CIVIL ENGINEERING Vol. II - Underground Mining Methods and Equipment - S. Okubo and J. Yamatomi UNDERGROUND MINING METHODS AND EQUIPMENT



Similar documents
CIVIL ENGINEERING Vol. II - Surface Mining Methods and Equipment - J. Yamatomi and S. Okubo SURFACE MINING METHODS AND EQUIPMENT

Types of Mining - Expert Table

By Gene Kitts, Senior Vice President-Mining Services, International Coal Group, Inc.

SECTION 10 SHRINKAGE METHODS

Mining with Paste Fill

Backfill for Bench Stoping Operations

THE PROVISIONAL CENTRAL PRODUCT CLASSIFICATION

WHAT YOU NEED TO KNOW ABOUT LIVING NEAR INDIANA COAL MINES

Accounting for stripping costs in the production phase costs of waste removal and the associated benefit

ABANDONMENT COST, FINANCIAL ASSURANCE AND PRESENTATION OF THE DOCUMENT. Abandonment cost :

Nuevas tendencias de la Minería Subterránea profunda Planeación, operación y estabilización del macizo rocoso

Trenching and Excavation Safety

ANNEX D1 BASIC CONSIDERATIONS FOR REVIEWING STUDIES IN THE DETAILED RISK ASSESSMENT FOR SAFETY

CIM DEFINITION STANDARDS - For Mineral Resources and Mineral Reserves

REQUIREMENTS FOR REGISTRATION AS A PROFESSIONAL ENGINEER WITH THE PROFESSIONAL ENGINEERS BOARD SINGAPORE

Stefan Sjöström, SEABB, PAPI UGM Automation ABB Underground mining Mobile Integration. ABB Group May 18, 2015 Slide 1 3BSE

Rainwater Harvesting

Patrik Westerlund & Marcello Sanchez, SEABB, PAPI UGM Automation ABB Underground mining Mobile Integration

vacon ac drives for mining & minerals

GPS BASED TRUCK DISPATCH SYSTEM (TDS) IN HIGHLY MECHANIZED BAUXITE MINES A CASE STUDY.

There is no water, surface tension cracks, nor other environmental conditions present that reduce the stability of the excavation.

ARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R Lecturer: Jim Cahill

Iron Ore Processing for the Blast Furnace (Courtesy of the National Steel Pellet Company)

Elevating Your House. Introduction CHAPTER 5

Candelaria and Ojos del Salado Chile

SECTION EARTH MOVING

Information Technology Career Path Overview

Savannah North Scoping Study Looking into the future 3 February 2016

How To Retaining Wall Guide

PVC PIPE PERFORMANCE FACTORS

Continental Gold Announces a Positive Preliminary Economic Assessment for the Buriticá Project

San Antonio Water System Standard Specifications for Construction ITEM NO POINT REPAIRS AND OBSTRUCTION REMOVALS

Exploration. Exploration methods

Establishing the feasibility of your proposed mining venture

Safety trends in mining

GUIDANCE FOR CARRYING OUT RISK ASSESSMENT SURFACE MINING OPERATIONS

Safe & Sound Bridge Terminology

Proposed Minimum Subterranean Termite Treatment Standards

Advanced Natural Gas Storage (ANGAS) Project and Verification Tests of Experimental Lined Rock Cavern in Japan

(1) Discuss the determination of the need for public visitation. Visitor center density within 100 miles.

West Virginia State Tax Department. Publication TSD-358 (Rev. July 2008) DIRECT USE CONCEPT

MAP KEYS GLOSSARY FOR THE DRAINAGE AND WATER REPORT

A guide to volume measurement solutions for the. Mining Industry. Changing the market from level to volume

LEARNING OUTCOMES EVALUATION. Mining Engineering

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

Mine Wide Risk Assessment What is the State of your Arteries. L.Human, J Doolan and L Potts Xstrata Zinc

Treatment Practice for Controlling Water Damage in the Annular Space of Shaft Freezing Hole

Layout Planning of Waste-to-Energy Plants

Proceedings 2005 Rapid Excavation & Tunneling Conference, Seattle

ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS

Numerical Modelling for Shallow Tunnels in Weak Rock By Evert Hoek Unpublished Notes

Mechanical Engineering and Material Handling Aspects of NSDF

WATERVIEW CONNECTION PROJECT. Ground Settlement WATERVIEW CONNECTION TEAM

AvestaPolarit - Operating with three divisions

Unit 6: Homework Questions

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

Estimation of Adjacent Building Settlement During Drilling of Urban Tunnels

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

ADVANCED CONTROL TECHNIQUE OF CENTRIFUGAL COMPRESSOR FOR COMPLEX GAS COMPRESSION PROCESSES

TRENCHLESS TECHNOLOGY RESOURCE CENTRE TRENCHLESS TECHNOLOGY GUIDELINES

Manitoba Technical-Vocational Curriculum Framework of Outcomes. Mining Engineering Technology 2015 Draft

Optimize Your Process

Issue. September 2012

the French experience

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas

DIVISION D ELECTRICITY, GAS, WATER AND WASTE SERVICES

Guidelines for the Estimation and Reporting of Australian Black Coal Resources and Reserves

March 2006 DIVISION 3 - CW 2140-R3 TABLE OF CONTENTS

Decree of the Ministry of the Environment on fire safety of ventilation systems

DGMS (Tech.) (S&T) Circular No. b_ of 2016 Dhanbad, datedcwdy/2016. Subject: Standards of illumination in opencast coal mines

Fall protection systems and practices Duty to have fall protection Protection at or above 6' level.

WORK BREAKDOWN STRUCTURE FOR A TYPICAL MINE

Tremie Concrete CM 420 CM 420 CM 420 CM 420. Temporary Structures. Tremie Concrete

BENEFITS OF USING MOBILE CRUSHING AND SCREENING PLANTS IN QUARRYING CRUSHED STONE. 1. Introduction. Mario Klanfar*, Darko Vrkljan*

COAL MINING SAFETY AND HEALTH REGULATION 2001

KAWERAU DISTRICT COUNCIL BUSINESS DISASTER RECOVERY PLAN 2011

Workplace Incident Fatalities Accepted by the Workers Compensation Board in 2014

De Grey Mining Ltd. Wingina Deeps Drilling Commenced (Turner River Project) Highlights. Turner River Unlocking Shareholder Value

TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL

STORM DRAIN PIPE MAINTENANCE. a. Develop standard operating procedures for maintaining storm drain pipes.

BRIDGES ARE relatively expensive but often are

Free Examples of plant layout drawing

The formation of polluted mine water

Construction Management

US&R Heavy Equipment & Rigging Specialist Training Module 3 Unit 3: Demolition Contractor Equip & Helicopter Ops

Independent Contractor Policy

ANALYSIS OF FAILURE STATISTICS FOR CONE CRUSHER MAINTENANCE Vis-a-Vis OPERATIONAL RELIABILITY ASSESSMENT

Discovering New Territories: Sustainable Systems for Efficient Mining Operation Mr. Norbert Becker

APPENDIX B. I. Background Information

CW 3110 SUB-GRADE, SUB-BASE AND BASE COURSE CONSTRUCTION TABLE OF CONTENTS

MINE DEVELOPMENT ACCESS TO DEPOSIT

Chapter 2 Basis of design and materials

SECTION 25. Excavation and Trenching

Transcription:

UNDERGROUND MINING METHODS AND EQUIPMENT S. Okubo and J. Yamatomi University of Tokyo, Japan Keywords: Mining method, underground mining, room-and-pillar mining, sublevel stoping, cut-and-fill, longwall mining, sublevel caving, block caving, backfill, support, ventilation, mining machinery, excavation, cutting, drilling, loading, hauling Contents 1. Underground Mining Methods 1.1. Classification of Underground Mining Methods 1.2. Underground Operations in General 1.3. Room-and-pillar Mining 1.4. Sublevel Stoping 1.5. Cut-and-fill Stoping 1.6. Longwall Mining 1.7. Sublevel Caving 1.8. Block Caving 2. Underground Mining Machinery Glossary Bibliography Biographical Sketches Summary The first section gives an overview of underground mining methods and practices as used commonly in underground mines, including classification of underground mining methods and brief explanations of the techniques of room-and-pillar mining, sublevel stoping, cut-and-fill, longwall mining, sublevel caving, and block caving. The second section describes underground mining equipment, with particular focus on excavation machinery such as boomheaders, coal cutters, continuous miners and shearers. 1. Underground Mining Methods 1.1. Classification of Underground Mining Methods Mineral production in which all extracting operations are conducted beneath the ground surface is termed underground mining. Underground mining methods are usually employed when the depth of the deposit and/or the waste to ore ratio (stripping ratio) are too great to commence a surface operation. Once the economic feasibility has been verified, the most appropriate mining methods must be selected according to the natural/geological conditions and spatial/geometric characteristics of mineral deposits. Considerations include: 1. Spatial/geometric characteristics of the deposit concerned: the shape, size, thickness, plunge, and depth.

2. Strength of the hanging wall, footwall, and ore body. 3. Economic value of the ore and grade distribution within the deposit. The selection of underground mining methods is primarily based on the geological/spatial setting of the deposit. Candidate methods can therefore be chosen and ranked based on estimated operational/capital costs, production rates, availability of labors and materials/equipments, and environmental considerations. The method offering the most reasonable and optimized combination of safety, economics, and mining recovery is then chosen. Reflecting the importance of ground support, underground mining methods are categorized in three classes on the basis of the extent of support required: unsupported, supported, and caving. Unsupported methods are essentially naturally or self-supported and require no major artificial system of support to carry superincumbent loads, instead relying on the natural competence of the walls of the openings and pillars. This definition of unsupported methods does not exclude the use of rock/roof bolts or light structural sets of timber or steel, provided that such artificial supports do not significantly alter the load-carrying ability of the natural structure. The followings are considered unsupported methods: Room-and-pillar mining Shrinkage stoping Sublevel stoping Of the unsupported methods, room-and-pillar mining is employed for extraction of flat-dipping and tabular deposits, whereas shrinkage and sublevel stoping are applied to vertical or steeply inclined ore bodies. Shrinkage stoping has in the past been very popular, particularly in non-coal mining. Gravity can be utilized for ore transportation and broken ore stored within the stope may function as a working platform and temporary wall supports. It was quite attractive in the period before mechanization became widespread, when small-scale operations on vein-type deposits prevailed. However, with rising costs, the scarcity of skilled labor and the trend toward mechanization, the method has been largely displaced by sublevel stoping and cut-and-fill. Sublevel stoping will therefore be the only unsupported methods examined in detail here. Supported methods require substantial amounts of artificial support to maintain stability in exploitation openings, as well as systematic ground control throughout the mine. Supported methods are used when production openings (stopes) are not sufficiently stable to remain open during operation, but the opening required to be held open to prevent caving or surface subsidence. In other words, the supported class is employed when the other two categories of methods, unsupported and caving, are not applicable. The supported class of mining methods is intended for application under ground conditions ranging in competency from moderate to incompetent. In the design of artificial support systems to provide varying degrees of controlled wall closure and ground movement, an evaluation of load-carrying capacity of the natural rock structure is a prerequisite. The most satisfactory forms of artificial support are backfilling/stowing, timbers/stulls, cribs/packs, and hydraulic/frictional props. There are three specific methods in the

supported class. Cut-and-fill stoping Stull stoping Square-set stoping Cut-and-fill and stull stoping are intended for moderately competent rock, whereas square-set stoping is suitable for the least competent rock. Supported methods have declined in use since World War II, primarily because cut-and-fill stoping is the only method that lends itself to mechanization. Stull stoping and square-set stoping are infrequently used and relatively unimportant today, because of excessive labor intensity and very low productivity, in addition to a scarcity of skilled work forces and available timber resources. Only cut-and-fill stoping will be described later in detail. Caving methods are defined as those associated with induced, controlled, massive caving of the ore body, the overlying rock, or both. The exploitation workings in caving methods are designed to collapse, with intentional caving of the ore and/or host rock. The three major caving methods are: Longwall mining Sublevel caving Block caving Longwall mining is used in horizontal, tabular deposits (mainly coal), while the others have applications in inclined or vertical, massive deposits, almost exclusively metallic or nonmetallic. Because the exploitation openings are intentionally destroyed in the progress of mining, the caving class is truly unique. Rock mechanics principles are applied to induce caving rather than to prevent the occurrence of caving. Moreover, development openings have to be designed and located to withstand moving and caving ground. Surface subsidence is inevitable and must be allowed for in the case of sublevel and block caving. Production must be maintained at a steady and continuous level to avoid disruptions or stoppages in the caving activity. Highly advanced mining technology as well as experienced management is indispensable to a successful caving operation. 1.2. Underground Operations in General Figure 1 shows a schematic mine layout for an underground mine as an explanation of common mining terms.

Figure 1: Example layout of an underground mine An inclined shaft is excavated for transportation of personnel and supplies in addition to a vertical shaft for hoisting mined ore and a ventilation shaft for enhancing circulation of fresh air with the aid of a fan. Alternatively, an inclined shaft can be used for main ore transportation and ventilation, and the vertical shaft can act as the main thoroughfare for employees and materials. The functions of inclined and vertical shafts are usually versatile in mining operations. Main levels are arranged for main haulage and connection between underground key facilities. A small number of sublevels may be situated between main levels within a stoping area for production. Raises and winzes are either vertical or sub-vertical openings driven between one level and another or the surface. Raises are driven upward, and winzes are driven downward. A ramp is an inclined opening connecting levels or stopes to enable the passage of vehicles and an orepass is a vertical or sub-vertical hole through which ore is transferred to lower levels. If backfilling (to fill mined-out spaces with rock, soil or tailings) is part of the underground operation for improving mining recovery, safety, and mitigating surface subsidence, a fill raise will be constructed for transporting backfill materials prepared at the backfill plant on the surface to underground stopes. If necessary, additional ventilation raises will be driven to improve underground climates. The primary operations required in underground are rock breakage and material handling. If the target is sufficiently soft (e.g., coal and rock salt), mechanical excavation utilizing continuous miners, shearers, ploughs/plows, and so on, can be employed. In contrast, drilling and blasting are usually employed when the ore is too hard for cutting. A drifting jumbo equipped with one or multiple rock drills is employed for penetrating horizontal blastholes and used for driving horizontal drifts and inclined ramps as well as production by crosscutting in room-and-pillar mining and cut-and-fill stoping. Fan/ring/parallel longhole drill rigs are commonly employed for large-scale production in sublevel stoping and sublevel caving. Ammonium nitrate and fuel oil (ANFO), slurries, and emulsions are widely used as explosives in mining operations. The explosive is usually charged by hand

if available in cartridge form, or pumped into blastholes for liquid or bulk explosives. The explosives are then fired by electrical or other means. The most common equipment for material handling such as loading and hauling excavated ore are slushers, gathering-arm loaders, front-end loaders, overhead loaders, Load-Haul-Dump units (LHDs), and rubber-tired shuttle cars and trucks, as well as transportation by conveyor, rail, and gravity flow. Ore is loaded into underground equipment and transferred to orepasses, where the ore is dumped. A drawpoint or chute is usually situated at the outlet of the pass on the lower level, where the ore is loaded and transported to the underground ore bins or directly to the main haulage level. Finally, ore is collected on the main haulage level and transferred to an underground crusher for size reduction to facilitate transportation by conveyors or skips through shafts (see Underground Mining Transportation Systems). The auxiliary/supporting operations required underground include: 1. Health and safety: ventilation, gas control (particularly in coal mines), dust suppression, noise reduction. 2. Ground control: supporting (rock-bolting, timbering, setting steel arches, etc.), scaling (removing rock fragments from working roofs). 3. Power supply and lighting 4. Drainage and flood control: pump stations and sumps are usually constructed at the bottom level to collect and drain water from underground after removing suspended solids. 5. Maintenance and repair of equipment: underground workshops and warehouses. In addition, surface facilities such as an administration office, milling plant, hoist & headframe, electric substation, emergency power generator, air compressor, and tailings pond are necessary. 1.3. Room-and-pillar Mining Room-and-pillar mining is suitable for flat or nearly horizontal tabular deposits. If the ore bodies are moderately inclined (>30 ) it is impractical to utilize tired mobile equipment, resulting in reduced productivity. If the competence of the hanging wall and/or the ore is insufficient, additional labor is also required for ground control, which is likely to cut productivity and raise auxiliary costs. A schematic illustration of room-and-pillar mining is given in Figure 2.

Figure 2: Room-and-pillar mining Pillars of original bedrock are left to support rock pressures and to protect personnel. Drill jumbos are usually used for driving crosscuts and connecting them. Blasted ore is mucked and hauled by LHDs. In coal mines, seams are generally large in scale and relatively uniform, and mechanical excavation is also applicable in such cases. Openings are driven orthogonally and at regular intervals to leave rectangular or square pillars for natural support, which gives the plan view a checkerboard-like appearance. It is not uncommon in non-coal mining for the pillars to be irregularly shaped, sized, and randomly located (Figure 3). The objective in placement of pillars is to locate them in areas of low-grade ore or waste rather than follow a systematic mining plan so long as adequate roof support is provided. In the case of a considerably thick deposit, a fairly high back is liable to degrade the safety of mining in a single pass, necessitating benching or slabbing (Figure 4). Partial extraction of a pillar, called robbing, is sometimes practiced, particularly if the pillars are larger than necessary to support the back, allowing more ore to be recovered safely. Figure 3: Pillar layouts for room-and-pillar mining

Figure 4: Room-and-pillar mining for a thick deposit Room-and-pillar mining is moderately favorable in terms of productivity and cost. Accordingly, it is appropriate for a large deposit with relatively low economic value, that is, deposits where some ore may be left without significant economic impact. The method is also flexible, allowing the production rate to be adjusted by varying the number of stopes. The method can also be regarded as selective. Moreover, it requires a less amount of development. For these reasons, the room-and-pillar mining is most popular among underground mining methods and prevailed worldwide. - - - TO ACCESS ALL THE 23 PAGES OF THIS CHAPTER, Visit: http://www.eolss.net/eolss-sampleallchapter.aspx Bibliography Hartman H.L. ed.(1992). Mining Engineering Handbook, 2 nd Ed. 2170 pp., Society for Mining, Metallurgy, and Exploration, Inc. (Littleton, USA). [A comprehensive handbook on mining engineering, including general descriptions of mining practices with many case studies. Also available on CD-ROM]

Hartman H.L. (1987). Introductory Mining Engineering, 633 pp., John Wiley & Sons, Inc. (New York, USA). Hustrulid W.A. ed. (1982). Underground Mining Methods Handbook, 1754 pp., Society for Mining, Metallurgy, and Exploration, Inc. (Littleton, USA). [A comprehensive handbook on mining engineering, including general descriptions of mining practices with many case studies. Also available on CD-ROM] Peng S.S. (1978). Coal Mine Ground Control, 450 pp., John Wiley & Sons, Inc. (New York, USA). [A comprehensive textbook on roof control of underground coal mine openings] Stack B. (1980). Handbook of Mining and Tunnelling Machinery, 742 pp., John Wiley & Sons, Inc. (New York, USA). [A very good and readable book with excellent content] Stout K.S. ed. (1980). Mining Methods & Equipment, 217 pp., McGraw-Hill, Inc. (New York, USA). [A visual course book for introductory mining engineering programs for undergraduate students, with illustrations] Biographical Sketches Prof. Dr. Seisuke Okubo (born 1947), is an expert on mining machinery and rock mechanics. He studied at the Mechanical Department of the University of Tokyo, where he obtained his PhD. His post-graduate studies at West Virginia University, USA, involved work in mine ground control and rock-pressure measurement. Working at the University of Tokyo, he designed several servo-control testing machines and carried out versatile rock testing. He also developed computer programs to simulate the complicated behavior of excavation machinery. He is now professor of the University of Tokyo. Prof. Dr. Jiro Yamatomi (born 1949), is professor of mining engineering and rock mechanics at the Department of Geosystem Engineering of the University of Tokyo. He obtained his PhD in the Mining Engineering Department of the University of Tokyo. He also worked for the Mining College, Akita University, for seven years, and during that time took study leave at the Department of Mineral Engineering, of Pennsylvania State University, USA.