Improve Net Present Value using cash flow weight



Similar documents
Project Scheduling to Maximize Fuzzy Net Present Value

Abstract Title: Planned Preemption for Flexible Resource Constrained Project Scheduling

( ) ( )( ) ( ) 2 ( ) 3. n n = = =

A SIMULATION MODEL FOR RESOURCE CONSTRAINED SCHEDULING OF MULTIPLE PROJECTS

MAXIMIZING THE NET PRESENT VALUE OF A PROJECT UNDER INFLATIONARY CONDITIONS

Clustering and scheduling maintenance tasks over time

Resource-constrained Scheduling of a Real Project from the Construction Industry: A Comparison of Software Packages for Project Management

Performing Net Present Value (NPV) Calculations

Resources Management

Criticality of Schedule Constraints Classification and Identification Qui T. Nguyen 1 and David K. H. Chua 2

e C P M : P o r t f o l i o M a n a g e m e n t f o r P r i m a v e r a P 6 W e b A c c e s s

NPV Versus IRR. W.L. Silber We know that if the cost of capital is 18 percent we reject the project because the NPV

Pricing complex options using a simple Monte Carlo Simulation

An Optimal Project Scheduling Model with Lump-Sum Payment

CRASHING-RISK-MODELING SOFTWARE (CRMS)

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects

5. Creating a Gantt Chart

Net Present Value (NPV)

Bank: The bank's deposit pays 8 % per year with annual compounding. Bond: The price of the bond is $75. You will receive $100 five years later.

Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi

A. O. Odior Department of Production Engineering University of Benin, Edo State.

Project Cost Management

A Computer Application for Scheduling in MS Project

Linear Programming Notes V Problem Transformations

Project Management Chapter 3

Scheduling Glossary Activity. A component of work performed during the course of a project.

Investment Appraisal

PROJECT PROPOSAL: PROJECT BLUE ZUMA

Methodical Notes for part-time BMCF TM study course M_SM / PROJECT MANAGEMENT

Leaving Certificate Technology. Project Management. Teacher Notes

An Investigation on the Impact of Laddering Technique in Project plan: a Case of Road Construction

A genetic algorithm for resource allocation in construction projects

Project Scheduling: PERT/CPM

CHAPTER 14 COST OF CAPITAL

Application of Critical Path Method scheduling to research plan and management of graduate students research project in engineering education

The Project Scheduling and Decision Mechanism Based on the Multi-Resource Leveling

STRATEGIC CAPACITY PLANNING USING STOCK CONTROL MODEL

PV Tutorial Using Calculator (Sharp EL-738)

Topic 3: Time Value of Money And Net Present Value

Systems Analysis and Design

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761

Resource Allocation and Scheduling

PhD Thesis Abstract Doctoral School of Business Administration

Important Factors for Success of Public Construction Projects

A Robustness Simulation Method of Project Schedule based on the Monte Carlo Method

Analysis of the critical path within a project with WinQSB software

Why Use Net Present Value? The Payback Period Method The Discounted Payback Period Method The Average Accounting Return Method The Internal Rate of

Global Financial Management

Which projects should the corporation undertake

Investment, Time, and Present Value

On The Multi-Mode, Multi-Skill Resource Constrained Project Scheduling Problem A Software Application

CLIENT-CONTRACTOR BARGAINING ON NET PRESENT VALUE IN PROJECT SCHEDULING WITH LIMITED RESOURCES

Multi Objective Project Scheduling Under Resource Constraints Using Algorithm of Firefly

8. Project Time Management

COMBINING THE METHODS OF FORECASTING AND DECISION-MAKING TO OPTIMISE THE FINANCIAL PERFORMANCE OF SMALL ENTERPRISES

Resource grouping selection to minimize the maximum over capacity planning

Chapter 31. Financial Management in Not-for-Profit Businesses

Finite Capacity Portfolio and Pipeline Management

Programmes. Unit 3: P lanning construction work processes and efficient use of resources in construction and the built environment.

Module 11. Software Project Planning. Version 2 CSE IIT, Kharagpur

IMCPM04 Project Scheduling and Cost Control. Course Outline

Automated Scheduling Methods. Advanced Planning and Scheduling Techniques

Winkler, D. T. "The Cost of Trade Credit: A Net Present Value Perspective." Journal of Business and Economic Studies, vol. 3, no. 1, 1996, pp

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072

6.231 Dynamic Programming Midterm, Fall Instructions

Quality Financial Analysis of Para-Rubber on Google-Maps Prototype System

Scheduling Resources and Costs

Resource Planning and Scheduling. CSTM 462 Resource Loading Fall 2012

1 The Black-Scholes Formula

CHAPTER 4 DISCOUNTED CASH FLOW VALUATION

Time Error in Project Management: A Case Study in Yanbu, Saudi Arabia

1. What are the three types of business organizations? Define them

Pearson Education Limited 2003

hp calculators HP 12C Internal Rate of Return Cash flow and IRR calculations Cash flow diagrams The HP12C cash flow approach

NETWORK ANALYSIS OF A TOLLING PROJECT

Chapter 3 Managing the Information Systems (IS) Project

Project Scheduling: PERT/CPM

ICT Project Management. Software Project Planning By J. Ogutu

18 CAPITAL INVESTMENT

Capital Budgeting OVERVIEW

Effective Project Management FIFTH EDITION

Chapter 2: Project Time Management

Problems, Methods and Tools of Advanced Constrained Scheduling

Multi-Project Management using Critical Chain Project Management (CCPM) The Power of Creative Engineering

Application Survey Paper

Capital Budgeting Techniques: Certainty and Risk

Lecture 3: Growth with Overlapping Generations (Acemoglu 2009, Chapter 9, adapted from Zilibotti)

Student Project Allocation Using Integer Programming

MBA (3rd Sem) MBA/29/FM-302/T/ODD/13-14

HYBRID GENETIC ALGORITHM PARAMETER EFFECTS FOR OPTIMIZATION OF CONSTRUCTION RESOURCE ALLOCATION PROBLEM. Jin-Lee KIM 1, M. ASCE

EXAM EXEMPLAR QUESTIONS

An Entropic Order Quantity (EnOQ) Model. with Post Deterioration Cash Discounts

Construction Planning, Equipment and Methods ENGI 8749 Fall Semester, 2008 Tutorial #2 Resource Leveling using MS Project

A firm s credit policy is composed of: Terms of the sale Credit analysis Collection policy

Software Project Planning and Resource Allocation Using Ant Colony Optimization with Uncertainty Handling

PAYBACK PERIOD. Calculated as: Payback Period = Cost of Project / Annual Cash Inflows

Transcription:

2011 2 nd International Conference on Construction and Project Management IPEDR vol.15 (2011) (2011) IACSIT Press, Singapore Improve Net Present Value using cash flow weight Vacharee Tantisuvanichkul 1 and Moray Kidd 1 1 School of Mechanical, Aerospace and Civil engineering The University of Manchester Abstract. The problem of scheduling project with resource constrained to maximise their Net Present Value (NPV) is studied in this paper. The performance of Cash Flow Weight (CFW) scheduling heuristics is evaluated. This heuristics procedure has been used to improve the NPV of the project activity. Despite their inherent simplicity, this approach performs well at improving project NPV in some certain cash flow patterns. Subsequent application of the shifting also performs well to improved activities assignment and help to increase project NPV over the initial solution obtained. Keywords: Cash flow weight, net, present value, project scheduling, shifting procedure 1. Introduction Project scheduling is the process where the various activities that need to be undertaken during a projects lifetime should be scheduled. It is concerned with the techniques that can be employed to manage the activities that need to be undertaken during the development of a project. It is primarily concerned with attaching a timescale and sequence to the activities to be conducted within the project. This paper will focus on project scheduling that is the subset of project management. Project scheduling is the process where the various activities that need to be undertaken during a projects lifetime should be scheduled. 2. Literature Review While majority of the past research has focused on minimizing project completion time, the primary goal of undertaking any commercial project is its potential profitability. The most pragmatic project objective is, therefore, to maximize project NPV [1]. Scheduling problem can be distinguished into two categories; the unconstrained project scheduling problem, which occurs when no constraints on resource usage are imposed such that the activities are only subject to precedence constraints, and the resource-constrained project scheduling problem (RCPSP). A.H. Russell [2] was the First to introduce the objective of maximizing the NPV of cash flows in a network. Russell deals with the unconstrained problem where both positive and negative payments occur as events in the project are completed. Russell's objective function is to maximize NPV = (1) where exp(αti) = β, the discount factor. CF = Cash Flow For uniformity of expression, the criterion Eq. (1) is sometimes rewritten as: maximize NPV = (2) 3. Research Methodology 98

The experiment was carried out to test the techniques in the set of problems. These problems consist of projects with up to 10 activities each, with at least one critical path per problem. Then the shifting procedure was used as the improvement method to enhance the NPV in each problem. The cash flow weight heuristic procedure (CFW) and the shifting improvement techniques were used in this paper. After that the results will be measured using percentage difference formula. This was done to access efficiency of each scheduling technique under different problems and cash flow patterns. 3.1. The cash flow weight heuristic procedure (CFW) The cash flow weight (CFW) is one of the heuristic procedures. They are easy to implement, intuitively based and show significant different in performance [3]. This approach is operated by selecting a high priority activity from a list of available activities for the assignment of resource. They are formulated on the notion that higher net present value (NPV) are achieved by advancing positive cash flows as close to the start of the project as possible, while delaying negative payment as far back (to the right) as possible, while not moving any activities on the critical path and still satisfying precedence and resource constraints. This notion is called Cash flow weighing (CFW) whenever resource conflicts arise, the activity that is holding back a greater sum of cash inflows is scheduled first or receives higher priority in the assignment of resources. Step 1 Determine the cash flow weight of each activity Step 2 Add all activities without predecessors to the available lists. From the list of precedence available tasks, select the task with the highest CFW. Determine the precedence-only; early start time t of the t of the selected task. Assign the chosen task to begin at the earliest possible period, at or after its early start time, such that resource availabilities are sufficient for the duration of the task. Update resource availabilities. Add any activities to the available list that become available by virtue of their predecessors being completed. Step 3 If no more tasks are available, stop. Otherwise go to step 2 3.2. The shifting improvement The shifting improvement is applied to enhance the CFW scheduling techniques. It attempts to position the activities with the negative cash flows to the right (later periods), and position positive cash flow activities to the left (earlier periods) whenever precedence and resource constraints allow it. 4. Discussion Test problems for evaluating the CFW heuristics and the shifting improvement procedure were generated and the results are given. 4.1. Project data 4.2. Network Diagram 99

Resource availability = 5, α = 0.2, Critical path = [1]=>[2]=>[6]=>[7] 4.3. Determination of CFWs 4.4. Schedule from the project data From equation (1) ; NPV = -20 + 55exp(-2α) + 35 + (30)exp(-5α) + (-50)exp(-6α) + 40exp(-6α) 100

+ (-10)exp(-8α) = 77.598 4.5. Schedule resulting from CFW heuristic NPV = -20 + 55exp(-2α) + 35exp(-α) + 30 + (-50)exp(-6α) + 40exp(-6α) + (-10)exp(-8α) = 79.760 NPV change = 2.162 % NPV change = 3 % 4.6. Schedule after applying the shifting improvement Task 5 shifted right by one period NPV = -20 + 55exp(-2α) + 35exp(-α) + 30 + (-50)exp(-7α) + 40exp(-6α) + (-10)exp(-8α) = 80.638 NPV change = 0.878 % NPV change = 1.5 % 5. Conclusion 101

This paper presents CFW scheduling heuristic that are effective at maximizing NPV of resourceconstrained project. These approaches are managerially significant because they are simple to compute in the context of project management and intuitively based on scheduling theory. Thus, it requires less computational effort than optimization-based approach. The experiment seeks to improve the NPV of the resource-constrained problem by applying the shifting procedure as the improvement techniques. Thus, after initial schedule with heuristics procedure, the shifting procedure is employed in an attempt to improve upon the heuristic result obtained. It was found out that the use of the shifting procedure could be expected to improve the NPV of the project. As the problem we used for evaluating the heuristics procedure here in this experiment had that only one resource. It should be worthwhile to experiment the heuristics under the condition of various resources available and limitation so that the impact of different levels of resource utilization could be assessed. However, it should be taking into account that each resource has a value associated with it, representing the available amount. 6. References [1] K. K.Yang, L. C. Tay and C. C. Sum. A comparison of stochastic scheduling rules for maximizing project net present value. European Journal of Operational Research, 85 (1995), pp 327-339. [2] A. H. Russell. Cash Flows in Networks. Management Science, 16(1970), pp 357-373. [3] S. M. Baroum and J. H. Patterson J. H. The development of cash flow weight procedures for maximizing the net present value of a project, Journal of Operations Management.1996, 14(3), pp 209 27. 102