SUBJECT: Concourse A, B and C Carpet Replacement project at Seattle-Tacoma International Airport (CIP #C800766)



Similar documents
PORT OF SEATTLE MEMORANDUM. COMMISSION AGENDA Item No. 5c ACTION ITEM Date of Meeting April 1, 2014

PORT OF SEATTLE MEMORANDUM. COMMISSION AGENDA Item No. 6a ACTION ITEM Date of Meeting January 6, 2015

PORT OF SEATTLE MEMORANDUM. COMMISSION AGENDA Item No. 6e ACTION ITEM Date of Meeting January 12, 2016

Development Fund; 18.3% General Fund; 5.2% General Fund Real Estate Est. State and Local Taxes: $9,000

PORT OF SEATTLE MEMORANDUM. COMMISSION AGENDA Item No. 4d ACTION ITEM Date of Meeting September 8, 2015

PORT OF SEATTLE MEMORANDUM. COMMISSION AGENDA Item No. 4g ACTION ITEM Date of Meeting November 10, 2015

Draft Plan of Finance

P.O. Box 1209 Seattle, Washington

PORT OF SEATTLE MEMORANDUM. COMMISSION AGENDA Item No. 6a ACTION ITEM Date of Meeting February 9, 2016

How to Estimate the Cost of Interior Building Finishes from Schematic Drawings. CPE Candidate No December 2014

P.O. Box 1209 Seattle, Washington

FRAConnect Incentive program

Chapter 12. Introduction to Value Determination

Finish Floor System Analysis

Flooring materials life-cycle costing for educational facilities

Review of Janitorial Services Contract at the Fort Lauderdale-Hollywood International Airport (RLI # AV-2)

Dubai International Airport

Finnair Q2 result info

MARQUETTE UNIVERSITY: McCabe Hall

COMMERCIAL AND GENERAL AVIATION

Tennessee s Facility Management Outsourcing State of Tennessee Department of General Services

Swedavia s Airport Charges 2016

PORT OF SEATTLE MEMORANDUM. COMMISSION AGENDA Item No. 6e ACTION ITEM Date of Meeting November 24, 2015

what are the main things you should know about deductible insurance

Broward County. Aviation Industry Edition. Source: Florida Department of Economic Opportunity, Bureau of Labor Market Statistics

Finnair Q1 result info

Current and Forecast Demand

June 1, 2016 LAGUARDIA CENTRAL FACT SHEET About the Project

Jeremy Webb, Aviation Environmental Programs Seattle-Tacoma International Airport. Airports Going Green Conference Hosted by AAAE/CDA October 31, 2011

Australian Edition. Redbook Carpets with total technology are proudly supplied by: Feltex Carpets Pty Ltd ABN:

2016 Performance Measures

Existing Facilities. Current and Forecast Demand

(The approximate point in the audio recording for the specific item is identified by minutes and seconds; example: 01:30)

GRADE A HEADQUARTER OFFICE BUILDING, LEEDS

Date: 10/10/2014 Initiated by: AAS-100

Design a learning environment that helps me reach my potential.

Economic Development Division Business Plan. Overview

FNB HOME BUYING ESTATE AGENT SURVEY 4 th QUARTER 2012

Airport Performance Measurement

Mold Treatment & Remediation. Introduction

SEATAC FUEL FACILITIES LLC

Airport preparedness guidelines for outbreaks of communicable disease

2012 King County Metro Transit Peer Agency Comparison on Performance Measures

Third Runway is Key to Hong Kong s Competitiveness. Professor Anthony Cheung Bing-leung Secretary for Transport and Housing

Best Average SIC Worst

General Terms and Conditions FRA Comfort Services and My Airport Guide Services Available from the Service Shop of Fraport AG

31289 ADOPTED BOARD OF TRUSTEES COMMUNITY COLLEGE DISTRICT NO. 508 JANUARY, , 2012

Outline. Owner Perspective CM Definition Working Relationships Why CM? Project Approach Pre-construction Construction. Iowa League of Cities // 2011

Academy teachers and Industry Partner staff jointly developed and facilitate the programme.

City of Toledo Bid Sheet

What is driving Australians' travel choices?

Public Works and Transportation Bus Service Hub Terminal HVAC, Canopy, AVL Sign Equipment

June Service Quality Performance Report 2014

THE CONFERENCE CENTER

Airports Architectural Design Solutions and New Design Technologies

You Said, We Did! Quarter 2 (2013/14)

Tripp Umbach developed a detailed survey with input from the PDP and distributed the survey to six Downtown Pittsburgh market segments:

Art-in-Architecture. R e q u e s t f o r Q u a l i f i c a t i o n s. Southern Illinois University Transportation Education Center

Information Bulletin No. 4 What happens over the life of a building?

Fatigue: The Flight Attendant Perspective

Strong First Half-Year 2016 Leads to Significant Earnings Improvement for the Flughafen Wien Group

Airport IT Services for Airlines. Kiel Barnekov, Manager Programs & Projects Greater Orlando Aviation Authority

ASTCCR2 - SQA Unit Code H Carry out and complete clean-room cleaning operations

AVAILABLE SEE INSIDE FOR MORE INFORMATION! PREMIUM OFFICE/RETAIL SPACE IN DOWNTOWN BREVARD! FRENCH BROAD PLACE CONDOMINIUMS BREVARD NC

Air Traffic Management Services Plan

RUBBERMAID COMMERCIAL PRODUCTS LLC s Cleaning Team conducted 3 rd Party Testing of their Wet Mop Microfiber Pads along with five competitor s Pads.

P.O. Box 1209 Seattle, Washington www. portseattle.org

Bid Tabulation for IFB #9708 (Asbestos and Mold Abatement Services)

Definition of a Lease

Introduction to Asset Management. Presented by: John J. Jackman, P.E. Associate - Asset Management Specialist

Media Guidelines 2016

ENTRANCE MATS & GRIDS

2014/15 Performance Measures and Targets

How To Get A Warranty From Shaw Industries

HAMAD INTERNATIONAL AIRPORT (RESTRICTED AREAS) REGULATIONS 2015

Fiscal Year 2015 Quarter 4 April - June 2015 Stephanie Pollack Secretary & CEO

END TO END AIRPORT. PASSENGER ANALYTICS November 9, 2015

EASYJET TRADING STATEMENT FOR THE QUARTER ENDED 30 JUNE 2015

Website. King County Council District # WA State Legislative District # Date Incorporated. Federal Tax ID. WA State UBI#

Vendor Selection Overview UNIT PRICES FOR ASBESTOS ABATEMENT & DISPOSAL SERVICES VARIOUS SITES

PRESTON A REGIONAL SERVICE CENTRE

Professional Property Management TREC 4507

What is Reliability Centered Maintenance? A Brief History of RCM

General Guidelines for Building Aluminum Production Injection Molds

Visual guidelines for student charges

PK-12 Public Educational Facilities Master Plan Evaluation Guide

SECTION POLISHED CONCRETE FINISHING

Soft FM Services Framework

Network Rail Consultation on Draft West Coast Main Line Route Utilisation Strategy Consultation Response by Birmingham International Airport Limited

Slips, Trips, and Falls

(The approximate point in the audio recording for the specific item is identified by hours, minutes, and seconds; example: 00:01:30)

Escalator incidents occur frequently at airports (some airports experience several per month).

Aerodrome Advisory Circular

Shaw Limited Lifetime Stain Warranty

Executive Flight Office & Hangar

Norwegian UK set to takeoff as airline is granted UK Air Operating License

Thin Whitetopping Application at Williamsburg Regional Airport and Other Thin Whitetopping Airport Applications.

Love Field Modernization Program (LFMP) & Airport Electronic Systems Management (AESM) Status Update

Massport, Delta & Terminal A. Presented by Betsy Taylor May 21, 2007

C. Clipping Report Media: Al Bayan Date: 05 June 2015 Genre: Circulation: 88,800 Page : 27 cc

Transcription:

PORT OF SEATTLE MEMORANDUM COMMISSION AGENDA Item No. 4d ACTION ITEM Date of Meeting May 17, 2016 DATE: TO: FROM: Wayne Grotheer, Director, Aviation Project Management Group Michael Ehl, Director, Aviation Operations SUBJECT: Concourse A, B and C Carpet Replacement project at Seattle-Tacoma International Airport (CIP #C800766) Amount of This Request: $3,636,000 Source of Funds: Airport Development Est. Total Project Cost: $3,661,000 Fund Est. State and Local Taxes: $247,000 ACTION REQUESTED Request a single Commission authorization for the Chief Executive Officer to: 1) proceed with design of carpet replacement on Concourses A, B and C; and 2) advertise and execute a construction contract to install carpet on Concourses A, B and C; and 3) authorize the use of Port Crews to assist in construction activities for the project. This single authorization is for $3,636,000 of a total estimated project cost of $3,661,000. SYNOPSIS The carpeting in the gate hold rooms in Concourses A, B and C has become so unsightly that our airline customers have requested that it be replaced as soon as possible. This customer driven urgency is the reason for the single authorization request for both design and construction. This project will remove the existing carpet on concourse A, B and C and replace it with a carpet tile system. The existing roll carpet was installed in the concourses in 2004 and 2005. It is worn and unsightly and in need of replacement. BACKGROUND Concourse A was constructed and opened to the public in 2004. Carpeting on Concourses B and C was installed in 2005 to match that installed in Concourse A. The service life expectancy of carpet is typically 5-7 years and the carpeting on these concourses has already exceeded this expectancy. Replacing carpeting in the aircraft gate hold rooms with terrazzo was an alternative that was evaluated but not determined to be the preferred alternative. Terrazzo is a hard surface material that is very wear resistant and an excellent choice for high traffic areas of the airport, like Template revised May 30, 2013.

Page 2 of 5 concourse circulation corridors. However it is not suitable for all locations. Not only is terrazzo a more expensive material to install (roughly five times more expensive than carpet alternatives), it requires a longer and more invasive installation method, with each location barricaded and separately ventilated. Further, as a hard material, it can introduce acoustic reflectivity problems creating a very noisy environment that would negatively impact customer experience. PROJECT JUSTIFICATION AND DETAILS The current rolled carpet was installed on Concourse A in 2004; the carpet on Concourses B and C was installed in 2005. The aging carpet is worn and badly stained in many areas. Our airline customers have requested that we replace all the carpet in hold room areas as soon as possible. Replacing the carpet with carpet tile will greatly improve the aesthetics of the concourses while providing a better option for replacing stained or damaged areas of carpet in the future as the individual tiles can be quickly replaced if needed. Project Objectives Improve the declining tenant and customer satisfaction and feedback related to the look and feel, of the departure experience in the hold rooms of Concourses A, B and C. Scope of Work The project will remove and replace carpeting on Concourses A, B and C and repair any adjoining terrazzo areas that may be damaged during installation. The project will also remove two payphone banks on Concourse A while preserving the floor power currently servicing these units to provide power, to future hold room seating that will to be installed later under a separate future project. Schedule Commission Authorization for Design and Construction 2nd Quarter 2016 Advertise for Construction Bids 3rd Quarter 2016 Construction Complete 1st Quarter 2017 FINANCIAL IMPLICATIONS Budget/Authorization Summary Capital Expense Total Project Original Budget $2,000,000 $0 $2,000,000 Budget Increase $1,661,000 $0 $1,661,000 Revised Budget 3,661,000 $0 $3,661,000 Previous Authorizations $25,000 $0 $25,000 Current request for authorization $3,636,000 $0 $3,636,000 Total Authorizations, including this request $3,661,000 $0 $3,661,000 Remaining budget to be authorized $0 $0 $0 Total Estimated Project Cost $3,661,000 $0 $3,661,000

Page 3 of 5 Project Cost Breakdown This Request Total Project Design Phase $814,000 $814,000 Construction Phase $2,600,000 $2,600,000 State & Local Taxes (estimated) $247,000 $247,000 Total $3,661,000 $3,661,000 Budget Status and Source of Funds This project, CIP #C8007666 was included in the 2016-2020 capital budget and plan of finance with a budget of $2,000,000. The scope and budget were increased to include Concourse A. The budget increase will be transferred from the Aeronautical Allowances CIP (C800404). The funding source of will be Airport Development Fund. Financial Analysis and Summary CIP Category Renewal/Enhancement Project Type Renewal & Replacement Risk adjusted discount rate N/A Key risk factors N/A Project cost for analysis $3,661,000 Business Unit (BU) Terminal Effect on business performance NOI after depreciation will increase IRR/NPV N/A CPE Impact CPE $.02 in 2018 Lifecycle Cost and Savings The proposed carpet tile system is not expected to have significant repair costs in the first 5 years. Preventative maintenance costs will be consistent with the current maintenance program. The average life expectancy for carpet in public areas of the airport is 6-7 years. STRATEGIES AND OBJECTIVES This project supports the Century Agenda strategy of advancing this region as a leading tourism destination and business gateway by providing targeted improvements to the hold rooms of Concourse A, B and C. Improving airport conditions such as carpeting will improve the passenger perceptions of Sea-Tac and help us reach a key goal of the Century Agenda to be the west coast gateway of choice for international travel. This project also supports the Aviation Division strategy to become one of the top customer service airports in the world. The style and perceived cleanliness of carpet in hold rooms (where dwell time is often significant) contributes to the quality of the overall passenger experience in the terminal.

Page 4 of 5 This project supports the Century Agenda strategy to be the greenest Port in North America by recycling the existing carpet material to the extent feasible. In addition, the project will install new carpet containing recycled materials and will minimizing the use of volatile organic compound containing materials. Elements of the scope of work associated with the construction and installation of the new carpet tile system support the utilization of small business to participate on this project. ALTERNATIVES AND IMPLICATIONS CONSIDERED Alternative 1 Status Quo Do not replace the carpet at this time. While the carpet does need to be replaced, it could be deferred for one or two years. Capital Cost: $0 in 2016, but $3.636 million plus escalation in either 2017 or 2018. No capital investment. Retaining the existing carpet will require continued maintenance, likely on a more frequent basis, as the carpeting continues to deteriorate. The carpet on Concourses A, B and C is 10 years old, worn stained and unsightly. This alternative perpetuates an impression that our hold rooms are dirty. This alternative does not respond to airline customers requests to replace carpet Alternative 2 Replace Carpet with In-Kind Roll Carpet Cost Implications: $3,771,000.00 [carpet $12.25 per square foot] Old stained carpet is replaced with new in-kind roll carpet greatly improving the aesthetics of the concourse. A slightly quicker installation process than carpet tile (Alternative 4) Requires a capital investment Slightly higher cost per square foot than carpet tile system (Alternative 4) When patched, the patched areas can be difficult to match up with the surrounding pattern and can also fray easily. Left over carpet for future repairs (called attic stock ) in rolls is bulky and more challenging to store than carpet tile that is typically delivered in smaller boxes.

Page 5 of 5 Alternative 3 Replace Carpet on Concourse A, B, and C with Terrazzo Cost Implications: $15,000,000 [Approximately $54 per square foot] Old stained carpet is replaced with terrazzo greatly improving the aesthetics of the concourse. Terrazzo flooring system provides a more permanent and durable solution than carpet. Terrazzo requires a significantly higher capital investment than carpet alternatives. Installing terrazzo on Concourse A, B and C would add more than a year to the project. Installation would require each site to be isolated from the public and separately ventilated. Terrazzo s hard surfaces reflect sound while carpeting s soft surfaces absorb sound. Replacing carpeting with terrazzo increases the acoustic reflectivity making gate hold rooms very noisy. Alternative 4 Replace Carpet on Concourse A, B, and C with Carpet Tile System Cost Implications: $3,661,000.00 [carpet $12.19 per square foot] Slightly lower cost per square foot than roll carpet alternative Old stained carpet is replaced with carpet tile system greatly improving the aesthetics of the concourse. Carpet tile system provides better solution for replacing stained or damage areas of carpet in the future as stained tiles can be quickly replaced and cleaned. Attic stock is easier to maintain than rolled carpet. This option requires a capital investment Installation can be slower than a rolled carpet alternative This is the recommended alternative. ATTACHMENTS TO THIS REQUEST Slide presentation of examples of existing carpet conditions. PREVIOUS COMMISSION ACTIONS OR BRIEFINGS None