STANDARD INSPECTION & TEST PLAN (ITP) FOR CIVIL WORKS :



Similar documents
C. Section TESTING LABORATORY SERVICE.

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13)

SECTION EARTH MOVING

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

Quality control: Annex-A.

Soils and Aggregates Division

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS

Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS

SECTION 4Aggegate Subbase

SECTION 311 PLACEMENT AND CONSTRUCTION OF CEMENT TREATED SUBGRADESOIL CEMENT BASE COURSE

The Manitoba Water Services Board SECTION Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

Construction Specification for Concrete Curb and Concrete Curb and Gutter

SPECIFICATIONS. INTERLOCKING CONCRETE POROUS PAVING UNITS or Permeable Interlocking Concrete Pavers (PICP)

Installation PowerPoint for Grasscrete Formers

CW 3110 SUB-GRADE, SUB-BASE AND BASE COURSE CONSTRUCTION TABLE OF CONTENTS

Section 2100-Trenching and Tunneling

CONCRETE: CONTRACTOR S QUALITY CONTROL PLAN

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

By K M Chanda, HUDCO

STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY

SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST

PLUMBING MAINTENANCE WORK FOR TOILETS IN HEAD OFFICE, SUPPLYCO ESTIMATE

Specification Guidelines: Allan Block Modular Retaining Wall Systems

SECTION PUBLIC STORM UTILITY DRAINAGE PIPING

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION

Chapter 8 Design of Concrete Mixes

SECTION PAVEMENT DESIGN

SECTION CEMENT-MORTAR LINED AND COATED STEEL PIPE

PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

The University of Toledo Soil Mechanics Laboratory

SECTION 1 GENERAL REQUIREMENTS

STANDARD SPECIFICATIONS SECTION PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES. 1. Structure Earthwork: 02200

NorthEast Transportation Training and Certification Program (NETTCP) Course Registration Form

Section 600 Incidental Construction

EXPERIMENT NO.1. : Vicat s apparatus, plunger

Inspections: Central Laboratory of the Regions

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

Acceptance Codes APPENDIX - A. Acceptance Criteria

CHAPTER 2 AGGREGATE TECHNICIAN TRAINING AND QUALIFICATION PROGRAM

Tender reference No : System ID : Tender title : CONSTRUCTION OF IMPERVIOUS DYKE AT BUDGE BUDGE

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

Example Specification for Concrete using Current Building Code Requirements

Section 2 Specification 2.18 Concrete and/or Corrugated Steel Storm Sewer TABLE OF CONTENTS

NOTE: FOR PROJECTS REQUIRING CONTRACTOR MIX DESIGN, THE DESIGN PROCEDURES ARE SPECIFIED IN THE SPECIAL PROVISIONS OF THE CONTRACT.

SECTION STORM DRAIN SYSTEM

SECTION 7: C - STRUCTURAL ENGINEERS SPECIFICATIONS

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

CHAPTER 2 AGGREGATE TECHNICIAN TRAINING AND QUALIFICATION PROGRAM

SECTION PERMEABLE INTERLOCKING CONCRETE PAVEMENT (1995 MasterFormat Section 02795)

Stormwater/Wetland Pond Construction Inspection Checklist

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

11 Guardrail. W-Beam Guardrail Pre-Installation Inspection During Installation Basis for Use. Modified Guardrail. End Treatments and Transitions

QUALITY ASSURANCE PROGRAM (QAP) City Rohnert Park

Construction Management Program

UFGS (August 2004) UNIFIED FACILITIES GUIDE SPECIFICATIONS

Effect of grain size, gradation and relative density on shear strength and dynamic cone penetration index of Mahi, Sabarmati and Vatrak Sand

KANTI BIJLEE UTPADAN NIGAM LIMITED (KBUNL) SCHEDULE (BILL) OF QUANTITIES (Percentage Rate Contract)

Division 2 Section Section 02795

Lab 1 Concrete Proportioning, Mixing, and Testing

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

Moving Small Mountains Vesuvius Dam Rehab

Owner's Manual & Assembly Instructions

CONSTANT HEAD AND FALLING HEAD PERMEABILITY TEST

HOUSE BUILDING DIGEST

UNIFIED FACILITIES GUIDE SPECIFICATIONS

HYDRAULIC STRUCTURES, EQUIPMENT AND WATER DATA ACQUISITION SYSTEMS Vol. IV - Testing of Materials and Soils - F. Druyts

CHAPTER 4 CONCRETE TRAINING AND QUALIFICATIONPROGRAM

TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL

HIGH PERFORMANCE PRE-APPLIED SYSTEM FOR BLIND SIDE & BELOW GRADE WATERPROOFING APPLICATIONS

SECTION PERMEABLE INTERLOCKING CONCRETE PAVEMENT (1995 MasterFormat Section 02795)

Pavement Thickness. esign and RCC-Pave Software. Roller-Compacted Concrete Pavement: Design and Construction. October 24, 2006 Atlanta, Georgia

MATERIALS CERTIFICATION SCHOOLS

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 888 PORTLAND CEMENT CONCRETE PAVEMENT USING QC/QA.

METHOD A10 (a) THE DETERMINATION OF THE IN-PLACE DRY DENSITY OF SOIL OR GRAVEL BY THE SAND REPLACEMENT METHOD

PROJECT TITLE : 2-STOREY RESIDENCE LOCATION : ALONG DAANG HARI,MOLINO.BACOOR,CAVITE OWNER : CUEVASVILLE REALTY

SPECIAL NOTE FOR ASPHALT WATERPROOFING MIX FOR BRIDGE-DECK OVERLAYS AND ADJACENT APPROACHES

Series 600: Earthworks

SECTION STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

METHOD A7 THE DETERMINATION OF THE MAXIMUM DRY DENSITY AND OPTIMUM MOISTURE CONTENT OF GRAVEL, SOIL AND SAND

High Strain Dynamic Load Testing of Drilled Shafts

SECTION PRECAST CONCRETE UTILITY STRUCTURES

Beacon Hill Sewer District Standard Specifications

CEG/GP/1534/257/RFQ27016/ [01] Technical specification for NB 350 CB pipe :

Section 100 Contractor Quality Control Program

Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS

SECTION PERMEABLE INTERLOCKING CONCRETE PAVEMENT

SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION CONCRETE BONDING COMPOUND.

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin PLAN SUBGRADES

SECTION GUARDRAILS

The AASHO Road Test site (which eventually became part of I-80) at Ottawa, Illinois, was typical of northern climates (see Table 1).

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

4-02 Gravel Base Ballast and Crushed Surfacing

CHAPTER 2 QUANTITY TAKE-OFF

GRADATION OF AGGREGATE FOR CONCRETE BLOCK

SECTION SHEETING, SHORING AND BRACING

SPECIAL INSPECTION AND TESTING AGREEMENT INTERNATIONAL BUILDING CODE

Transcription:

CONSTRUCTION OF BG RAILAY SIDING AT KADAPA IRD (ITP) F CIVIL KS : 1.0 GENERAL NOTES: Inspection & Test Plan (ITP) given herein is indicative only. Contractor shall prepare and submit ITP for all activities. The provisions indicated herein for stage wise inspection are minimum and the Engineer-in-charge may decide to increase the Hold Point/itness Point basis the work being carried out at site. Contractor has to prepare ITPs for any of the activities not covered herein, submit the same to CL and obtain their approval. Contractor to prepare required reporting formats and job procedure for each activity i.e. Setting out of work, levels at 5 m grid, prior to excavation, submission of murrum samples meeting tender specifications along with soil lab test report, concreting, etc., to CL for approval well in advance prior to commencement of activity. Any deviation to ITP shall be subjected to CL's written approval. Contractor to carry out 100% examination; satisfy that the specifications as per PO are complied & thereafter submit to CL for witness/review as applicable. 2.0 LEGEND: 2.1 : HOLD POINT A point which requires inspection/verification and acceptance by CL before any further processing is permitted. PAGE 1 OF 10

CONSTRUCTION OF BG RAILAY SIDING AT KADAPA IRD The Contractor shall not process the activity/item beyond the Hold Point without written approval from Engineer-in-charge. 2.2 : itness Point Any point which requires witness by CL when activity is performed. 2.3 R: review of contractors documentation Contractor s documentation to be reviewed by CL. 2.4 S: Surveillance inspection by CL Monitoring of observations to verify whether or not materials/items/services confirms to specified requirement. Surveillance activities may include audit, inspection, witness of testing, review of quality documentations and records, personnel qualifications etc. 2.5 : 100% examination by contractor. 3.0 THE INDICATIVE INSPECTION AND TEST PLAN IS AS BELO, PAGE 2 OF 10

CONSTRUCTION OF BG RAILAY SIDING AT KADAPA IRD CL 1 LEAD LINE, R&D YARD AND UNLOADING SIDING 1.1 Fixing of Centre line & levels with respect to CL coordinates & Bench Marks with Total Station. Setting out of various control points & alignment, grid levels at every 3m c/c bothways before filling. 1.2 The readings will be taken after filling each layer 1.3 Submission of soil test reports confirming to PO Specifications to CL for approval with all requisite details like grain size analysis, atterberg limits, modified proctor dry density with graph. 1.4 Submission of following documents to CL pertaining to soil being brought for filling purposes. a) Contractor to submit activities to be carried out under this item for CL s review. b) NOC from land owner or owner of borrow pit c) 7/12 extract and village map indicating the location of the plot/quarry. d) Royalty payment slips 1.5 A) Rolling of each layer after filling & testing for specified lab dry density achieved in case of soil only. B) Each layer shall not exceed specified loose thickness PAGE 3 OF 10

CONSTRUCTION OF BG RAILAY SIDING AT KADAPA IRD CL 1.6 A) Embankment formation : Specified layer checking with templates/tools at various coordinates & recording. atering the layer, checking the OMC through Moisture tester & recording co-ordinate wise. B) Compaction : Rolling the OMC watered layer immediately till specified Modified Proctor lab dry density is achieved. Testing for compaction to confirm its specified Modified Proctor dry density achieved coordinate wise, recording the levels co-ordinate wise. (Min. test as specified per layer) Offering tested layer to CL to inspect & witness to give clearance for next layer. 1.7 Obtaining NOC from District Mining Officer/relevant statutory authority as regard to royalty payment for executed quantity basis CL letter before final bill. PAGE 4 OF 10

CONSTRUCTION OF BG RAILAY SIDING AT KADAPA IRD CL 1.8 Construction of side shoulders, watering and compaction up to a thickness of compacted thickness and trimming of inside edge to vertical. Laying of courses and rolling with Vibromax/10T roller to specified thickness and checking with templates/ tools at various coordinates and recording layer wise. Offering to CL layer wise to inspect & witness and to give clearance for next layer. PAGE 5 OF 10

CONSTRUCTION OF BG RAILAY SIDING AT KADAPA IRD CL 2 RCC,PCC & assoc. works 2.1 Laying of PCC beneath foundations Checking of layout and materials, compaction of sub grade Visual inspection, sieve analysis and carrying out all the field tests of the sand and coarse aggregates as per attached specifications. Verification of the test reports of all the tests of cement, sand, water and coarse aggregates specified in tender documents from govt. approved laboratory supplied by the contractor with respect to the specifications Mix proportion Check for shuttering, dewatering if any Concreting with proper compaction with plate vibrators Checking of top level of PCC Curing PAGE 6 OF 10

CONSTRUCTION OF BG RAILAY SIDING AT KADAPA IRD CL 2.2 Bottom Raft, side walls & wingwalls: Carrying out PCC as per drawings and specifications. hold point clearance for center points for side walls and Rafts and center lines for haunch Submission of design calculations for formwork including shuttering and props. Approved quality shuttering to be provided. Inside dimensions to be marked. Reinforcement steel to be placed as per CL approved bar bending schedule/drawings with cover blocks/spacers. Contractor will provide the gauge/template for measuring the diameter of reinforcement bars. The sample piece will be taken out from above supplied steel; the same will be tested at designated laboratories as given in attached specifications. Placement of concrete will be started only after the receipt of test report of the steel testing. Counting authorized laps and chairs. Visual inspection, sieve analysis and carrying out of all the field test of the sand and coarse aggregates as per attached specifications. PAGE 7 OF 10

CONSTRUCTION OF BG RAILAY SIDING AT KADAPA IRD CL 2.2 Verification of the test reports of all the tests of cement, water, sand and coarse aggregates specified in tender documents from approved laboratory Mass batching of aggregates, sand and cement as per mix designed & placing of concrete. Vibrating, tamping and finishing smooth. Measurement of finished dimensions. It shall be the sole responsibility of the contractor to ensure the members are in a proper grade & levels as per the approved drawing. Curing of the cast concrete. Slump cone test. 2.3 Cube test sample collection from the mix, curing and its testing as per IS: 456, submission of following laboratory reports, a) slump test - field b) cube strength - lab/field PAGE 8 OF 10

CONSTRUCTION OF BG RAILAY SIDING AT KADAPA IRD CL 3.1 Plastering : Visual inspection, sieve analysis and carrying out of all field tests of sand as per attached specifications Verification of the test reports of all the tests of cement and sand specified in tender documents from approved laboratory supplied by the contractor with respect to the specifications Carrying out plastering of specified thickness with CM as per specification. Final acceptance after checking thickness of plaster with thickness gauge to be provided by the contractor at some random places as decided by CL. PAGE 9 OF 10

CONSTRUCTION OF BG RAILAY SIDING AT KADAPA IRD CL 4.0 BACK FILLING: Back filling in foundation trenches after construction of foundation or wherever required as per the directions of CL engineer in charge, using the serviceable earth Offering the selected material from excavated earth for backfilling to CL to inspect and witness. Filling the material in layers of specified thicknesses atering the layer and compaction using plate vibrator Offering tested layer to CL to inspect & witness to give clearance for next layer. PAGE 10 OF 10