DIVISION 5 SANITARY SEWERS



Similar documents
SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.

SECTION SANITARY SEWER AND STORM DRAIN SYSTEMS

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION STORM DRAIN SYSTEMS PART 1 - GENERAL

SECTION STORM DRAINAGE SYSTEM

SANITARY SEWER SPECIFICATIONS

STANDARD SPECIFICATIONS SECTION INSTALLATION OF GRAVITY SEWER PIPELINES. 1. Trenching, Backfilling and Compacting: 02223

Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

SUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors.

SECTION SANITARY SEWER PIPE

Section SEWER PIPE INSTALLATION AND TESTING

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

CHAPTER 6 - SANITARY SEWER

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

DESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES SITE UTILITIES

Section 2100-Trenching and Tunneling

SECTION CEMENT-MORTAR LINED AND COATED STEEL PIPE

SECTION POLYVINYL CHLORIDE (PVC) PIPE

SECTION STORM DRAIN SYSTEM

DIVISION 4300 STORM DRAINAGE

CITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General

Model Specification 509 DRISCOPLEX 4200 and DRISCOPLEX 4300 Gravity Flow Sanitary Sewer

INDEX. Sec. No. Items Page Nos.

SECTION GRAVITY SANITARY SEWERS

Wastewater Capital Projects Management Standard Construction Specification

SECTION HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION

53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines:

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

San Antonio Water System Standard Specifications for Construction ITEM NO SLIP-LINING SANITARY SEWERS

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.

SECTION 21 REHABILITATION OF SANITARY SEWER MAINS BY THE PIPE BURSTING AND TRENCHLESS PIPE REPLACEMENT METHOD

SECTION 9.02 BUILDING SUBSURFACE DRAINS (PERIMETER, ETC.)

SECTION 603 SANITARY SEWER FORCE MAINS

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe

SECTION HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS

LS 2540 SEWER LATERALS AND INSPECTION TEES

SECTION STORM DRAINAGE TABLE OF CONTENTS

INSTALLATION OF INSITUFORM LINER

SECTION POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

San Antonio Water System Standard Specifications for Construction ITEM NO POINT REPAIRS AND OBSTRUCTION REMOVALS

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES

SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS

ASTM C76, Class III, Wall B, except as modified herein. Clean natural sand, ASTM C33. Artificial or manufactured sand will not be permitted.

Bethel Township Municipal Authority (BTMA) RESIDENTIAL SEWER CONNECTION MANUAL

STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY

Beacon Hill Sewer District Standard Specifications

Sewer Line Rehabilitation

SECTION PUBLIC STORM UTILITY DRAINAGE PIPING

City of Virginia Beach Public Utilities HRPDC Regional Construction Standards, 5 TH Edition Amendments May 19, 2014

Sewer Water Pipeline Replacement with CERTA LOK RESTRAINED JOINT PVC PIPE

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.

SECTION FACILITY STORM DRAINAGE PIPING

TECHNICAL SPECIFICATIONS GRAVITY AND PRESSURE SEWER LINE AND MATERIALS

SECTION 724 PIPE CULVERTS

STANDARD SPECIFICATIONS SECTION CLEANING AND LINING WATER MAINS

SECTION 5: SANITARY SEWER SYSTEM DESIGN

ARTICLE VI (ALTERNATE) STANDARD SPECIFICATIONS. for (PVC) SANITARY SEWER MAIN CONSTRUCTION

FY08 SEWER POINT REPAIRS BID TABULATION

Section 402. STORM SEWERS

SECTION IV - TESTS AND INSPECTIONS PART 1 - GENERAL Testing - General

The Manitoba Water Services Board SECTION Standard Construction Specifications September 2013 Page 1 of 21

SECTION BUILDING SEWERS. B. Connection of building sanitary drainage system to municipal sewers.

SECTION STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS

Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS

OAR52 A-1 (September, 1981)

CLEANING, INSPECTION, AND TESTING OF SEWERS

TABLE OF CONTENTS SECTION 500 SANITARY SEWER AND FORCE MAIN

Specifications for Residential Property Owners Connection to New Public Sewer

SECTION ASBESTOS CEMENT PIPE REPAIRS, DEMOLITION, AND DISPOSAL

Town House Center Highway North Huntingdon, PA 15642

STANDARD SPECIFICATIONS SECTION PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES. 1. Structure Earthwork: 02200

SECTION PRECAST CONCRETE UTILITY STRUCTURES

725-R-599 PIPE LINING. (Revised ) SECTION 725, BEGIN LINE 1, INSERT AS FOLLOWS: SECTION 725 SLIP LINING OF EXISTING PIPE

SECTION REINFORCED CONCRETE PIPE. A. The following is a list of SPECIFICATIONS, which may be related to this section:

EXHIBIT "A. Technical Specifications for Water and Sewer Service Lines

September 2012 Brunswick County Engineering Department Revision 1.0. Technical Specification GRAVITY SANITARY SEWER SYSTEM

Section C-1 Pipes and Fittings

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13)

SECTION DUCTILE IRON PIPE AND FITTINGS

Section 2 Specification 2.18 Concrete and/or Corrugated Steel Storm Sewer TABLE OF CONTENTS

San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS

SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA (7300 Short Road, Serene Lakes)

SECTION PVC PRESSURE PIPE AWWA C900

SECTION POLYVINYL CHLORIDE (PVC) PIPE

SECTION 7- STORM SEWER

ARTICLE II (2) ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH Purpose and Application.

Customer Procedures and General Information for Sewer Customers

SECTION 200: STORM SEWER CONSTRUCTION STANDARDS

SECTION DUCTILE IRON PIPE AND FITTINGS

Exhibit A. Rules and Regulations for House Connections and Sewer Extensions

SECTION DUCTILE-IRON PIPE AND FITTINGS

900 SEWERAGE WORK ITEM PIPE SEWERS COMPLETE IN PLACE

City of West Linn Public Works Standard Construction Specifications. Table of Contents

REHABILITATION OF UNDERGROUND SEWER LATERAL PIPES WITH CURED-IN-PLACE-PIPE LINER SECTION 02542

CITY OF ANN ARBOR PUBLIC SERVICES PLAN REVIEW CHECKLIST

Sewer Rehabilitation Design Requirements

Transcription:

501 SANITARY SEWER PIPE AND FITTINGS... 5-1 501.01 DESCRIPTION... 5-1 501.02 MATERIALS... 5-1 501.03 CONSTRUCTION... 5-6 501.04 MEASUREMENT AND PAYMENT... 5-21 502 MANHOLES AND CONCRETE STRUCTURES... 5-22 502.01 DESCRIPTION... 5-22 502.02 MATERIALS... 5-23 502.03 CONSTRUCTION... 5-26 502.04 MEASUREMENT AND PAYMENT... 5-31 503 WORK ON EXISTING SANITARY SEWERS... 5-32 503.01 DESCRIPTION... 5-32 503.02 MATERIALS... 5-33 503.03 CONSTRUCTION... 5-33 503.04 MEASUREMENT AND PAYMENT... 5-37 504 PIPE REHABILITATION... 5-38 504.01 DESCRIPTION... 5-38 504.02 MATERIALS... 5-42 504.03 CONSTRUCTION... 5-45 504.04 MEASUREMENT AND PAYMENT... 5-53

DIVISION 5 SANITARY SEWERS 501 SANITARY SEWER PIPE AND FITTINGS 501.01 DESCRIPTION 501.01.A This work consists of furnishing and installing gravity and pressure sanitary sewer pipe and fittings and sewer laterals typically associated with sanitary sewer systems. 501.01.B The Contractor shall provide all materials, labor, equipment, tools, etc., and perform all required work and services necessary for and incidental to completing the Work as shown on the Plans and in complete accordance with the Specifications. 501.01.C Supplementary or miscellaneous items, equipment, appurtenances, or devices necessary for or incidental to a complete and functional installation, whether or not shown on the Plans or addressed in the Specifications, shall be provided and installed as part of the Work. 501.01.D MANUFACTURER S CERTIFICATION 1. The Contractor shall furnish manufacturers certification for construction materials when such information is requested by the City Engineer. Certification submitted to the City Engineer shall be sufficient to show the materials meet the specified requirements. Information and cut sheets shall be originals, copies will not be accepted. A minimum of 5 original certification documents shall be provided. Costs associated with providing certification, including materials and testing, shall be borne by the Contractor. 501.02 MATERIALS 501.02.A GENERAL 1. Use sewer pipe and fittings of the size, strength, material, and joint type specified on the drawings and/or in the Contract Documents. Use jointing material as hereinafter specified for each pipe material. Each piece of pipe shall be clearly identified as to strength, class, and date of manufacture. The manufacturer or fabricator shall furnish appropriate certification, based on manufacturer's routine quality control tests, that the materials in the pipe and fittings meet the requirements specified herein. Strength, permeability, hydrostatic tests, and pipe joints will be used as the basis of acceptance as described under Subsection 501.03.Q. Minimum length of pipe shall be 3 1/2-feet. 2. It is not intended that materials listed herein are to be considered equal or to be generally interchangeable for all applications. The type, class, and size of pipe as applicable, will be specified in the Contract Documents for all City improvement projects. The Design Engineer shall determine the materials suitable for the project and so specify. 2010 EDITION Page 5-1

3. Use pipe and fittings for service branches of one type of material throughout; no interchanging of pipe and fittings will be allowed. Use 4-inch minimum diameter pipe for residential services when not otherwise specified. 4. Do not coat pipes for sewers, internally or externally, with any substance of any type in an attempt to improve its performance when air or hydrostatically tested. 5. The Contractor shall furnish Materials and shall perform Work in Close Conformance to the Plans and Specifications. See Section 106.07 for acceptability of Materials and Work. 501.02.B DUCTILE IRON PIPE 1. Ductile iron pipe shall be Class 52 or greater, shall be centrifugally cast of 60-42-10 iron, and shall conform to ANSI/AWWA C-151/A21.51. Joints shall normally be push-on, or mechanical joint, conforming to ANSI/AWWA C-111/A21.11. If specified and approved by the City in writing, flanged pipe may be used and shall conform to ANSI/AWWA C-115/A21.15. 2. Ductile iron pipe shall be lined with cement mortar and seal-coated in accordance with ANSI/AWWA C-104/A21.4. 3. When specified, tube type polyethylene encasement shall conform to ANSI/AWWA C- 105/A21.5. 501.02.C POLYVINYL CHLORIDE (PVC) PIPE NON PRESSURE PIPE & FITTINGS 1. PVC pipe for non-pressure applications for pipe sizes 4-inches through 15-inched in diameter shall conform to ASTM D-3034, SDR-35. 2. PVC pipe for non-pressure applications for pipe sizes 18-inches through 27-inches in diameter shall conform to ASTM F-679, SDR-35. 3. Joints shall be bell and spigot joints with a rubber gasket conforming to ASTM D-3212 and ASTM F-477. 4. Additives and fillers, including but not limited to, stabilizers, antioxidants, lubricants, etc., shall not exceed ten (10) parts per one-hundred (100) by weight. 5. Where required for added strength, AWWA C-900 or C-905 may be used. 6. The Contractor shall use the same material for all pipes and fittings for both the sewer mainline and any service connections between consecutive manholes. Pipe bedding for PVC pipe shall be in accordance with Section 209. 501.02.D POLYVINYL CHLORIDE (PVC) PRESSURE PIPE & FITTINGS 1. PVC pressure pipe and fabricated fittings for pipe diameters 4-inches to 12-inches shall conform to AWWA C-900 Class 150, max SDR-18 or as specified. 2. PVC pressure pipe and fabricated fittings for pipe diameters 14-inches and above shall conform to and AWWA C-905 Class 165, max SDR-25, or as specified. 2010 EDITION Page 5-2

3. Fittings shall be mechanical joint ductile iron and shall conform to the requirements of AWWA C110, Class 250. The PVC pipe bevel shall be modified per AWWA C111 for use with ductile iron fittings. 501.02.E HIGH DENSITY POLYETHYLENE (HDPE) PIPE, SOLID WALL 1. Provide pipe and fittings meeting the requirements of ASTM F-714 and ASTM D-3261 as modified for the specified material. Use pipe made from premium high-density polyethylene resin qualified as Type III, Category 5, Class C, Grade P34 as specified in ASTM D-1238. This material shall have a long-term hydrostatic strength of 1,600psi when tested and analyzed in accordance with ASTM D-2837 and shall be listed by the Plastic Pipe Institute as a PE 3408 resin. Pipe sizing is to be according to ASTM F-714 and ASTM D-3035. MINIMUM ENGINEERING DESIGN PROPERTIES Tensile Strength Yield ASTM D-638 (2 /min) 3200 psi Elongation at Break ASTM D-638 750% Modulus of Elasticity ASTM D-638 105,000psi Flexural Modulus ASTM D-3350 124,000psi Environmental Stress Crack Resistance, Condition C Long-term Hydrostatic Strength @ 73.4 F ASTM D-1693 ASTM D-2837 F20 at >5,000 hours 1,600psi 2. The pipe shall contain no recycled compound except that generated in the manufacturer's own plant from resin of the same specification from the same raw material supplier. 3. The polyethylene pipe shall be homogeneous throughout and free of visible cracks, holes, foreign inclusions, or other injurious defects. The pipe shall be uniform in color, opacity, density, and other physical properties. The raw material shall contain a minimum of 2 percent and not more than 3 percent by weight of well-dispersed and finely divided carbon black when tested according to ASTM D 1603 and ASTM D 4218. Additives that can be conclusively proven not to be detrimental to the pipe may be also used, provided the pipe produced meets the requirements of this standard. 4. Pipe and fittings shall be marked including nominal size, OD base (ie: 12-inch ductile iron pipe sizing, DIPS), dimension ratio, pressure class, manufacturer's name, manufacturer's production code including day, month, and year extruded, and manufacturer's plant and extrusion line. 5. Compliance with requirements of these specifications shall be certified in writing by the pipe supplier. 6. JOINTS FOR HDPE PIPE a. High-density polyethylene (HDPE) pipe and fittings shall be jointed by the thermal butt fusion per ASTM A-2657 and the manufacturer's specific recommendations or approved coupler. The temperature of the heater plate should be 400 degrees F to 450 degrees F. The tensile strength at yield of the butt fusion joints shall be not less than that of the pipe. 2010 EDITION Page 5-3

b. The HDPE pipe may be adapted to fittings or other systems by means of an assembly consisting of a HDPE stub-end, butt-fused to the pipe, a backup flange of ductile iron made to Class 150, ANSI B1 6.1/B1 6.5 dimensional standards with exceptions, bolts of comparable material, and a gasket of suitable neoprene, red rubber or non-asbestos rubber compound cut to fit the joint. In all cases, the bolts shall be drawn up evenly and in line. c. HDPE pipes of the same outside diameter but different wall thickness shall be joined by means of a flange assembly as designated above or by thermal butt fusion, and will only be allowed when expressly approved by the City Engineer. d. The pipe supplier shall be consulted to obtain machinery and expertise for the joining by butt fusion of HDPE pipe and fittings. No pipe or fittings shall be joined by fusion by any Contractor until he is qualified in the techniques involved. 7. SERVICE BRANCHES a. Tee and wye fittings to connect service branches shall be either molded butt fusion fittings, or molded saddle fusion fittings. 501.02.F JOINTING MATERIALS (GASKETS) 1. GENERAL a. Only lubricants for jointing materials approved by the manufacturer shall be used. b. Furnish to the City Engineer a certified statement from the manufacturer of the gaskets, setting forth the basic polymer used in the gaskets, and results of the tests of the physical properties of the compound. Gaskets shall be shipped in containers with identification of the batch from which the gaskets were fabricated. 2. DUCTILE IRON PIPE a. Rubber gaskets shall conform to ANSI A21.11/AWWA C-111. 3. POLYVINYL CHLORIDE (PVC) PIPE 501.02.G FITTINGS a. Rubber gaskets for PVC pipe shall conform to ASTM F-477. 1. GENERAL a. Provide tee or wye fittings in the sewer main for sewer service laterals. Manufactured tees and wyes for sewer service laterals shall be a minimum of 4-inches nominal diameter, unless otherwise specified. Fittings shall be of sufficient strength to withstand all handling and load stresses encountered, including pressure testing that will be encountered in the work. 2010 EDITION Page 5-4

b. Fittings shall be of the same materials as the pipe, unless otherwise specified. Material joining the fittings to the pipe shall be free from cracks and shall adhere tightly to each joining surface. Use the same type of joints on all fittings that are used on the main sewer pipe. Tee or wye fittings shall not be closer than 18-inches to any joint or bell of main line sewer. c. Where approved by the City Engineer, connections to existing sewers shall be made with an insert-a-tee connection compatible with the pipe being connected. 2. DUCTILE IRON FITTINGS Use mechanical-joint, cast-iron fittings conforming to ANSI A21.10/AWWA C-110, and a class of at least equal to that of the adjacent pipe. Use push-on fittings of gray cast iron with body thickness and radii of curvature conforming to ANSI A21.10 and joints conforming to ANSI A21.11/AWWA C-111. 3. POLYVINYL CHLORIDE (PVC) FITTINGS a. PVC fittings shall be in conformance with the requirements of ASTM D-3034, SDR-35 and ASTM F-679 as applicable. b. Ductile iron fittings conforming to the requirements above shall be used with PVC AWWA C-900 and AWWA C-905 pressure pipe. c. PVC PIPE CONNECTIONS TO MANHOLES 1) Pipe shall be connected to sanitary sewer manholes using a flexible, watertight Kor-N- Seal, or approved equal pipe-to-manhole connector or other approved equal specifically manufactured for the intended service. Field fabricated waterstops or improvised adapters such as gaskets stretched over the pipe will not be allowed. 2) Connections requiring the use of grout for installation, such as sand collars, shall be used only on a case-by-case basis, where approved by the City Engineer. Where approved, connections shall be bonded, anchored, and finished using an approved non-shrink grout as specified in Subsection 208.02.G.3. Plain Portland Cement mortar is not acceptable. Sand collars shall be fabricated by an approved manufacturer and not field made. Sand collars shall be coated with an epoxy adhesive compatible with both PVC and concrete grout and coated with aggregate. The installation of the sand collar shall be such that the bell portion of the adapter is adjacent and external to the wall of the manhole, and the spigot shall protrude through and into the manhole 3-inches beyond the interior of the wall of the manhole. 4. HDPE PIPE FITTINGS a. The pipe used to fabricate fittings shall comply with AWWA C-906 and ASTM D-1248 requirements for Type III, Class C, Category 5, Grade P34 polyethylene material. Standard fittings and special fittings shall be manufactured from the same class of material as the pipe and be fully compatible. b. Fittings shall be manufactured in accordance with ASTM D-3261. Fabricated fittings shall be pressure-rated to match the system piping. 2010 EDITION Page 5-5

c. HDPE PIPE CONNECTION TO MANHOLES 1) Pipe shall be connected to sanitary sewer manholes using a flexible, watertight Kor-N- Seal, or approved equal pipe-to-manhole connector or other approved equal specifically manufactured for the intended service. Field fabricated waterstops or improvised adapters such as gaskets stretched over the pipe will not be allowed. 501.02.H PIPE COUPLING ADAPTERS 1. GENERAL a. Rigid couplers (solid sleeves) shall be used for connecting pipe, unless otherwise approved by City Engineer. 2. COUPLINGS FOR HDPE PIPE a. Mechanical connections of polyethylene pipe to fittings or other materials shall be by means of flanged connections (flanged coupling adapters and ANSI backup rings rated for the same pressure service as the system piping) or flexible couplings designed for joining polyethylene pipe to polyethylene pipe or to another piping material such as a head PVC coupler as applicable, as approved by the City Engineer. b. Flanged joints shall use bolts of compatible material. Gaskets shall be required when joining to non-polyethylene materials. In all cases, the bolts shall be evenly torqued using a crisscross pattern. Flanged joints are to be re-torqued after one (1) hour or more has passed since initial torquing. 501.02.I CLEANOUTS 1. Pipe for cleanouts shall be of the same material as the main line. Cleanouts shall be of the same size as the line it is serving or shall be 8-inch nominal diameter, whichever is smaller. 501.02.J LOCATING (TRACER) WIRE 1. Locating wire shall be a minimum of 12 AWG, UF solid copper wire with green colored insulation. The use of THHN wire will not be acceptable. Splices shall only be used when necessary. At splices, the connecting ends of the wires shall be stripped, overlapped, and tied. Splice shall made waterproof with an approved waterproof silicone splice kit. Contractor shall ensure splices have a waterproof electrical connection at all times. 501.02.K SERVICE CONNECTION MARKERS 1. Service connection markers shall be 2-inch x 4-inch pressure treated random length lumber. Markers shall be continuous and extended at least 2-feet above the ground surface. 501.03 CONSTRUCTION 501.03.A EXCAVATION AND BACKFILL 1. Excavation and backfill shall conform to the requirements of Section 209 as further specified herein. 2010 EDITION Page 5-6

2. EXCAVATION Excavation shall be unclassified, unless otherwise specified. 3. BACKFILL a. TRAFFIC AREA TRENCH BACKFILL For public sewer pipe installations within dedicated street rights-of-way or where current or future hard-surfaced improvements will be made, select backfill material as specified in Subsection 209.02.E.2 for granular backfill shall be used. b. NON-TRAFFIC AREA TRENCH BACKFILL For public sewer pipe installations outside of dedicated street rights-of-way, or where current or future hard-surfaced improvements will not be made, native backfill material as specified in Subsection 209.02.D for use above the pipe zone may be used. 501.03.B LINE AND GRADE FOR GRAVITY AND PRESSURE SANITARY SEWERS 1. GENERAL a. Do not deviate from the line or grade, as established by the City Engineer, more than 1/2-inch for line and 1/4-inch for grade, provided that such variation does not result in a level or reverse sloping invert. Due to permissible variations in pipe wall thicknesses, measure for grade at the pipe invert and not at the top of the pipe. b. Line and grade for pipe shall be established and maintained by the use of pipe lasers. The Contractor shall check the line and cut from the offset stakes at maximum intervals of 50- feet. c. Impounding of water, regardless of amount, will not be permitted in any section of the completed sanitary sewer system. d. Any pipe or run of pipe that has not been installed within the allowable tolerance for line and grade or impounds water to any extent shall be removed and reinstalled or replaced as necessary to bring the work into compliance with the specified requirements 2. LINE AND GRADE FOR SEWER SERVICE LATERALS a. Sewer service laterals shall have a minimum diameter of 4-inches and shall be installed with a minimum slope of 1/4-inch per foot of run. Minimum depth of service laterals at the flow line of curb and gutters within street right of ways, or edge of pavements in easements, shall be 5-feet below finish surface grade, unless otherwise approved by City Engineer. More depth may be required to accommodate existing site conditions. b. Individual sewer service laterals shall not be connected to manholes unless specified as such in the Contract Documents or approved by the City Engineer. c. The maximum line or grade change made with any one fitting shall not exceed 45 degrees. d. Ends of service lines and service fittings shall be provided with approved watertight plugs, caps, or stoppers, suitably braced to prevent blowoff during internal air testing. Such plugs or caps shall be removable without damage to the pipe or fitting. 2010 EDITION Page 5-7

e. Deep trench service connections shall be constructed as specified in the Contract Documents and the applicable Standard Drawing. 501.03.C PIPE DISTRIBUTION AND HANDLING 1. Distribute material on the job no faster than it can be used to good advantage. Unload pipe only by means recommended by the pipe manufacturer. Do not unload pipe by dropping it to the ground. For publicly financed improvement projects, do not distribute more than one (1) week's supply of material in advance of installation, unless approved by the City Engineer. 2. Pipe shall be stored as recommended by the pipe manufacturer, including those recommendations for storage of pipe to prevent UV damage. Pipe shall not be unloaded or stored in the public right-of-way or easement unless it has been certified and accepted by the City Engineer. Inspect all pipe and fittings prior to lowering into trench to ensure no cracked, chipped, broken, or otherwise defective materials are used. Clean ends of pipe thoroughly. Remove foreign matter and dirt from inside of pipe and keep clean during and after laying. 3. Use proper implements, tools, and facilities for the safe and proper protection of the work. 4. Construction materials that are showing kinks, cracks, buckles, cuts, gouges or any other damage or that do not have approved certification shall be immediately removed from the job site or stockpiled in a location away from, or separate from, the work area 501.03.D PIPE LAYING AND JOINTING OF PIPE AND FITTINGS 1. GENERAL a. Sheet shoring and movable trench shields shall be placed, removed, and/or operated in conformance with applicable requirements in Subsection 209.03.L. Take special care to prevent movement of the pipe after installation when placed within a movable trench shield. b. Cracked, broken, or otherwise defective pipe and fittings shall not be used. Pipe shall be lowered into the trench by slings or other suitable means. Do not drop or dump pipe into trenches. c. Pipe and fittings with damaged protective coatings shall be repaired using methods and materials recommended by the manufacturer of the pipe and/or fittings. d. Proceed with pipe laying upgrade with spigot ends pointing in direction of flow. Place pipe in such a manner as to ensure solid bearing between the pipe and the full cross-sectional area of the bedding for the full length of the pipe between joints. Make assembly of the joint in accordance with the recommendations of the manufacturer. Take care to properly align the pipe before making the joint. Upon completion of pipe placement, all pipe joints shall be in the "home" position, which is defined as the position where the least gap (if any) exists, when the pipe components that comprise the joint are fitted together as tightly as the approved joint design will permit. Joints with gaps exceeding the normal gap in the "home" position by more than 1/4-inch shall be repaired as required by the City Engineer at no cost to the City. In cases where gaps exist in joints but do not exceed the normal gap in the "home" position by more than 1/4-inch, the City Engineer may require repair of the joint if, in his judgment, these detract from the integrity of the joint based upon soil conditions and the intended use of the pipeline. 2010 EDITION Page 5-8

e. After installation, each length of pipe shall be covered with a sufficient amount of backfill to maintain the pipe at the specified line and grade during subsequent construction operations. f. When pipe laying operations are not in progress, the open end of the pipe shall be covered to prevent entry of rock and debris. Each section of pipe shall be cleaned as necessary to remove excessive amounts of dirt or other debris that may not be removed during the flushing operation. g. Plug pipes that are stubbed out for manhole construction or for connection by others by use of a cap or plug designed for that purpose. Such plugs or caps shall be removable and their removal shall provide a bell end suitable for extension of the line. h. When cutting and/or machining of the pipe is necessary, use only tools and methods recommended by pipe manufacturer. All types of pipe shall be sawcut when special lengths or end configurations are needed to complete the work as specified. Striking concrete pipe with hammers or other similar tools to induce transverse cracking of the pipe barrel is not permitted. PVC and ductile iron pipe ends that have been sawcut shall be beveled as necessary to prevent damage to the gaskets in push-on joint connections. i. Pipe alignment shall not be deflected from a straight line in either the vertical or horizontal plane, unless such deflections are specified in the Contract Documents or approved by the City Engineer. Where approved, pipe and fitting connections shall not be deflected in excess of that recommended by the manufacturer of the pipe and fittings. j. Fittings shall not be installed closer than 12-inches to any joint in a main line sewer that is 12-inches or less in diameter. k. Pipe and fitting ends shall be cleaned and properly aligned before making the joint connection. l. Joints shall be fitted together as tightly as the joint design will permit. Gaps at pipe joints shall not exceed that recommended by the manufacturer of the pipe and fittings. M. Fabricated fittings and connections incorporating materials or methods of construction not specified herein or in the Contract Documents shall not be used in the work. 2. DUCTILE IRON PIPE a. Ductile iron pipe and fitting connections shall be made in conformance with Subsection 401.03.G. 3. POLYVINYL CHLORIDE (PVC) PIPE a. The Contractor shall use the same material for pipe and fittings for both mainline and service laterals between two consecutive manholes, unless otherwise approved by the City Engineer. b. Connections to manholes shall be made by an approved flexible, watertight pipe-tomanhole connection. 2010 EDITION Page 5-9

c. Service laterals shall be connected to new mainline PVC sewer pipe with full-line tees or wyes and bends. Service laterals for existing sewers shall be with an insert-a-tee as approved by City Engineer. 4. HIGH DENSITY POLYETHYLENE (HDPE) PIPE a. Fusing of pipe joints shall meet the requirements of ASTM D2657. Installation practices shall follow the standard practices as set forth in ASTM F-585. b. Prior to placing the HDPE pipe, joints shall be complete except as noted. The full length of each section of pipe shall rest solidly upon the pipe bed. Pipe that has the grade of the joint disturbed after laying shall be taken up and re-laid. c. Pipe fusion shall be performed as recommended by the manufacturer and shall not be done in water or when trench conditions are unsuitable for the work. Water shall be kept out of the trench until joining is completed. When work is not in progress, the open ends of pipe and fittings shall be securely closed so that no trench water, earth, or other substance will enter the pipe or fittings. Pipe ends left for future connections shall be immediately plugged or capped. d. HDPE pipe shall be brought to within 5 degrees F of earth temperature prior to cutting to length for placement of tee, elbows, or other fittings. e. HDPE pipe shall be joined by the thermal, butt-fusion method or other coupling methods specifically approved by the City Engineer prior to installation. f. Joints shall have a smooth, uniform, double rolled back bead made while applying the proper melt, pressure, and alignment. The joint shall be allowed adequate cooling time before removal of pressure. The fused joint shall be watertight and shall have tensile strength equal to the pipe. g. Any jointing shall be only conducted by personnel possessing the qualifications and certifications specified herein. The joining sites shall be cleared and graded, if necessary, to provide enough space for pipe storage and fusion. The site shall be free of rocks, stumps, and other debris that could cut, scar, gouge, or otherwise damage the pipe. The Contractor shall provide a shelter over the joining operation during adverse weather conditions. Particular caution is required to prevent any water from coming in contact with the heater plate. h. The Contractor shall be responsible to provide training and instruction for his personnel at no cost to the City. Training shall include, but not be limited to, familiarization with HDPE pipe and fittings, fusion, testing, and installation of pipe. The personnel requiring training includes, but is not limited to, quality control personnel and polyethylene fusion machine operators as applicable for the project. Only instructed personnel will be allowed to perform the installation or supervision of polyethylene fusion joints. i. A listing of those authorized for polyethylene fusion work shall be submitted and approved by the City Engineer prior to any installation or work on the HDPE pipe. j. The Contractor shall make training sessions available to City Engineer and Inspectors and other quality assurance personnel at no charge and shall schedule the training sessions at a date, place, and time agreeable to the City. 2010 EDITION Page 5-10

501.03.E PIPE COUPLING ADAPTERS 1. Prior to installing mechanical couplers and adapters, pipe ends shall be sawcut as necessary to produce an edge that is free of cracks or other irregularities. Pipe ends shall be cut perpendicular to the length of the pipe. 2. After installation of the coupler or adaptor, pipe zone materials shall be thoroughly compacted to maintain proper alignment of the flow line and to prevent any movement of the pipe ends. 501.03.F INSTALLATION OF SEWER SERVICE LINES, TEES, AND WYES 1. Sewer service lines shall be constructed in accordance with the Plans, Standard Drawings, Standard Construction Specifications, and applicable provisions of the Oregon Plumbing Specialty Code. 2. Existing sewer service shall not be interrupted without the approval of the City Engineer and sewer service owner and/or user. The Contractor shall obtain all necessary permits required to construct service lines on both public and private property. 3. Connection of service lines to new or existing gravity sewer lines shall be as per the Plans and shall be inspected and accepted by the City Engineer prior to backfilling. All sewer service connections shall be watertight utilizing appropriate tees, wyes, and approved taps or service saddles. An approved tee or wye manufactured fitting shall be used when new sewer mains are being constructed. All holes and taps into an existing sewer main shall be cut using an approved tapping machine in the presence of the City Engineer. 4. The minimum slope of service lines shall be 1/4-inch per foot unless otherwise approved by the City Engineer. The pipe size of service lines shall be a minimum 4-inch diameter unless otherwise specified. Maximum vertical deflection permissible with any one fitting shall not exceed 22.5 degrees, unless otherwise approved. No horizontal deflection is allowed. Ends of service lines shall be at the location and elevation shown on the Plans. 5. Install continuous 12 gauge green locating wire from mainline wire up to the ground surface at the property line cleanout, then loop back down to the end of the service, and then up along the service connection marker, as shown in the Standard Drawings. 6. Provide pipe-bedding material, compacted to a minimum of 90 percent of maximum density as determined by AASHTO T-180, under tees, wyes, and service branch fittings extending to the springline of the fittings. Place pipe bedding material on undisturbed native material or compacted foundation stabilization material. 7. Provide ends of service lines and fittings with approved watertight plugs or caps suitably secured and braced to prevent blow-off during internal air testing. Such plugs or caps shall be removable and their removal shall provide a socket suitable for making a flexible joint service connection or extension. 2010 EDITION Page 5-11

501.03.G LOCATING (TRACER) WIRE 1. A continuous looped solid copper tracer or locating wire shall be installed along the top of all mainlines and service lines. These wires shall be secured to the top of the pipe at maximum 10-foot intervals using 6-inch strips of 2-inch wide duct tape. All splices shall be tied, electrically continuous, and made waterproof. Access to terminal ends of the locating wire shall be made at all manholes, catch basins, service line cleanouts, etc. and as shown on the Plans. Locating wire penetrations into manholes shall be 3/8 diameter holes drilled within 18-inches of the rim elevation and adjacent to the manhole steps. Extend the locating wire through the opening in the manhole wall and provide a minimum 3-foot of additional wire. Coil and tie the locating wire to the top manhole step, or otherwise support to allow retrieval from the outside of the manhole. Seal the opening in the manhole wall with silicone sealant. 2. The result of this installation shall be a continuous wire circuit electrically isolated from the ground. The Contractor shall be responsible for testing continuity and for testing isolation from the ground in the wire after all work has been completed on the test section. The Contractor is advised to do intermediate testing after backfilling operations and prior to surface restoration work to be sure continuity is maintained. If there is a break or defect in the wire, it shall be the Contractor's responsibility to locate and repair the defect. The continuity of the location wire shall be tested from one test load point to the next by use of a temporary wire laid between test points in-line with an ohmmeter. 501.03.H SERVICE CONNECTION MARKERS 1. In new subdivisions, undeveloped areas, and where connections will not be made after the service is installed, block the capped or plugged end and install a continuous 2-inch x 4-inch pressure treated marker. Extend markers at least 2-feet above the ground surface. 2. The top portion of the marker shall be painted after its installation with first-quality green, quickdrying enamel. After the paint has dried, use black, quick-drying enamel and neatly indicate the distance from the natural ground surface to the top of the service pipe in feet and inches. If curbs are present or to be poured as part of the project, stamp the top of the curb and gutter pan with an "SS" over the service crossing. 3. Markers shall be in one continuous piece. Splicing of lumber used for markers is only permitted in situations where the depth of the pipe is in excess of standard lumber lengths. Markers shall be installed in a vertical position with the bottom end of the marker against the end of the pipe. Markers that are broken, too short, or are not installed vertically in the ground shall be replaced by removing the backfill and replacing and/or repositioning the marker. In areas where it is not practical to extend markers above the ground surface, as approved by the City Engineer, the tops of the markers shall be installed flush with the ground surface. 501.03.I CLOSURE COLLARS 1. GENERAL a. The use of concrete closure collars in lieu of mechanical-type couplers or other specified or approved connection materials and procedures is not permitted unless approved by the City Engineer. 2010 EDITION Page 5-12

2. CONCRETE CLOSURE COLLARS a. Use concrete closure collars only when specified or approved. Concrete closure collars shall be constructed in conformance with the details provided and the following additional requirements: 1) Concrete shall conform to applicable requirements in Section 208. 2) Concrete shall be contained in forms constructed in conformance with applicable requirements in Section 211. Backfill materials or earth shall not be used in lieu of forms. Concrete shall be confined to the specified dimensions of the collar. Forms shall be constructed such that the concrete will not be allowed to enter the pipe or structure around which the collar is being constructed. 3) Concrete reinforcement materials shall be supplied and placed in conformance with applicable requirements in Section 211. 4) Surfaces of pipe and fittings that are to come into contact with the concrete shall be thoroughly washed to remove all dirt and loose material. 5) Concrete shall not be placed on non-compacted base materials or in water. 6) The entire amount of concrete necessary to construct the collar shall be placed in one continuous operation. If the concrete is allowed to harden or obtain initial set prior to completion of the collar, the Contractor shall remove the concrete and reconstruct the collar. 7) Concrete shall be consolidated in conformance with applicable requirements in Subsection 211.03.H. The concrete shall be thoroughly consolidated around the pipe or structure as necessary to ensure that no voids will be formed in the collar. 8) Concrete shall be allowed to obtain initial set prior to placing backfill over the collar. Concrete shall be allowed a minimum of seven (7) days of cure time prior to compacting the backfill over and adjacent to the collar. 3. FLEXIBLE COUPLING CLOSURE COLLARS a. Use flexible coupling collars only when specified or approved. Couplings must incorporate full length and full diameter stainless steel shear bands. Couplings shall be of the type produced by "Fernco", "Mission", or approved equal. 501.03.J DISCONNECT AND RECONNECT EXISTING SEWER LATERALS 1. When shown or required, disconnect existing sewer laterals from existing sewers and reconnect them to the new sewers. The Contractor shall be responsible for locating the existing sewer laterals prior to installing the tee or wye in the new wastewater line. The Contractor shall verify and reconnect all active sewer laterals to the wastewater main line. 501.03.K REPAIR OF EXISTING UTILITIES 1. Existing utilities that are damaged as a result of the Contractor's operations shall be repaired immediately at the Contractor s expense. 2010 EDITION Page 5-13

501.03.L UTILITY CROSSINGS 1. Minimum allowable clearance between pipes at crossings shall be 6-inches, unless otherwise approved by City Engineer. 2. In locations where new sanitary sewers cross over an existing water line or under an existing water line with less than 18-inches of clearance between the two pipes, the Contractor shall substitute the specified sewer pipe with a full length of AWWA C900 PVC (DR 18) or Class 52 ductile iron pipe of equivalent size, centered at the crossing point. Watertight, mechanical couplers or adapters shall be used to connect the sewer pipe to the C900 PVC or ductile iron pipe, as approved by the City Engineer. 501.03.M CONCRETE PIPE ENCASEMENT 1. Where required or approved by the City Engineer, the installation of concrete encasement for sanitary sewer pipe shall conform to applicable requirements in Section 209.03.O.2. 501.03.N FIELD FABRICATED CONNECTIONS 1. The use of field fabricated connections is not permitted unless approved by the City Engineer. "Insert-a-tees" or approved equal shall be used in lieu of field fabricated connections. See Standard Drawings. 501.03.O CLEANOUTS 1. Cleanouts shall be constructed per the Standard Drawings. The cleanout shall stand vertical and the Contractor shall bring compacted bedding material up around the vertical portion of the top. Frames and covers shall be per Standard Drawings and comply with requirements of Subsection 502.02.G. 501.03.P SURFACE RESTORATION 1. Surface restoration shall be in conformance with applicable requirements of Section 212, Section 213, and Section 215. 501.03.Q TESTING SANITARY SEWERS 1. GENERAL a. Gravity sanitary sewers including service branch sewers and appurtenances shall successfully pass an air test prior to acceptance and shall be free of leakage and visible infiltration of water. Pressure sewer lines shall be tested in accordance with the Contract Documents. b. Manholes shall be tested as specified in Subsection 502.03.G. c. Pressure sewer force mains shall be pressure and leakage tested in accordance with applicable portions of Section 405, when not otherwise specified. 2010 EDITION Page 5-14

d. Perform the tests in a manner satisfactory to the City Engineer. Calibrate gauges for air testing with a standardized test gauge provided by the Contractor at the start of each testing day. The calibration shall also be witnessed by the Inspector; notify the Inspector at least twenty-four (24) hours prior to each test. e. The City Engineer may require testing of manhole-to-manhole sections as they are completed in order to expedite the acceptance of completed portions of the system and allow connections prior to the whole system being completed. f. Deflection testing shall be performed on sanitary sewers and storm drains when such systems are constructed of PVC pipe. g. Sewer pipe 30-inches in diameter and larger may be tested using an approved pneumatic joint testing device. Such testing methods and equipment shall meet the approval of the City Engineer. h. Sanitary sewers shall not be coated internally or externally with any substance of any kind in an effort to improve the performance of the pipe when tested i. All testing, including but not limited to deflection and air tests and closed-circuit television (CCTV) inspections, must be passed prior to any paving operations. j. At the Contractor s expense, the City will make a televised inspection of the sanitary sewer pipe after the Contractor has completed the installation of the sewer pipe, including backfill, deflection, and air testing. When the Contractor has jetted and cleaned the sewer pipe, the inspection shall be scheduled by the Contractor with the Inspector. Any defects in material or workmanship shall be satisfactorily corrected at no expense to the City. The Contractor shall re-tv the pipe after any corrections in accordance with Subsection 501.03.Q.9 and supply the CCTV video and the report to the City Engineer for review and approval. This process will repeat until the pipe complies with the specifications. Acceptance is required prior to any paving operations. 2. WATER AND EQUIPMENT FOR TEST a. The Contractor shall make arrangements, perform the test, and provide personnel, plugs, and other necessary equipment to complete the tests at no cost to the City except that the initial CCTV inspection will be performed by the City at the Contractor's expense. The method, equipment, and personnel shall be subject to approval by the City Engineer. 3. CLEANING PRIOR TO TESTING AND ACCEPTANCE a. Prior to any testing for acceptance, the Contractor shall jet rod and clean all parts of the system. Remove accumulated construction debris, rocks, gravel, sand, silt, and other foreign material from the system at or near the closest downstream manhole. If necessary, use mechanical rodding or bucketing equipment. The Contractor shall continue to clean the system until the CCTV inspection shows no foreign material in the pipe. City Engineer's re-inspection may be required if the amount of debris is, in the City Engineer's opinion, excessive. 2010 EDITION Page 5-15

4. TESTING PROCEDURE a. Perform the tests in a manner satisfactory to the City Engineer. Any arrangement of testing equipment which will provide observable and accurate measurements of air leakage under the specified conditions will be permitted. Notify the City Engineer twentyfour (24) hours prior to each test. b. Make tests of sections of constructed sanitary sewer for acceptance only after service connections, manholes, backfilling, and compaction are completed between the stations to be tested. City may require testing of manhole-to-manhole sections as they are completed in order to expedite the acceptance of sections of sewer and allow connections prior to the whole system being completed. 5. REPAIRS a. Repair or replace in accordance with Subsection 501.03.D, and in a manner satisfactory to the City Engineer, any section of pipe not meeting the air test requirements, deflection test requirements, joint testing requirements, alignment requirements, or that has leakage. Rerounding of the pipe will only be allowed if approved by the City Engineer. 6. DEFLECTION TEST FOR FLEXIBLE PIPE (HDPE AND PVC) a. In addition to air testing, perform a deflection test for sanitary sewers constructed of flexible pipe not less than thirty (30) days after the trench backfill and compaction has been completed, unless otherwise specifically approved by the City Engineer. The test shall be conducted by pulling an approved solid pointed mandrel having at least six (6) vanes through the completed pipeline. The diameter of the mandrel shall be 95 percent of the internal pipe diameter. Conduct testing on a manhole-to-manhole basis, and only after the manholes have been channeled and the line has been completely cleaned. Locate and repair any sections failing to pass the test and retest the section at the Contractor's sole expense. 7. STANDARD AIR TESTING a. GENERAL 1) The Contractor shall furnish necessary testing equipment and shall perform the tests in a manner satisfactory to the City Engineer. Testing equipment shall provide observable and accurate measurements of air leakage under the specified conditions. 2) Plugs used to close the pipe for the air test must be capable of resisting the internal pressures and must be securely braced. Place all air testing equipment above ground and allow no one to enter a manhole or trench where a plugged pipe is under pressure. Release pressure before the plugs are removed. The testing equipment used must allow continuous monitoring of the test pressures in order to avoid excessive pressure. Use only qualified personnel to conduct the test. 3) The entire sewer system shall be cleaned prior to air testing. The system shall be flushed as many times as necessary to remove debris. 4) Air testing shall be accomplished after service connections, manholes, and backfilling and compaction operations have been completed between the stations to be tested. 2010 EDITION Page 5-16

5) The testing equipment shall include a pressure relief device designed to relieve pressure in the sewer under test at 10 psi or less and shall allow for continuous monitoring of the test pressures in order to avoid excessive pressure. 6) Only qualified personnel will be allowed to conduct the test. Plugs used to close the system for the testing shall be capable of resisting the expected internal pressures. Securely brace plugs, if necessary. b. GROUND WATER 1) The presence of ground water will affect the results of the test. Determine the average height of ground water over the pipe immediately before starting the test. 2) In every case, determine the height of the water table at the time of the test by exploratory holes or such other methods satisfactory to the City Engineer. The City Engineer will make the final decisions regarding test height for the water in the pipe section being tested. 3) The test pressures shall be increased 0.433 psi for each foot of average water depth over the invert of the pipe, as further outlined below. c. METHOD 1) Use the time-pressure drop method for air testing. The test procedures are described as follows: Step Procedure 1 Clean the pipe to be tested and remove debris where noted. 2 Wet the pipe prior to testing, if desirable. 3 Plug pipe outlets with suitable test plug. Brace each plug securely. 4 5 6 7 8 9 Check the average height of the groundwater over the pipe. The test pressures required below shall be increased 0.433 psi for each foot of average water depth over the invert of the pipe. Add air slowly to the section of pipe being tested until the internal air pressure is raised to 4.0 psig greater than the average backpressure of any groundwater that may submerge the pipe. After the internal test pressure is reached, allow at least 2-minutes for the air temperature to stabilize, adding only the amount of air required to maintain pressure. After the temperature stabilization period has passed and the pressure has been elevated to the specified test pressure, disconnect the air supply. Determine and record the time, in seconds, that is required for the internal air pressure to drop from 3.5 psig to 2.5 psig greater than the average backpressure of any ground water that may submerge the pipe. Compare the time recorded in step 8 with the time required as determined hereinafter. 2010 EDITION Page 5-17

d. ACCEPTANCE 1) The tested section will be acceptable if the time recorded in step 8 above is greater than the required time, in seconds (T), computed by the formula: T=K/C Where: K = The sum of the computations (0.011 D^2*L) for each size of pipe and its length in the section C = The sum of the computations (0.0003882 D*L) for each size of pipe and its length in the section, except that the minimum value for C shall be 1. D = Inside diameter of the pipe, in inches. L = Length of pipe, in feet. 2) The time required shall be as computed according to the following procedure: a) Record the diameter in inches (D) and the length in feet (L) of pipe in the section to be tested, including the house service laterals. b) Compute values for K and C by using the above formulas (D=inside diameter in inches and L=length in feet) and record them in the table. c) Add all values of K and all values of C for the section being tested. d) If the total of all the C values is less than one, the time required by the specifications shall be the total of the K values. e) If the total of all the C values is more than one, the time required by the specifications shall be found by dividing the total of all the K values by the total of all the C values. The quotient is the time required by the specifications. e. SUBSEQUENT FAILURE 1) Following a successful air test, visible infiltration of ground water in any section will be considered evidence that the original test was in error or that failure of the section has occurred. Correct such failures and retest the repaired sections at no expense to the City. 8. JOINT AIR TESTING FOR SEWERS WITH PIPE DIAMETERS GREATER THAN 36-INCHES a. GENERAL 1) Because of the difficulty of adequately restraining plugs and the inherent danger of air pressure on large surfaces, the Contractor is encouraged to test each individual joint for leakage using a pneumatic joint testing apparatus in lieu of performing the above required pipe section air testing. Such testing apparatus for each pipe size to be tested shall be tested, calibrated, and approved prior to acceptance testing. 2) The City Engineer may, at any time, require a calibration check of the instrumentation used. A pressure gauge having a minimum division of 0.1 psi and an accuracy of 0.0625 psi shall be used for the check. All air shall pass through a single control panel. 2010 EDITION Page 5-18

b. GROUNDWATER 1) The presence of ground water will affect the results of the test. Determine the average height of ground water over the pipe immediately before starting the test. 2) In every case, determine the height of the water table at the time of the test by exploratory holes or such other methods satisfactory to the City Engineer. The City Engineer will make the final decisions regarding test height for the water in the pipe section being tested. 3) The test pressures shall be increased 0.433 psi for each foot of average water depth over the invert of the pipe. c. EVALUATION 1) The allowable minimum for a drop in the test air pressure from 3.5 to 2.5 psi greater than the average backpressure of any groundwater will be the time per unit length, along centerline of pipe, (T) in seconds, from the following table. Minimum time = T. PIPE INSIDE DIAMETER INCHES TIME PER UNIT LENGTHS (ALONG CENTERLINE OF PIPE) SEC./IN. 36 11.1 42 12.9 48 14.8 54 16.7 60 18.4 66 20.2 72 22.0 78 23.9 84 26.0 d. TESTING 1) Testing of individual mainline pipe joints shall be done as mainline pipe laying progresses. It is the intent of this specification that a joint test will be made immediately after each mainline pipe section is laid and backfilled, and the joint gap, excluding settlement allowance, is found to be within acceptable tolerances. 2) At the sole discretion of the City Engineer, upon satisfactory installation and testing of the first ten (10) successive pipe joints of each pipe size, the Contractor may elect to test joints at no greater than one (1) work-day intervals instead of making tests after laying each pipe section. 3) If a joint does not meet the test time established herein, a reinforced concrete closure collar shall be constructed around the joint or the joint shall be reassembled as approved by the city engineer at no expense to the City. 2010 EDITION Page 5-19