Project Management Glossary



Similar documents
Appendix A of Project Management. Appendix Table of Contents REFERENCES...761

Scheduling Glossary Activity. A component of work performed during the course of a project.

Chapter 2: Project Time Management

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects

PMBOK GLOSSARY. Activity Duration Estimating. Estimating the number of work periods which will be needed to complete individual activities.

Goals of the Unit. spm adolfo villafiorita - introduction to software project management

Precedence Diagram Method. CSTM 462 Planning & Scheduling

Project Planning and Scheduling

Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014

Time Management. Part 5 Schedule Development. Richard Boser

Collaborative Scheduling using the CPM Method

Project Time Management

MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc.

CPM -100: Principles of Project Management

PROJECT TIME MANAGEMENT. 1 Powered by POeT Solvers Limited

Chapter-6. Developing a Project Plan

CPM-200: Principles of Schedule Management

Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

Project Time Management

Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc.

Chapter 6: Project Time Management

8. Project Time Management

Project Time Management

Chapter 4: Project Time Management

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

Operational Research. Project Menagement Method by CPM/ PERT

State of Michigan (SOM) August Department of Technology, Management & Budget

Dashboards and Reporting for Program Management

Featured Paper Satya Narayan Dash By Satya Narayan Dash, PMP, CSM, MCP

PROJECT TIME MANAGEMENT

Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration

CSC 443: IT Project Management Midterm 1 exam - Spring semester March 21 st, 2012

Scheduling. Anne Banks Pidduck Adapted from John Musser

Project Time Management

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza

Basic CPM Calculations

WORK PROGRAM GUIDELINES

The work breakdown structure can be illustrated in a block diagram:

Learning Objectives. Learning Objectives (continued) Importance of Project Schedules

Information Technology Project Management

Unit 4: Time Management (PMBOK Guide, Chapter 6)

Topics. Project plan development. The theme. Planning documents. Sections in a typical project plan. Maciaszek, Liong - PSE Chapter 4

Lecture 6: Project Time Management By: Prof. Lili Saghafi. Information Technology Project Management, Fifth Edition

PROJECT MANAGEMENT GLOSSARY OF TERMS

Project Time Management

The Project Planning Process Group

Module 3: The Project Planning Stage

Planning and Scheduling Your Project Using Microsoft Project 2003

Project Planning. Lecture Objectives. Basic Reasons for Planning. Planning. Project Planning and Control System. Planning Steps

Systems Analysis and Design

CRITICAL PATH METHOD (CPM) SCHEDULES

ME 407 Mechanical Engineering Design Spring 2016

專 案 管 理 實 務 嘉 義 縣 政 府 學 分 班 : 管 理 實 務 專 題 2006 中 正 大 學 企 管 系 助 理 教 授 周 瑞 生

PMI Lexicon of Project Management Terms

Introduction to Project Management

TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain *

PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM)

Procurement Management S# What? Formula Additional Notes CPPC CPFF CPAF CPIF T&M FPEPA FPAF FPIF FFP

Project Time Management Activity Definition Activity Sequencing Duration Estimating Schedule Development Schedule Control

Use project management tools

MC9252 SOFTWARE PROJECT MANAGEMENT UNIT I PART A

Chapter 6. (PMBOK Guide)

SE351a: Software Project & Process Management

SCHEDULING AND TIME MANAGEMENT. Project Management and Leadership 2015D, PhD, PMP

Project Management Institute (PMBOK 2000) PMP Preparation Worksheet

added to the task, using Project, it will automatically calculate the schedule each time a new resource is added.

Network Calculations

PROJECT SCHEDULING AND TRACKING

The Project In the beginning was The Project, and then arose the Assumptions.! And The Project was without form and the Assumptions were void.

IMCPM04 Project Scheduling and Cost Control. Course Outline

The Plan s Journey From Scope to WBS to Schedule

Object-Oriented Analysis. with the Unified Process. John W. Satzinger Southwest Missouri State University. Robert B. Jackson Brigham Young University

SYSTEMS ANALYSIS AND DESIGN DO NOT COPY

CISC 322 Software Architecture. Project Scheduling (PERT/CPM) Ahmed E. Hassan

Assignment 2: Microsoft Project Toolset. Eric Palmer & Mahindra Bheodari. Kennesaw State University. IS 8100 Spring 2015

As a result of the above inclusions and exclusions, this glossary includes:

Certification Exam Objectives: PK0-003

ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by

Unit 1: Project Planning and Scheduling

Synergy between PMBOK and MS Project 2007 A Schedule Management Perspective

Scheduling Best Practices

Project Management Dr. James A. Bednar

Cambridge International AS and A Level Computer Science

CSSE 372 Software Project Management: Software Project Scheduling

Chapter 3 Managing the Information Systems (IS) Project

Project Scheduling. Introduction

MECH 896 Professional Development for MEng Students. Homework Discussion. Scheduling Overview. Winter 2015: Lecture #5 Project Time Management

pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

Agenda. CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016

PMP Exam Preparation Answer Key

10.1 Communications Planning 10.2 Information Distribution Figure Performance Reporting 10.1 Communications Planning 10.

Abar Solutions Petroleum Consultancy & Training Qualified From KPC Training & Consulting Services Provider. Code Period Language Start End Location

Define Activities Sequence Activities Estimate Activity Resources Estimate Activity Durations Develop Schedule Control Schedule

Project Control. 1. Schedule Updating

Earned Value Analysis Exercise

technical tips and tricks

Project Management Guidebook

Transcription:

Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686

This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project Management with Microsoft Project 2003, which is available in bookstores January 2005. For additional tools, checklists, forms, and articles, or to subscribe to Ron s free Productivity PowerTools e-zine, go to www.ronblack.com.

1 GLOSSARY activity An element of work that must be accomplished to complete the project. Also known as a task. activity duration estimating Estimating the number of work periods needed to accomplish an activity. Activity-On-Arrow (AOA) A network diagramming method that uses arrows to represent activities. Activity-On-Node (AON) A network diagramming method that uses nodes or boxes to represent activities. Actual Cost of Work Performed (ACWP) The total of all costs incurred during a given time period. Actual Finish Date (AF) The date work on an activity was completed. Actual Start Date (AS) The date work actually started on an activity. administrative closure Formally closing the project in accordance with the organization s documentation procedures. arrow The link between tasks in a network diagram that shows the sequence of workflow. Arrow Diagramming Method (ADM) A network diagramming method in which activities are shown as arrows. as-of date The date the data was collected. backward pass Calculating the late finish dates and late start dates of activities by adding the duration of the successor task to the dependent task in a network diagram. side and activity durations are shown as a horizontal bar scaled to the length of the activity. Also known as a Gantt chart. baseline The scheduled dates, durations, resources, and costs according to the original plan, used to compare progress. baseline finish date The originally scheduled finish date. baseline start date The originally scheduled start date. Budget at Completion (BAC) The planned total cost of the finished project. Budgeted Cost of Work Performed (BCWP) The total value of activities actually completed within a given period according to the planned costs. Budgeted Cost of Work Scheduled (BCWS) The total value of activities as planned for a given period. calendar The methodology used to schedule workdays, shifts, resources, tasks, and the project as a whole. There are four calendar types in Microsoft Project: base, project, resource, and task. change in scope A change in the goals and objectives of the project after the project has been planned. chart of accounts An accounting numbering system used to relate project costs to the organization s financial control system. charter The responsibilities and authorities assigned to the project. contingencies An allowance set aside for potential problems to mitigate risk. bar chart A network diagram of activities where the tasks are listed down the left

2 contingency planning A planning technique used to identify and mitigate potential problems. control Measuring, evaluating, and taking action based on actual performance compared to the planned performance. cost estimating Estimating the total direct and indirect expenses required to achieve project activities. Cost Performance Index (CPI) Budgeted costs divided by actual costs (BCWP/ACWP). Sometimes used to predict the project s completed costs. Cost Variance (CV) The difference between actual and estimated costs of an activity. crashing Compressing the project s schedule through extraordinary means. Also known as expediting. critical activity Any activity that is part of the longest sequence of tasks from project start to project end. If the completion of a critical activity is delayed, the total duration of the project is delayed. critical path The series of tasks in a network diagram that requires the most time to complete. Activities on the critical path have zero slack or float. Critical Path Method (CPM) A project scheduling technique where the duration of the longest complete series of tasks from project start to project completion is used to predict project duration. Cross functional team A workgroup that embodies diverse professions, skills, or expertise. deliverable Any specific, measurable project accomplishment or outcome. dependency Term used to describe the relationship between two or more activities or tasks. See logical relationship. dummy activity A drafting convention used as a placeholder to show a logical relationship in a network diagram, but where no duration is planned. Duration (DU) The number of minutes, hours, weeks, or months required to complete an activity or task. Early Finish Date (EF) The earliest possible date an activity can be completed based on the schedule. Early Start Date (ES) The earliest possible date an activity can start based on the schedule. Earned Value (EV) The total cost of work calculated by comparing planned work for a period against actual work accomplished. effort The amount of work units needed to complete an activity. estimate A forecast of cost or duration for an activity. Estimate at Completion (EAC) The expected total cost of an activity or project when finished. Estimate to Complete (ETC) The expected additional cost needed to complete an activity or project. Event-on-Node A network diagramming technique in which activities are shown as nodes or boxes and workflow logic is shown with arrows. The original Program Evaluation and Review Technique used event-on-node to diagram workflow. expediting Shortening the duration of a task or project by any means available. Usually increases costs. Also known as crashing. fast tracking Compressing a project s schedule by running tasks in parallel that are normally run in sequence, such as

3 beginning construction before design is complete. Usually increases risk. finish date The actual, planned, estimated, early, or late date an activity is to be completed. Finish-to-Finish (FF) The workflow logic between two tasks in which the dependent task may not finish until its predecessor task is finished. Finish-to-Start (FS) The workflow logic between two tasks in which the dependent task may not start until its predecessor task is finished. float The amount of time a task may be delayed without pushing out the project finish date. Also called slack. forward pass The calculation of the early start and early finish dates of all activities in the network diagram. Free Float (FF) The amount of time a task can be delayed without pushing out the start of any immediately following activities. Also called free slack. Free Slack See free float. Gantt Chart A network diagram of activities in which the tasks are listed down the left side and durations are shown as a horizontal bar scaled to the length of the activity. lag Describes the delay of a successor task from its predecessor s start or finish. See also lead. Late Finish Date (LF) The latest a task may finish without delaying the project s finish date. Late Start Date (LS) The latest a task may begin without delaying the project finish date. lead Describes the advance of a successor task s start from its predecessor s start or finish. See also lag. leveling The process of effectively allocating resources to tasks. link The arrow that shows the logical work sequence relationship between tasks. logic The workflow sequence. logic diagram A project s network diagram. logical relationship The workflow logic between two project tasks or activities (the predecessor and the dependent tasks) described as a finish-to-start, finish-tofinish, start-to-finish, or start-to-start relationship. Also know as dependency. milestone A point in the network diagram that shows significant accomplishment. monitoring Collecting progress information for judging progress against the plan. network diagram A diagram showing the workflow sequence of all tasks required to complete a project. network logic The workflow sequence as shown by a network diagram. network path Any series of tasks in a network diagram. overlap The concurrent period of time two or more parallel tasks share. See lead, lag, and parallel task. noncritical task Any task or activity that does not fall on the longest (critical) path. Over-allocation The condition having of too much work for the available resource capacity.

4 parallel task A task undertaken during the same time period as another task. path A series of activities in a network diagram. path float See float. Percent Complete (PC) Estimate of progress derived by comparing the amount of work completed with the amount of work planned for an activity or project. PERT Chart A critical path scheduling method using an activity-on-node network diagram and the Program Evaluation and Review Technique of weighted average duration estimates. phase A major subunit of a project s work or set of project deliverables. Planned Finish Date (PF) The scheduled finish date of the project. Planned Start Date (PS) The scheduled start date of the project. precedence relationship The description of two or more task s workflow sequence. predecessor activity The task which immediately precedes the dependent task. program A group of projects that are related and managed in a cohesive way. Program Evaluation and Review Technique (PERT) A critical path method of scheduling a project using the weighted average method to estimate durations. project The implementation of a strategy to create a specific, measurable outcome. project charter The document that authorizes a project manager to use the organization s resources and outlines the intended outcomes of the project. project management The process of undertaking and completing a course of action to meet the stated goals and objectives of an endeavor. Project Manager (PM) The person responsible for planning and implementing the project. Remaining Duration (RDU) The amount of time required to complete a task. Request for Proposal (RFP) A solicitation for proposals from potential vendors for good or services. Request for Quotation (RFQ) A solicitation for quotations from vendors for goods or services. resource leveling Applying available resources to a project to determine task start and finish dates, project duration, and resource utilization rates. resource planning Estimating the people, equipment, and material resources required to complete a project. resources All the people, equipment, materials, and money required to complete a project. risk assessment Evaluating potential risks and their affect on the project. S-Curve The graph of cumulative project expenditures plotted against time. Schedule Performance Index (SPI) The work performed compared to the work scheduled (BCWP/BCWS). Schedule Variance (SV) The actual versus the planned cost, duration, work, or percentage complete of an activity. Scheduled Finish Date (SF) The date the task was to be completed according to the plan.

5 Scheduled Start Date (SS) The date the task was to be started according to the plan. scope The description of the project s intended breadth and depth. scope change Alterations in the project s goals or objectives at any time after the project has been initiated. slack The amount of time a task or path can slip without causing the project to finish late. See float. slope The dependent variables that describe the change in cost and duration when expediting (crashing) a task. Used to compare alternate methods and calculate the total costs required to shorten a project s duration. start date The actual, planned, early, late, or baseline date a task is scheduled to start. Start-to-Finish (SF) The workflow logic between two tasks where the dependent task may not finish until its predecessor task has started. Start-to-Start (SS) The workflow logic between two tasks where the dependent task may not start until its predecessor task has started. successor activity The activity that follows a predecessor activity. target schedule The baseline schedule. Target Finish Date The baseline date work is scheduled to finish. Target Start Date The baseline date work is scheduled to start. task An element of work which must be accomplished to complete the project. Also known as an activity. Total Float (TF) The amount of time a task or path can be delayed without delaying the completion of the project. triple constraints The interrelationship of a project s time, cost, and performance elements. Understanding their relative importance facilitates decision making and problem solving. Usually described as a driver, middle, and weak constraint. Under-allocation The condition having of too much resource capacity for the available work. Work Breakdown Structure (WBS) The decomposition of the project s goals and objectives into increasingly detailed units of work, eventually identifying all tasks that are essential to the project s successful completion. ABOUT RON BLACK Throughout 30 years of business leadership experience, Ron has built a reputation for delivering down-to-earth, results-proven content in all he does. As a business consultant, author, and award-winning speaker, he works with top managers who want to move their organizations to new levels of performance and entrepreneurs launching new products and services. POPULAR TOPICS Project Management Fundamentals The Elements of Success Acrobatics for Overachievers The Art and Science of Managing Multiple Projects and Priorities Tools of Change: People and Process the Essentials of Managing Change Managing Projects the Easy Way with Microsoft Project Creating an Environment for Project Success Executive Briefing Building the Championship Team Workshop for Leaders

Ron Black The Mentor Group www.ronblack.com ronblack@thementorgroup.com 503-618-8703 800-381-8686 toll-free in USA