISHING SHEET No 2. Registered Charity No Saws for Woodworking

PowerPoint: Graphics and SmartArt

Gate Leg Drop Leaf Table Plans

CONSTRUCTION SEQUENCE & PROGRAMME

ADA Checklist for Polling Places

W E C O N V E Y Q U A L I T Y DISCHARGE SYSTEMS

Information Technology Career Path Overview

Update on Heap Leach potential of the Murchison gold project

Asset Management Guide For Project Design Format

Functional overview. PRECISE l RELIABLE l REAL-TIME MONITORING Document Number: MW

Sale of surplus Road Planings price structure

Using the Leadership Pipeline transition focused concept as the vehicle in integrating your leadership development approach provides:

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED NEW COAL-FIRED POWER STATION IN THE LEPHALALE AREA, LIMPOPO PROVINCE

GEAROLOGY 4-1 WORMS AND WORM GEARS WORMS AND WORM GEARS

CONVEYING TECHNOLOGY LOADING TECHNOLOGY PALLETIZING TECHNOLOGY PACKAGING TECHNOLOGY SORTATION AND DISTRIBUTION SYSTEMS

1,300 people, $100M annually into the regional economy. Upgrading Mine-Wide Wireless Network with Zero Downtime. square miles,

Pallet Rack: How to Avoid Costly Errors in Planning & Installing

Optical Cable Pre-Construction Survey. Keywords Stationary Reel Method, empty innerducts, sub-ducts, microducts, Intermediate-feed manholes

301.7D. Mini Hydraulic Excavator

CHAPTER 8 CIVIL DESIGN

Traffic Management Issue 1.0 Revision: v2 October 2014

IP Network Control: Turning an Art into a Science. Case Study: Global Crossing

9. The kinetic energy of the moving object is (1) 5 J (3) 15 J (2) 10 J (4) 50 J

Transcription:

EVALUATING THE LACK OF FLEXIBILITY AGAINST THE BENEFITS OF IN-PIT CRUSHING AND CONVEYING Optimizing Mine Operations Conference Toronto 2013 Date Bob McCarthy Snowden

Outline Introduction IPCC basics Mine planning concepts for IPCC Guidelines for flexibility Conclusions

Introduction flexibility Flexibility is necessary? Just a matter of perspective Consider underground mining Fixed stope location and geometry Fixed development options Lack of flexibility bad? Consider underground mining technology Longwall coal mining Continuous miners and conveying Not too different from IPCC

Introduction paradigms Paradigm shift UG Miners are used to working under constraining conditions Open pit miners not so Requires a paradigm shift, but one with lateral familiarity How to survive the paradigm shift? Mine planning Change management

Introduction why bother? Potential rewards (study results) Cash cost reductions between US$0.18/t and US$0.82/t Net Present Cost improvements US$900m (@10% discount) Typical reduction in manning averages 6.5 persons per truck saved Typical reduction in ancillary equipment 25% Reduction in infrastructure costs (greenfields) Overall capital for long life mines is near neutral (when truck replacements are taken into account) Reduced carbon footprint

Introduction why bother? Truck savings

Outline Introduction IPCC basics Mine planning concepts for IPCC Guidelines for flexibility Conclusions

IPCC basics Integrated open-pit mining system A true alternative to pure truck-shovel operations Not a new technology Three general types of IPCC systems From MMD Group Fixed or Semi-fixed Semi-Mobile Fully Mobile

IPCC basics IPCC system components Crushers In-pit conveyors (fully mobile) Stationary conveyors Conveyor crossing Slewing spreader, radial stacker or tripper car spreader Ancillary equipment (crawlers, cranes, etc.)

IPCC basics fully mobile in-pit conveyors Bench transfer conveyor the conveyor that moves material from the mobile crusher to the bench conveyor It can come in many variations: belt wagons transfer bridges mobile conveyors per Sandvik Belt wagons and transfer bridges can convey to a bench conveyor above or below the current bench elevation per Metso

IPCC basics fully mobile in-pit conveyors Bench conveyor the conveyor that runs the length of a mining area (defined here as a panel), along which the mobile crusher traverses It can be fed from up to three benches (typical maximum) It is relocated by either track shifting (pipeline dozer) or selfpropelling Its length may change according to the width of the panel (but has minimum, driven by frequency of shifting) Bench conveyors on different benches Visonta lignite mine (Hungary) A.Oberrauner

IPCC basics fully mobile in-pit conveyors Portable conveyor a movable conveyor, used to extend the reach from or to a bench conveyor or dump conveyor of shorter length (up to 100 m), can be self-propelled may be used when erratic shaped benches are encountered or when dumps need extending can be used in series (piggy-back, grasshopper) per Terra Nova Technologies Ltd

Mining Direction Bench Trunk Conveyor IPCC basics fully mobile in-pit conveyors Bench trunk conveyor the conveyor to which the bench conveyor discharges is aligned in the overall mining direction (90 to the bench conveyor) needs to be extendable as mining advances Face Travel Bench Conveyor

IPCC basics stationary conveyors Stationary conveyor conveyors that are not regularly moved, but can be moved through dismantling and re-assembling modules Connection conveyor any non-specialised conveyor that transports material within the pit to a pit exit conveyor. Pit exit conveyor the last leg on the journey out of the pit, this typically ascends an incline, whether a pit haul ramp, a steeper dedicated conveyor ramp, or a tunnel incline; also used for ascending a waste dump Overland conveyor this conveyor connects the pit to the dumping area. This can be to a waste dump or an ore treatment facility per Sandvik

IPCC basics crossings Two common solutions to equipment / conveyor interactions Tunnel (culvert) Conveyor bridge

IPCC basics dumping / spreading systems Spreaders Radial stackers Tripper cars Track shiftable Self-propelled From Sandvik Mining and Construction

From FLSmidth IPCC basics dumping / spreading systems Discharge boom Transfer Bridge Tripper Car 50m >50m From Sandvik Mining and Construction

Outline Introduction IPCC basics Mine planning concepts for IPCC Guidelines for flexibility Conclusions

Mine planning Fully mobile panels and strips Semi-mobile crusher access Relocation of crushers Dump development

Mine planning fully mobile panels and strips Panels are serviced by a single bench conveyor on a single bench Multiple panels can operate in one pushback or terrace Panels are aligned in long dimension Panels are multiples of strips wide Bench conveyor can serve up to three benches in a panel

Mine planning fully mobile panels and strips When all benches in current strip are complete, bench conveyor track shifts When all strips in panel are complete, the system is relocated Relocation is either to another region of the pit of similar elevation or to a box cut to sink down

Mine planning fully mobile panels and strips Three bench operation (B3-C1-P1-N1) B Three benches per bench conveyor C One crusher per bench conveyor P One pass per strip N One bench conveyor per terrace

Mine planning semi-mobile crusher access Access options Permanent Temporary

Mine planning semi-mobile crusher access A permanent designed alcove into the high wall along the haul road access path Crusher Station Conveyor Access Ramp Slot Catch Berm Conveyor Bridge Down Ramp Direction Permanent Ramp System Up to Crusher Station & Waste Dumps Ramp Turning Area onto Crusher Tip Head Shovel

Mine planning semi-mobile crusher access A permanent location within an over-width haul road

Mine planning semi-mobile crusher access Taking advantage of a temporary wall for a permanent station location

Mine planning semi-mobile crusher access A temporary location along the haul road with access to the truck tip off the haul road Conveyor Bridge Ramp Conveyor Crusher Station Operating Shovel Operating Shovel

Mine planning semi-mobile crusher access A temporary location along the haul road with access to the truck tip via temporary ramps off the bench TurningArea.. No Access to Exit Pit Ramp Shovel Face CrusherStation TEMPORARYRamp Shovel Face

Mine planning semi-mobile crusher access For each additional bench, the length of a temporary ramp (and footprint on the working bench) increases. Each additional bench increases the average cycle time for the trucks and therefore the number of trucks needed. Balancing this is the desire to reduce the frequency of crusher shifts. Beyond four benches per crusher shift, the footprint of the temporary access ramp becomes significant relative to the available bench area. While a crusher could be relocated once every 6 months, no more than once per year is preferable; therefore, 4 benches per year is a good maximum bench advance rate.

Mine planning relocation of crushers Common misconception that relocation takes months and is a major engineering task Crusher relocation can be accomplished in 7 days or less From Sandvik Mining and Construction

Mine planning relocation of crushers From Sandvik Mining and Construction

Mine planning conveyor pit exits Primary challenge is the pit exit corridor Options include: Alongside haul roads Dedicated conveyor routes (can be greater than 20%) Tunnel Most common route is the haulage ramp Complex exits increase the number of transfer points

Mine planning haul road considerations Extra width required for conveyor allocation

Mine planning dedicated conveyor pit exit Truck Turning Circle Area Dedicated Conveyor Ramp at 15 degree angle Double Crusher Station Temp Haul @ 10% Road Ramp for Truck Access to Dump Pocket Area Crusher Station Relocation Access Area

Mine planning dedicated conveyor pit exit Using what geology gave you

Mine planning flexibility? you bet Conveyor distribution point, Hambach lignite mine, Germany per RWE

Mine planning IPCC dump designs Generic simplified radial dump layout

Mine planning IPCC dump designs Can be very high dump heights

Mine planning IPCC dump designs Waste dumping starting bottom-up dump

Mine planning IPCC dump designs IPCC dumps differ from truck waste dumps per: The location of the dump does not need to be immediately adjacent to the pit. With spreaders, there is no dump lift height restriction due to the risk of crest failure as a spreader can stand far back from the dump edge. Geotechnical investigation is still required of foundation, but also resized waste material. Leachates?

Outline Introduction IPCC basics Mine planning concepts for IPCC Guidelines for flexibility Conclusions

Guidelines to IPCC mine planning Key considerations in planning for all IPCC systems Material characteristics determination (UCS, fines, abrasiveness) Loading equipment matching to IPCC Operating hours of overall system Mining above IPCC ramp conveyors is generally not allowed; blasting adjacent to IPCC equipment to be reduced or eliminated Maximize size of push backs for: vertical bench advance, elbow room, pit exit conveyor on haul road Pit exit conveyors use footwalls or temporary walls to advantage; establish lowest accessible depth SMIPCC vs FMIPCC Dump construction generally not an issue unless construction is bottom up in which case consider truck built starter platforms or if no trucks, a viable sequence. Electricity supply; is it there?

Guidelines to IPCC mine planning Key considerations in planning for Semi-Mobile IPCC Elaborateness of crusher stations; <240t trucks vs. ultra class Blast design; multiple bench and pre-split blasting for crusher stations Crusher relocation planning; temporary ramps vs permanent ramps Vertical advance rate is constrained; though 8 benches per year are technically possible, 4 or less are preferred to reduce crusher relocations Ensure truck dump traffic flow allows for achieving expected crusher feed rates

Guidelines to IPCC mine planning Key considerations in planning Fully Mobile IPCC Minimum strip/bench conveyor length; balance maximizing IPCC usage vs. conveyor shifting and relocation delays Maximize IPCC mineable material by appropriate panel/strip configurations Multiple bench configurations; maximize benches served by a single bench conveyor datum (three bench operation optimal) Plan out box cut sequence, schedule accordingly; consider extra bench conveyor to minimize delays Plan out dump construction, particularly if bottom up and no trucks available

Outline Introduction IPCC basics Mine planning concepts for IPCC Guidelines for flexibility Conclusions

Conclusions IPCC means a whole new terminology and way to approach mine planning Cost savings and other benefits are substantial, while loss of flexibility is real There is no replacement for good planning to create a mine plan that builds in flexibility that is lost operationally IPCC is a new paradigm and transitioning to it is a significant change Ensure change management aspects are addressed, if not a full change management approach