Concrete Removal Using Hydrodemolition



Similar documents
7.8 Excessive Water Jet Pressure

Waterproofing System for Wastewater Tanks in Petrochemical Industries and Refineries

SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION CONCRETE BONDING COMPOUND.

Proper use of the Rebound Hammer Updated to reflect the changes to ASTM C805

738-B-297 POLYMERIC CONCRETE BRIDGE DECK OVERLAY. (Adopted )

SECTION XXXXXX TECHNICAL SPECIFICATIONS FOR INSTALLATION OF PROTECTIVE COATINGS FOR MANHOLES, WETWELLS, AND OTHER SANITARY SEWER STRUCTURES

CORROSION ENGINEERING RESIN-BASED POLYMER CONCRETES AND GROUTS

LOWELL REGIONAL WASTEWATER UTILITY SPECIFICATIONS FOR THE LOWELL MA CONCRETE FLOODWALL REPAIRS

PART E SPECIFICATIONS

Strengthening of Large Storage Tank Foundation Walls in an Aggressive Environment by External Post-tensioning. May 7th 2013: Dominique Deschamps

Condition assessment and repair of antenna towers concrete foundations

Concrete Repair. Applications and Procedures

University of Missouri Hospitals and Clinics. Structural Repair and Protection of Post-tensioned Parking Garage

ARDEX GUIDE SPECIFICATION ARDEX Exterior Concrete Repair & Resurfacing Polymer-Modified, Cement-Based, Patch & Horizontal Overlay Materials

REPAIR AND PREVENTATIVE MAINTENANCE OF THE EAST MONROE PARKING GARAGE

Causes and Repair Method

Precast Concrete Parking Structures

Minor Cracks in Horizontal Surfaces

PRE INSTALLATION MANUAL

Concrete Design Manual

MASONRY RESTORATION Lime Putty Mortar Repointing Guide

Wastewater Capital Projects Management Standard Construction Specification

BRIDGE FIELD PAINTING, REPAINTING, 412 AND PAINT RESIDUE CONTAINMENT. A. Field Painting, Bridge Repainting and Residue Containment:

The ACI 562 Repair Code

Release: 1. CPCCWP3004A Apply waterproofing remedial processes

CA-48 TECHNICAL SPECIFICATION

Operations and Instruction Manual Might Swivel - Part # Concrete and Steel Anchorage Connector ANSI Z ,000 lbs / 44kn

Specification for Pipe Coating Repairs Offshore

Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements

REHABILITATION OF UNDERGROUND SEWER LATERAL PIPES WITH CURED-IN-PLACE-PIPE LINER SECTION 02542

Example Specification for Concrete using Current Building Code Requirements

Moisture and Resilient Floor Covering

Standard Method for Sampling and Analysis of. of Chlorine Containing Bleaches. Soap Products

These recommendations generally follow the Construction Specifications Institute (CSI) Master Format.

2006 ICRI Baltimore Washington Chapter Outstanding Repair Project Award George Washington University Ross Hall Façade Restoration

Successful Approach to the Repair of Reinforced Concrete Support Structures in Delayed Coking Units

Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI

Joint Rehabilitation. Driving Forces for Concrete Pavement Joint Repairs

DiscPlus DX195 and DX225 Air Disc Brakes

San Antonio Water System Standard Specifications for Construction ITEM NO POINT REPAIRS AND OBSTRUCTION REMOVALS

Structural Failures Cost Lives and Time

PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE. By H P Gupta & D K Gupta

SECTION POLISHED CONCRETE FINISHING

Sto Specification No. RC100 Guideline Specifications for Cleaning Wall Surfaces

Float and Thermostatic Traps Series H, C and X

Technical Services. Product MM INCH Installation direction Seams treatment GTI CONNECT (interlocking)

Construction. 3-part thixotropic epoxy patching mortar. Product Description. Tests

2013 WJTA-IMCA Conference and Expo September 9-11, 2013 Houston, Texas Paper REFRACTORY REMOVAL BY HIGH PRESSURE WATERJET

VC 104+ Rigid Grade / Rigid Grade Imagine VC 104 Rigid Grade Commercial Customised

NAPCA BULLETIN APPLICATION PROCEDURES FOR CONCRETE WEIGHT COATING APPLIED BY THE COMPRESSION METHOD TO STEEL PIPE

Project Report. Structural Investigations Hotel del Sol Yuma, Arizona

PIPING SYSTEM - ABRASIVE SLURRIES Engineering Standard Specification. 96 B. Riutta

BENTLEY ELEMENTS COLLECTION LVT

C. Section TESTING LABORATORY SERVICE.

Division 9. SignaFlor Pad and Pour Flooring System

SECTION PRECAST CONCRETE UTILITY STRUCTURES

Moisture Testing of Concrete Slabs

Course Title: Safety Issues in Electronics Engineering Technology Number of Credits: 3 B.A. B.S. B.A.S A.A. A.S. Degree Type

Pressure Vessels (Air Compressors) and LPG Tanks

Proposed Minimum Subterranean Termite Treatment Standards

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

Demonstration of an Innovative Large-Diameter Sewer Rehabilitation Technology in Houston, Texas

Fire Damage Evaluation. Concrete Garage. Vehicular fires in parking garages are not an

NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003)

Chapter 7: Pavement Rehabilitation 7-1 Asphalt Pavement Overlays 7-1 Surface Preparation Methods 7-2 Concrete Pavement Preparation 7-3 Recycling

SANITARY SEWER SPECIFICATIONS

Guide Specification Precast Concrete Products

SPECIFICATIONS. INTERLOCKING CONCRETE POROUS PAVING UNITS or Permeable Interlocking Concrete Pavers (PICP)

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)

SECTION 1 GENERAL REQUIREMENTS

NRDCA 400 GUIDELINE FOR FIELD APPLICATION of LIGHTWEIGHT INSULATING CONCRETE REROOFING/RECOVER SYSTEMS

SPECIAL INSPECTION AND TESTING AGREEMENT INTERNATIONAL BUILDING CODE

Code Requirements for Load Testing of Existing Concrete Structures (ACI ) and Commentary

SECTION POLISHED CONCRETE FINISHING. InovaCrete Polished Concrete Floor Finish (GUIDE SPEC)

Concrete Repair and Protection

SECTION 807 PUMP STATION REHABILITATION

Chapter. Restoration of Damaged Structures

Field Damage Inspection and Static Load Test Analysis of Jiamusi Highway Prestressed Concrete Bridge in China

AGREGADOS RECICLADOS MITOS Y REALIDADES

RECOATING AND RENEWING SPF ROOFING SYSTEMS

have been provided with information on whether they do or do not contain asbestos before starting work;

SECTION ASBESTOS CEMENT PIPE REPAIRS, DEMOLITION, AND DISPOSAL

Construction Specifications for Keyhole Pavement Coring and Reinstatement

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 848 BRIDGE DECK REPAIR AND OVERLAY WITH CONCRETE USING HYDRO-DEMOLITION

15GAL STEEL OIL DRAIN WITH 110V PUMP

CCU Engineering Specifications. Section PRECAST CONCRETE PRODUCTS

PROPERTIES AND MIX DESIGNATIONS

SECTION EARTH MOVING

Pervious Concrete Pavement Maintenance and Operations Guide

Routine Maintenance and Inspection

SECTION III-06 Surfacing Page 1 Revised 3/2/10. See the DESIGN GUIDELINES in Section I-06 for requirements for cross slope of the roadway.

Measuring the Condition of Prestressed Concrete Cylinder Pipe

Experimental assessment of concrete damage due to exposure to high temperature and efficacy of the repair system

Notes. Material 1. Tools the employee is expected to operate

ALVERNIA UNIVERSITY OSHA REGULATION: 29 CFR WELDING, CUTTING, AND BRAZING ( HOT WORK ) SECTION: 3600

Chapter 2 Basis of design and materials

OVERVIEW. 1 Intent: Applicability: Referenced Standards Invert Repair Mortar... 3

Resurfacing Concrete. Page 1 of 5

North American Stainless

CONDITION SURVEY REPORT & REPAIR RECOMMENDATIONS. for the. PHOENIX PLAZA & PARKING GARAGE Pontiac, MI. Prepared for: City of Pontiac Pontiac, MI

Transcription:

ACI RAP Bulletin 14 American Concrete Institute Advancing concrete knowledge FIELD GUIDE TO CONCRETE REPAIR APPLICATION PROCEDURES Concrete Removal Using Hydrodemolition Concrete Removal Using Hydrodemolition (ACI RAP-14) 1

2 Repair Application Procedures Bulletin

ACI RAP Bulletin 14 Field Guide to Concrete Repair Application Procedures Concrete Removal Using Hydrodemolition Reported by ACI Committee E706 David W. Whitmore Chair J. Christopher Ball H. Peter Golter Kenneth M. Lozen David A. VanOcker * Gerald Churry Fred R. Goodwin John S. Lund Patrick M. Watson Paul E. Gaudette Bob Joyce Kelly M. Page Patrick M. Winkler * Timothy R. W. Gillespie Brian F. Keane George I. Taylor * Primary author. It is the responsibility of the user of this document to establish health and safety practices appropriate to the specific circumstances involved with its use. ACI does not make any representations with regard to health and safety issues and the use of this document. The user must determine the applicability of all regulatory limitations before applying the document and must comply with all applicable laws and regulations, including but not limited to, United States Occupational Safety and Health Administration (OSHA) health and safety standards. Structural Disclaimer This document is intended as a voluntary field guide for the Owner, design professional, and concrete repair contractor. It is not intended to relieve the user of this guide of responsibility for a proper condition assessment and structural evaluation of existing conditions, and for the specification of concrete repair methods, materials, or practices by an experienced engineer/designer. ACI Repair Application Procedure 14. Copyright 2010, American Concrete Institute. All rights reserved including rights of reproduction and use in any form or by any means, including the making of copies by any photo process, or by electronic or mechanical device, printed, written, or oral, or recording for sound or visual reproduction or for use in any knowledge retrieval system or device, unless permission in writing is obtained from the copyright proprietors. Printed in the United States of America. The Institute is not responsible for the statements or opinions in its publications. Institute publications are not able nor intended to supplant individual training, responsibility or judgment of the user, or the supplier of the information provided. Concrete Removal Using Hydrodemolition (ACI RAP-14) 3

Introduction Concrete repair and restoration will typically require removal of deteriorated concrete, preparation of the repair surface, and cleaning of the reinforcing steel and embedded items. Hydrodemolition is a method of concrete removal and surface preparation using high-pressure water jets. When used to remove concrete, the remaining surface is roughened sufficiently to enhance bond and help ensure composite action between the base concrete and the repair material (Fig. 1). Unlike impact methods of demolition, hydrodemolition does not induce microcracking, a condition that can be detrimental to the longevity of a repair. Concrete removal using hydrodemolition can be fast and efficient, expediting the repair project. Removal using robotic hydrodemolition equipment can eliminate fatigue and potential injury to employees. Using water during concrete removal can suppress dust and provide a healthier work environment. This document focuses on the concrete removal and surface preparation required for the installation of cementitious repair materials or bonded overlays having a material thickness of 12 mm (0.5 in.) or greater. Terms bruised surface a surface layer weakened by interconnected microcracks in concrete substrates caused by use of high-impact, mechanical methods for surface preparation. hydrodemolition a method for removal of concrete by means of water under high pressure directed against a surface. microcracks small, numerous cracks that develop in hardened concrete. surface preparation the process of removing deteriorated or contaminated concrete and roughening and cleaning a substrate to enhance bond of a repair material or protective coating. When do I use hydrodemolition? This method may be used in a broad range of applications requiring concrete removal and surface preparation prior to installation of a repair material. Removal of deteriorated concrete may include concrete that is spalled, cracked, delaminated, chloride contaminated, carbonated, or damaged by fire or cycles of freezing and thawing. It may also include removal of sound concrete to provide proper clearance under the reinforcing steel or to provide a minimum thickness of repair material. The process may be used when vibration of the structure from the use of impact removal methods may lead to further damage or where vibration and sound is easily transmitted and will interfere with the simultaneous occupancy and use of the structure. Hydrodemolition is particularly effective in removing concrete from around embedded metal elements such as reinforcing steel, anchors, and pipe conduits (Fig. 2). Embedded metal elements may block the water jet from removing the concrete directly beneath the element, leaving a concrete shadow. If the concrete removal depth is sufficient, however, the angle of the water jet will undercut the metal element and remove the shadow. Otherwise, the shadow may be removed using a hydrodemolition hand lance or chipping hammers. Fig. 1 Surface profile after hydrodemolition. Fig. 2 Reinforcing steel exposed using hydrodemolition. Impact removal techniques can bruise the surface, creating a fractured layer typically extending 1/8 to 3/8 in. (3 to 10 mm) deep and frequently results in lower bond strengths compared to surfaces prepared with nonimpact methods. Where impact removal techniques such as jack-hammers, rotomilling, or similar methods are used, hydrodemolition may be used to perform final concrete removal and surface preparation to remove resulting microcracking. High-pressure water jetting may also be used to remove corrosion products from reinforcing steel (Fig. 3). What should I consider when using hydrodemolition? The process should not be used in areas where the wastewater cannot be controlled and water leakage into adjacent areas can cause damage. Because there is the possibility that the water may enter the post-tensioned tendon sheathing and cause long-term durability issues, hydrodemolition may not be suitable and is not recommended for removing concrete from around posttensioned tendons. In addition, caution should be exercised with post-tensioned structures, as hydrodemolition may remove concrete around the tendon anchorages, resulting in 4 Repair Application Procedures Bulletin

Fig. 3 Reinforcing steel and bar joist top chords exposed using hydrodemolition. Fig. 5 Hydrodemolition robot. Fig. 4 Hydrodemolition pump trailer. movement or de-tensioning of the tendons. Sudden release of anchorages or removal of support for the tendon profile could lead to equipment damage, personal injury, or structural integrity loss. Refer to International Concrete Repair Institute s (ICRI s) ICRI Technical Guideline No. 310.3, Guide for the Preparation of Concrete Surfaces Using Hydrodemolition Methods, for additional information regarding considerations for hydrodemolition use. Removal of concrete can reduce structural capacity. A qualified engineer should verify the integrity of the structure and determine whether shoring is required. The weight of the robotic tractor, if used, should be included in the shoring calculations. Shoring should be installed prior to the start of removal, and the shoring layout should accommodate debris removal because it will remain until after replacement occurs. What equipment do I need? Hydrodemolition equipment consists of high-pressure pumps (Fig. 4); self-propelled robotic units to hold and maneuver the water jet (Fig. 5); small push or self-propelled units (mowers) used for small removal areas (Fig. 6); and hand lances (Fig. 7). The robotic units move the water jet uniformly over the surface. Where the concrete quality is consistent, the removal will be uniform and result in a finished surface profile amplitude approximately the size of the coarse aggregate. Travel speed of the unit can be adjusted to control the overall amount and depth of removal. The Fig. 6 Hydrodemolition mower. Fig. 7 Hand lance for hand-held hydrodemolition Concrete Removal Using Hydrodemolition (ACI RAP-14) 5

removal units may or may not be connected to vacuum systems to collect the water and debris during the removal and surface preparation operation. Specialized equipment is available for a variety of applications including overhead, vertical, tunnel, and underwater removal. How do I dispose of the wastewater? Wastewater disposal requirements for the local area must be determined and followed. The wastewater contains cement fines with a ph ranging from 11 to 13. Where the wastewater will be discharged to the local sanitary systems, a permit may be required, and the water may have to be treated to meet the sanitary system s discharge requirements. Commonly encountered sanitary discharge requirements may range from 300 to 400 mg/l (0.0025 to 0.0033 lb/gal.) total suspended solids (TSS), and a ph between 5 and 10. Discharge requirements vary, and the local governing authority should be contacted prior to discharging water. In some areas, wastewater may be discharged on the ground and allowed to evaporate or be absorbed into the ground. Wastewater may not be discharged into lakes, streams or wetlands. How do I clean up after hydrodemolition? Following hydrodemolition, the surface must be cleaned to remove all debris, slurry, and wastewater. This may be done using vacuum equipment, water blasters operating at up to 70 MPa (10,000 psi), pressure washers, air lances, and other equipment that will remove waste from the repair substrate. Cleanup operations should follow immediately behind the hydrodemolition removal to prevent re-solidification of the debris, which can occur if the debris is allowed to dry. The surface should be thoroughly rinsed to remove all cement fines (slurry). How do I check the surface following concrete removal? The surface should be visually inspected to verify that it is free from dirt, dust, debris, oils, slurry, and other bondinhibiting materials. Aggregate protruding from the surface should not be fractured or damaged. Clean, crisp aggregate protruding from the repair surface will enhance the mechanical bond between the existing surface and the repair material (Fig. 1). The surface can be sounded using a chain drag or hammer to locate any delaminations. The bonding capacity of the prepared surface can be randomly checked using a direct tensile pull-off test (Fig. 8) as described in ICRI Technical Guideline No. 210.3, Guide for Using In-Situ Tensile Pull-Off Tests to Evaluate Bond of Concrete Surface Materials, and ASTM C1583/C1583M, Standard Test Method for Tensile Strength of Concrete Surfaces and the Bond Strength or Tensile Strength of Concrete Repair and Overlay Materials by Direct Tension (Pull-off Method). How do I operate the equipment safely? All high-pressure equipment should be operated by individuals experienced in the use and maintenance of this specialized equipment. Hydrodemolition uses high-pressure water jets; the water jet is very dangerous and can cause Fig. 8 Tensile bond test on prepared substrate. serious injury or death. Water jets can propel debris at high velocity, resulting in injury or death as well as damage to property. The water jet should be shielded to minimize the possibility of flying debris. Items in the work area that may be damaged should be protected. Electrical conduits and equipment should be deenergized. The area both around and below the removal area should be closed to prevent access. Anyone entering the work area should wear Personal Protective Equipment (PPE) including safety glasses (face shield if necessary), hearing protection, hard hat, long pants, long-sleeved shirt, and steel toed boots. Additional protective clothing may be necessary when operating hand-held tools. Preconstruction meeting Prior to proceeding with concrete removal using hydrodemolition, a preconstruction meeting is recommended. The meeting should include representatives from all participating parties (including the owner, engineer, contractor, and materials manufacturer), and should specifically address the following: 1. Location and schedule of the work; 2. Location and layout of shoring, if required; 3. Location and layout of the hydrodemolition equipment; 4. Location and layout of the temporary water supply, including materials to be used, and any permits required to secure the use of the water; 5. Location and layout of exhaust system to avoid exhaust intake into adjacent buildings; 6. Location and layout of fuel system required for the equipment, including method of fuel delivery; 7. Location and layout of the system to be used to contain the waste water, including methods of reducing the suspended particles to acceptable levels, adjusting the ph, if required, and discharging the waste water; any water tests that will be required and who will perform the tests; and any permits required to properly discharge the wastewater; 8. The impact tools (jackhammers) required to perform the work, whether the vibration noise will affect the structure or the occupants, and any additional surface preparation required in areas in which impact tools were used; 6 Repair Application Procedures Bulletin

9. Equipment and method of removal for the debris from concrete demolition, including proposed active drive lanes to move debris off the structure such that the removal does not impact the ongoing operations; and 10. Methods to insure the safety of all personnel, property, and equipment. References ASTM C1583/C1583M-04 e1, 2004, Standard Test Method for Tensile Strength of Concrete Surfaces and the Bond Strength or Tensile Strength of Concrete Repair and Overlay Materials by Direct Tension (Pull-off Method), ASTM International, West Conshohocken, PA, 5 pp. ICRI, 2004a, Guide for the Preparation of Concrete Surfaces for Repair Using the Hydrodemolition Method, ICRI Technical Guideline No. 310.3, International Concrete Repair Institute, Des Plaines, IL, 16 pp. ICRI, 2004b, Guide to Using In-Situ Tensile Pull-Off Test to Evaluate Bond of Concrete Surface Materials, 2004, ICRI Technical Guideline No. 210.3, International Concrete Repair Institute, Des Plaines, IL, 12 pp. Sources for additional information ACI Committee 318, 2008, Building Code Requirements for Structural Concrete (ACI 318-08) and Commentary, American Concrete Institute, Farmington Hills, MI, 473 pp. ACI Committee 546, 2004, Concrete Repair Guide (ACI 546R-04), American Concrete Institute, Farmington Hills, MI, 53 pp. ICRI, 2006, Guide for the Repair of Unbonded Post-Tensioned Concrete Structures, ICRI Technical Guideline No. 320.4, International Concrete Repair Institute, Des Plaines, IL, 24 pp. ICRI, 2009, Guide for Selecting and Specifying Materials for Repair of Concrete Surfaces, ICRI Technical Guideline No. 320.2R, International Concrete Repair Institute, Des Plaines, IL, 34 pp. Concrete Removal Using Hydrodemolition (ACI RAP-14) 7