A guide to reactive power



Similar documents
Electricity prices explained

e-factsheet Feed-in Tariffs what we have to offer

Electricity Market Reform

Fixed + Protect Electricity supply contracts explained for large business customers

Fixed + Peace of Mind Electricity supply contracts explained for large business customers

e-guide Value Added Tax and Climate Change Levy explained

Fixed + Protect Electricity supply contracts explained for large business customers

Power factor correction. An introduction to technology and techniques

Understanding Power Flow and Naming Conventions In Bi-directional Metering Applications

Explaining How Voltage Optimisation Can Save Energy and Protect Your Site

Electricity Terminology. Simplifying energy management

UTILITY RATE STRUCTURE

factor max Delivering Electrical Efficiency INFORMATION PACK factor max

Commercial Use Tariffs. Codes 15, 16, 17, 60, 61, 62, 63, 64 and 66

Safe as houses. What to expect when someone from EDF Energy calls at your home

Metering for today s systems

Understanding Power Factor and How it Affects Your Electric Bill. Presented by Scott Peele PE

Electric Rate Book Revision: 13 ( ) Page No. 1 Effective date: SMALL COMMERCIAL

7. Reactive energy compensation

Statement of Charges for Use of Energetics Electricity Ltd s Distribution System

Power Factor The Basics

Guide to using Prepayment Meters for Gas and Electricity

A guide to. Using your prepayment meter

[DNO LOGO] SP MANWEB PLC. Use of System Charging Statement SP MANWEB PLC NOTICE OF CHARGES. Effective from. 1st April 2016 to 31st March 2017

How To Get A Better Deal On Power From Powerline Power From Pse

A guide to our. Priority Services and ways we can help you manage your energy

Voltage optimisation Reducing energy, saving money

The standards you can expect

NOTES ON AURORA LINE CHARGES FOR NETWORK DESIGNERS, CONSULTANTS AND ELECTRICAL CONTRACTORS

User Manual V SDM220MODBUS. Single-Phase Two Module DIN rail Meters

APPLICATION FOR AN ELECTRICITY CONNECTION (PROJECTS)

Design Guide. Managing Peak Energy Demand In Live Performance Venues

Improvement of Power Factor for Industrial Plant with Automatic Capacitor Bank

Energy Toolkit Surgery. Utility Bills. Sustainability Team. March Philip Pike Energy Manager

Energy Display Meter User Guide Engage, educate and inspire smart energy usage

NORTHERN IRELAND ELECTRICITY Ltd STATEMENT OF CHARGES FOR USE OF. THE NORTHERN IRELAND ELECTRICITY Ltd ELECTRICITY DISTRIBUTION SYSTEM

GO ENERGY SHOPPING GUIDE

STATEMENT OF CHARGES FOR USE OF SP MANWEB s ELECTRICITY DISTRIBUTION NETWORK

HOW HARMONICS HAVE CONTRIBUTED TO MANY POWER FACTOR MISCONCEPTIONS

Newfoundland and Labrador Hydro Electricity Rates

Section 5 Electricity

INTRODUCTION Tariff Objective Factors

ONS Methodology Working Paper Series No 6. Analysing low electricity consumption using DECC data

Energy Price Fact Sheet

Technical Paper E1 (a) Energy Consumption in Cornwall. Cornwall Council January N.B. This is a live document that will be updated.

STATEMENT OF CHARGING METHODOLOGY FOR USE OF ELECTRICITY NORTH WEST LIMITED S ELECTRICITY DISTRIBUTION NETWORK

POWER FACTOR CORRECTION

Jemena Electricity Networks (VIC) Ltd - Network Tariffs For The 2015 Calendar Year (Exclusive of GST)

SSE s criteria used for GHG emissions reporting

SALT RIVER PROJECT AGRICULTURAL IMPROVEMENT AND POWER DISTRICT E-33 EXPERIMENTAL PRICE PLAN FOR SUPER PEAK TIME-OF-USE GENERAL SERVICE

Online Fixed Energy A Guaranteed Deal

Houston Power Services Company Power Factor Correction Sales and Service. Energy Management for Today s Commercial and Industrial Customer

How to monitor your energy use

Online Investments. Our Fund Range and Investments

South East Region Leakage Code of Practice. Affinity Water Limited CODE OF PRACTICE ON LEAKAGE

EDF Energy customers won't wait to benefit from Government action on energy charges

At Load Power Factor Correction Phase 2: Refrigerated Vending Machines

REAL TIME PRICING - HOUR AHEAD SCHEDULE: RTP-HA-5

Domestic Use Tariffs. Codes 05, 06, 07 and 08

red zone management white paper Making the most of Distribution Use of System (DUoS) Charges

Chapter L Power factor correction and harmonic filtering

I USE OF SYSTEM CHARGES EFFECTIVE FROM 1 APRIL 2015

Large Power -Secondary 46,50,51 Monthly Charge $ All kwh All kw 18.50

Energy saving technology to deliver the fastest returns. Top 10 energy saving options

AREVA's Energy Storage Solutions

Starting Current Reduction of Residential HVAC System and Peak-Load Impact of Power System: A Case Study

Your guide to the Energy Company Obligation (ECO) How we can make it work for you. A5_ECOguide_AW.indd 2 24/10/ :04

Energy Cost Reduction through Load Balancing & Load Shedding

Guideline for Energy Efficient Electrical systems for building. Presentation by TERI

Reactive Power and Importance to Bulk Power System OAK RIDGE NATIONAL LABORATORY ENGINEERING SCIENCE & TECHNOLOGY DIVISION

EDF Energy s Deemed tariff

AC Power. by Prof. Dr. Osman SEVAİOĞLU Electrical and Electronics Engineering Department

ENJOY LOWER PRICES FOR YOUR ELECTRICITY AT NIGHT AND WEEKENDS

Carbon Footprint Calculator for Royal Society of Arts

Energy Saving systems for Induction motors.

El Paso Electric Company

Competition in British household energy supply markets

Motor Efficiency and Power Factor ME 416/516

Commonly asked Question about Green Power, and Kit Carson Renewable Energy Program.

Power Factor Correction - The Easiest, Biggest, Green Initiative

Welcome to Smart Pay As You Go

Energy Tariffs and Associated Charges

Professional indemnity section only Summary of cover

SA Power Networks Network Tariffs - Residential APPLIES TO USAGE FROM 1 JULY 2015

Sample Bill. Understanding Large Commercial Electric Bills. White Paper #22. Demand-Based Time of Use Electric Rates Have Some Unique Terms

ENERGY-SAVINg DRIVE PACKAGE DE ES FR IT. Overview

Simple Methods for Calculating Short Circuit Current Without a Computer By Dennis McKeown, PE GE Senior System Application Engineer

Transcription:

e-guide A guide to reactive power For large business customers

2/5 Changing energy prices explained What is reactive power and how is it measured? Reactive Power (kvarh) is the difference between working power (active power measured in kw) and total power consumed (apparent power measured in kva). Some electrical equipment used in industrial and commercial buildings requires an amount of reactive power in addition to active power in order to work effectively. Reactive power therefore generates the magnetic fields which are essential for inductive electrical equipment to operate - especially transformers and motors. This load is measured via the reactive register on your half hourly meter. What is Power Factor and how is it caused? Power Factor is the relationship between active and reactive power and indicates how effectively electrical power is being used: Bad power factor - is low (less than 0.95) so more reactive power is required. Good power factor - is high (greater than 0.95) so power is used more effectively. Perfect power factor - (1.0) this is known as unity and does not use any reactive power. Most electrical equipment, such as motors, compressors, welding sets and even fluorescent lighting, create an inductive load on the supply. An inductive load requires a magnetic field to operate, which then causes the electrical current to lag the voltage - i.e. the current is not in phase with the voltage. How is Reactive Power charged? Reactive power is charged according to the accumulated volume on your reactive register. These charges will also vary depending on two elements: 1. Contract type 2. Local Network Operator charging methodology Contract type If you have a fully inclusive contract, you will pay the rate which you agreed to on your contract. If you have an energy only (supply only) contract, you will pay the rate which has been passed through from your Local Network Operator; which may change if they alter their charging methodology. Local Network Operator charging methodology Local Network Operator charging steps differ depending on the location of your site in Great Britain and who serves your network (*see table). Where the first step excludes a percentage figure, the currently charge for reactive power. Where the first step is 33%, the

3/5 charge for reactive power for the first 33% of units (kwh). Charges therefore apply when the difference between the total units recorded on the reactive register (kvarh) is less than 33% of the total units consumed (kwh). Where the first step is 50%, the charge for reactive power for the first 50% of units (kwh). Charges therefore apply when the difference between the total units recorded on the reactive register (kvarh) is less than 50% of the total units consumed (kwh). For example: Where a meter consumes 2,500 kwh and 2,000 kvarh, reactive charges would be applied on 1,175 units if the charging step was 33% or 750 units if the charging step was 50%: 33% charging step 2,500 kwh x 33% = 825 units 2,000 kvarh 825 = 1,175 chargeable units 50% charging step 2,500 kwh x 50% = 1,250 units 2,000 kvarh 1,250 = 750 chargeable units How will this be shown on my bill? If reactive power charges are applicable for your site, they will appear within the Consumption charges section of your bill, specifically: MPAN Local Network Operator 1st step 2nd step 10 UK Power Networks 33% 90% 11 Central Networks 33% - 12 UK Power Networks 33% 90% 13 Scottish Power 33% - 14 Central Networks 33% - 15 CE Electric UK - - 16 United Utilities 33% - 17 Scottish & Southern Energy - - 18 Scottish Power 33% - 19 UK Power Networks 33% 90% 20 Scottish & Southern Energy 21 Western Power Distribution 22 Western Power Distribution - - 50% - 50% - 23 CE Electric UK - - How will this be shown on my bill? If reactive power charges are applicable for your site, they will appear within the Consumption charges section of your bill, specifically: Reactive power charge Price per unit Total units Amount ( ) XXX XXX XXX From 1st July 2008, you may also notice some additional lines which reconcile and adjust for differences between previous reactive power units billed and units charged from your Local Network Operator. This will be shown as follows, for example: Reactive power charge adjustment for 30 June 08 Price per unit Total units Amount ( ) XXX XXX XXX

4/5 What can I do to avoid reactive power charges? To avoid reactive power charges, you can install Power Factor Correction equipment. If you are interested in a quotation to install this equipment, please contact our expert: Andrew Morphew andrew.morphew@edfenergy.com

5/5 e-factsheet- a better way of working Why an e-factsheet? At EDF Energy we are committed to using the most sustainable working practices wherever possible and this includes when delivering communications to our customers. E-factsheets significantly reduce the volume of printed material we need, reducing our carbon footprint. Our customers appreciate e-factsheets because they offer timely delivery of easy to access information in an ideal format for the modern screen based working environment. edfenergy.com/largebusiness To view our fuel mix visit edfenergy.com EDF Energy Customers plc with registered number 2228297. EDF Energy 1 Limited with registered number 3986835. Registered offices at 40 Grosvenor Place, Victoria, London, SW1X 7EN. Incorporated in England and Wales. EDF Energy 1 Limited acts as agent of EDF Energy Customers plc for the purposes of collecting all payments in connection with its supply contracts. The responsibility for performance of supply obligations rests with EDF Energy Customers plc.