THE TAIWAN LIGHT SOURCE AND SUPERCONDUCTING CAVITY



Similar documents
The BESSY HOM Damped Cavity with Ferrite Absorbers. Review of prototype cavity test results, taperedwaveguidesvshomogenouswaveguides

Damping Wigglers in PETRA III

BEPC UPGRADES AND TAU-CHARM FACTORY DESIGN

RF SYSTEM FOR VEPP-5 DAMPING RING

Status of the HOM Damped Cavity for the Willy Wien Ring

Frequency Map Experiments at the Advanced Light Source. David Robin Advanced Light Source

Investigations on Critical Higher Order Modes in CEBAF Upgrade Cavities

Status of Radiation Safety System at

Industrial Involvement in the Construction of Synchrotron Light Sources

CAVITY DESIGN REPORT

FIVE PROJECTS OF HIGH RF POWER INPUT COUPLERS & WINDOWS FOR SRF ACCELERATORS*

Status of the Diamond Storage Ring RF Systems. Morten Jensen on behalf of Diamond Storage Ring RF Group

Large Systems Commissioning

Status of the SOLEIL project Commissioning from Linac to beamlines

C.-K. Ng. Stanford Linear Accelerator Center. and. T. Weiland. University oftechnology. FB18, Schlossgartenstr. 8. D64289, Darmstadt, Germany.

HIGH-ENERGY COLLIDER PARAMETERS: e + e Colliders (I)

SIMULATIONS OF ELECTRON CLOUD BUILD-UP AND SATURATION IN THE APS *

Figure 1: Lattice drawing for the APS storage ring.

Coupling Impedance of SIS18 and SIS100 beampipe CERN-GSI-Webmeeting

Zero Degree Extraction using an Electrostatic Separator

10 Project Costs and Schedule

Ferroxcube. For more information on Product Status Definitions, see page Sep CBW625

Development of Radiation Resistant Quadrupoles Based on High Temperature Superconductors for the Fragment Separator

Tune and Chromaticity Tracking in the Tevatron. C.Y. Tan 09 May 2006

Calculation of Eigenmodes in Superconducting Cavities

FLS 2010 Storage Ring Working Group Session 4: Future ring technology and design issues

Activities at the University of Frankfurt (IAP)

FCC JGU WBS_v0034.xlsm

OVERVIEW OF PROTON DRIVERS FOR NEUTRINO SUPER BEAMS AND NEUTRINO FACTORIES*

HIGH CURRENT OPERATION OF THE ACSI TR30 CYCLOTRON

Results: Low current ( ) Worst case: 800 MHz, GeV, 4 turns Energy oscillation amplitude 154 MeV, where

Reliability and Availability Aspects of. the IPHI Project

The accurate calibration of all detectors is crucial for the subsequent data

14.5GHZ 2.2KW CW GENERATOR. GKP 22KP 14.5GHz WR62 3x400V

Undulators and wigglers for the new generation of synchrotron sources

The half cell of the storage ring SESAME looks like: Magnetic length =

Brookhaven Magnet Division - Nuclear Physics Program Support Activities

WAVEGUIDE-COAXIAL LINE TRANSITIONS

LHC MACHINE PROTECTION

SOLEIL Current Performances. And. Futur Developments

Introduction to Superconducting RF (srf)

Institute of Accelerator Technologies of Ankara University and TARLA Facility

An octave bandwidth dipole antenna

A. Martinez, A. L. Klebaner, J. C. Theilacker, B. D. DeGraff, M. White and G. S. Johnson

EH-20 20m antenna. By VE3RGW

MYRRHA Injector Design

Lecture VI Magnetic Design

Status Overview The Australian Synchrotron. Steven Banks Control Systems Group

Thermal insulation. Don t be afraid of low temperatures. Institute for Technical Physics Holger Neumann

RF-thermal-structural-RF coupled analysis on the travelling wave disk-loaded accelerating structure

Insertion Devices Lecture 4 Permanent Magnet Undulators. Jim Clarke ASTeC Daresbury Laboratory

AUTOMATION OF OPERATIONS ON THE VEPP-4 CONTROL SYSTEM

ELECTRON-CLOUD EFFECTS IN THE TESLA AND CLIC POSITRON DAMPING RINGS

A Quick primer on synchrotron radiation: How would an MBA source change my x-ray beam. Jonathan Lang Advanced Photon Source

High Bandwidth Wall Current Monitor

The design and performance of Static Var Compensators for particle accelerators

Peter C. Vander Arend Cryogenic Consultants, Inc. Allentown, Pennsylvania

Design and Fabrication of a Power Supply House in Brazil

Status of EVOLVE boiling flow regime experiments

Wireless RF Distribution in Buildings using Heating and Ventilation Ducts

THE ALIGNMENT STRATEGY FOR THE SPIRAL2 SUPERCONDUCTING LINAC CRYOMODULES

Development of a Low Frequency Superconducting RF Electron Gun. September 2010

Development of High Stability Supports for NSLS-II RF BPMS

1. Straight Sections

3 Main Linac. 3.1 Introduction. 3.2 Beam Dynamics II-63

National Laboratory of Antennas and Microwave Technology Xidian University Xi an, Shaanxi , China

The commissioning of the LHC: first the technical systems, then the commissioning with beam

- thus, the total number of atoms per second that absorb a photon is

BB-18 Black Body High Vacuum System Technical Description

Connected U-Slots Patch Antenna for WiMAX Applications

Possible Upgrades and New Design. F. Velotti and B. Goddard

DEVELOPMENT OF BUTTON ELECTRODES FOR SUPERKEKB RINGS

An equivalent circuit of a loop antenna.

Review Paper for Broadband CPW-Fed T-Shape Slot Antenna

ESRF Upgrade Phase II: le nuove opportunitá per le linee da magnete curvante

MECHANICAL AND THERMAL ANALYSES OF THE CABLE/ STRAND STRAIN TEST FIXTURE

SIW 2D PLANAR ARRAY WITH FOUR CROSS SLOTS RADIATOR AND TUNING VIAS

RARE ISOTOPE ACCELERATOR (RIA) PROJECT*

RF data receiver super-reactive ASK modulation, low cost and low consumption ideal for Microchip HCS KEELOQ decoder/encoder family. 0.

Selected Radio Frequency Exposure Limits

AMSC s Superconductor Cable Technologies for Electric Utilities

Characterization of Spatial Power Waveguide Amplifiers

EM Noise Mitigation in Circuit Boards and Cavities

Status of High Current Ion Sources. Daniela Leitner Lawrence Berkeley National Laboratory

Libera at ELETTRA: prehistory, history and present state

Oscar E. Morel UtilX Corporation

Beam Energy (GeV) 2 Beam Current (ma) 400 Horizontal Emittance (nm)

A Guide to Acousto-Optic Modulators

A Study of RF Absorber for Anechoic Chambers Used in the Frequency Range for Power Line Communication System

Study of electron cloud at MI and slip stacking process simulation

JITAI Technology Co., LTD. Your 1 st Partner. Product Catalog. Microwave Passive Device Design and Manufacture

HIGH-CAPACITY HIGH TEMPERATURE SUPERCONDUCTING POWER CABLES

Analysis of Broadband Slot Cut Semi-Circular Microstrip Antennas

Wake Field Calculations at DESY

AS COMPETITION PAPER 2008

ULTRAFAST LASERS: Free electron lasers thrive from synergy with ultrafast laser systems

MINIMUM USAGE OF FERRITE TILES IN ANECHOIC CHAMBERS

Planar Inter Digital Capacitors on Printed Circuit Board

Transcription:

THE TAIWAN LIGHT SOURCE AND SUPERCONDUCTING CAVITY G.H. Luo, Ch. Wang, L.H. Chang, M.C. Lin, T.T. Yang and C.T. Chen SRRC, No. 1 R&D Road VI, HSIP, Hsinchu, Taiwan Abstract The Taiwan Light Source (TLS) is a third-generation light source with low-emittance and low operating energy, 1.5 GeV, which is used as ultra-violet and soft x- ray light source in Taiwan. Doubling the photon flux and stored beam current has been proposed to users by upgrading the RF system to superconducting cavity. The cavity s upgrading project is expected to reduce the longitudinal coupled bunch instability and increase beam lifetime by doubling the operation gap voltage. Machine status, beam parameters, RF characteristics, cryogenics system, safety issues on operation and simulation of high-power components will be presented. 1 INTRODUCTION The Taiwan Light Source (TLS) is the first thirdgeneration synchrotron light source in Asia located at Synchrotron Radiation Research Center (SRRC) at Hsinchu, Taiwan. Three beam lines are initially constructed when TLS opened to synchrotron users in 1993 with 1.3 GeV of nominal beam energy and 00 ma stored beam current. Currently, there are 1 operation beam lines, two beam lines under construction and five beam lines in design or planning stage. Three branches of operation beam lines are used as diagnostic beam lines to acquire transverse beam size and the information of integral photon stability. The electron beam energy of TLS storage ring is upgraded to 1.5 GeV in 1996 [1] and full energy injection capability from booster in 000. Basic parameters of storage ring are listed in Table 1. The schematic drawing of TLS synchrotron facility is shown in Fig. 1. The storage ring is a six-fold symmetry Triple-Bend- Archomat (TBA) lattice with six straight sections. One section is for injection and planned to install a 3-poles with 6.5 Tesla of peak-field s superconducting wavelength shifter at downstream of the injection kicker. Figure 1. The schematic drawing of TLS storage ring, transport line and booster

One section is for the Doris Cavities, which will be replaced by a SRF cavity and a 9-poles 3.5 Tesla superconducting multipoles-wiggler. The rest four sections are installed with conventional normalconducting insertion-devices, U9, U5, W0 and Elliptical Polarized Undulator EPU5.6. Hardware parameters and radiation loss for the insertion devices are listed in Table. The radiation spectrum for the bending magnet, wiggler and undulators at various harmonics are shown in Fig. with 00 ma stored beam current and 1.5 GeV beam energy at TLS. Table 1. Basic parameters of the TLS storage ring Beam Energy E 1.5 GeV Circumference 10 m Harmonic number 00 Working tune (H/V) 7.18/4.13 Nature chromaticity (H/V) -15.7/-6.61 RF frequency f RF 499.654 MHz Compaction factor α 0.00678 Nature emittance ε 5.5 nm-rad. Nature energy spread 0.000756 Operation RF voltage V RF 800kV Particle numbers (00mA/140) 3.95*10 9 /bunch Damping time (H/V/L) 6.96/9.37/5.67 ms Radiation loss due to bending 18 kev/turn Table. The operation parameters of insertion devices W0 U5 U9 EPU SWS Period λ ID [cm] 0 5 9 5.6 ~5 # of periods N ID 13 76 47 6 1.5 Mini. Gap [mm].5 18 18 18 18 Magnetic field [T] 1.8 0.64 1.45 0.67 6.5 Rad. Loss [kev/turn] 18.5. 9.3.4 13.9 Total length [m] 3.04 3.9 4.5 3.9 0.65 PERFORMANCES OF TLS DURING USER S SHIFT User s beam time is scheduled 11 hours per week in normal operation period. More than 4600 hours was scheduled for users beam time during year 000. The operation statistics between August 000 and July 001 is shown is Fig. 3. Successful delivery rate to users during this period is better than 96.4%. Hours 600 500 400 300 00 100 0 Schedule User Time Delivered User Time Available Ratio Aug. Sept. Oct. Nov. Dec. Jan.01 Feb.01 Mar01 April01 May01 June01 July01 Month Figure 3. The statistics of users beam time between August 000 and July 001. Average available ratio is better than 96.4%. Beam stability, lifetime, current and emittance are the key parameters to the beam line users. The beam lifetime is better than 1 hours at 00 ma store beam current and the measured emittance is 0 nm-rad. The average static pressure and the dynamic pressure at 00 ma are 0.1 ntor and 0.16 ntor, respectively. The photon stability is measured through a 50 µm pinhole combined with a diode detector, which intercepts the synchrotron light focused by a vertical focusing mirror []. The improved cooling system of vertical focusing mirror makes the stability parameter as a reliably monitoring indicator. One of typically weekly statistics of the beam stability is shown is Fig. 4. This figure shows that there 100 90 80 70 60 50 available ratio (%) 1. photon beam stability δi/i0 (%) 1.0 0.8 0.6 0.4 0. Figure. The spectrum for bending magnets, wiggler and undulators at various harmonics with 00 ma and 1.5 GeV electron beam at TLS. 0.0 0 0 40 60 80 100 available beam stability ratio (%) Figure 4. Beam stability ratio during users shift

is more than 90% of users beam time that the photon fluctuation ratio is less than 0.5%. The temperature variation in the tunnel and the chilly-water, which is affected by the weather, the cooling capacity and operation condition, were causing long-term drift of the beam orbit. We observed a large orbit swing, more than 150 µm, at the first session of users shift immediately after accelerator start up. It was correlated to the swing of working temperature of dipole magnets. A better temperature control of chilly water and tunnel temperature have been carried out [3] and full energy injection system also been implemented to reduce the temperature fluctuation of each injection. Figure 5 shows the beam position variation for six consecutive user s shifts currently. The average position variation is less than 10 µm among six consecutive users shifts. The beam orbit is locked by global feedback system for individual shift. The orbit drift for each shift can be controlled down to less than 1.5 µm. Figure 5. Beam position variation for 6-consecutive users shifts detected by beam position monitor with resolution better than 0.1 µm. 3 DORIS CAVITY AND CESR S CAVITY Two Doris cavities were installed to provide proper operation power and gap voltage. A broadband loop-type damping antenna attached to the cavity cannot effectively suppress the Higher-Order-Modes (HOM). The damping antenna was replace by a plunger-type tuner in each cavity [4] to detune the most troublesome HOM. The improvement of the temperature control, ± 0.1 o C, of each cavity with dynamic range of ± 0 o C helps in suppressing the excitation of HOM. An RF gap-voltage modulation technique has also been implemented during routine operation [5]. With all of these manners, the photon fluctuation can be successfully suppressed to less than 0.3-0.4% during the users shifters as shown in Fig. 4. However, for demanding experiments and users, the photon fluctuation is targeted to be less than 0.1% persistently. Superconducting RF cavity together with longitudinal feedback system is expected to suppress the coupled bunch instability and further reduce the photon fluctuation. 4 BEAM LIFETIME Beam lifetime is one of the key issues in the SRF project. Touschek lifetime is a dominating factor for a low-energy synchrotron facility. The bunch length, dynamic aperture, energy acceptance and the gap voltage are the major parameters in the evaluation. The radiation of bending and insertion devices will tend to increase the quantum fluctuations and lower the damping time. The definition of Synchrotron Radiation Integrals (SRI) constants for the operation lattice can be evaluated as reference [6]. The emittance, energy spread and bunch length can be expressed in terms of SRI. The bunch length can be expressed as: 1/ 1/ παhc E 55hγ I3 σ =, L ϖ RF cosφ s evrf 3 3 I + I 4 where I 1 to I 5 are SRI defined as reference [6], ϕ s is the synchrotron phase and h is the harmonic number. The relationship between bunch length and gap voltage can be easily evaluated according to above equation by the assumption of operating parameters described in Table 1. The Half-Touschek lifetime can be expressed as: 1 π r e cnf( ς) =, ' 3 1. 5 τ σ xγ ε accpt 8π σ xσ yσ L where σ x, σ y, σ L are the bunch size in x, y, and z dimension, r e is the classical electron radius, N is the ' number of electrons per bunch and ς = [ ε accpt / γσ x ]. The calculated Touschek lifetime by ZAP [7] for various operating gap voltages and dynamic aperture is shown in Fig. 6. From this graphs, we could find the beam lifetime will saturate around the 1.6 MV. It is an indication of a competition factor between the bunch shorting and the energy acceptance of the ring. The target operation gap voltage for TLS storage ring will be doubled from 0.8 MV, currently, to 1.6 MV for SRF cavity. Half Touschek Lifetime (Hrs.) 8 7 6 5 4 3 DA 0mm DA 18mm DA 15mm DA 1mm 1 0 1 3 4 5 Gap Voltahge (MV) Figure 6. Half Touschek Lifetime as function of gap voltage for various dynamic apertures.

5 SRF SYSTEM From several aspects, doubling the stored beam current, reducing couple-bunch-instability, increasing the lifetime, and compact in size, SRF cavity provides all the needs for synchrotron facility. The installation of SRF cavity will be one of the major renovations of TLS in the next decade. It will be also the first installation of SRF cavity in a dedicated synchrotron light source facility around the world. The dramatic reduction of the Q-value and shunt impedance of higher-order-mode in SRF cavity due to the large opening of beam tube will help increasing the threshold current [8]. A comparison of operation parameters for Doris cavity and CESR s SRF cavity at TLS is shown in Table 3. The CESR s Nb cavity and cryostat is shown in Fig. 7. The round beam tube can couple most of the HOM out of the cavity. The flute-type beam tube will couple two deflecting modes (TM 110 and TE 111 ) from the SRF cavity [9]. A rectangular waveguide is connected to the round beam tube to sever as the input coupler. Two ferrite-tiles HOM absorbers are located at the upstream and downstream of the Nb cavity at room temperature. Superconducting Nb cavity is then bath in a 4.5 K LHe vessel. The LHe vessel is insulated by vacuum, LN jacket and multi-layers insulation. The earth magnetic field, 500 mg, is shield by mu-metal and cryoperm layer, hence the residual magnetic field at the equator of the Nb cavity can be guaranteed to less than 0 mg to reduce the residual resistance and cryogenic loss. 6 NUMERICAL SIMULATION OF CESR S CAVITY A commercial 3-D High-Frequency Structure- Simulator (HFSS) [10] is used to simulate characteristics of the RF components. The TM 010 resonance frequency, external Q, coupling coefficient β, HOMs, and the power handling capability of ceramic window were simulated and calculated by the program. These parameters are the key factors that influence the operation of RF system and photon stability. The full structure of CESR s cavity without input RF coupling slot has been simulated in order to find out the resonance frequency and shunt impedance of HOMs. Figure 8 shows the E-field intensity of typical higherorder mode with and without the ferrite absorber. The 3-D model of matching rods, step changed waveguide and ceramic window was constructed to evaluate the matching condition of RF window section. The relative dielectric constant was found to be 9.6 with minimum reflection coefficient. Table 3. The comparison of operating parameters for the Doris cavities and SRF cavity. Parameter Doris cavity SRF cavity Beam Energy (GeV) 1.5 1.5 RF Frequency (MHz) 499.666 499.666 Beam Current (ma) 00 500 Bunch Length (mm) 9. 6.5 Energy Loss (kev/turn) 18 18 (168) RF Gap voltage (kv) 800 1600 Number of Cavities 1 Number of klystrons 1 Wall Dissip. (W/cavity) 7.5k <30 Beam Power (kw) 5.6 64 (84) Klystron P out (kw/kly.) 60 60 (100) R s/q 0 77.441 44.5 Synchro. Freq. (khz) 6.5 37.8 Energy Acceptance ± 1.4% ±.1% RF Transmission Line EIA6 1/8 WR1800 Tuning Angle Offset 0 o 0 0 > ψ offset >-10 o Figure 7. The engineering drawing of TLS SRF cavity, RF input line and cryostat

A sinusoid profile taper has been designed to provide a smooth transition between the cross section of RF window and the double elbow to reduce reflection coefficient. The cavity structure with input coupling section has been modeled to optimize the dimension of coupling tongue in order to find the proper coupling coefficient. Figure 8. the HOMs with and without ferrite absorbers 7 THE CRYOGENIC SYSTEM There is a maximum 50 Ws heater inside the LHe vessel of cryostat in order to maintain the operation pressure and keep the cryogenic load constant as the beam current changed. Vacuum vessel, LN insulation and multi-layers insulator have been used to lower the static heat loss of cryostat and distribution box. Table 4. The estimated cryogenic budget for the transmission loss, the static and dynamic loss of cryostat. Cryostat *(80 W+0.18 g/s) Distribution Box 10 W Multi-Channel Line (5 m) 15 W Flexible Transfer Line 30 W Dewar 30 W (heater) Junctions, Valves and Misc. 40 W Total 85 W+0.36 g/s Two 100 m 3 and 50 psig gas helium tank will be installed nearby the compressors area. A 000 liters liquid helium dewar is used to provide at least two times refill of LHe vessel in cryostat. The detail heat loss budget is listed in Table 4. The total heat loss plus operation margin is the capacity of desired refrigerator. It is expected to have 435 W of refrigeration capacity with LN pre-cooling. Screw compressor and turbine type expander are the expected combination of cryogenic system for the reliability and easy maintenance. The turbine expander and dewar will be allocated nearby the cryostat in order to reduce the multi-channel line s heat loss. For the first phase, the cryogenic system will provide adequate cooling capacity for the 500MHz SRF cryostat and the superconducting-multipoles-wiggler. An SC harmonic cavity is another long-term plan to increase the beam lifetime at TLS. Additional refrigerator and screw compressor should be easy to installed with current configuration to accommodate the cryogenic loss from the harmonic cavity. 8 SUMMARY Two SRF modules and on cryogenic system were contracted to ACCEL and AIR LIQUIDE, respectively. One of two Nb cavities has competed the vertical test with satisfactory results [11]. Two RF windows have finished with high power RF processing with maximum temperature gradient less than 40 o C at 0 kw. Cryostats are in final assembly phase and will be tested with copper cavity insert by LN. The detail design review of cryogenic system is scheduled on October 001. The scheduled commission period is the fourth quarter of 00 and will be extended to the first quarter of 003. 9 ACKNOWLEDGE The authors would like to thank staff members of Beam Line Division, Instrument Development Division and Light Source Division for the valuable discussion, and suggestion at TLS. The authors are especially appreciated for the staffs, H. Padamsee, S. Belomestnykh, J. Knobloch. R.L. Geng, J. Sears, P. Quigley, J. Reilly, R. Ehrlich and M. Tigner at LNS laboratory, Cornell University, in setting up the testing system and constant guidance during our stay. The appreciation also extends to Dr. M. Pekeler at ACCEL for his dedication to this project. The HFSS simulation program is supported by National Center for High-performance Computing (NCHC) in Taiwan. 10 REFERENCE [1] Y.C. Liu, et al., PAC 97, p.847-849, Vancouver, Canada. [] G.H. Luo, et al., EPAC 98, p.605-607, Stockholm, Sweden. [3] H.M. Cheng, et al., PAC 99, p.1150-115, New York, USA. [4] Ch. Wang, et al., PAC 97, p.1638-1640, Vancouver, Canada. [5] M.H. Wang, et al., PAC 99, p.837-839, New York, USA. [6] R.H. Helm, et al., Evaluation of Synchrotron Radiation Integrals, IEEE Trans. Nucl. Sci 0, p900 (1973). [7] M.Zisman, et al., ZAP User s Manual, LBL-170 [8] G. Flynn, A Comparison of the SLAC PEP-II and Cornell CESR-B Cavities for Use in the SRRC, unpublished report. [9] S. Belomestnykh, et al., Cutoff Frequencies of Several SRF and CESR Beam Pipe, Report 9510-18, Cornell, LNS, Ithaca, NY. [10] HFSS, by Ansoft Corp., Pittsburgh, 1999 [11] G.H. Luo, et al., SSILS001, to be published.