Scheduling Document Creation



Similar documents
OVERVIEW. Microsoft Project terms and definitions

Microsoft Project 2007 Level 2: Working with Resources and Managing a Project

LECTURE -08 INTRODUCTION TO PRIMAVERA PROJECT PLANNER (P6)

Microsoft Project 2013 Guide to Task and Resource Planning

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by

Microsoft Access 2010 handout

Explore commands on the ribbon Each ribbon has groups, and each group has a set of related commands.

ELECTRO-MECHANICAL PROJECT MANAGEMENT

Open Workbench. User Guide. v2.0.00

Task Force on Technology / EXCEL

Beginning Microsoft Project

MS Project Tutorial for Senior Design Using Microsoft Project to manage projects

Microsoft Access 2010 Part 1: Introduction to Access

Microsoft Project 2007 Level 1: Creating Project Tasks

PLANNING AND SCHEDULING USING MICROSOFT PROJECT 2010 PAUL EASTWOOD HARRIS

How To Use Ms Powerbook On A Pc Or Mac Or Macbook 2 (Windows)

ECDL. European Computer Driving Licence. Project Planning Project Management Software BCS ITQ Level 2. Syllabus Version 1.0

Tracking Project Progress

PROJECT MANAGEMENT IN PRIMAVERA P6 WEB ACCESS REL 7

EXCEL Using Excel for Data Query & Management. Information Technology. MS Office Excel 2007 Users Guide. IT Training & Development

Virto SharePoint Gantt Chart App for Office 365 Release User and Installation Guide

MICROSOFT OFFICE ACCESS NEW FEATURES

Oracle Primavera P6 Enterprise Project Portfolio management Overview Programme Reference # 201A

Using Spreadsheets, Selection Sets, and COGO Controls

USER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS

INTRODUCTION 5 COLLABORATION RIBBON 5 SELECT THE UPDATING METHOD 6 MAKE YOUR PROJECT COLLABORATIVE 8 PROCESSING RECEIVED TASK UPDATES 9

Project Management: Intermediate Microsoft Project 2010

At the top of the page there are links and sub-links which allow you to perform tasks or view information in different display options.

Project Quick Reference. The Assignment Equation. EPM Architects

Using Microsoft Office to Manage Projects

Project Management within ManagePro

Aras Corporation Aras Corporation. All rights reserved. Notice of Rights. Notice of Liability

User's Guide. ver RSRicksoft.

WebSphere Business Monitor V6.2 Business space dashboards

WBS Schedule Pro. User's Guide

Creating and Using Forms in SharePoint

Project Initiation and Revision Training Manual. Table of Contents

REUTERS/TIM WIMBORNE SCHOLARONE MANUSCRIPTS COGNOS REPORTS

Introduction to Microsoft Project 2010

Virto SharePoint Gantt Chart Web Part for SharePoint 2013 Release User and Installation Guide

Creating tables in Microsoft Access 2007

Laboratory 1 Initiating a Project

Outlook . User Guide IS TRAINING CENTER. 833 Chestnut St, Suite 600. Philadelphia, PA

I N FO RM A T I O N T EC H N O L O G Y S ERV I C ES M I C ROSOFT PROJ EC T T A S K M A N A GEM EN T LEARNING GUIDE

PROJECTS. onepoint PROJECTS 13. Group Server and. Enterprise Cloud/Server. Tutorial

PROJECT PLANNING & SCHEDULING USING PRIMAVERA P6 TM. in an PAUL EASTWOOD HARRIS

Creating Reports with Smart View s Ad Hoc Analysis

FAST Travel System. Guide: Creating Expense Reports

PROJECT PLANNING & SCHEDULING USING PRIMAVERA ENTERPRISE. In An. Established Project Environment PAUL EASTWOOD HARRIS

Creating a New Project

Project 2010 Introduction

SAP Business Intelligence (BI) Reporting Training for MM. General Navigation. Rick Heckman PASSHE 1/31/2012

Excel Reports and Macros

Practice Management Application Suite

WebSphere Business Monitor V7.0 Business space dashboards

Custom Reporting System User Guide

Module A2 Item Activities, Gantt Chart and Utilization Sheet. A2.1 Project item activities A2.2 Gantt chart A2.3 Utilization sheet

Advanced Presentation Features and Animation

Planning and Managing Projects with Microsoft Project Professional 2013

Applied Project Management ( APM )

Planning and Managing Projects with Microsoft Project Professional 2013

Produced by Flinders University Centre for Educational ICT. PivotTables Excel 2010

Module A2 Item Activities, Gantt Chart and Utilization Sheet

Teacher References archived classes and resources

Module One: Getting Started Opening Outlook Setting Up Outlook for the First Time Understanding the Interface...

Editor Manual for SharePoint Version December 2005

University of Rochester

Microsoft Project Server 2010 Project Manager s Guide for Project Web App

EXCEL PIVOT TABLE David Geffen School of Medicine, UCLA Dean s Office Oct 2002

MICROSOFT PROJECT II

GUIDE TO USING MICROSOFT PROJECT 2013

In This Issue: Excel Sorting with Text and Numbers

MS Excel Template Building and Mapping for Neat 5

SAP Business Intelligence ( BI ) Financial and Budget Reporting. 2nd Edition. (Best Seller Over 1,000,000 copies sold)

PRINCE2 PLANNING AND CONTROL USING MICROSOFT PROJECT UPDATED FOR MICROSOFT OFFICE PROJECT 2007 PAUL EASTWOOD HARRIS

SHAREPOINT 2010 FOUNDATION FOR END USERS

DreamTeam User Guide. Product Usage and Best Practices Guide. By Adam Buxbaum

Microsoft Project 2010

Basic Microsoft Excel 2007

Basic Excel Handbook

DIRECTV Rio Track 2 Dispatch 3 rd Party QA Truck Roll Activities Instructor Guide

Using Excel As A Database

Create task relationships by linking tasks. Switch task scheduling from manual to automatic. Set nonworking days for the project plan.

Excel 2007 Basic knowledge

DROOMS DATA ROOM USER GUIDE.

Intellect Platform - Tables and Templates Basic Document Management System - A101

Microsoft PowerPoint 2010 Handout

Time & Expense Entry WalkThrough

Project planning with MindGenius

Microsoft Word Track Changes

Microsoft Excel 2013: Using a Data Entry Form

M-Files Gantt View. User Guide. App Version: Author: Joel Heinrich

Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6)

Appointment Scheduler

Applicant Tracking System Job Aids. Prepared by:

Using Microsoft Project 2000

MICROSOFT OUTLOOK 2010 READ, ORGANIZE, SEND AND RESPONSE S

State Analytical Reporting System (STARS)

FastTrack Schedule 10. Tutorials Manual. Copyright 2010, AEC Software, Inc. All rights reserved.

Appointment Scheduler

Transcription:

Scheduling Document Creation What is a Schedule in epm? Schedules The epm Schedule application is an integral part of the Portfolio Management suite of applications. Start and end dates for each summary event, milestone, and task can be established. Also, the epm Administrator can set up email alerts and epm notifications for when a task exceeds the approved milestone. Project schedules can be viewed at the project level, or rolled up into a Program-level Critical Path Method (CPM) or Collaborative Gantt view, complete with collapsible/expandable visibility into the schedules, resources, linked WBS structure, attached documents, tasks, milestones, cost summaries, progress percentage complete, and more summary detailed information. epm Schedule can import file from Primavera, Microsoft and other applications. Like other epm documents, the Schedule document has workflows, activity logs and attachments available. Schedules can also be cross linked to other epm documents, such as RFI s, Submittals, Drawings, etc., to provide easy cross reference. Who Will Use This? General Contractor Construction Manager Project Manager Calendars The epm calendar document allows the user to define normal working hours for a project schedule. On the calendar, exceptions can be set for particular non working days. Customized calendars for each project can be created, though each schedule document is limited to a single calendar. Resources The Resource document enables the creation of resources and the ability to link these resources to tasks in the Gantt chart. A user can also associate a contact with a resource in the Resource document. When a contact is not associated with a resource, the resource is a generic resource. Generic resources are useful for denoting material resources. QRG.042_Schedule Document Creation Page 1

Creating and Using a Schedule Document 1. Log into epm as a user with security permissions that include the Schedule-Creator or Schedule- Approver role. 2. Navigate to your project, then to Applications > Scheduling > Schedules. The Schedule document register displays. 3. Click the New button. A blank schedule document opens. Enter a Title for the schedule. In the Start Date and End Date fields, enter the overall start and end dates for the schedule. The Activity Code Group allows assignment of meta data to each task or milestone in the schedule. This additional data can be useful in reports related to the schedule. In the Calendar field, you can select a single calendar that designates working days for all tasks in the schedule. You also can assign separate calendars to each task in the schedule. Note- the Schedule document shown at left contains basic information about the schedule. Open the Gantt views to enter tasks, change durations, assign resources, set baselines, etc. QRG.042_Schedule Document Creation Page 2

Creating and Using a Schedule Document, Cont. 4. Finally, click the Save button to save the schedule. 5. There are three ways to open the schedule in Gantt view: a. From the register, check the box next to the schedule (or schedules) you wish to view, then click Tools and select to either open in Collaborative or CPM Gantt view. b. In the register, in the Open As drop down list, select Collaborative or CPM Gantt, then simply click on the schedule number or title link. c. Open the schedule document by clicking on its number in the register. Then in the Tasks section of the Main page, click on either the View Collaborative Gantt or View CPM Gantt buttons. Note: Each Gantt view (Collaborative and CPM) enables you to work with tasks, milestones, assignments, WBS Codes, etc. Although the two Gantts are very similar, you can use the Collaborative Gantt to set baselines and approve schedules, and the CPM Gantt to automatically recalculate schedules according to task dependencies. Also, in Collaborative Gantt, all of your changes are saved immediately. In CPM Gantt, you must click the Save button to save your changes. This feature in CPM Gantt enables you to play with the schedule without updating the database. QRG.042_Schedule Document Creation Page 3

Creating and Using a Schedule Document, Cont. 6. To add tasks, summaries and milestones to your schedule, right click on the top level schedule name, or on any existing task, summary or milestone. From the resulting list, choose Insert Task, Insert Milestone, Create Task or Create Summary. Note: - Insert Task adds a task with a default name and duration. - Create Task allows you to specify details about the task, and also allows creation of multiple tasks at one time 7. Selecting Create Task opens a separate Create New Task dialog box, where you can enter information about the task. You can also choose to create multiple tasks in this dialog, as well as creating links between the newly created tasks. QRG.042_Schedule Document Creation Page 4

Creating and Using a Schedule Document, Cont. 8. Once tasks are created, links can be edited or created by right-clicking a task and selecting Edit Links. 9. To change the Gantt view (which columns appear to the left of the Gantt bars, how those columns are sorted, etc), simply click on the View dropdown list and select a view. If you security permissions allow it, you can create your own views by clicking on the Gantt Views button QRG.042_Schedule Document Creation Page 5

Creating and Using a Schedule Document, Cont. 10. To change a task s start date, end date or duration, either select a new date by clicking the triangle in the lower right corner of a date field or, in the Gantt chart, hover over the task bar in the Gantt chart, and when the bar changes color, click and drag the bar left or right to change a task s start and end date. QRG.042_Schedule Document Creation Page 6

Creating and Using a Schedule Document, Cont. 11. To change a task s duration, hover the mouse over the right edge of the task bar, and when a large red arrow head appears, click and drag it to the left or right. QRG.042_Schedule Document Creation Page 7

Toolbar Icons & Their Functions Icon Meaning Use/Description Go Pre filter planning objects before they are displayed in the Gantt. Only available when Use Prefiltering is selected in the Gantt Preferences. Edit Gantt Preferences Displays the Gantt Preferences dialog box View Allows you to control the columns displayed in the Gantt Filters Allows you to narrow down the information displayed in the columns. Filters 2 & 3 appear once you click the Show Advanced Filters button Show Advanced Filters Displays filters 2 and 3, as mentioned above. Manage Views Enables you to customize the views available in the Gantt. Show Gantt Chart View Displays chart and table Show Spreadsheet View Displays the Gantt table and a Usage table for each planning object as per period values. Show Combined View Displays the Gantt chart, table and usage curves. Export Allows you to export table information directly into Excel (requires Export Plugin installation). Row Specific Commands Displays commands for the currently selected planning object. Also enables you to perform actions such as Insert Task, Create Task, and Create Summary. Undo and Redo Allows you to clear the last change you made or reapply the change you cleared. QRG.042_Schedule Document Creation Page 8

Toolbar Icons & Their Functions Cont d Icon Meaning Use/Description Sort Order Allows you to apply the sort order to the planning objects (for example Sort by Task Name ). Descending Sort Order Allows sorting the planning objects in alphabetically descending order. Summaries, Milestones, Tasks, Resources, Deleted, Links Show/Hide Allows you to include or eliminate certain types of planning objects in Gantt and Combined views. Approved, Baseline, Current Schedule Schedule Schedule Rollup to Summary Used to display the child planning object summaries in the parent summary in Gantt and Combined Views. Change Timescale Used to display the desired time line in Usage chart. Choose D for days, W for weeks, M for month, Q for quarters, or Y for years. Show Levels Quickly expand or collapse planning object levels to the desired level. The? enables you to choose a level from 0 to 9. The * expands all levels. QRG.042_Schedule Document Creation Page 9

Toolbar Icons & Their Functions Cont d Icon Meaning Use/Description Go to Selected Task Used to scroll timescale to display the currently selected planning object. This button is helpful if you ve selected a task, then scrolled the Gantt up or down. Zoom Selected Task Used to adjust the timescale to the best fit for the selected planning object in Gantt chart. Reschedule to Status Date Used to reschedule all incomplete tasks and their assignments for all dates prior to Status Date. When you click this button, the calendar appears. Choose the new resume date for tasks. Note: rescheduling the incomplete tasks allows you to accurately reflect their impact to the overall schedule. Chain Tasks Creates Finish-to-Start links between the selected tasks, in the order that they appear. Unchain Tasks Deletes the links between selected tasks. Split Assignment Splits the time that the task assignment is scheduled for. This enables you to indicate that a task should start at a certain date that work may stop on it for a period of time and that work shall resume at a later date. CPM Calculation Turns the CPM calculation on or off. Available in CPM Gantt only. QRG.042_Schedule Document Creation Page 10

Gantt Table & Chart Icons A planning object is waiting to be approved. A planning object was modified after it was approved and needs to be re-approved. Information in a cell can be edited. Click this triangle to make the cell editable. The planning object contains references to epm documents. A summary. The dark blue in the icon indicates that work has started in the summary. A summary with the milestones and tasks rolled up. A milestone. The milestone may also be approved or baselined. In this case, a second orange or blue diamond appears behind this diamond. A task has a current, baselined, or approved schedule. The current schedule is displayed in green, the approved in blue, and the baselined in orange. A planning object is linked to another planning object. The lines between one part of the task and the next part indicate that the assignment has been split. QRG.042_Schedule Document Creation Page 11