NEC Users Group Workshop Defined Cost



Similar documents
NEC ECC Option F ERF 2066 Duynefontein building refurbishment

How To Write A Contract

Appendix 18 NEC3 Options

Insurance Audit Form HELP

NEC3: The Engineering and Construction Contract An overview

Guidance Notes for the NEC Engineering and Construction Contract

International Accounting Standard 11 Construction Contracts

EXPERIENCE SHARING ON THE ADMISITRATION OF THE DSD PILOT CONTRACT (NEC

The South African Council for the Project and Construction Management Professions. Guideline Scope of Services and Tariff of Fees

To be used in conjunction with the Invitation to Tender for Consultancy template.

Construction Contracts

[Project Name] NZTA Contract No. [Contract Number] Schedule of Prices

NEPAL ACCOUNTING STANDARDS ON CONSTRUCTION CONTRACTS

TRANSPORT INDUSTRY COUNCIL

Schedule 11. The Transfer of Undertakings (Protection of Employment) Regulations 2006

A Guide to Standard forms of Construction Contract Outlining Key Characteristics and Components

The following Accounting Standards Interpretation (ASI) relates to AS 7. ASI 29 Turnover in case of Contractors

DEMO Version. Owner and Contractor OCNMP103

Schedule of Prices. Project Name Contract No. Contract Number

A Guide to Small Works. A brief explanation

Overview of the Transfer of Undertakings (Protection of Employment) Regulations 2006

GUIDANCE NOTE Cost Control: Price Variation Clauses

REQUEST FOR PROPOSALS FOR Franchise Fees, Sales and Use Tax Audits

Construction Contracts

How To Write New Government Construction Contracts

Basic Guide. General Conditions of Contract for Construction Works (GCC 2004)

(CAS-4) COST ACCOUNTING STANDARD ON COST OF PRODUCTION FOR CAPTIVE CONSUMPTION

Pricing of Construction Contract Change Order Documentation

Sri Lanka Accounting Standard -LKAS 11. Construction Contracts

PREFACE. The Contract for the Supply and Delivery of Goods has been prepared for use in supplies contracts which have the following characteristics:

NEW YORK STATE DEPARTMENT OF ENVIRONMENTAL CONSERVATION DIVISION OF ENVIRONMENTAL REMEDIATION

Single Project Professional Indemnity Insurance Proposal Form. Note: This is a proposal form for a claims made policy

Contracting Practices in Mega Projects

4 Guidelines on Administration Charges for Reporting of Site Accidents

TREASURER S DIRECTIONS CASH MANAGEMENT TRANSACTION MANAGEMENT Section C3.3 : Corporate Credit Cards

inform practice note SUBCONTRACTING ARRANGEMENTS Content Synopsis: Practice Note # 7 May 2007 (Version 1 - May 2007) construction industry development

CONTRACT CONDITIONS FOR LOGISTICS (2014)

The following amendments have been made to the June 2005 edition deleted: and of notified early warning matters

NEC3 Engineering & Construction Contract An Overview

How To Account For Construction Contracts In Hong Kong Kongsong Accounting Standard 11

7 Contract Costing. Basic Concepts. Contract Costing

Introduction to NEC3. Course agenda. Course objectives. Session 1 Background and underlying principles the concept

Alienation of personal services income

GENERAL CONDITIONS OF CONTRACT MINOR WORKS AND SERVICES

Financial Planner Remuneration Policy October 2009

Partnerships review: limited liability partnerships: treatment of salaried members

The following information has been obtained in relation to the contract:

MASTER AGREEMENT FOR PROJECT MANAGEMENT AND CONSTRUCTION MANAGEMENT SERVICES

The New Standard Construction Contracts: NZS3910, 3916 and 3917

Contractor / Self-employed Person?

Standard conditions of purchase

Section A: Compensation on Termination for Board Default and Voluntary Termination

a. Proposals shall be submitted in a sealed envelope and addressed as follows:

C1.2 CONTRACT DATA PROVIDED BY EMPLOYER (ECC3)

Contract Works and What you need to Know

LEAD PROVIDER FRAMEWORK CALL OFF TERMS AND CONDITIONS

ANNEX 8 Contract Management Strategy

Agency Temporary Worker Processes (IA /F v1) Tricia Riley, HR Director. Audit Conclusion: Audit Closed

a) To achieve an effective Quality Assurance System complying with International Standard ISO9001 (Quality Systems).

Marginal and. this chapter covers...

Questionnaire CONTRACTOR PAYMENTS

Sealed bids will be received by the City of Dearborn, at the Office of the Purchasing

California Senate Bill 474 Impact on Owners & Contractors

RBI ASSET MANAGEMENT STANDARD CONDITIONS OF BUSINESS

The South African Council for the Project and Construction Management Professions (SACPCMP)

JCT Standard Building Contract SBC/Q

AGENCY AGREEMENT. Between 3Keys Limited company registration number of Town End Doncaster DN5 9AG Postcode..

Construction Contracts

INLAND REVENUE BOARD MALAYSIA CONSTRUCTION CONTRACTS

GOVERNMENT OF MALAYSIA

Practical Cost Savings Strategies

DAVID THOMAS LTD GUIDE TO COMPANY INSOLVENCY

Warranties, Bonds and Guarantees in the Construction World

Schedule 12 - Insurances

OH&S MANAGEMENT SYSTEM CHECKLIST - AS 4801:2001 (STATUS A = Acceptable; N = Not Acceptable; N/A = Not Applicable)

GETTING STARTED WITH THE NEC3

CHAPTER 3.0: PROCUREMENT AND CONTRACTING

The Society of Garden Designers

Performance indicators, quality benchmarking and cost/efficiency of emergency services Cost analysis of Emergency Call Answering Services

Actuarial Speak 101 Terms and Definitions

Derbyshire Healthcare NHS Foundation Trust. Lease Car Scheme

KEY MORTGAGE INFORMATION & EXPLANATIONS

Producing a programme under the NEC form of contract

Financial errors in FP7. How to improve the quality of financial statements? Paris, 21 February 2013 Vittorio MORELLI Svetozara PETKOVA Simona STAICU

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER-AT-RISK

GENERAL CONDITIONS OF THE FEDERAL DEPARTMENT OF FOREIGN AFFAIRS FOR LOCAL MANDATES

We: - all references to 'we' below shall be taken as meaning Kierbeck Thames Ltd.

How to get value for money from service providers on major projects

RTI Statement for New Starters Please tick the relevant box below:

Business Interruption Insurance. Module 1: The Basics of BI

BP NEW ZEALAND PURCHASE ORDER GENERAL TERMS

Transcription:

NEC Users Group Workshop Defined Cost Ian.Heaphy@turntown.com; July 2014 Turner & Townsend plc July 14 making the difference

Introduction Practicalities in assessing of Defined Cost & Disallowed Cost Assumption that you have a basic understanding of Defined Cost and the Schedule of Cost Components Focus particularly on it being the method for reimbursing the Contractor under Options C, D & E of ECC3 Defined Cost in the assessment of compensation events under Options A, B, C, D & E Interactive workshop Share experiences / issues / knowledge Ask questions, debate, challenge 2

Defined Cost Defined Cost - Definition changes between Main Options Serves 2 purposes Under all Main Options basis for assessing the financial impact of compensation events Under Main Options C, D, & E it is also the basis for reimbursing the Contractor for the Price for Work Done to Date 3

Defined Cost as the basis for Payment of the PWDD making the difference

Defined Cost = Actual Cost? Under cost reimbursable contracts Contractor is paid their actual cost? What is actual cost? Cost reimbursable contracts do not pay real actual cost It is very difficult / impossible to work out the actual cost Many costs are not project specific and are shared over many projects Cost reimbursable contracts contain a set of rules over what costs can be claimed and how Cost needs to be clearly and completely defined in the Contract ECC Defined Cost that defines what costs can be recovered and how 5

Defined Cost - Definition ECC - Options C, D & E, 11.2 (23) Defined Cost is and the amount of payments due to Subcontractors for work which is subcontracted without taking account of amounts deducted for retention payment to the Employer as a result of the Subcontractor failing to meet a Key Date the correction of Defects after Completion payments to Others and the supply of equipment, supplies and services included in the charge for overhead cost within the Working Areas in this Contract the cost of components in the Schedule of Cost Components for other work less any Disallowed Cost 6

Schedule of Cost Components There are two Schedules of Cost Components Shorter Schedule of Cost Components used with Options A & B (and if agreed options C-E) only used to assess compensation events Schedule of Cost Components used with C-E used to assess compensation events and determine the Price for Work Done to Date The schedules are a set of rules to define those components of the Contractor s cost which are included in Defined Cost Linked to Contract Data Part 2 7

Schedule of Cost Components Subcontractors Direct Cost Your experiences / issues? Common issues Value for money tests Value is achieved by driving efficiency in the Contractor and their supply chain How do you ensure value for money achieved? Works undertaken by internal or affiliated companies 8

Schedule of Cost Components ECC approach Amounts included in Defined Cost are at open market or competitively tendered prices with deductions for all discounts, rebates and taxes which can be recovered Competitive testing of prices or Open market prices - benchmarking Additional requirements to enforce competitive tendering? Quality v price VFM should be driven by pain / gain mechanism? 9

Schedule of Cost Components Contactor s other costs Schedule of Cost Components is split into the following sections 1. People 2. Equipment 3. Plant and Materials 4. Charges 5. Manufacture and fabrication 6. Design 7. Insurance 10

People Costs incurred in the Working Area Definition? Who determines the Working Areas? Can it change? 11

People Direct costs of employment of the staff and labour engaged by the Contactor to deliver the works Your experiences / issues? Common issues True cost of staff or salary costing rate? Key to understand the basis of the rate Total hours divided by annual costs holidays / sick days / training etc. Overtime Benefits in kind phone / car / fuel card / expenses Pay rises, bonuses and redundancy costs 12

Equipment & Plant Costs incurred in the Working Areas Direct cost for hired Equipment Agreed schedule of rates for Contractor s own Equipment Additional Equipment at notional external hire rates Equipment purchased - a payment for the difference in value between purchase price and open market sale price for Equipment bought specifically for the works Your experiences / issues? Common issues Ability to benchmark discount agreement What if internal costs are higher but quality / performance is better VFM 13

Materials Direct costs incurred in purchasing the Plant and Materials Your experiences / issues? Common issues Volume / annual company wide discounts how are these accounted for? Do they still exist? Should they be shared with the Employer 14

Charges Direct costs of water, gas and electricity used in the Working Areas Direct costs of payments to authorities and listed items Application of a Working Areas overhead percentage to the total cost of People to cover for a list of overhead costs incurred within the Working Areas Your experiences / issues? Common issues with Working Areas Overhead Purpose Coverage Pricing 15

Manufacture and Fabrication & Design Costs incurred outside the Working Areas Shared facilities Difficult to allocate the actual costs of the shared facility to the project Pre-agreed schedule of hourly rates Plus pre-agreed percentage for overheads Your experiences / issues? Commons issues Ensure this information is competed as part of Contract Data Part 2 Design by the Contractor s own staff sub-consultant would be a Subcontractor under the ECC 16

Insurance Deducted from Defined Costs The costs of events which the Contractor has to insure Other costs paid to the Contractor by insurers Your experiences / issues? Common issues Identifying and valuing insurable events Insurance excesses borne by the party who carries the risk Insurance provided by Employer but risk carried by Contractor? 17

Verifying Defined Cost Need to put in place an audit process to validate Contractor s costs Contractor is required to keep these records Accounts of payments of Defined Cost Proof that the payment has been made - what does this mean, banking records? Communications about and assessments of compensation events for Subcontractors and Other records as stated in the Works Information chance to enhance and clarify requirements Commonly no further requirements added and no pre-agreement over the level of information required Your experiences / issues? 18

Verifying Defined Cost Common issues Need to understand and validate Contractor s costing system On site costing system can be different to accounting software and can act more as a profit and loss account for the Project than a true record of costs incurred Costs posted but not paid / journal entries Allocation of costs to projects such as staff costs / equipment depreciation etc. Audit of cost Sample audit common approach 10% - vertical and horizontal audit Computer aided audit systems 100% audit Review resources on site and material deliveries to ensure that these are correct and not excessive 19

Disallowed Cost making the difference

Disallowed Costs Costs that do not form part of the definition of Defined Cost - covered by the Fee non allowable costs Disallowed Cost is cost the Contractor may have incurred and fall within the definition of Defined Cost, but The costs have only been incurred due to some failure or default of the Contractor The Project Manager can reject payment Disallowed costs are therefore cost borne entirely by the Contractor Have to be covered by the Fee 21

Disallowed Cost Amounts not justified by the Contactor s accounts and records To what level of detail actual records of payment via bank records Accruals / liabilities / journal entries Should not have been paid to a Subcontractor or supplier in accordance with their contract Clause 26 Project Manager needs to see copies of subcontracts Settlement agreements? 22

Disallowed Cost Costs incurred because the Contractor did not follow an acceptance or procurement procedure stated in the Works Information Assessing the extra over cost due to the failure what costs could have been saved Contractor failed to give an early warning which this contract required him to give Gift of hindsight - assess what could have happened, what costs could have been saved Disallow all costs incurred and / or add back the costs that would have been incurred if so how? 23

Disallowed Cost Plant and Materials not used to Provide the Works (reasonable wastage) What is reasonable Pre-agree wastage allowances Resources not used to Provide the Works (reasonable availability and utilisation) Standby plant? Pre-agree any debateable items Preparation for adjudication / tribunal When does commercial management become preparation for adjudication? 24

Disallowed Cost Correcting Defects after Completion Correcting Defects prior to Completion Defect not in accordance with the Work Information or applicable law Not all Defects covered only Defects caused by the a failure to comply with a constraint on how to provide the works stated in the Works Information What is a constraint on how? Examples 25

Disallowed Cost Majority of Defects prior to Completion will be allowable There will always be Defects during construction Someone will have to bear the cost of correction ECC has drafted clauses to allocate risk but definition is difficult Identification and capture an issue and cost Behaviours the approach creates Hiding Defects Snag free hand over Pay anyway as part of the Fee? Costain V Bechtel Ltd [2005] EWHC 1018 (TCC) independent certifier 26

Compensation Events making the difference

Compensation events Under all Main Options basis for assessing the financial impact of compensation events By agreement rates and lump sum prices can be used under Options C, D & E Option C, D & E Definition as used for payment Same issues apply 28

Option A & B Defined Cost Options A & B Only used for assessing compensation events Defined Cost is the cost of the components of the Shorter Schedule of Cost Components whether work is subcontracted or not excluding the cost of preparing quotations for compensation events Determining the cost of preparing quotations as opposed to normal commercial activities 29

Option A & B If work is Subcontracted ignore the actual cost of the Subcontractor and price based on the Shorter SoCC Lump sum quotation from Subcontractor how do you work out man hours etc? Level of breakdown required into categories or rates for staff etc? Specialist work which the Contractor does not undertake what basis for pricing? No overheads and profit allowed for Subcontractor work has to be in included in the Fee - subcontracted fee percentage 30

Summary making the difference

Summary Recap of the session Clarify any issues Capture actions / learning points Thank You 32