Software Project Management

Similar documents
Scheduling Glossary Activity. A component of work performed during the course of a project.

Project Time Management

Chapter 2: Project Time Management

Collaborative Scheduling using the CPM Method

MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc.

Project Planning and Scheduling

MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc.

Frequently Asked Questions in Project Management

CSC 443: IT Project Management Midterm 1 exam - Spring semester March 21 st, 2012

Project Management Glossary

Scheduling. Anne Banks Pidduck Adapted from John Musser

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects

Project Time Management

Systems Analysis and Design

SE351a: Software Project & Process Management

Time Management. Part 5 Schedule Development. Richard Boser

Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

Precedence Diagram Method. CSTM 462 Planning & Scheduling

Module 3: The Project Planning Stage

Metadata-Based Project Management System. A Case Study at M-Files Corporation. Iulia Adomnita

Dashboards and Reporting for Program Management

Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

Network Calculations

Project Scheduling & Tracking

8. Project Time Management

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761

Chapter 4: Project Time Management

Goals of the Unit. spm adolfo villafiorita - introduction to software project management

CRITICAL PATH METHOD (CPM) SCHEDULES

Chapter 3 Managing the Information Systems (IS) Project

Operational Research. Project Menagement Method by CPM/ PERT

TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain *

SWEN 256 Software Process & Project Management

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza

ME 407 Mechanical Engineering Design Spring 2016

The Plan s Journey From Scope to WBS to Schedule

CSSE 372 Software Project Management: Software Project Scheduling

Software Project Management. Software Engineering SW Project Management Slide 1

Chapter-6. Developing a Project Plan

CISC 322 Software Architecture. Project Scheduling (PERT/CPM) Ahmed E. Hassan

Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014

Chapter 6. (PMBOK Guide)

added to the task, using Project, it will automatically calculate the schedule each time a new resource is added.

pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072

The work breakdown structure can be illustrated in a block diagram:

Planning of Project Work (IS PM 6. Lecture, 2011 Spring)

Project Time Management

Module 11. Software Project Planning. Version 2 CSE IIT, Kharagpur

CRITICAL PATH METHOD (CEE 320 VDC SEMINAR)

Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration

Pearson Education Limited 2003

Scheduling Resources and Costs

Cambridge International AS and A Level Computer Science

Develop Project Charter. Develop Project Management Plan

02 Project planning. There are two approaches to identifying the components of a project: productbased and work- or activity-based.

MECH 896 Professional Development for MEng Students. Homework Discussion. Scheduling Overview. Winter 2015: Lecture #5 Project Time Management

Chapter 6: Project Time Management

Project Scheduling and Gantt Charts

WORK PROGRAM GUIDELINES

Project management. Objectives. Topics covered. Organizing, planning and scheduling software projects DISCUSSION

(Refer Slide Time: 01:52)

ICT Project Management. Software Project Planning By J. Ogutu

Systems Analysis and Design in a Changing World, Fifth Edition

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa

Project Time Management

SOFTWARE PROJECT MANAGEMENT

Chapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False

Introduction to Project Management. What is the Project Management Life Cycle? Common Life Cycle Characteristics

Problems, Methods and Tools of Advanced Constrained Scheduling

Software Application: Information System Elements. Project Management in Information Technology (IT) Projects. Project Scheduling basics

OPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT)

Define Activities Sequence Activities Estimate Activity Resources Estimate Activity Durations Develop Schedule Control Schedule

MICROSOFT OFFICE PROJECT - SYLLABUS

PROJECT TIME MANAGEMENT

Topics. Project plan development. The theme. Planning documents. Sections in a typical project plan. Maciaszek, Liong - PSE Chapter 4

Project Time Management

Project Management Guidebook

The 10 Knowledge Areas & ITTOs

ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS

Project Management Dr. James A. Bednar

PROJECT TIME MANAGEMENT. 1 Powered by POeT Solvers Limited

Project Management (CS 3730) Lecture 4 Name:

Introduction to Software Engineering. 9. Project Management

The Project Planning Process Group

Project Management. Lecture 3. Software Engineering CUGS. Spring 2012 (slides made by David Broman) Kristian Sandahl

Introduction and Overview

PMI Lexicon of Project Management Terms

Demonstrate and apply knowledge of project management in

Project Management Concepts and Strategies

Basic CPM Calculations

Critical Path Analysis & PERT Charts (taken from

PMP Exam Preparation Answer Key

Software Engineering. Project Management. Based on Software Engineering, 7 th Edition by Ian Sommerville

Featured Paper Satya Narayan Dash By Satya Narayan Dash, PMP, CSM, MCP

Synergy between PMBOK and MS Project 2007 A Schedule Management Perspective

Should I Resource Load My Schedule?

Redesigned Framework and Approach for IT Project Management

Project Integration Management

Transcription:

Software Project Management Project: unique process, consisting of a set of coordinated and controlled activities with start and finish dates, undertaken to achieve an objective conforming to specific requirements, including the constraints of time, cost and resources. ISO 9000:2005 - Quality management systems - Fundamentals and vocabulary Kondorosi, K. 2008. Development of Information Systems 1

Software Project Management Phases Definition goals, players, stakeholders, resources, constraints, deliverables, success-criteria Planning work-breakdown-structure, work-packages, activities, package/activity relations, resource planning, scheduling Execution monitoring, evaluation, correcting actions, communication Closing closing declaration, evaluation Kondorosi, K. 2008. Development of Information Systems 2

Definition phase Fundamental goals (correspondence to organization s goals, commitment, top-management support) Outcomes ( deliverables ) Players participants, stakeholders, project organization structure Success-criteria Resource estimation Timing, scheduling Cost estimation Kondorosi, K. 2008. Development of Information Systems 3

Planning phase Work Breakdown Structure (well-defined activities, responsibilities, milestones) Pert Chart (logical activity structure, dependencies, overlapping) Gantt Chart (timing, SS, FS, FF dependencies) Critical Path (slack-times, ASAP, ALAP scheduling) Resource Planning (human, tangible, tools, cost, cashflow) Risk Analysis (risk-yield techniques) Kondorosi, K. 2008. Development of Information Systems 4

Planning phase Work Breakdown Structure The development of a WBS divides the overall project into an interconnected set of manageable components. Typically, the WBS is a product oriented structure that provides a scheme for identifying and organizing the logical units of work to be managed, which are called work packages. Kondorosi, K. 2008. Development of Information Systems 5

Planning phase Pert chart The Program Evaluation and Review Technique (PERT) is a network model that allows for randomness in activity completion times. Kondorosi, K. 2008. Development of Information Systems 6

Pert chart Kondorosi, K. 2008. Development of Information Systems 7

Planning phase PERT planning involves the following steps: 1. Identify the specific activities and milestones. 2. Determine the proper sequence of the activities. 3. Construct a network diagram. 4. Estimate the time required for each activity. 5. Determine the critical path. 6. Update the PERT chart as the project progresses. Kondorosi, K. 2008. Development of Information Systems 8

Planning phase Dependencies A B Finish to start (FS) B can start only if A ended A B Start to start (SS) B can start only if A started A B Finish to finish (FF) B can finish only if A finished A B Start to finish (SF) B can finish only if A started Kondorosi, K. 2008. Development of Information Systems 9

Planning phase Determine the following quantities for each activity: ES - Earliest Start time EF - Earliest Finish time LS - Latest Start time LF - Latest Finish time D Duration (F - Float) Kondorosi, K. 2008. Development of Information Systems 10

Planning phase Critical Path: the longest possible continuous pathway taken from the initial event to the terminal event. It determines the total calendar time required for the project; and, therefore, any time delays along the critical path will delay the reaching of the terminal event by at least the same amount. Critical Activity: An activity that has total float equal to zero. Activity with zero float does not mean it is on critical path. Kondorosi, K. 2008. Development of Information Systems 11

Planning phase Work Breakdown Structure (well-defined activities, responsibilities, milestones) Pert Chart (logical activity structure, dependencies, overlapping) Gantt Chart (timing, SS, FS, FF dependencies) Critical Path (slack-times, ASAP, ALAP scheduling) Resource Planning (human, tangible, tools, cost, cashflow) Risk Analysis (risk-yield techniques) Kondorosi, K. 2008. Development of Information Systems 12

Kondorosi, K. 2008. Development of Information Systems 13

Planning phase Work Breakdown Structure (well-defined activities, responsibilities, milestones) Pert Chart (logical activity structure, dependencies, overlapping) Gantt Chart (timing, SS, FS, FF dependencies) Critical Path (slack-times) Resource Planning (human, tangible, tools, cost, cashflow) Risk Analysis (risk-yield techniques) Kondorosi, K. 2008. Development of Information Systems 14

Planning phase - Resource Planning 1. 2. 3. 4. Resources Over allocation Availability Time Kondorosi, K. 2008. Development of Information Systems 15

Planning phase - Resource Planning 1. 2. 3. 4. Resources Availability Time Kondorosi, K. 2008. Development of Information Systems 16

Planning phase Work Breakdown Structure (well-defined activities, responsibilities, milestones) Pert Chart (logical activity structure, dependencies, overlapping) Gantt Chart (timing, SS, FS, FF dependencies) Critical Path (slack-times) Resource Planning (human, tangible, tools, cost, cashflow) Risk Analysis (risk-yield techniques) Kondorosi, K. 2008. Development of Information Systems 17

Risk Management Categories Risk is measured in terms of impact and likelihood I. prepare alternative solutions II. prevention techniques III. negligible Monitoring in execution phase Impact High Medium Low Category I. Category II. Category III. High Medium Low Likelihood of occurrence Kondorosi, K. 2008. Development of Information Systems 18

Execution phase monitoring (how to measure progress, data acquisition, evaluation, plan-fact comparison) difference-analysis (reasoning, impact prediction) intervention modification of plan communication to stakeholders Kondorosi, K. 2008. Development of Information Systems 19

Execution phase Project monitoring, controlling: Progress is primarily determined by comparing actual work product and task attributes, effort, cost, and schedule to the plan at prescribed milestones or control levels within the project schedule or work breakdown structure (WBS) (CMMI) Kondorosi, K. 2008. Development of Information Systems 20

Closing phase Evaluation: measuring and evaluation success factors Summarizing experiences (most efficient way to learn: analyze your mistakes) Declaration: Project is closed Final conclusion: Success/Miss Kondorosi, K. 2008. Development of Information Systems 21

Managing OO development Inception Elaboration Construction Transition User use-cases High level package structure not constant intensity Developer use-cases, communication diagrams Class diagrams Coding modules, integration System integration and test Kondorosi, K. 2008. Development of Information Systems 22

OO development lifecycle Incremental controlled iteration I E C T round 1 I E C T round 2 round 3 I E C T Kondorosi, K. 2008. Development of Information Systems 23

Problems Project Plan requires some progress in analysis Where is project planning in the lifecycle< Anywhere at the beginning of the first I phase Costs not more, than 5 10 % of the total budget How to estimate? What organizational structure is efficient? How to manage the phases and phasetransitions? Kondorosi, K. 2008. Development of Information Systems 24

Estimation Imprecise (25% tolerance), but enough for go/no go decision make this decision as soon as possible at minimal cost (disappointing to spend 30 % of the budget to decide go/no go) Necessary estimations Size: line of code, function-point, n. of modules, n. of classes Workload: manmonth Duration: month Efficiency: size / workload Cost: qualification-dependent human resources Kondorosi, K. 2008. Development of Information Systems 25

Estimation (cont) Factors: language, toolset, reuse, skills, previous experiences... Sources: Our earlier experiences Experts Based on: system analogy package analogy Parametric model COCOMO (Constructive Cost Model) family: routine task direct data early design architecture-based data Kondorosi, K. 2008. Development of Information Systems 26

Organizational structure Example Project-leader Quality-assurance Chief system-architect Domain expert Customer-representative Chief developer Toolsmith Development manager Tester team Package 1 team Package 2 team Package n team Kondorosi, K. 2008. Development of Information Systems 27

Phases, phase-transitions Inception - Elaboration transition Requirement inspection Elaboration Construction transition Architectural plan inspection Construction Transition Operational test End of transition System test and delivery Kondorosi, K. 2008. Development of Information Systems 28

Hints for project managers For the sake of success Take care of the team Stay focused, keep the project in moving Refuse late good ideas I: accept ideas, define priority for them E: take into consideration, analyze impact C: only critical problems T: too late, refuse, delay to next round Kondorosi, K. 2008. Development of Information Systems 29

Project statistics 1998 28,0% 46,0% 26,0% 1996 40,0% 33,0% 27,0% Failed Problematic Success Smaller (less complex) Shorter periods Less people to manage 1994 31,0% 52,7% 16,2% 0% 20% 40% 60% 80% 100% (Standish Group) Kondorosi, K. 2008. Development of Information Systems 30

Success factors Involving user 20% Top manager (CEO) support 15 % Clear business goals 15 % Experienced project management 15 % Small milestones 10 % Clear requirements 5 % Talented programmers 5 % Leadership 5 % Others 5 % Kondorosi, K. 2008. Development of Information Systems 31

Fail factors Incomplete requirement 13.1% Lack of user involvment 12.4% Shortage in resources 10.6% Too ambitious goals 9.9% Lack of CEO support 9.3% Changing requirements 8.7% Lack of design 8.1% Lapse of interest 7.5% Lack of IT management 6.2% Incompetence in technologie 4.3% Others 9.9% Kondorosi, K. 2008. Development of Information Systems 32