8. Project Time Management



Similar documents
Project Time Management

Project Time Management

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects

Chapter 2: Project Time Management

Scheduling Glossary Activity. A component of work performed during the course of a project.

Project Time Management

PROJECT TIME MANAGEMENT

PROJECT TIME MANAGEMENT. 1 Powered by POeT Solvers Limited

Project Time Management

Project Planning and Scheduling

Chapter 6: Project Time Management

Scheduling. Anne Banks Pidduck Adapted from John Musser

Chapter 4: Project Time Management

Time Management. Part 5 Schedule Development. Richard Boser

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza

Project Management Glossary

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

Goals of the Unit. spm adolfo villafiorita - introduction to software project management

Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014

Learning Objectives. Learning Objectives (continued) Importance of Project Schedules

Lecture 6: Project Time Management By: Prof. Lili Saghafi. Information Technology Project Management, Fifth Edition

Operational Research. Project Menagement Method by CPM/ PERT

ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS

Collaborative Scheduling using the CPM Method

Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration

Chapter 6. (PMBOK Guide)

ME 407 Mechanical Engineering Design Spring 2016

SWEN 256 Software Process & Project Management

Define Activities Sequence Activities Estimate Activity Resources Estimate Activity Durations Develop Schedule Control Schedule

CPM-200: Principles of Schedule Management

The Plan s Journey From Scope to WBS to Schedule

Unit 4: Time Management (PMBOK Guide, Chapter 6)

Systems Analysis and Design

MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc.

The work breakdown structure can be illustrated in a block diagram:

Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

Cambridge International AS and A Level Computer Science

MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc.

Precedence Diagram Method. CSTM 462 Planning & Scheduling

CRITICAL PATH METHOD (CPM) SCHEDULES

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761

Project Management SCM Pearson Education, Inc. publishing as Prentice Hall

MECH 896 Professional Development for MEng Students. Homework Discussion. Scheduling Overview. Winter 2015: Lecture #5 Project Time Management

The Project Planning Process Group

Introduction to Project Management

Project Scheduling & Tracking

Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose

Scheduling Resources and Costs

Module 3: The Project Planning Stage

CSC 443: IT Project Management Midterm 1 exam - Spring semester March 21 st, 2012

Chapter 6 (part 1) Project Time Management. (Project Scheduling)

B D E F

Project Time Management

Network Calculations

Introduction to Project Management

專 案 管 理 實 務 嘉 義 縣 政 府 學 分 班 : 管 理 實 務 專 題 2006 中 正 大 學 企 管 系 助 理 教 授 周 瑞 生

SE351a: Software Project & Process Management

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza

Dashboards and Reporting for Program Management

CISC 322 Software Architecture. Project Scheduling (PERT/CPM) Ahmed E. Hassan

Chapter-6. Developing a Project Plan

CRITICAL PATH METHOD (CEE 320 VDC SEMINAR)

Time Management. Herb Pollard III

Object-Oriented Analysis. with the Unified Process. John W. Satzinger Southwest Missouri State University. Robert B. Jackson Brigham Young University

Project Management Chapter 3

Project Scheduling and Gantt Charts

SYSTEMS ANALYSIS AND DESIGN DO NOT COPY

Project Management Institute (PMBOK 2000) PMP Preparation Worksheet

CPM -100: Principles of Project Management

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time

Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi

Project Management Dr. James A. Bednar

PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM)

Project Planning. Lecture Objectives. Basic Reasons for Planning. Planning. Project Planning and Control System. Planning Steps

WORK PROGRAM GUIDELINES

Basic CPM Calculations

Module 11. Software Project Planning. Version 2 CSE IIT, Kharagpur

TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain *

Chapter 11 Monte Carlo Simulation

Chapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False

PMP : Project Management Professional Study Guide Kim Heldman

PROGRAM EVALUATION AND REVIEW TECHNIQUE (PERT)

Unit 1: Project Planning and Scheduling

Project Time Management

10 Project Management with PERT/CPM

PERT/CPM. Network Representation:

Use project management tools

Should I Resource Load My Schedule?

Project Time Management Activity Definition Activity Sequencing Duration Estimating Schedule Development Schedule Control

Notes on the Critical Path Method for project planning and management.

Project Scheduling: PERT/CPM

Basic Concepts. Project Scheduling and Tracking. Why are Projects Late? Relationship between People and Effort

12 Network Scheduling Techniques

CIS Project Management

Project management Project Management

Project Scheduling: PERT/CPM

Project Management. ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann. Riko Wichmann, MPY Zeus Student Seminar - PM,

Transcription:

8. Project Time Management Project Time Management closely coordinated Two basic approaches -bottom-up (analytical) -top-down (expert judgement) Processes required to ensure timely completion of the project Work packages are decomposed into schedule activities PTM Processes 1. Define Activities what are activities to produce deliverables 2. Sequence Activities what are dependencies among activities 3. Estimate Activity Resources what and how many resources needs each activity work packages are decomposed into schedule activities such that the project objectives will be met. List (not hierarchy) of activities 4. Estimate Activity Durations how many work period needs each activity 5. Develop Schedule analysing activities, resources and constraints to create the project schedule 6. Control Schedule controlling changes to the project schedule Approved schedule is is a time baseline. Without realistic dates, project is unlikely to be finished as scheduled - Control account for planning future work without associated work packages. Management control point. - Planning package for planning future known work without detailed schedule activities. - Work package the lowest WBS level. - Schedule activities the lowest planning level Not the deliverable rather work todo.

Project Time Management cd. 1 Sequence Activities Dependencies: identifying and documenting logical dependencies among activities. Support the latter development of a realistic schedule Mandatory physical limitations, hard logic, prototypes needed; inherent in nature of work being done Discretionary defined by pm team; best practices or unusual aspects of project soft logic, External relationship between project activities and non-project activities (company policies, procurement, etc.) - Project Management software often used - 2 methods to construct the diagram: PDM - Precedence Diagramming M. ADM - Arrow Diagramming M. PDM more popular But needs 4 types of dependencies ADM - simpler but may need dummy activities Begin Begin FINISH-START The most common e.g. Installation-tests START-START e.g. concrete deliverypouring fundamentals FINISH-FINISH e.g. final works -cleaning START-FINISH (the rarest overlapping ) e.g. disassembly of scaffolding - elevation End End What are arrows? What are nodes?

Project Time Management cd. 2 Develop Schedule Program Evaluation and Review Technique (PERT)- Determining start and finish dates for project activities. Often iterates as more information are available Two categories of time constraints: - imposed dates on activities starts/finishes e.g. Start/Finish No Later Than... (contract, restrictions) - key events/milestones for completing deliverables by specified date (initially requested+expected may be interfaces with work outside the project) Some of the Develop Schedule Techniques uses weighted average duration to calculate project duration differs from CPM by using mean (expected value) instead of most-likely estimate in CPM Schedule Network Analysis generates the schedule with different methods calculates early/late start/finish dates / eliminates loops and open ends. Critical Path Method (CPM) single early/late start and finish date for all activities. based on specified, sequential network and single duration estimate. calculates float to determine flexibility and shows critical path. Schedule Compression look to shorten the schedule without affecting scope crashing cost and schedule trade-offs to determine greatest amount of compression for least incremental cost often results in higher costs fast tracking performing activities in parallel that normally would be sequenced often results in re-work and usually increases risk

Project Time Management cd. 3 Brief introduction to CPM/time Critical Path Method Two important definitions: Float: the amount of time an activity can be delayed without delaying the entire project. Calculated by the difference between Early and Late Start/Finish. Critical path is the longest path, the duration of the project and identifies activities without float (critical activities) that need monitoring Algorithm: how to draw the network diagram (PDM) 1. Not too long list of activities (max 10-15) 2. Every activity is to be described like this (indicating ES/EF early start/finish and LS/LF late start/finish) 3. Every activity in the list needs duration, predecessors and dependency 4. Draw the network 5. Two passes - forward and backward Forward: put earliest start and finish dates on forks put MAXIMAL dates of coming Final earliest finish = final latest finish Backward: put latest finish and start dates on forks put MINIMAL dates of returning Calculate float for every activity (LS-ES or LF - EF) Remember: only 1 start, only 1 finish of the network ES duration EF Activity name LS float LF

Project Time Management cd. 4 Brief introduction to PERT (Program Evaluation and Review Technique) The whole difference to CPM results from other treatment of the estimation of each activity duration, which is considered as random variable with known distribution (beta), defined by three estimates: o optimistic, m most probable, p - pessimistic. Thus for each activity we calculate Duration (expected value) Standard Deviation: Variance (how unsure we are with duration): μ = σ = 2 σ o + 4 m + p 6 p o 6 2 p o 6 = μ project = μ critical σ project = σ ( critical 2 ) μ ± 1σ μ ± 2σ μ ± 3σ 68,26% activity duration estimates 95,45%... 99,73%... You can draw the network like in CPM using expected value, but knowing more on the whole project, incl. some risk estimations

Project Time Management cd. 5 Control Schedule Determining the current status of the project schedule Influencing factors which create schedule changes Determining that schedule has changed Different forms of schedule have different purposes Schedule Updates Revisions change schedule baseline a.k.a. rebaselining Important issue to network diagram: Projects can have more than 1 critical path (increased risk) and can involve dummy tasks DIFFERENT FORMATS OF PROJECT SCHEDULE ALWAYS: CALENDARS BASED data date = as-of date = time now date BAR CHART (summary or detailed with dependencies) MILESTONE CHART NETWORK DIAGRAM (time-scaled)