SE351a: Software Project & Process Management



Similar documents
Project Planning and Scheduling

Scheduling Glossary Activity. A component of work performed during the course of a project.

Operational Research. Project Menagement Method by CPM/ PERT

Chapter 2: Project Time Management

Project Time Management

Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761

Scheduling. Anne Banks Pidduck Adapted from John Musser

The work breakdown structure can be illustrated in a block diagram:

Goals of the Unit. spm adolfo villafiorita - introduction to software project management

Time Management. Part 5 Schedule Development. Richard Boser

Module 11. Software Project Planning. Version 2 CSE IIT, Kharagpur

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072

Chapter 3 Managing the Information Systems (IS) Project

CPM-200: Principles of Schedule Management

Project Management Glossary

Network Calculations

ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS

PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM)

The Project Planning Process Group

Project Scheduling & Tracking

SWEN 256 Software Process & Project Management

Use project management tools

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects

Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi

CISC 322 Software Architecture. Project Scheduling (PERT/CPM) Ahmed E. Hassan

Scheduling Resources and Costs

Chapter-6. Developing a Project Plan

Systems Analysis and Design

8. Project Time Management

Cambridge International AS and A Level Computer Science

Module 3: The Project Planning Stage

Project Planning. Lecture Objectives. Basic Reasons for Planning. Planning. Project Planning and Control System. Planning Steps

CSC 443: IT Project Management Midterm 1 exam - Spring semester March 21 st, 2012

Collaborative Scheduling using the CPM Method

ME 407 Mechanical Engineering Design Spring 2016

Should I Resource Load My Schedule?

Chapter 4: Project Time Management

Chapter 6: Project Time Management

Object-Oriented Analysis. with the Unified Process. John W. Satzinger Southwest Missouri State University. Robert B. Jackson Brigham Young University

SYSTEMS ANALYSIS AND DESIGN DO NOT COPY

MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc.

Project Management Chapter 3

10 Project Management with PERT/CPM

Learning Objectives. Learning Objectives (continued) Importance of Project Schedules

Project Time Management

Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

Fundamentals of Project Management. Who am I. Schedule

CPM -100: Principles of Project Management

Precedence Diagram Method. CSTM 462 Planning & Scheduling

SENG 380:Software Process and Management. Resource Allocation Part 1

Critical Path Analysis & PERT Charts (taken from

MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc.

02 Project planning. There are two approaches to identifying the components of a project: productbased and work- or activity-based.

PROJECT TIME MANAGEMENT

Software Project Management

Project Time Management

Lecture 6: Project Time Management By: Prof. Lili Saghafi. Information Technology Project Management, Fifth Edition

Scope management can be defined as controlling what is and what is not a part of the project.

PROGRAM EVALUATION AND REVIEW TECHNIQUE (PERT)

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

Project Scheduling and Gantt Charts

Chapter 6. (PMBOK Guide)

CIS Project Management

Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose

CRITICAL PATH METHOD (CPM) SCHEDULES

Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

Project Management (CS 3730) Lecture 4 Name:

Chapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False

PROJECT TIME MANAGEMENT. 1 Powered by POeT Solvers Limited

Define Activities Sequence Activities Estimate Activity Resources Estimate Activity Durations Develop Schedule Control Schedule

Project Time Management

Basic Concepts. Project Scheduling and Tracking. Why are Projects Late? Relationship between People and Effort

專 案 管 理 實 務 嘉 義 縣 政 府 學 分 班 : 管 理 實 務 專 題 2006 中 正 大 學 企 管 系 助 理 教 授 周 瑞 生

IT2403-SOFTWARE PROJECT MANAGEMENT 2 MARKS QUESTIONS

12 Network Scheduling Techniques

ICT Project Management. Software Project Planning By J. Ogutu

Introduction to Project Management ECE 480. Erik Goodman

Introduction to Project Management

Leaving Certificate Technology. Project Management. Student Workbook

22 Project Management with PERT/CPM

Network analysis: P.E.R.T,C.P.M & Resource Allocation Some important definition:

Project Management for Scientists

Dashboards and Reporting for Program Management

Unit 4: Time Management (PMBOK Guide, Chapter 6)

March 30, 2007 CHAPTER 4

Chapter 6 (part 1) Project Time Management. (Project Scheduling)

Project Management Concepts and Strategies

MECH 896 Professional Development for MEng Students. Homework Discussion. Scheduling Overview. Winter 2015: Lecture #5 Project Time Management

A. O. Odior Department of Production Engineering University of Benin, Edo State.

WORK PROGRAM GUIDELINES

Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza

Graphical Project Planning Techniques: An Overview of Gantt, PERT, and CPM Charts Prepared for groups in ECE480 1/6/02, D. Grover

Work Breakdown Structure (WBS)

Project Scheduling: PERT/CPM

PERT/CPM. Network Representation:

Basic CPM Calculations

Application Survey Paper

Transcription:

SE351a: Software Project & Process Management W8: Software Project Planning 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa

SE351 Roadmap Introduction to Software Project Management Project Management Software Development Life Cycles Requirements Engineering Software Process & Project Metrics Software Project Planning Project Monitoring & Control Risk Management Software Quality Assurance 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 2

Notes References Effective Project Management, R.K. Wysocki et al., John Wiley and Sons, 1995, ISBN 0-471-36028-7 Project Management: A Systems Approach to Planning, Scheduling, and Controlling, 6th Ed, by Harold Kerzner ISBN: 0-471-28835-7, Published: July 1997, Imprint: Wiley 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 3

CMM L2 SE351a Perspective 2.1 Requirements management 2.2 Software project planning & control 2.3 Software subcontract management 2.4 Software quality assurance 2.5 Software configuration management Project Management Ad hoc 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 4

The Architecture of PMLC Scope the Project State the problem or opportunity Establish the project goal Define the project objectives Identify the success criteria List assumptions, risks and obstacles Launch the Plan Recruit and organize project team Establish team operating rules Level project resources Schedule work packages Document work packages Project Close-Out Obtain client acceptance Install project deliverables Complete project documentation Complete post-implementation audit Issue final project report Develop Detailed Plans Identify project activities Estimate activity duration Determine resource requirements Construct & analyze project network Prepare the project proposal Monitor & Control Progress Establish progress reporting system Install change control process Define problem escalation process Monitor progress versus plan Revise project plan 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 5

Project Management: The Control panel Activity Plan A A A PERT Assessment overall system B C Check specifications B C B C Integrate/ test system Expected Date D D D Personnel Resource Allocation Cumulative Cost 5 10 Cost Schedule 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 6

Recall: Definitions The Work Breakdown Structure (WBS) a deliverable-oriented grouping of the project components (products and services) which organizes and defines the total project scope Work Activity a collection of work tasks spanning a fixed duration within the schedule of a software project Work Task the smallest amount subject to management accountability Work Package a specification of the work that must be accomplished to complete a work task Work Product any tangible item produced during the project 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 7

Detailed WBS: Software Lifecycle Software System (SS) SS Defined Software Lifecycle Reqmts Analysis Subsystem (SS A ) Subsystem (SS A1 ) Requirements of SS A1 SS A SS A1 Work packages WP 1 of SS A1 WP 2 Code WP 3 Code of SS A1

From WBS to Schedule & Budget Items SS Software System (SS) Subsystem (SS A ) SS A Subsystem (SS A1 ) SS A1 Cost Account Requirements of SS A1 Work packages WP 1 WP 2 WP 3

Estimations Product size, e.g., LOC, FP & FeP Effort & Resources Cost & Schedule e.g., COCOMO & others 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 10

Preliminary Scheduling Steps 1. Identify project activities and products An activity must have a clearly defined start and end point, o normally marked by the production of a tangible deliverable 2. Identify dependency Some activities may require other activities to be completed before they can begin Establish a preliminary activity and product flow diagram 3. Allocate resources that an activity requires must be forecastable 4. Revise plan to create controllable activities 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 11

Project Networks A pictorial representation of the sequence in which the project work can be done Activity Plan Several types of project networks Activity-on-the-Node (AON) Activity-on-the-Arrow (AOA) overall system A B C D Check specifications A B C D A B C D Integrate/ test system 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 12

Project Networks: Activity-on on-the-node (AON) Activity Precedence network (AON) a directed graph with o o activities (nodes) and dependencies between them (directed arrows) Activity label Earliest start Latest start The only activity with no predecessor is the start activity The only activity with no successor is the final activity overall system A B C Activity span Activity description D Check specifications A B C Activity Node Duration A B C Earliest finish Latest Integrate/ test finish system Float= D D (Latest finish Earliest finish ) 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 13

Example: 4 s Project Consider a system that will have 4 major software s Develop specifications for the overall system and for each of the s the specifications of each need to be V&V together to make sure that they are mutually consistent Each needs to be designed, coded, and tested, and then all of the s need to be integrated and tested as a system 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 14

AON: The 4 Module Project A A A overall system B C V&V Specs. B C B C Integrate/ test system D D D 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 15

Critical Path Method Two main objectives Planning the project so that it is completed as quickly as possible Identifying activities where a delay in their execution will affect the overall end date or later activities start dates The most crucial part of the project network is the critical path the longest time sequences of tasks in a scheduling network 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 16

CPM Rules A project network may only have one start node and one end node A network may not contain loops nor dangles Precedents are the immediate preceding activities Time moves from left to right Nodes are numbered sequentially 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 17

Critical Path Method Steps 1. A forward pass (Early Schedule) Activity label Earliest start Latest start Activity span Activity description the Earliest dates at which activities can start and the project completed is determined Float= Activity Node Duration Earliest finish Latest finish (Latest finish Earliest finish ) 2. A backward pass (Late Schedule) the Latest dates for the activities is determined 3. Determine the critical path of the schedule 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 18

Precedence Network: FW /BW Passes 2 4 5 9 ES Time slot 1 1 A 0 1 1 1 B 0 3 D 0 5 2 4 5 9 2 3 4 5 C 1 2 E 4 2 10 12 F 0 3 10 12 LS LF EF Duration 3 4 8 9 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 19

The Critical Path For any activity within the network if LF - EF (float) equal zero o it is on the critical path Otherwise, o The float describes the length of time that is possible for the activity to be delayed from its ES time without delaying the project 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 20

Precedence Network: Critical Path Calculation 1 1 A 0 1 1 1 2 4 5 9 B 0 3 D 0 5 2 4 5 9 2 3 4 5 C 1 2 E 4 2 3 4 8 9 10 12 F 0 3 10 12 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 21

The Critical Path It represents earliest time required to complete a project If something on the critical path slips, the whole project slips Accelerating tasks not on the critical path o will not change the project completion date Need to have the optimal allocation of resources to its tasks 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 22

Float-Slack Time Free float the amount of time an activity may be delayed without o affecting the early start of any successor activities Total float the amount of time an activity may be delayed without o affecting the project completion date When we choose to delay the start of an activity First consider activities with free float 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 23

Project Networks: Activity-On On-the-Arrow (AOA) Milestone network AOA is a diagram with Links (arrowed lines) represent activities A link has duration Nodes (circles) represent the events of activities starting and ending Nodes have no duration 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 24

A A A CPM Network: 4 Module Project overall system B C Check specifications B C B C Integrate/ test system D D D A B overall system 1 2 3 4 C D Check specifications Event number A Expected 5 date B 6 C D 7 8 Target date A Standard deviation B C C 9 10 Integrate/ test system 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 25

PERT Charts PERT (Program Evaluation and Review Technique) uses three task duration estimates: 1. Most likely time (average): m 2. Optimistic time (best case): a 3. Pessimistic time (worst case): b The expected duration, t e, is given by (1:4:1) average formula: t a + 4m + b e = 6 with Standard deviation, s, is given by: b - a s = 6 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 26

Estimated Durations: 4 Module Project Estimated Estimated Activity duration Activity duration (days) (days) 1 overall 34 9 C 4 2 A 20 10 D 4 3 B 15 11 A 30 4 C 25 12 B 28 5 D 15 13 C 15 6 Check-specification 2 14 D 25 7 A 7 15 System integration 6 8 B 6 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 27

Expected Times and Standard Deviations: 4 Module Project Estimated duration (days) Activity Optimistic Most Likely Pessimistic Expected Standard (a) (m) (b) (t e ) (s) deviation 1 overall 29 34 38 33.83 1.50 2 A 16 20 26 20.33 1.67 3 B 13 15 18 15.17 0.83 4 C 21 25 28 24.83 1.17 5 D 12 15 17 14.83 0.83 6 Check-specification 1 2 3 2.00 0.33 7 A 5 7 10 7.17 0.83 8 B 5 6 8 6.17 0.50 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 28

Expected Times and Standard Deviations: 4 Module Project(Cont.) Activity Estimated duration (days) Optimistic Most Likely Pessimistic Expected Standard (a) (m) (b) (t e ) deviation (s) 9 C 3 4 6 4.17 0.50 10 D 3 4 7 4.33 0.67 11 A 24 30 34 29.67 1.67 12 B 23 28 31 27.33 1.33 13 C 11 15 17 14.67 1.00 14 D 22 25 29 25.17 1.17 15 System integration 4 6 8 6.00 0.67 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 29

PERT Node A A 5 A B B B overall system 6 Event number Target date 1 2 3 4 C D Check specifications C D 7 8 C C 9 1 Integrate/ 0 test system Expected date Standard deviation Expected date: largest t e along a path leading to node Standard deviation of a node: square root of the largest sum of squares of all standard deviations along a path leading to node Target date: a desired date 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 30

PERT Network: 4 Module Project 3? t = 20.33 s = 1.67 54.16 2.24 1 0 0 0 t = 33.83 s = 1.50 2 33.83 1.50 t = 15.17 s = 0.83 3? 49.00 1.71 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 31

Z Values and Probabilities PERT Assessment For each node that has a target date, T Expected Date z = T - t e s The z value can be converted to a probability of not meeting the target date using Z graph 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 32

Probability of Not Meeting the Target Date vs. Z Value for a Normal Distribution 100 90 80 70 60 50 40 30 20 10 0 Probability of not meeting target date (%) -3.25-3.00-2.75-2.50-2.25-2.00-1.75-1.50-1.25-1.00-0.75-0.50-0.25 0.00 0.25 0.50 0.75 1.00 1.25 1.75 2.00 2.25 2.50 2.75 3.00 3.25 Z value 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 33

A Comparison of CPM and PERT Charts PERT is event oriented, which can be considered milestones CPM emphasizes activities PERT is more likely to be used in projects that have relatively high levels of uncertainty PERT, explicit treatment of probability for its time estimates CPM does not Either network approach should have a minimum of about 20 events networks that are not computerized o should be limited to less than 100 events 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 34

Gantt Charts In use since the early 1900 s Shows activities as bar charts with start and completion times Depicts start and stop times relative to calendar and milestones Typically used for high-level planning but may also show detailed tasks Represents overlap between activities May show progress (status) 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 35

Gantt Charts A Gantt or bar chart is frequently used for smaller projects Usually, less than 25 activities Gantt charts are easier to understand than a PERT chart or CPM Weeks Task 1 2 3 4 5 6 7 8 A B A 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 36

Full Wall Charts Full wall charting uses a wall sized chart having an entire project team gather to schedule a project at one time using post-its to represent activities and milestones Post-its are rearranged until the schedule is optimized Full wall charting requires all participants to be in the same room at the same time not suitable for geographically dispersed team members 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 37

Selecting a Scheduling Technique Criteria Milestone Gantt Full Wall CPM PERT Activities v. Event Oriented Events Activity Event Activity Event Suitability for Large Projects Poor Poor Fair Excellent Excellent Suitability for Small Project Good Good Poor Poor Poor Degree of Control Very Low Low Moderate High Highest Acceptance by unsophisticated user Best Excellent Good Fair Poor Ease of Assembly Easiest Easy Hardest Hard Harder Degree of Flexibility Lowest Low Moderate High Highest Ease of Manual Calculation Easiest Easy Moderate Hard Hardest Accuracy of Projection Fair Fair High Higher Highest Cost to Prepare and Maintain Lowest Low Highest High Higher Vague Project Scope Poorest Poor Fair Good Excellent Complex Project Logic Poorest Poor Better Excellent Excellent Critical Completion Date Fair Fair Good Good Excellent Freq t Progress Check Req d Good Good Good Fair Hard Frequent Updating Req d Easiest Easy Hardest Hard Harder Frequent Logic Changes Req d Poor Poor Poor Fair Fair Appeal to Client Good Good Excellent Excellent Excellent 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 38

Resource Allocation Match the activity plan to available resources Labor, equipment, funding,... Personnel Resource Allocation Develop a resource schedule o Resource requirements over time Develop a cost schedule o Planned cumulative expenditure over time 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 39

Staffing Curves Staffing is not constant with time; there is typically a buildup, peak, and decline in personnel level large projects Average Person Level Small projects typically have flatter manpower curves than larger projects intermediate projects small projects Percent of Schedule Completed 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 40

How Programmers Spend Their Time Read Programs & manuals 16% Developing programs 13% Job communication 32% Mail, miscellaneous documents 5% Training 6% Miscellaneous (walking, offsite,... ) 15% Personal 13% 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 41

Allocating HR People: They come with different skill sets. o The task is to match the skill sets with the tasks Skills Skills Activities Activities Needs Inventory + Staff = Staff Skills Inventory Staff Assignments 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 42

Revisit the 4 Module Project Phase 1 Phase 2 Phase 3 Phase 4 Phase 5 Phase 6 A A A overall system B C Check specifications B C B C Integrate/ test system D D D 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 43

Resource Requirements: The 4 Module Project Phase Activity Skills Duration (days) All Project Mgr. 104 1 1 overall Senior analysts 34 2 2 A Analyst/designer 20 3 B Analyst/designer 15 4 C Analyst/designer 25 5 D Analyst/designer 15 3 6 Check-specification Senior analyst 2 4 7 A Analyst/designer 7 8 B Analyst/designer 6 9 C Analyst/designer 4 10 D Analyst/designer 4 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 44

Resource Requirements vs. Activity Plan Assuming Earliest Start Date Week Number 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 1 2 3 4 No. Personnel Activities 5 6 7 8 9 10 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 45

Earliest Start Date Scheduling Often Leads to Inefficiencies Earliest start date scheduling frequently creates resource loadings that start with a peak and tail off Changing the level of personnel over time generally adds cost to a project o o Recruiting costs Training costs Key people may be idle for periods of time Ideal resource loading will be smooth with, possibly an initial build-up and phased run-down 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 46

Smoothing Resource Requirements: Activities Rescheduling Week Number 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 1 No. Personnel Activities 2 2 3 55 44 3 2 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 47

Cost Schedule Converting a resource schedule to a time-phased Budget Identify required personnel Cumulative Cost 5 10 Cost Schedule o by name and labor rate Skills Skills Activities Activities Needs Inventory + Staff = Staff Skills Inventory Staff Assignments Factor in overhead rates o travel, equipment costs, etc. Usually overheads are a % of direct labor costs Convert personnel loading vs. time to budget loading vs. time 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 48

Snippet of Cumulative &Weekly Costs: 4 Module Project Week Number 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 $100K $75K/15 $50K/10 $25K/5 Cumulative Cost /Weekly Cost 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 49

Project Management: The Control panel Activity Plan A A A PERT Assessment overall system B C Check specifications B C B C Integrate/ test system Expected Date D D D Personnel Resource Allocation Cumulative Cost 5 10 Cost Schedule 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 50

Smoothing Resource Requirements: Activities Rescheduling Week Number 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 1 No. Personnel Activities 2 5 4 3 2 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa 51