CIMS Information Systems Used to Manage Capital Projects. Samuel Hutchins September 14, 2010

Similar documents
Eni s Implementation of a Project Management Information System for the Goliat Project

Designer & Builder Symposium Construction Scheduling. Glenn Saito NAVFAC Pacific Construction Division December 1, 2010

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 COST MANAGEMENT WITH EXPENSES

Cash flow is the life line of a business. Many start-up

Projectmates User Guide for Montclair State University Facilities Construction Projects

BlueCielo Meridian Today

COST MANAGEMENT WITH EXPENSES

PRIMAVERA CONTRACT MANAGEMENT

Design Consultant Project Management Requirements

City Contract Management System (CCMS) Prime and Subcontractor Training

Business Intelligence Experts for SmartPlant integration. Technical Specifications

Thank you for joining today s technical webinar

YARDI Voyager Residential

ORACLE S PRIMAVERA CONTRACT MANAGEMENT, BUSINESS INTELLIGENCE PUBLISHER EDITION

ipm IPM PROJECT MANAGEMENT

REQUEST FOR INFORMATION. for the purchase of a PROGRAM, PROJECT AND DOCUMENT MANAGEMENT SYSTEM SOFTWARE MPA A308-S2

OFFICE OF AUDITS & ADVISORY SERVICES BEHAVIORAL HEALTH SERVICES CONTRACT MONITORING AUDIT FINAL REPORT

[UNIFIER USER MANUAL]

product guide PORTFOLIO, PROGRAM & PROJECT MANAGEMENT 1 Pope Street Wakefield, MA USA

AIM for the Cloud. Product Strategy & Roadmap BlueCielo Meridian Customer Day June 26, 2014 Gilze Rijen The Netherlands

Module 8: QUALITY CONTROL SYSTEM (QCS) and RESIDENT MANAGEMENT SYSTEM (RMS) Submodule 1: Introduction and Overview

Course Objectives: COR Contracting Officer's Representatives in a Contingency Environment

Strategic Plan Progress Report Goal 4 Focus with Employee Survey Update. February 2016 San Francisco, California

REGIONAL MUNICIPALITY OF WOOD BUFFALO VENDOR / CONTRACTOR PERFORMANCE EVALUATION FOR SERVICES & CONSTRUCTION

Improving the Efficiency of Managing a Construction Project: A Collaborative Web-based Solution

JobSuite Sample Workflow and Template

PROJECT MANAGEMENT HANDBOOK, PART 1 - ISSUES COMMON TO ALL PROJECT MANAGERS. Table of Contents. Introduction Why Do We Need Schedules?...

Invoice Automation. Invoice Automation Challenges

SAP WORKFORCE MANAGEMENT 3.0: LEARNING MAP FOR SOLUTION CONSULTANTS

A Presentation to the Houston Hispanic Architects and Engineers

Agenda. CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016

Risk Management in the Development of a Penta-P Project

How To Use P6 For A Project Scheduling System

Service Procurement process improvement in SAP. Copyright 2008, Advanced Contractor Cost Management Inc. All Rights Reserved 1

Linear Schedules for Tunnel Projects

Notes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive

Common File Server The secure common file server provided by the Department for storage of all contract documents.

Solicitation No Oracle Enterprise Content Management System Services

Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E.

InTime. Contractor Guides

Lab 1 Introduction to Microsoft Project

Procurement Improvement Plan

In4velocity Systems In4Suite Product Overview

MS-10750: Monitoring and Operating a Private Cloud with System Center Required Exam(s) Course Objectives. Price. Duration. Methods of Delivery

Request for Proposals Erate Category 1 Hosted VoIP Service Hinds County School District

Foundation Repair Permit - Residential and Commercial

Loan Operations/Settlement System Solutions Mike Johnstone - LMA

The Financial Planning Analysis and Reporting System (FPARS) Project: Implementation Status Update

B2B ecommerce Selling Online Isn t Just for Retailers Ryan Burnham k-ecommerce

Desired Outcomes of WSDOT s Improvement to its Project Management Processes

Project Management On-line Guide

Copyright Soleran, Inc. esalestrack On-Demand CRM. Trademarks and all rights reserved. esalestrack is a Soleran product Privacy Statement

PERFORMANCE MANAGEMENT

City and County of San Francisco GreenFinanceSF Commercial Program REQUEST FOR PROJECT APPLICATIONS

Applied Project Management ( APM )

Mt. San Antonio College. Information Technology Report Card. EDUCAUSE: 2013 Top 10 IT Issues

Construction Project Management (e-builder) Audit October 2012

The new licensing model increases the flexibility of organizational use and reduces total cost of ownership.

55034-Project Server 2013 Inside Out

Project Execution, Monitoring and Control (IS PM 8. Lecture; 2012 Spring)

Spec. Standard: 11/27/ Revision: 11/27/06

More information >>> HERE <<<

Grant Accounting Processes

The Business Value of a Web Services Platform to Your Prolog User Community

DELCO Home Health Care Fund Grant Application

A GUIDE TO IMPLEMENTING SAP BUSINESS ONE

INDEFINITE DELIVERY CONTRACT(IDC) GENERAL CONTRACTOR CONSTRUCTION SERVICES DELIVERY ORDER WORK RELEASE AND CHANGE ORDER PROCEDURES

Vendor Performance Evaluation Requirements

Primavera Unifier v9.14 / 2014 EPPM Day Hands On Session Exercise Document

PMO Metrics Recommendations

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information

CITY OF SAN ANTONIO. Mike Frisbie, P.E., City Engineer and Director of Capital Improvement Management Services

STAFF AUGMENTATION REQUEST FOR QUOTE - REPOST

Task Order Manager. Project Planning, Engineering, Architecture service contract with experience in passenger rail or other modes, and

PN /16/ CRITICAL PATH METHOD PROGRESS SCHEDULE

EXHIBIT A SCOPE OF SERVICES CONSTRUCTION MANAGEMENT TEAM POSITIONS AND REQUIREMENTS

Title: Contract Management Software Solutions (CMS) and Procurement Front-End System

Transcription:

CIMS Information Systems Used to Manage Capital Projects Samuel Hutchins September 14, 2010

Department Overview Department Created in October 2007 to manage Capital Improvements Program Cost recovery for project management Handles the majority of the City s real estate efforts Handles majority of Environmental work for City Public Art San Antonio (PASA) 2

CIMS Organizational Structure Director/ City Engineer Mike Frisbie, P.E. Assistant Director Project Support Debbie Sittre Assistant Director Project Delivery Jorge A. Perez Assistant Director Real Estate Mike Etienne Contracts Fiscal Portal Compliance Technical Services Project Management Environmental Services Aviation Expansion Acquisitions Disposition Leasing Downtown Dev. 3

Mission & Value Statements Together, Dedicated to Our Community... Building a Great San Antonio. Forward thinking Accountability & Integrity Respecting our customers, valuing our diversity & history Enjoying every day 4

Goals of CIMS Information Systems Improve Project Delivery to deliver projects on time, within budget and to scope Increase Accountability Identify issues upfront Provide Project Managers and Management accurate and timely information Provide transparency to the Public

Program Relationships Project Management Portal Schedules SAP Accounting System Project Information Sheets Scheduling Software Performance & Schedule Data CIMS Dashboard Live Connection Manual Connection

SAP System (Capital Projects Perspective) Accounting system for Projects since 2004 Contains basic information on all Capital Projects Financial data by Project Captures costs by spending category (Design, Construction, etc) Handles contracts and payments Provides single location for all project financial information

City of San Antonio Portal Project management tool to improve project delivery and increase Accountability Go live date - Sept 15, 2006 Consists of several different software SharePoint, Primavera Contract Manager, Primavera Scheduling Software, Citrix Current status Used for all contracts 900+ Users 250+ Active projects 2,000+ Workflows Supports multiple departments, managed by central CIMS team

Key Components of Portal Electronic development and routing of invoices, change orders and select close out documents Electronic processing of RFIs, submittals, punch lists Storage of documents Coordination between Project Manager, utilities, consultants, contractors, etc. Uploads Invoice Data to accounting system Accessible by web through Citrix front end Controlled access to projects

Results Improved invoicing Quicker and more accurate Increased Accountability/Visibility Improved Document Control Improved Coordination/Reduced Printing Costs Standardized Procedures Challenges Large upfront requirements Bureaucratic Learning Curve

Contract Data

Invoice Data

Construction Schedules Require construction schedules from contractors in Primavera P5 or Primavera Contractor P4 or higher (Allow MS Project if project < $300K and < 90 days) Tasks are limited to 20 days in duration City provides contractor a template Acceptable baseline schedule required prior to notice to proceed Schedule Updates due monthly prior to submittal of bill CIMS Scheduler maintains baseline and schedule updates in City System. Attaches baseline to schedule update and provides schedule/reports for review by Project Manager and Inspector.

Construction Schedule Impacts Issues: New contractors unfamiliar with strict schedule requirements Quality and timeliness of schedules varies among contractors Training staff on schedules is a challenge Benefits: Forces contractor to think about how to execute project Allows City to review plan Assists in determining time impacts of delays and changes Helps spot issues earlier and require contractor to provide a recovery plan if appropriate

2007 Bond Master Schedules Developed project schedules for every project Started with standardized project templates and customized the tasks to each project Schedules include all tasks Schedules were cost loaded to support the use of Schedule Performance Index (SPI) Base lines were established initially and schedules are updated monthly PMs/Environmental/Real Estate update a schedule report with actual start and finishes or anticipated finishes. Schedulers input the data.

Master Schedule Benefits Value is in what is done with the information Basis for reporting Program status Helped develop more realistic completion dates and forced inclusion/coordination of non-design tasks upfront Allows CIMS management to review projects by exception (Monthly review meetings for projects with low SPIs or slipping past base line finish) Provides work load and other information

CIMS 2007 Bond Dashboard Provides City Management and Public an overview of Bond Program Updated on a monthly basis ~ 17th of the month Sources of data Master Schedules Performance data SAP Project and Budget Data Information displayed Project Status Design, Construction or Complete Expenditure of Bond Funds Number of projects on schedule Project Information Sheets

Project Information Sheets Provides project info to Management and Public SAP is the data source Active projects within SAP are available for viewing Allows user to select projects by Council District, Program, Project Status and Type Project

Goals of CIMS Information Systems Improve Project Delivery to deliver projects on time, within budget and to scope Increase Accountability Identify issues upfront Provide Project Managers and Management accurate and timely information Provide transparency to the Public

Samuel Hutchins IV, P.E., FSAME Division Manager Reporting and Web Portal Support 210-207-6940 Samuel.hutchins@sanantonio.gov City Web Site: www.sanantonio.gov CIMS Web Site: www.sanantonio.gov/cims