ME 407 Mechanical Engineering Design Spring 2016



Similar documents
Project Planning and Scheduling

Operational Research. Project Menagement Method by CPM/ PERT

Network Calculations

Cambridge International AS and A Level Computer Science

Project Time Management

Scheduling Glossary Activity. A component of work performed during the course of a project.

MECH 896 Professional Development for MEng Students. Homework Discussion. Scheduling Overview. Winter 2015: Lecture #5 Project Time Management

8. Project Time Management

MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc.

Collaborative Scheduling using the CPM Method

ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS

Chapter 2: Project Time Management

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects

technical tips and tricks

Project Management Glossary

Project Scheduling & Tracking

Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi

Time Management. Part 5 Schedule Development. Richard Boser

B D E F

MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc.

Unit 1: Project Planning and Scheduling

Use project management tools

CISC 322 Software Architecture. Project Scheduling (PERT/CPM) Ahmed E. Hassan

Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration

PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM)

Systems Analysis and Design

SWEN 256 Software Process & Project Management

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072

Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

Precedence Diagram Method. CSTM 462 Planning & Scheduling

Chapter-6. Developing a Project Plan

Module 3: The Project Planning Stage

Project Management SCM Pearson Education, Inc. publishing as Prentice Hall

Notes on the Critical Path Method for project planning and management.

SE351a: Software Project & Process Management

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761

CRITICAL PATH METHOD (CEE 320 VDC SEMINAR)

CPM-200: Principles of Schedule Management

Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014

Dashboards and Reporting for Program Management

Project Planning. Lecture Objectives. Basic Reasons for Planning. Planning. Project Planning and Control System. Planning Steps

Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

Project Management Chapter 3

PROGRAM EVALUATION AND REVIEW TECHNIQUE (PERT)

Chapter 4: Project Time Management

Goals of the Unit. spm adolfo villafiorita - introduction to software project management

The work breakdown structure can be illustrated in a block diagram:

Should I Resource Load My Schedule?

Network Planning and Analysis

Project Scheduling. Introduction

PROJECT PROPOSAL: PROJECT BLUE ZUMA

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time

Module 11. Software Project Planning. Version 2 CSE IIT, Kharagpur

CRITICAL PATH METHOD (CPM) SCHEDULES

Chapter 6 (part 1) Project Time Management. (Project Scheduling)

Lecture 26 CPM / PERT Network Diagram

10 Project Management with PERT/CPM

MS Project Tutorial. CS 587 Software Project Management Instructor: Dr. Atef Bader. Prepared by Milton Hurtado

Chapter 6: Project Time Management

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza

Basic Concepts. Project Scheduling and Tracking. Why are Projects Late? Relationship between People and Effort

CSC 443: IT Project Management Midterm 1 exam - Spring semester March 21 st, 2012

Chapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False

Basic CPM Calculations

Chapter 3 Managing the Information Systems (IS) Project

Scheduling. Anne Banks Pidduck Adapted from John Musser

Introduction to Project Management

02 Project planning. There are two approaches to identifying the components of a project: productbased and work- or activity-based.

Programmes. Unit 3: P lanning construction work processes and efficient use of resources in construction and the built environment.

Frequently Asked Questions in Project Management

Scheduling Resources and Costs

Software Project Management. Software Engineering SW Project Management Slide 1

Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose

A. O. Odior Department of Production Engineering University of Benin, Edo State.

Project Management DISCUSSION QUESTIONS

Topic: The easiest way to calculate Critical Path, Total Float, Free Float, Early Start, Early Finish, Late Start, and Late Finish.

CRITICAL-PATH ANALYSIS FOR NETWORK SCHEDULING

The Project Planning Process Group

Chapter 11 Monte Carlo Simulation

Project Scheduling and Gantt Charts

SECTION CONSTRUCTION SCHEDULE B. Part 1 - General Work Included Related Requirements Reference Standards...

HOW TO START WORKING WITH P2WARE PROJECT MANAGER 7?

Software Project Management

Project Scheduling: PERT/CPM

PROJECT MANAGEMENT Critical Path Method-- Program, Evaluation & Review Technique (CPM/PERT)

5. Creating a Gantt Chart

Leaving Certificate Technology. Project Management. Teacher Notes

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

EXAM EXEMPLAR QUESTIONS

EdExcel Decision Mathematics 1

Critical Path Analysis

Define Activities Sequence Activities Estimate Activity Resources Estimate Activity Durations Develop Schedule Control Schedule

Project Time Management

Object-Oriented Analysis. with the Unified Process. John W. Satzinger Southwest Missouri State University. Robert B. Jackson Brigham Young University

CIS Project Management

SYSTEMS ANALYSIS AND DESIGN DO NOT COPY

Lecture 6: Project Time Management By: Prof. Lili Saghafi. Information Technology Project Management, Fifth Edition

7. PROJECT MANAGEMENT

Basic Project Management & Planning

Transcription:

ME 407 Mechanical Engineering Design Spring 2016 Project Planning & Management Asst. Prof. Dr. Ulaş Yaman Acknowledgements to Dieter, Engineering Design, 4 th edition Ullman, The Mechanical Design Process, 4 th edition

Outline Introduction Building a Plan Sample plan Gantt Charts Critical Path Method Review of the Project Planning and Management Report Template R3 Concluding Remarks

Introduction Main goal of planningis to have products developed in timely and cost-effective manner. Planning generates a scheme for developing needed information and distributing it to the correct people at the correct time. Figure 5.1, Ullman

Building a Plan Project plan is a document that defines the tasks that need to be completed during the design process, keeps project under control. For each task, the plan states objectives personnel requirements time requirements schedule cost

Building a Plan There are 5 steps to establish a plan 1. Identify the tasks 2. State the objective for each task 3. Estimate the personnel, time, and other resources needed to meet the objectives 4. Develop a sequence for the tasks 5. Estimate the product development costs

Building a Plan Step 1 Identify the tasks As the team understands the problem, the tasks become clearer. Tasks are initially thought of in terms of the activities. The tasks should be made as specific as possible. They should focus on what needs to be achieved rather than the activities. In some industries, the exact tasks to be accomplished are clearly known from the beginning of the project. However, for a totally new product, the tasks may not be so clear.

Building a Plan Step 2 State the objective for each task The tasks need to be refined so that the results of the activities are the stated objectives. Each task objective must be Defined as information to be refined or developed and communicated to others (deliverables) Presented in terms of the decisions and the responsible team members Easily understood Specific Feasible

Building a Plan Step 3 Estimate resources to meet the objectives For each task, followings should be identified Responsible members Percentage of their time Period Design takes time, often twice as long as the initial estimate Pessimists suggest 1 day 2 weeks

Building a Plan Step 3 Estimate resources to meet the objectives Table 5.2, Ullman

Building a Plan Step 3 Estimate resources to meet the objectives Time estimation is not easy! It is suggested that it should depend on Optimistic estimate (o) Pessimistic estimate (p) Most-likely estimate (m) Time Estimate

Building a Plan Step 3 Estimate resources to meet the objectives Distribution of time across design phases Phase Time Percentages Project planning 3 5 Specification definition 10 15 Conceptual design 15 35 Product development 50 70 Product support 5 10

Building a Plan Step 4 Develop a sequence for the tasks Scheduling can be complex The main aim is to have each task done before its results are required. It is important to define the predecessors and successors of each task. Critical Path Method can be used to determine the most efficient sequence of tasks.

Gantt Charts Best way to develop a schedule Tasks are plotted against a time scale Personnel requirements are noted Design reviews are shown Task dependencies are important

Gantt Chart Software Microsoft Project Microsoft Excel tom splanner teamgantt smartsheet smartdraw

Building a Plan Step 5 Estimate the product development costs Design costs are about 5% of the manufacturing costs. Salaries constitute most of the project costs. There are extra burdens on companies Cost of buildings Utilities Support personnel General equipment Travel costs

Sample plan Developing a Baja car Identify the steps Figure 5.10, Ullman

Critical Path Method (CPM) Gantt chart for prototype testing a heat exchanger (Figure 4.14, Dieter)

Critical Path Method (CPM) Network logic diagram for heat exchanger prototyping tests (Figure 4.15, Dieter)

Critical Path Method (CPM) Definitions and Rules An activity is a time-consuming effort that is required to perform part of a project. An event is the end of one activity and the beginning of another. An event is assumed to consume no time. Every activity in a CPM diagram is separated by two events.

Critical Path Method (CPM) Definitions and Rules 1. An activity cannot be started until its tail event is reached. 2. An event cannot be reached until all activities leading to it are complete.

Critical Path Method (CPM) Definitions and Rules 3. Sometimes an event is dependent on another event preceding it, even though the two events are not linked together by an activity. A dummy activity (dashed) requires zero time and has zero cost.

Critical Path Method (CPM) Definitions and Rules Duration (D): The duration of an activity is the estimated time to complete the activity. Earliest start (ES): The earliest start of an activity is the earliest time when the activity can start. Latest start (LS): The latest time an activity can be initiated without delaying the minimum completion time for the project. Earliest finish time (EF): EF = ES + D Latest finish time (LF): LF = LS + D Total float (TF): The slack between the earliest and latest start times. TF = LS - ES. An activity on the critical path has zero total float.

Critical Path Method (CPM) Description of the activities (Table 4.9, Dieter)

Critical Path Method (CPM) CPM network for prototype testing of new heat exchanger design (Figure 4.17, Dieter)

Critical Path Method (CPM) Calculation of Early Start Times (Table 4.7, Dieter)

Critical Path Method (CPM) Calculation of Late Start Times (Table 4.8, Dieter)

Critical Path Method (CPM) Critical path: A-D-G-H-J-K Summary of Scheduling Parameters for Prototype Testing Project (Table 4.9, Dieter)

In class activity The development of an electronic widget is expected to follow the following steps. Determine the arrow network diagram and determine the critical path by using the CPM technique (Problem 4.11, Dieter)

Project Planning and Management Report Template R3 I. Introduction II. Organization of the project A. Explanation of the tasks and their definitions B. Time table (distribution of the workload) C. Timeline (Gantt Chart) III. Summary and Conclusions (risky tasks, backups, tools) Max 6 pages

Concluding Remarks Planning is a must. Products developed through 5 phases Discovery Specifications Conceptual design Product development Product support There are 5 planning steps: Identification of the tasks Stating the objectives Estimating resources Developing a sequence Estimating the cost