MICROPILE FOUNDATIONS IN KARST: STATIC AND DYNAMIC TESTING VARIABILITY



Similar documents
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

Paper The relation of Micropile Diameters in case of Pressure casting and non-pressure casting (30)

Outline MICROPILES SUBJECT TO LATERAL LOADING. Dr. Jesús Gómez, P.E.

The advantages and disadvantages of dynamic load testing and statnamic load testing

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils

High Strain Dynamic Load Testing of Drilled Shafts

Pent Up Load and Its Effect on Load Test Evaluation

DYNAMIC TESTING OF MICROPILES. COMPARISON OF STATIC AND DYNAMIC TEST RESULTS

Dynamic Load Testing of Helical Piles

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

Step 11 Static Load Testing

METHOD OF STATEMENT FOR STATIC LOADING TEST

GLOSSARY OF TERMINOLOGY

CHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE

SECTION 700 STRUCTURES SECTION 701 DRIVEN PILING MATERIALS Materials Materials shall be in accordance with the following:

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

The International Workshop on Micropiles, 2007

IJESRT. Scientific Journal Impact Factor: (ISRA), Impact Factor: [205] [Elarabi, 3(12): December, 2014] ISSN:

Kentucky Lake Bridge Pile Load Testing Overview Ohio Transportation Engineering Conference Columbus, Ohio 10/28/2015

Dynamic Pile Analysis Using CAPWAP and Multiple Sensors Camilo Alvarez 1, Brian Zuckerman 2, and John Lemke 3

UNDERPINNING OF NEW STUDENT HOUSING BUILDING USING MICROPILES, NORTH CAROLINA USA

Design and Construction of Auger Cast Piles

VERTICAL MICROPILE LATERAL LOADING. Andy Baxter, P.G.

Foundation Underpinning Process and Relationship with Groundwater in West- Central Florida

Dr. Jesús Gómez, P.E. 36th Annual Conference on Deep Foundations, Boston, MA

Geotechnical Measurements and Explorations Prof. Nihar Ranjan Patra Department of Civil Engineering Indian Institute of Technology, Kanpur

Comprehensive Design Example 2: Foundations for Bulk Storage Facility

SECTION 1 GENERAL REQUIREMENTS

METHOD STATEMENT HIGH STRIAN DYNAMIC TESTING OF PILE. Prepared by

PILE FOUNDATIONS FM 5-134

Anirudhan I.V. Geotechnical Solutions, Chennai

Load Testing of Drilled Shaft Foundations in Limestone, Nashville, TN Dan Brown, P.E., Ph.D.

Lymon C. Reese & Associates LCR&A Consulting Services Tests of Piles Under Axial Load

PROVA DINAMICA SU PALI IN ALTERNATIVA ALLA PROVA STATICA. Pile Dynamic Load test as alternative to Static Load test

NEW DEVELOPMENTS AND IMPORTANT CONSIDERATIONS FOR STANDARD PENETRATION TESTING FOR LIQUEFACTION EVALUATIONS. Jeffrey A Farrar M.S.

Driven Concrete Pile Foundation Monitoring With Embedded Data Collector System

ENCE 4610 Foundation Analysis and Design

Proceedings of the ASME 28 TH International Conference on Ocean, Offshore and Arctic Engineering OMAE2009 May 31 June 5, 2009, Honolulu, Hawaii, USA

APPENDIX A PRESSUREMETER TEST INTERPRETATION

SECTION 411 DRILLED PIERS

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

KWANG SING ENGINEERING PTE LTD

Method Statement for Static Load Testing (Compression) for Micropiles

INSITU TESTS! Shear Vanes! Shear Vanes! Shear Vane Test! Sensitive Soils! Insitu testing is used for two reasons:!

Figure A-1. Figure A-2. continued on next page... HPM-1. Grout Reservoir. Neat Cement Grout (Very Flowable) Extension Displacement Plate

ATLAS RESISTANCE Pier Foundation Systems

An Automatic Kunzelstab Penetration Test

ADVANCEMENTS IN STATNAMIC DATA REGRESSION TECHNIQUES

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT

TENSION AND COMPRESSION MICROPILE LOAD TESTS IN GRAVELLY SAND

PDCA Driven-Pile Terms and Definitions

System. Stability. Security. Integrity. 150 Helical Anchor

Stability. Security. Integrity.

Instrumented Becker Penetration Test for Liquefaction Assessment in Gravelly Soils

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

INDIRECT METHODS SOUNDING OR PENETRATION TESTS. Dr. K. M. Kouzer, Associate Professor in Civil Engineering, GEC Kozhikode

LEGACY REPORT ER ICC Evaluation Service, Inc. Reissued November 1, Legacy report on the 1997 Uniform Building Code

Page B-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2014 LOAD TESTS

ITEM # OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations

Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations

MICROPILES: RECENT ADVANCES AND FUTURE TRENDS

How To Design A Foundation

vulcanhammer.net This document downloaded from

APPENDIX G SETTLEMENT

Caltrans Geotechnical Manual

CIVL451. Soil Exploration and Characterization

Ecoflex Wall Penetration Systems: An efficient, sustainable solution for penetrating concrete or block walls

The Installation and Load Testing of Drilled Shafts

ALLOWABLE LOADS ON A SINGLE PILE

Use of the Cone Penetration Test for Geotechnical Site Characterization in Clay-Mantled Karst. T. C. Siegel 1 and P. E. Cargill 2

PILE TESTING SPECIFICATION

DESIGN OF PILES AND PILE GROUPS CONSIDERING CAPACITY, SETTLEMENT, AND NEGATIVE SKIN FRICTION

Equivalent CPT Method for Calculating Shallow Foundation Settlements in the Piedmont Residual Soils Based on the DMT Constrained Modulus Approach.

Buckling of Micropiles

Post Grouted Single Bore Multiple Anchors at Hodenpyl Dam, Michigan

Dams and Extreme Events Reducing Risk of Aging Infrastructure under Extreme Loading Conditions

DEM modelling of the dynamic penetration process on Mars as a part of the NASA InSight Mission

LABORATORY DETERMINATION OF CALIFORNIA BEARING RATIO

How to Design Helical Piles per the 2009 International Building Code

Axial Behaviour of Hollow Core Micropiles Under Monotonic and Cyclic Loadings

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge.

STATIC PILE LOAD TEST MANUAL. GEOTECHNICAL CONTROL PROCEDURE GCP-18 Revision #4

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

BUTE Department of Construction Management and Technology

Improvement in physical properties for ground treated with rapid impact compaction

Statnamic Load Testing Overview

High Capacity Helical Piles Limited Access Projects

DRIVEN PILE COST COMPARISON FOR TWO LARGE WISCONSIN DOT BRIDGE PROJECTS

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska

FOUNDATION DESIGN. Instructional Materials Complementing FEMA 451, Design Examples

Numerical Simulation of CPT Tip Resistance in Layered Soil

Washington ,

Comparison Between Dynamic and Static Pile Load Testing

DESIGN-BUILD SUPPORT OF EXCAVATION FOR BLOCK 76. Rick Deschamps and Tom Hurley, Nicholson Construction, Pittsburgh, PA USA

SECTION STORM DRAIN SYSTEM

California Department of Transportation Doyle Drive Test Program Contract No. 04A3362

Table of Contents 16.1 GENERAL Overview Responsibilities

PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE

Transcription:

MICROPILE FOUNDATIONS IN KARST: STATIC AND DYNAMIC TESTING VARIABILITY Jesús Gómez, Ph.D., P.E Allen Cadden, P.E. O. Christopher Webster, P.E. Schnabel Engineering, Inc. Schnabel Engineering, Inc. Schnabel Engineering, Inc. West Chester, PA-USA-1938 West Chester, PA-USA-1938 Charlottesville, VA-USA-2291 ABSTRACT Development of a major industrial facility required support of large loads from machine foundations. The site was underlain by highly variable karstic limestone conditions, which resulted in irregular depths to rock, very soft residual soil layers, and potential for voids in the rock and soil matrix. Foundation mats on micropiles were selected for support of the machines. The benefits associated with the micropiles were the speed of installation, and relative cost and schedule savings. Two load tests were performed before the start of micropile installation. One of these tests failed prematurely. A third test, performed during the initial stages of construction, also failed prematurely. Pile Driving Analyzer (PDA) testing of micropiles was used to investigate the capacity and variability of production piles that were already installed. The authors believe this may be the first application of the PDA technology to estimate the carrying capacity of micropiles bonded into rock. Because of the lack of previous experience in this application of PDA testing, suitable testing procedures needed to be developed in the field to reduce the potential for damage of the production micropiles, and to assess the accuracy of the tests. The results of the testing program showed that PDA testing may provide very accurate estimates of the capacity of micropiles bonded into rock. This paper discusses the techniques used for PDA testing of the micropiles, and compares the results of the PDA tests to the data from static load tests. The paper also contains a brief discussion on the site conditions, and the effect of the construction methods on the measured capacity of the micropiles and their variability. INTRODUCTION Micropile technology has evolved significantly since its inception in the 195s. Early applications of micropiles in Europe consisted of lightly loaded groups of elements intended to enclose and reinforce an unstable soil mass for slope stabilization or underpinning of historic buildings (Lizzi, 1982). Micropile technology developed slowly in Europe over the next 2 or 3 years, until publication of successful case histories induced its rapid growth in the United States, where it evolved more towards the use of heavily reinforced micropiles with high axial load-carrying capacities. In the United States, the most common application of micropiles has traditionally been underpinning of existing structures. For this particular application, micropiles are often a more economical alternative. In addition, they may install more quickly than other underpinning alternatives within confined spaces and low headroom conditions, and produce a limited amount of spoils. More recently, foundation designs of new structures have used micropiles as an economical alternative to other foundation systems. The authors have designed foundations for several new structures using micropiles. One good example is in Manhattan, New York City, NY, where micropiles were used for foundations of a new building. The micropiles traversed the upper layers of old fill containing rubble and debris typical of the area, and the deeper hardpan to reach the underlying granite. The owner preferred micropiles over driven piles since the micropiles could be installed with less disturbance to adjacent old structures and could achieve higher working capacities. Another recent example of the application of micropiles for new structures is a new electric power generation plant in the Piedmont of Virginia. The plant is located in a karst area, where depths of significant karst features varied from a few feet to over 1 ft. Large interconnected voids and layers of very soft clays and silts existed within the formation among harder limestone pinnacles and ledges. Micropiles provided a suitable foundation alternative since they could be installed through the upper karst features into competent rock. A single unit price per linear foot could be defined regardless of the type of the material traversed. This represented a significant advantage over drilled shafts, where rock drilling and concrete Paper No. 9.5 1

overages in the karst terrain could easily exceed the foundation construction budget. In this project, the specialty foundation contractor tested three micropiles before or right after the start of production pile installation. Two of the three piles failed prematurely during load testing. This prompted an investigation by the geotechnical consultant into the causes of failure, and the capacity of the production piles that the contractor had already installed. The geotechnical consultant concluded that the piles failed due to a combination of the installation procedures selected by the contractor, lack of adequate field observation during installation, and the variable karstic conditions existing at the site. It was also concluded that, to be able to estimate the available capacity of the production piles already installed, a significant portion of the piles had to be tested. After careful consideration of the testing options available, the geotechnical consultant decided that the micropiles be dynamically tested using the Pile Driving Analyzer (PDA) (Smith, 196; Goble Rausche Likins, 1996). This testing program presented several challenges, the most important of which was reducing the potential for damage of the production micropiles tested. Stiff Silts and Clays Soft epi-karst Limestone 7 5/8 inch O.D.,.43-inch thick casing 2#18, 75 ksi reinforcing bars Bond into suitable limestone This paper focuses on the techniques used for PDA testing of the micropiles, and presents several interesting conclusions regarding the use of PDA as a Quality Control (QC) tool. The most important finding is that PDA may be a suitable procedure for verifying the capacity of micropiles bonded into rock, provided that certain precautions are taken during testing to prevent pile damage. GEOLOGICAL SETTING The site is located in the Piedmont Geographic Province in north central Virginia. The major site stratigraphy consists of karst terrain of the Everona Limestone and its overlying residual soils and disintegrated rock. The Everona Limestone Formation varies in depth from 2 to 11 ft and is likely of Early Paleozoic Age. Figure 1 illustrates the general stratigraphy at the site. Surface and near surface intervals consist of residual soils composed by medium stiff to hard silts and clays. A layer of soft to very soft silt underlies the stiff residual soils. This layer is commonly referred to as epi-karst. The epi-karst is not a continuous layer; instead, the epi-karst appears randomly within stiffer layers of soil and rock and in seams of variable thickness. The boundary between the epi-karst and the underlying limestone is not well defined. Based on the field observations, the geotechnical consultant estimated that the contractor would likely encounter suitable limestone for foundation purposes at depths ranging from 4 to 11 ft. Fig. 1. Typical stratigraphy at the site. MICROPILE INSTALLATION As shown in Fig. 1, each micropile consisted of a 7e inch O.D.,.43-inch thick casing along the unbonded zone. The bonded zone consisted of two central #18, 75-ksi All-Thread bars extending from 5 ft above the tip of the casing and into the bond zone. The foundation design established the design load of the micropiles at 15 kips, a relatively low value for micropiles adequately bonded into rock. The specialty foundation contractor installed the micropiles by pre-drilling with a Down-Hole Hammer (DHH). The final tip elevation of the micropiles was established using a 1-ft penetration criterion into the bearing material. Thus, determination of the length of the micropile was highly dependent on the operator and the field inspector, who should identify continuous rock based on the resistance to drilling with the DHH. Once pre-drilling was complete, the casing was spun to the bottom of the predrilled hole. The bond zone was typically established by raising the casing 1 ft above the bottom of the hole. Simultaneous injection of pressurized air was used throughout the process. Contamination of the bond zone due to ingress of soft soil and mud was an important concern. Before grouting, the hole was probed with a weighted tape and tremie-flushed with water to attempt to displace soils and mud often detected inside the bond zone during probing. The contractor used a tremie pipe inserted to the bottom of the hole Paper No. 9.5 2

to gravity fill grout, and continued until the grout reached the top of the casing. During drilling, communication between predrilled holes was observed frequently (see Fig. 2). In a number of piles, the level of grout inside the casing decreased over time, which indicated the existence of open voids along or near the bond zone. The compressive axial load tests were conducted in general accordance with the procedure for quick load tests described in ASTM D1143, and recommendations by the Federal Highway Administration (FHWA) presented in the Micropile Design and Construction Guidelines Implementation Manual (FHWA-SA-97-7). The test piles were loaded to twice the design load. Figure 3 illustrates the results of the compression load tests. Settlement (in).1.2.3.4.5.6.7.8.9 1 1.1 1.2 Load (kip) 5 1 15 2 25 3 35 Fig. 2. Communication with adjacent holes was often evident during drilling. Settlement (in).1.2.3.4.5.6.7.8.9 1 1.1 1.2 STATIC LOAD TESTING Initially, the contractor conducted two static load tests in sacrificial micropiles. To address the particular design characteristics of the project, the contractor conducted compression, tension, and lateral load testing on the micropiles. To allow for tension testing, the project requirements included reinforcing the upper 1 ft of the unbonded zone of each micropile with one #13, 15 ksi Williams All-Thread bar. The contractor installed both piles following the general procedures described previously. Micropile TP-1 was drilled to a depth of 39 ft. The tip of the casing was left at a depth of approximately 29 ft. Micropile TP-2 was drilled to a depth of approximately 56 ft. The tip of the casing was left at a depth of 46 ft. During installation of this micropile, it was observed that some zones within the overburden contained very moist and soft soils, and multiple flushing of the casing was necessary to remove these sediments from the bond zone, and ensure that the casing was set at the proper depth. Settlement (in).1.2.3.4.5.6.7.8.9 1 1.1 1.2 Fig. 3. Static load test results. TP-1 TP-2 TP-3 As can be seen in the figure, Micropile TP-1 failed during compression testing under a load of approximately 19 kips (125 percent of design load). Micropile TP-2 tested Paper No. 9.5 3

successfully. The gross settlement at the design load of 15 kips was approximately.23 inch. The gross settlement under the maximum test load of 3 kips was approximately.5 inch. Creep during load application was negligible. Interpretation of the elastic rebound data (Gómez et al., 23) during each of the unloading cycles suggested that failure of Micropile TP-1 was due to poor bond along the grout-rock interface, and that no structural failure of the micropile took place. application since they may allow better control on the energy imparted to the piles. Due to the failure of Micropile TP-1, the contractor performed a third load test on a production pile. This pile also failed prematurely under a load of approximately 26 kips. This was cause for concern requiring the geotechnical consultant to investigate the causes for the failure and evaluate the available capacity of the production micropiles that the contractor had already installed. The geotechnical consultant concluded that the causes for the failure of the two micropiles were contamination of the contact between the grout and the rock due to the particular subsurface conditions, and the difficulties encountered to clean the bond zone by flushing with water. Fig. 4. View of the accelerometer and strain gauge used for PDA testing. It was decided that it was necessary to evaluate the capacity of the production piles that had already been installed. Two alternatives were available from a practical point of view. Statnamic Testing (Middendorp and Van Foeken, 2) could be used to perform several load tests per day on production micropiles. Furthermore, this technique had been successfully applied to driven piles and drilled shafts. PDA testing was another practical alternative. Although PDA testing had been used in some cases to predict capacity of drilled shafts in soils, the geotechnical consultant could find no records on the use of PDA testing for micropiles bonded into rock. There was also a concern about potential structural damage of the micropiles during each impact. Finally, it was also believed that degradation of the micropile bond to the rock might take place during PDA testing. PDA TESTING RESULTS PD A testing of production micropiles was performed at different locations on micropiles of varying length. Once 22 production micropiles were tested, the General Contractor decided to discontinue further PDA testing. PDA testing was performed using two accelerometers and two strain gauges (Fig. 4) attached to the casing and close to the head of each tested micropile. The head of each test pile was impacted using a Vulcan 1 air hammer (see Fig. 5). The hammer had an energy rating of approximately 15, ft-lb. This selected hammer was the only low energy hammer that was readily available at the time. Although this hammer performed well for this application, the authors own experience and additional input from GRL suggest that hydraulic hammers may be more convenient for this Fig. 5. PDA testing on a production micropile using a Vulcan 1 air hammer. The top of each production pile was fitted with reinforcing bars for connection with the pile cap. Consequently, a custom follower device was fabricated and placed between the hammer and the pile head to permit testing without damage to Paper No. 9.5 4

the reinforcement. Cushioning was provided between the head of the pile and the follower device, and consisted of approximately 5 to 7 inches of plywood, as illustrated in Fig. 6. The amount of cushioning needed to prevent damage to the piles was determined during calibration testing of Micropiles TP-1, TP-2, and TP-3. Fig. 6. View of the follower device and cushioning. Note the reinforcing steel of the micropiles. T esting of each production pile was performed by striking the pile initially with a low energy blow. Once the first blow was applied and the PDA results were examined onscreen, the pile was subjected to two or more additional full hammer strokes. Striking was discontinued once a PDA capacity of 3 kips or more was measured, or if damage to the micropile was imminent based on the estimated stresses along the pile. Table 1 shows a summary of the results of PDA testing. In addition to PDA testing, Case Wave Pile Analysis Program (CAPWAP) analyses were performed on selected piles to obtain additional data on pile response to loading and to confirm the capacity obtained from PDA testing. The results of CAPWAP analyses are also included in Table 1. A s seen in the table, the PDA results on Micropiles TP-1, TP- 2, and TP-3 were consistent with the ultimate capacity values determined from the static load tests. In Micropiles TP-1 and TP-3, the PDA capacity was approximately 2 kips higher than the static load capacity. The CAPWAP and PDA results for Micropile TP-2 indicated a capacity larger than 3 kips, which was consistent with the static load test results. It is noted that the ultimate capacity given by PDA and CAPWAP on Micropile TP-2 is consistent with the authors experience on micropiles bonded into limestone (Cadden et al., 21). T able 1. Summary of Results from PDA Testing, CAPWAP Analyses, and Static Load Testing Test Length Capacity (Kip) (ft) PDA CAPWAP Static TP- 1 4. 243 25 225 TP-2 57.3 42 495 >3 TP-3 46.4 281 263 26 1 5. 318 2 44.6 37 3 46. 38 4 64.8 312 399 5 53.3 198 6 96.5 272 288 7 55.5 285 8 46. 272 33 9 81.5 29 1 45.7 21 11 41.3 226 12 74. 251 29 13 37.2 319 14 45. 314 15 4. 312 16 41. 199 258 17 41.9 75 81 18 41.3 319 19 37. 288 2 57. 293 21 41.1 272 22 69.2 282 Based on the comparison between PDA and static load test results, it was concluded that the dynamic testing, as performed, could provide reasonably accurate estimates of capacity for the rest of the production micropiles tested. It must be noted that PDA testing of each micropile was discontinued if a capacity of 3 kips or more was measured. Therefore, it must be kept in mind that the capacity of the piles that exceed 3 kips in Table 1 may actually be significantly greater. In these piles, it is possible that the impact energy applied was not sufficient to mobilize the bond strength along the bond zone. It is believed that capacity values of less than 25 kips are reasonably accurate, as they were typically obtained after several blows with increasing energy and after some measurable permanent displacement of the micropile. The results presented in Table 1 are shown graphically in Fig. 7. It may be noted that there was a number of piles that did not reach a capacity of 25 kips. Pile 17 only showed a PDA Paper No. 9.5 5

capacity of 75 kips. During testing of this pile, large displacements at the head of the pile were noticeable. Ultimate Capacity (Kip) 45 4 35 3 25 2 15 1 5 TP-1 TP-3 2 4 PDA Data Static Test 6 8 Fig. 7. Variability of micropile capacity as determined from PDA testing. 1 Pile No. It is interesting to note the variation of capacity from one micropile to another. Relatively large variations were common in micropiles that were installed in close proximity and with similar lengths. This variability in micropile capacity may be attributed to the installation methods used. Based on the results of the PDA tests, recommendations were developed to establish a reduced bearing capacity for the micropiles that could be used to adjust the original foundation design. C ONCLUSIONS It is believed that the low capacity piles as identified by the P DA testing and static load tests were the result of inadequate development or inadequate cleaning of the bond zone. A review of the overall PDA data indicates that of the 25 piles te sted, ten micropiles (4 percent) had PDA capacities equal or greater than 3 kips, which corresponds to a factor of safety of 2 or more for a design working load of 15 kips. Eight micropiles (32 percent) had PDA capacities between 25 and 3 kips. As mentioned earlier, in some of these piles, PDA testing was stopped if there was potential for pile damage; therefore, their actual capacity may have been larger. Seven micropiles (28 percent) had ultimate capacities of less than 25 kips, which corresponds to a factor of safety of 1.7 or lower. It can a lso be noted that 24 of the piles had ultimate capacities in excess of the design working load of 15 kips. Only one pile tested lower than this value, with an ultimate capacity measured of about 8 kips. Considering the testing completed to date, this could indicate that about five percent of the piles would not develop the intended design working capacity before geotechnical failure. Also, 3 to 5 percent of the piles 12 14 16 18 2 22 did not meet the intended factor of safety of at least two over the ultimate capacity. The authors believe th at the variability in micropile capacity w as due to a combination of the difficult karstic conditions at the site and the methods of installation of micropiles. Adequate installation of micropiles requires identification of suitable rock for load transfer during drilling, and adequate cleaning and thorough grouting of the piles, which was difficult to achieve given the presence of the epi-karst. It is noted that the drilling method selected for the mic ropiles w as essentially open-hole. Duplex drilling methods are believed to be much better suited for installation of micropiles in karst. PDA test ing of micropiles bonded into rock can be performed su ccessfully. It is recommended that calibration tests be performed that allow comparison of measured static capacity values to PDA results. The calibration tests would also aid in establishing testing procedures that reduce the potential for damage to production piles. PDA testing should not be used as a substitute for static load testing. Hydraulic hammers may be better suited for PDA testing of m icropiles. However, air hammers can also be used successfully provided that the operator is experienced and able to control the drop height with some accuracy. It is noted that testing of cased micropiles with a diameter of less than seven inches may require additional precautions to prevent structural damage during testing. A CKNOWLEDGEMENTS We would like to thank the Old Dominion Electric C ooperative (ODEC) for kindly allowing the publication of the information contained in this paper. Additional thanks must also go to Scott Webster of GRL Engineers, Inc., of Charlotte, North Carolina, who provided invaluable help during dynamic testing. Finally, we want to thank Schnabel Engineering for providing significant resources during the preparation of this paper. R EFERENCES Cadden, A.W, D.A. Bruce, and L.M. Ciampitti [21]. Micropiles in karst: a case history of difficulties and success, Foundations and Ground Improvement, Proceedings of a Specialty Conference, American Society of Civil Engineers, Blacksburg, VA, June 9-13, Geotechnical Special Publication No. 113, pp. 24-215. Goble Rausche Likins and Associa tes, Inc. [1996]. CAPWAP In troduction to dynamic pile testing methods. Gómez, J.E., A.W. Cadden, and D.A. B ruce [23]. Micropiles founded in rock. Development and evolution of Paper No. 9.5 6

bond stresses, Soil and Rock America 23, Proceedings of the 12th Panamerican Conference on Soil Mechanics and Geotechnical Engineering, pp. 1911-1916, Cambridge, MA June 22-26, 23. Kulhawy, F. H., and M.S. Peterson [1979]. "Behavior of sand- interfaces," Proceedings of the 6th Panamerican concrete Conference on Soil Mechanics and Foundation Engineering, Lima, Perú, December 2-7, 1979. II, 225-236. Middendorp, P., and R.J. van Foeken [2]. When to apply dynamic load testing and Statnamic testing, Statnamic Loading Test, Proceedings Second International STATNAMIC Seminar, Tokyo, Japan, 28-3 October 1998. A.A. Balkema/Rotterdam/Brookfield, 2. Smith, E.A.L. [196]. Pile driving analysis by the wave equation, Journal of Soil Mechanics and Foundations, ASCE, 86, pp 35-61. Paper No. 9.5 7