Contents. The Planning Hierarchy. Capacity / Load. TPPE37 Manufacturing Control



Similar documents
ISE 421 QUANTATIVE PRODUCTION PLANNING

Material Requirements Planning (MRP)

CHAPTER 6 AGGREGATE PLANNING AND INVENTORY MANAGEMENT 명지대학교 산업시스템공학부

TU-E2020. Capacity Planning and Management, and Production Activity Control

1 Material Requirements Planning (MRP)

2.4 Capacity Planning

Production Planning Solution Techniques Part 1 MRP, MRP-II

A DECISION SUPPORT SYSTEM FOR CAPACITY MANAGEMENT. A Senior Project. presented to

Chapter 7. Production, Capacity and Material Planning

INDEPENDENT STUDY PAILIN UDOMSANTI

Functional Area Systems Production / Operation Systems

26/10/2015. Functional Area Systems Production / Operation Systems. Examples: Functional Area Info Systems. Functional Area Information Systems

BILL OF RESOURCES AND PRIORITY-CAPACITY BALANCING

Agenda. TPPE37 Manufacturing Control. A typical production process. The Planning Hierarchy. Primary material flow

Operations Management

Material Requirements Planning. Lecturer: Stanley B. Gershwin

Manufacturing Planning. Master Production Schedule. Material Requirements Plan. Work Order/ FPO Maintenance. Soft Bill Maintenance

ERP(Enterprise Resource Planning) & MRP

OR topics in MRP-II. Mads Jepsens. OR topics in MRP-II p.1/25

Short-term Planning. How to start the right operation at the right shop at the right time? Just in Time (JIT) How to avoid waste?

BSCM Sample TEST. CPIM(Certified In Production & Inventory Management) - 1 -

2.5 Checklist for ERP Implementation

Chapter 7 Production Planning

An Introduction to Capacity Planning

Rough Cut Capacity Planning-(RCCP)-(Case Study)

Universidad del Turabo MANA 705 DL Workshop Eight W8_8_3 Aggregate Planning, Material Requirement Planning, and Capacity Planning

PARADIGMS THAT DRIVE COSTS IN MANUFACTURING. The whole purpose of a business enterprise is pretty simple to make a profit by selling

12 MRP and ERP. Dr. Ron Lembke

Table of Contents. Planning the ERP System...1

1.3 ERP System Evolution

Dependent vs Independent Demand. The Evolution of MRP II. MRP II:Manufacturing Resource Planning Systems. The Modules In MRP II System

IM 322 Inventory Management

IT-375 using the 6 th Edition PRODUCTION AND INVENTORY CONTROL CHAPTER 1: INTRODUCTION TO MATERIALS MANAGEMENT

QAD Enterprise Applications Standard & Enterprise Edition. Training Guide MRP/CRP

Material Requirements Planning MRP

Master Scheduling and Rough-cut Capacity Planning

Issues in Information Systems Volume 14, Issue 2, pp , 2013

SAP ERP Versus SAP APO: Which Production Planning Functionality Do I Use, and How Can I Be Successful?

SPREADSHEET SIMULATOR FOR INVENTORY MANAGEMENT IN A SUPPLY CHAIN

MATERIAL REQUIREMENTS PLANNING

INVENTORY MANAGEMENT

Consumption-Driven Finite Capacity Inventory Planning and Production Control. A thesis presented to. the faculty of

Visual Planning and Scheduling Systems. A White Paper. Gregory Quinn President Quinn & Associates Inc September 2006 Updated October 2006

INTRODUCTION. What is Enterprise Resource Planning?

Release: 1. MEM30019A Use resource planning software systems in manufacturing

How To Learn How To Manage A Business

Basics of Supply Chain Management (BSCM) Curriculum

IE 367 PRODUCTION PLANNING AND CONTROL. Office Hours: T, Th: 12:00 1:00 p.m. Other times by appointment; please call or e- mail.

Functional Area Systems Lecture 5

THE USE AND APPLICABILITY OF CAPACITY PLANNING METHODS

GESTION DE LA PRODUCTION ET DES OPERATIONS PICASSO EXERCICE INTEGRE

Master Planning The Forgotten, But Vital, Manufacturing Supply Chain Planning Process

Chapter 1. The Production Paradigm

Waiting Times Chapter 7

An investigation into production scheduling systems

Operations Management

ERP Course: Production and Materials Management Reading: Chapter 6 from Mary Sumner

Production Planning & Control. Chapter 2. Aggregate Planning & Master Production Scheduling. Chapter2 1

Integrated Supply Chain Management Course

Cadena de suministro. Mtro. William H. Delano Frier

APS1028 Operations and Production Management - Fall 2014 (Monday Noon-2 PM starting 8 th September 2014: BA B025 (the basement classroom)

Utilizing KolibriMFG Software System to Schedule and Control Shop Floor

CISCM STUDY GUIDE. International Purchasing and Supply Chain Management Institute,

Manufacturing. Manufacturing challenges of today and how. Navision Axapta solves them- In the current explosive economy, many

Manufacturing Applications in Microsoft Dynamics GP 10.0

MASTER PRODUCTION SCHEDULE

BEDIFFERENT A C E I N T E R N A T I O N A L

Material Requirement Planning (MRP) Mohd Yusnurahman Bin Mohd Yuznah

TU-E2020 ADVANCED OPERATIONS MANAGEMENT. Demand management Sales & Operations Planning Master Production Scheduling

Management Information Systems

APICS acknowledges the Basics of Supply Chain Management Committee for its contributions in the development of this resource.

Document Summary: HowTo Manufacturing Light v3.odt

Go Beyond Simple Productivity improvement with Optimized Production Scheduling

Manufacturing Management

A New Approach for Finite Capacity Planning in MRP Environment

DESIGN & IMPLEMENTATION OF A BESPOKE MRPII SYSTEM FOR A SMALL AND MEDIUM ENTERPRISE (SME) MANUFACTURING COMPANY

A Diagnostic Approach to Scheduling

EnterpriseOne Requirements Planning 8.9 PeopleBook

NETWORK BUSINESS SYSTEMS SOFTWARE SYSTEM DOCUMENTATION MANUFACTURING SYSTEM FEATURES

Manufacturing Planning and Control for Supp Chain Management

Oracle Capacity User s Guide

MRP, ERP och JIT. Styrningsnivåer. Johann Packendorff. The development of ERP. Increasing impact on the whole supply

Production Management

May 2011 V6.1. Training Course. OP203: Fundamentals Manufacturing

Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras

MODULE B1 MANUFACTURING RESOURCE PLANNING (MRP II)

Manufacturing Planning and Control for Supply Chain Management

Production Planning and Execution (PP)

BEYOND THE BASICS OF MRP: IS YOUR SYSTEM DRIVING EXCESSIVE ORDER QUANTITITES? Michael D. Ford, CFPIM, CSCP, CQA, CRE Principal, TQM Works Consulting

Hessel Visser NCOI Les 6 A P 373. Operations Management, 7E: Chapter 14 en15

Evolving To The Enterprise Production System (EPS)

Capacity Requirements Planning (CRP)

MANAGEMENT ISSUES-MRP

Transcription:

TPPE37 Manufacturing Control Contents Lecture 6 Capacity Planning Capacity theory RoughCut Capacity Planning Three different techniques Comparison of of the the techniques Capacity Requeriments Planning (CRP) Manufacturing Resource Planning (MRPII) Capacity theory, RCCP, CRP, MRPII 1 Capacity theory, RCCP, CRP, MRPII 2 The Planning Hierarchy Capacity / Load Master planning Demand management Feedback Final assembly schedule Vendor systems Sales and operations planning Production planning Master prod. schedule Material planning Shop floor systems Resource planning Master (production) scheduling Roughcut capacity plan Detailed capacity planning Front end Engine Back end Capacity: The capability of ofa resource to to produce output per time period Load: The amount of of planned work scheduled for for and actual work released to toa resource for for a specific time Capacity utilization Load/Capacity Capacity theory, RCCP, CRP, MRPII 3 Capacity theory, RCCP, CRP, MRPII 4

Traditional definition of capacity Capacity definitions (1) C = T E U ( L ) C= Calculated capacity T= Theoretical capacity E= Efficiency factor U= Utilization factor L= Load Efficiency = a ameasure of of how how closely predetermined standards are are achieved Utilisation = a ameasure of of how how intensely a resource is isbeing used Capacity theory, RCCP, CRP, MRPII 5 Theoretical capacity Based on on clock hours Example: 4 machines 8 hrs/day 5 days/week = 16 16hrs/week.2.2 standard hours/pcs 16/.2 = 8 8pcs/week Theoretical capacity (T)= (T)= 8 8pcs/week or or16 16hrs/week Calculated capacity, Planned capacity Theoretical capacity adjusted for forutilization and andefficiency Example: 16 16theoretical hrs/week 9% 9% util. util. 8% 8% eff. eff. = 1.2 hrs/week.2.2 standard hours/pcs 1.2/.2 = 576 576pcs/week Calculated capacity (C) (C) = 576 576pcs/week or or1.2 hrs/week Capacity theory, RCCP, CRP, MRPII 6 Capacity definitions (2) Load / Queues Demonstrated capacity Based on on historical averages over over the the previous periods Example: The Thelast lastsix sixperiods production: = 58, 58, 565, 565, 575, 575, 57, 57, 59, 59, 56 56 Average production = 573 573 pcs/week.2.2 standard hours/pcs 573.2 = 114.6 hrs/week Demonstrated capacity = 573 573pcs/week or or114.6 hrs/week Queue (length/time) Maximum capacity The Themaximum possible capacity a system can can provide without further investments 1% Load Capacity theory, RCCP, CRP, MRPII 7 Capacity theory, RCCP, CRP, MRPII 8

RoughCut Capacity Planning Techniques for RCCP Better name: RoughCut Load Estimation Rough estimation of of future loads of of the resources Most common in inbatch manufacturing (classical RCCP) which is is a dynamic and information intensive environment InOnetime manufacturing is iseach order given a detailed schedule from the thestart which makes RCCP superfluous InFlow manufacturing the the environment is isstatic and a detailed analysis is iscarried out for foreach change Estimation whether more capacity, less capacity or or load leveling is isnecessary for for a better fit fit between capacity and load. Three different techniques: Capacity Planning Using Overall Factors Capacity Bills, Bill Billof of Resources Resource Profiles Capacity theory, RCCP, CRP, MRPII 9 Capacity theory, RCCP, CRP, MRPII 1 Ex: RCCP Capacity Planning Using Overall Factors A company has two end products, A och B, B, that are manufactured in inthree critical resources,, WC2 and WC Work Center Capacity (hours per period) 36 (= 4.9 1.) WC2 38 (= 4.95 1.) WC 2 (= 4.5 1.) Period 1 2 3 4 5 6 7 8 MPS: A 33 33 4 4 37 37 MPS: B 17 17 13 13 27 27 Information required: Master Production Schedule Resources demanded (end (end items) Historical load load of of resources Assumptions: The The historical level level will will continue The Thesame sameproduct mix mix Capacity theory, RCCP, CRP, MRPII 11 Capacity theory, RCCP, CRP, MRPII 12

Ex: CPOF (1) Ex: CPOF (2) Product Standard time / item A.95 hours B 1.85 hours Quarter 1 Quarter 2 Quarter 3 Quarter 4 Total Historical percentage 1 9 14 55 6,3 % WC2 55 6 8 6 5,4 % WC 18 2 78 9,3 % Week 1 2 3 4 5 6 7 8 Total (%) : A : B : A+B WC2: A WC2: B WC2: A+B WC: A WC: B WC: A+B 18.9 18.96 37.86 9.53 9.56 19.9 2.92 2.92 5.84 18.9 18.96 37.86 9.53 9.56 19.9 2.92 2.92 5.84 22.91 14.5 37.41 11.55 7.31 18.86 3.53 2.24 5.77 22.91 14.5 37.41 11.55 7.31 18.86 3.53 2.24 5.77 17.19 27.89 45.8 8.66 14.6 22.72 2.65 4.38 6.95 17.19 27.89 45.8 8.66 14.6 22.72 2.65 4.38 6.95 21.2.12 51.32 1.69.18.87 3.27 4.65 7.92 21.2.12 51.32 343.34 (6.3) 1.69.18.87 173.8 (.4) 3.27 4.65 7.92 52.96 (9.3) Total 62.79 62.79 62.4 62.4 74.75 74.75 85.11 85.11 569.38 (1) Capacity theory, RCCP, CRP, MRPII 13 Capacity theory, RCCP, CRP, MRPII 14 Capacity bills Ex: Capacity bills (1) Information required: Master Production Schedule Capacity bills bills Resources demanded (end (end items itemsand andcomponents) Bill Billof ofmaterial, BOM BOM Assumption: The The historical level level continues. Independent of of time time phasing. Standard lot lot sizes. Capacity theory, RCCP, CRP, MRPII Product Lot size Work center Setup time [hrs/batch] Setup [hrs/pcs] Oper. time [hrs/pcs] Total [hrs/pcs] A 4 1....5 B 2 1..5 1. 1. C 4 WC2 WC 1. 1....575.175.6.2 D 6 WC2 2..33.67.1 E 1 WC2 2..2.8.1 F 1 WC2 2..2.4.6 Bill of capacity: Work center A [hrs/pcs] B [hrs/pcs].5 1. WC2.7.55 WC.2. Total [hrs/pcs].95 1.85 Capacity theory, RCCP, CRP, MRPII 16

Ex: Capacity bills (2) Resource Profiles Week 1 2 3 4 5 6 7 8 Total (%) : A : B : A+B WC2: A WC2: B WC2: A+B WC: A WC: B WC: A+B 1.65 22.1 23.75 23.1 9.35 32.45 1.65 22.1 23.75 23.1 9.35 32.45 2. 16.9 18.9 2 7. 35. 2. 16.9 18.9 2 7. 35. 1.5 32.5 34. 21. 13.75 34.75 1.5 32.5 34. 21. 13.75 34.75 1.85 35.1 36.95.9 14.85 4.75 7.4 7.4 1.85 35.1 36.95 227.2 (39.9).9 14.85 4.75 286.2 (5.3) 7.4 7.4 5 (9.8) Total 62.8 62.8 62.5 62.5 74.75 74.75 85.1 85.1 569.4 (1.) Information required: Master Production Schedule Resources demanded (end (end items and andcomponents) Bill Billof ofmaterial, BOM Lead Lead time timeoffsets Assumption: Standard lot lot size size Capacity theory, RCCP, CRP, MRPII 17 Capacity theory, RCCP, CRP, MRPII 18 Ex: Resource Profiles (1) Ex: Resource Profiles (2) Resources required Standard time/item and and period Product Work center 2 1 A B WC2 WC WC2.6..1.2..5 1. Capacity theory, RCCP, CRP, MRPII 19 Week 1 2 3 4 5 6 7 8 Total (%) :A :B :A+B WC2:A1* WC2:A2* WC2:B1* WC2:B2* WC2:A+B WC:A WC:B WC:A+B 3. 39.6 5.1 8.5 56.5 1.65 22.1 23.75 3. 24. 5.1 3. 35.65 1.65 22.1 23.75 4. 24. 3.9 3. 35. 2. 16.9 18.9 4. 1 3.9 6. 32. 2. 16.9 18.9 3. 1 7.5 6. 34.75 1.5 32.5 34. 3. 22.2 7.5 6.75 39.45 1.5 32.5 34. 3.7 22.2 8.1 6.75 4.75 7.4 7.4 1.85 35.1 36.95 3.7 8.1 11.8 7.4 7.4 1.85 35.1 36.95 227.2 (39.9) 286.2 (5.3) 5 (9.8) Total 63.1 6 66.9 59.5 59.65 79.45 82. 56. 36.95 569.4 (1.) * A1,B1 A1,B1 och och A2,B2: A2,B2: Capacity required requiredfor for order ordertoto be bedelivered in in 1 or or2 periods. periods. These These are are assumed to tobe be in in process, process, if ifnot notthey they are are (past (past due) due) and and must must be beadded to to the theplan for for period period 1 and and forward forward Capacity theory, RCCP, CRP, MRPII 2

Ex: Comparison of results Summary (1) Work center WC2 Week 1 2 3 4 5 6 7 8 Total CPOF 19.9 19.9 18.86 18.86 22.72 22.72.87.87 173.8 (4) Capacity bills 32.45 32.45 35. 35. 34.75 34.75 4.75 4.75 286.2 (4) Resource prof. 56.5 35.65 35. 32. 34.75 39.45 4.75 11.8 286.2 (4) 6 4 CPOF Capacity bills 2 Resource profiles 1 2 3 4 5 6 7 8 Capacity theory, RCCP, CRP, MRPII 21 Capacity Planning Using Overall Factors, CPOF Advantages + Small amount of ofdata dataneeded + Simple calculations Disadvantages Valid only onlyas aslong longas asthe historical percentage is isapplicable Based on on historical production No Noexplicit relation between end end items produced and andhow the the items are are manufactured and andresourcesare required (e.g. (e.g. via via BOM) No Nolead time timeoffsetting which is isnecessary when demand varies Capacity theory, RCCP, CRP, MRPII 22 Summary (2) Summary (3) Capacity Bills Advantages + Better coupling between enditems and andresource requirements + Simple + Valid also also when the the product mix mixchanges Disadvantages Requires detailed data dataconcerning BOM and androuting (setup and and operation times) No Nolead time timeoffsetting which is isnecessary when demand varies The The setup time timeisis allocated based on onstandard lot lot sizes sizes (could be be misleading if if dynamic lot lot sizing is isused) Capacity theory, RCCP, CRP, MRPII 23 Resource profiles Advantages + Better coupling between enditems and andresource requirements + Lead Lead time timeoffsetting which is isnecessary when demand varies + Valid also also when the the product mix mixchanges Disadvantages Requires detailed data dataconcerning BOM and androuting (setup and and operation times) The The setup time timeisisallocated based on onstandard lot lot sizes sizes (could be bemisleading if if dynamic lot lot sizing is isused) Capacity theory, RCCP, CRP, MRPII 24

Resource planning, RP Ex: Resource planning A weighted sum of of resources required according to torccp Work center A [hrs/pcs] B [hrs/pcs] AB [hrs/pcs].5 1..89 WC2.7.55.6 WC.2..7 Total [hrs/pcs].95 1.85 1.55 Capacity theory, RCCP, CRP, MRPII Capacity theory, RCCP, CRP, MRPII 26 Capacity requirements planning What is the timing of load? Information about planned order from the thempc system Info. about released orders from manufacturing (and from purchasing in insome cases) Deterministic simulation based on on released and planned orders Load reports (CRP reports) are the the outputs Estimated load is iscompared to to available capacity RoughCut Capacity Planning (RCCP) Focuses on on average load load (over the the planning horizon) Capacity Requirements Planning (CRP) Focuses usually on on cumulate load load (by (by period) Capacity theory, RCCP, CRP, MRPII 27 Order start and order due date are set setbut when are the the individual operations performed? Forward scheduling Based on onorder start Back scheduling Based on on due dates Capacity theory, RCCP, CRP, MRPII 28

Example: CRP Ex: Material data Time phased manufacturing MRPbased MPC system one enditem, three work centers Planning principle: One operation per week Planning horizon is is 12 weeks but only 7 weeks are included in inthe matrices Todays date: Friday /6 Level Item Antal per moderartikel Beskrivning 1 1 End item 1 11 2 Sub assembly 2 121 3 Component A 2 122 5 Component B Item no. Lot sizing On hand invent Sched. receip. Lead time Allocations [Weeks] 1 LFL (3/7) 1 11 FOQ = 4 5 4 (1/7) 2 121 FOQ = 24 24 (1/7) 3 122 FOQ = (1/7) 4 Capacity theory, RCCP, CRP, MRPII 29 Capacity theory, RCCP, CRP, MRPII Ex: Operation data and MPS Ex: Routing Work center Available time [min/week] Utilization Efficiency Planned queue [days] 24 (= 5 8 6) 1% 1% 4 WC2 24 1% 1% 4 WC3 24 1% 1% 4 W eek 1 2 3 4 5 6 7 8 9 1 11 12 MPS 2 2 2 2 2 Item Work center Setup time [min/batch] Operation time [min/unit] 1 2.5 11 WC2 121 WC3 WC2 122 WC2 WC3 WC3 1 75.75.5.3...75..5.35 Capacity theory, RCCP, CRP, MRPII 31 Capacity theory, RCCP, CRP, MRPII 32

Ex: Material flows Ex: RCCP Capacity Bills Week 1 2 3 4 5 6 7 Average load 263 283 263 62 283 3124 62 2231 WC2 2657 2126 2657 94 2126 3189 94 2278 WC3 1734 1387 1734 141 1387 281 14 1486 24 12 WC2 WC3 1 2 3 4 5 6 7 Avera. Capacity theory, RCCP, CRP, MRPII 33 Capacity theory, RCCP, CRP, MRPII 34 Ex: MRPcalculation (1) Item no: 1 Description: End item Lead time: 1 week Buffer: Lot sizing: LFL Period 1 2 3 4 5 6 7 Gross requirements 2 2 Scheduled receipts Inventory position 2 45 8 11 1 Net requirements 2 2 Net req. consid. planned orders 2 2 Planned order receipts 2 2 Projected available balance Planned order releases 2 2 Item no: 11 Description: Sub assembly Lead time: 2 weeks Buffer: Lot sizing: FOQ=4 Period 1 2 3 4 5 6 7 Gross requirements (2*1) 4 5 4 5 Scheduled receipts 4 Inventory position 5 1 7 1 17 2 Net requirements 4 5 Net req. consid. planned orders 5 4 Planned order receipts 4 4 5 4 4 Projected available balance 5 1 1 1 1 Planned order releases 4 4 5 4 4 4 4 Ex: MRPcalculations (2) Item no: 121 Description: Component A Lead time: 3 weeks Buffer: Lot sizing: FOQ=24 Period 1 2 3 4 5 6 7 Gross requirements (3*11) 12 12 12 12 12 12 Scheduled receipts 24 Inventory position 12 24 3 48 Net requirements 12 12 12 12 Net req. consid. planned orders 12 12 Planned order receipts 24 24 Projected available balance 12 12 Planned order releases 24 24 24 24 Item no: 122 Description: Component B Lead time: 4 weeks Buffer: Lot sizing: FOQ= Period 1 2 3 4 5 6 7 Gross requirements (5*11) 2 2 2 2 2 2 Scheduled receipts Inventory position 5 45 2 2 4 Net requirements 2 2 2 Net req. consid. planned orders 2 Planned order receipts Projected available balance 5 45 2 4 2 Planned order releases Capacity theory, RCCP, CRP, MRPII 35 Capacity theory, RCCP, CRP, MRPII 36

Ex: Setup matrix (planned orders) Ex: Op. time matrix (planned orders) 1 11 121 122 WC2 1 11 121 122 WC3 1 11 121 122 Item 1 2 3 4 5 6 7 75 75 Total 7 12 7 45 145 7 1 1 1 1 1 1 1 Total 35 1 35 1 Total 45 Capacity theory, RCCP, CRP, MRPII 37 1 11 121 122 WC2 1 11 121 122 WC3 1 11 121 122 Item 1 2 3 4 5 6 7 5 6 2 375 2 5 75 2 375 2 6 2 Total 5 14 3575 135 95 4175 14 45 375 45 Total 48 975 48 9 9 9 21 9 21 Total 9 21 21 Capacity theory, RCCP, CRP, MRPII 38 Ex: Capacity req. for planned orders Ex: Capacity req. for released orders Setup time + Operation time Week 1 2 3 4 5 6 7 Average load 5 1495 3695 142 995 432 1495 1993 WC2 4835 31 1 4835 9 31 9 1877 WC3 6 9 6 21 45 6 21 1226 Remaining operations for forreleased orders (Sched. receipts.). This information is isobtained from the thempc system. Item Work center Week Setup time Operation time Total time 1 1 2.5 = 6 655 11 WC2 121 WC2 122 WC3 1 2 1 2 1 2 1 75 4.75 = 4.5 = 2 24. = 24. =.5 =.35 = 21 31 2 6 6 75 21 Capacity theory, RCCP, CRP, MRPII 39 Capacity theory, RCCP, CRP, MRPII 4

Ex: Total capacity req. acc. to CRP Ex: CRP Load report Week 1 2 3 4 5 6 7 Average load 4885 171 3695 142 995 432 1495 2634 WC2 5145 9 1 4835 9 31 9 29 WC3 6 6 6 21 45 6 21 1 1 Work center 2 Cum. dev. 48 24 1 2 3 4 5 6 7 Avera. WC2 WC3 Week 1 2 3 4 5 6 7 Capaciy [min.] 24 24 24 24 24 24 24 Load [min.] 5145 9 1 4835 9 31 9 Utilization [%] 214.4 38.5 41.7 21.5 26. 12.9 38.5 Deviation [min.] 2745 1475 14 2435 1475 29 1475 Cumulative dev. [min.] 2745 127 1 8 126 2735 Capacity theory, RCCP, CRP, MRPII 41 Capacity theory, RCCP, CRP, MRPII 42 Ex: Result of setup reduction 1 Ex: Result of setup reduction 2 5% reduction of of setup times Lot sizing: According to tolfl Week 1 2 3 4 5 6 7 Average load 316 186 2273 2173 2273 2323 2198 2323 WC2 2433 228 22 5 22 613 688 1842 WC3 1893 23 1778 13 1488 1338 89 1 Item no. Previous lot sizing New lot sizing 1 LFL LFL 11 FOQ (4) LFL 121 FOQ (24) LFL 122 FOQ () LFL 24 1 2 3 4 5 6 7 Avera. WC2 WC3 Capacity theory, RCCP, CRP, MRPII 43 Capacity theory, RCCP, CRP, MRPII 44

Ex: Result of setup reduction 3 Definitions of MRPconcepts 5 1 Work center 2 Cum. dev. 1 Week 1 2 3 4 5 6 7 Capacity [min.] 24 24 24 24 24 24 24 Load [min.] 2433 228 22 5 22 613 688 Utilization [%] 11.4 92 91.7 16.2 91.7.5 28.7 Deviation [min.] 33 192 2 85 2 1787 1722 Cumulative dev. [min.] 33 9 359 129 149 3196 4918 Capacity theory, RCCP, CRP, MRPII 45 MRP, also MRP I, I, mrp or or little MRP: Material requirements system based on on the the net net requiement calculations Closed loop MRP: MPS + RCCP + MRP + CRP + feedback (PAC) MRPII: Manufacturing resource planning concerns all all the the resources of of the the company and also generates output in in terms of of financial consequences of ofall decisions. Capacity theory, RCCP, CRP, MRPII 46 Closedloop MRP system Capacity theory, RCCP, CRP, MRPII 47