September Webinar Integrating Costs With Primavera Contract Manager, P6 Scheduler, and P6 Web presented by: Jonathan McNatty, PSP DRMcNatty & Associates, Inc.
The Primavera Solution! Primavera allows you to effectively manage time, costs, resources, contracts and changesin a single integrated solution. Primavera s IntegratedProgram Management (IPM) provides each project participant with anytime, anywhere access to their project information. 2
Primavera s Integrated Program Management P6 Planner Schedules + costs & resources in the perspective of time Integrated Program Management Interactive Program Dashboard and Reporting Scheduling Manageme Resource Manageme Contract Change and nt Job Control Cost Mitigation Risk Work nt Document Control Flow - Collaboration - Document Management Contract Management Contracts, Costs, Changes & Correspondence P6 Web Web interface accesses Planner & CM data, provides collaboration platform 3
Primavera Deployment P6 WEB USER P6 Web Project data from P6 (Schedule) and Contract Management (Contracts) can be viewed in P6 Web Internet CM USER Contract Management Web Server P6 Web Server LAN, VPN RDP, Citrix P6 USER Contract Management Database Linking Projects Local Area Network P6 Database 4
Primavera Contract Management Who uses Contract Management Project Managers Construction Managers Contract Administrators Cost Engineers Job Cost Administrators Field Superintendents Contractors Subcontractors Architects Owners Contracts Change Management Job Cost Document Control 5
P6 Project Management Who uses P6 Project Management? Program Management Team Program Master Schedule Construction Managers Project Master Schedule Cost Engineers Project cost & resource loading & reporting Contractors Project execution schedules Subcontractors Subcontract execution schedules Architects Design milestone schedules Owners regulatory compliance milestones & schedules Scheduling Resource Management Costs & Resources in Perspective of Time 6
Project Setup Needs To Be Standardized The projects in Contract Management and P6 Project Management need to match when linking the projects between the two systems. Contract Management Project Tree P6 Project Structure The Project Tree in Contract Management & the EPS- Enterprise Project Structure in P6 should mirror each other. Projects can be created in matching nodes. 7
Getting Them Linked Once the project structure is set up the two systems can be linked to share data. The project structure is integral to linking the systems. An Application Administrator should be responsible for setting up the link between the two systems, it requires some IT knowledge. 8
Getting The Projects Linked P6 Access the Admin Preferences in P6 to link to Contract Management & P6 Web. Click Admin Choose Admin Preferences Fill in the URL address for P6 Web Access the Options Tab Check the box for Contract Management & Choose version Fill in the URL address for Contract Management 9
Getting The Projects Linked P6 Access the Admin Preferences in P6 to link to Contract Management & P6 Web. Click Admin Choose Admin Preferences Fill in the URL address for P6 Web Access the Options Tab Check the box for Contract Management & Choose version Fill in the URL address for Contract Management 10
Getting The Projects Linked P6 (cont.) Select a project in P6 and click on the Contract Management tab. Click on a project Select the project from the Contract Management database Check box to link to Contract Management Select to access Contract Management Click to access the Contract Management database Type in the Contract Management ID and Password Click on the Contract Management tab 11
Getting The Projects Linked Contract Management Access the Project Settings from a project to link to a project in P6. Right Click on a project Select Project Settings to access the Schedule section 12
Getting The Projects Linked Contract Management Select the Database & Project from P6. Choose Primavera Select the database from the P6 database list Select the project from P6 13
Managing The Costs & Schedule Together Project Managers need the Costs & Schedule to be integrated between Contract Management & P6 to not duplicate data entry. Project Managers wantto to create all the Committed contracts in Contract Management with costs and import to P6 to create a summary cost loaded baseline schedule with dates. Subcontractorschedules can then be imported under the Summary activities. Managementwants to see the status of the project without knowing how to use Contract Management or P6. 14
Importing Contracts From Contract Management To P6 Use the Contracts module Committed or Budgeted. Importing a Contract creates an activity in P6 with a unique Activity ID. Costs from Contract Management are allocated to the Expense tab on the activity in P6. Cost Codes from Contract Management update the Cost Accounts list in P6. Otheruseful data is transferred from Contract Management such as Codes and Document links. 15
Create Cost Codes In Contract Management Enter Cost Codes in the Cost Worksheet module. Use the Add Cost Code button to add Cost Codes Import capability exists with Microsoft Excel. 16
Create Contracts In Contract Management Create a Contract and provide Cost and Contract name. Enter Cost data. SOV- Schedule of Values for Contract. Imports to Expense Tab in P6 Provide name of Contract. Imports as Activity Name in P6 17
Create Contracts In Contract Management (cont.) Enter cost data for contract and allocate to Cost Codes. Enter $ value for the total contract value Add Cost Codes and allocate $ value for each line item 18
Create Contracts In Contract Management (cont.) Enter the Schedule data in the Schedule Section of the Contract. Enter the Activity ID #. The # imports into P6 as the Activity ID Enter the dates for the Contract. They import as the Start & Finish dates for the Activity in P6 19
Create Contracts In Contract Management (cont.) Create all the Contracts to be imported into P6 as activities. Activity ID Activity Name Contract Activity Code Responsibility Activity Code Start Date/ End Date Budgeted Total Cost 20
Import Contracts Into P6 as Activities Schedule before the import of contracts from Contract Management - LOE 21
Importing Contracts & Other Documents Into P6 Select Import from Contract Manager from the File menu in P6 for a specific project. Select File from the Menu bar in P6 Choose Import from Contract Manager to bring up the selection menu screen 22
Importing Contracts & Other Documents Into P6 (cont.) Select the types of documents to import from Contract Management to P6. Select Import when finished make selections 23
Importing Contracts & Other Documents Into P6 (cont.) The Contract Manager Import Report will display all changes After review select the Commit Changes button 24
Import Contracts Into P6 As Activities Schedule after the import of contracts from Contract Management. 25
Import Contracts Into P6 As Activities (cont.) Schedule after the import of contracts from Contract Management 26
Imported Activities In P6 Costs are distributed to the Expenses tab in P6 from Contract Management Each Line Item from the Contract is added to the Expense tab 27
Summary Level Schedule With Costs Group by Contract and total the costs. Subcontractor schedules can be imported for each contract or trade performing work 28
Record Actual Cost With Payment Requisitions Generate a Payment Requisition from an existing contract. Record actual costs in the Schedule of Values section 29
Record Actual Cost With Payment Requisitions (cont.) Enter the billing amount and select the activity from the P6 schedule. Enter the billing amount for this period Select the Activity ID from the P6 Schedule Must be a 1 to 1 relationship with activity in P6 to update costs 30
Record Actual Cost With Payment Requisitions (cont.) Certify the Requisition to record Actual to Date costs. Requisition must be certified to update costs in P6 Schedule Contract is updated with Actual to Date Costs 31
Record Actual Cost With Payment Requisitions (cont.) Import the Schedule of Values into P6 from Contract Management to update costs. 32
Record Actual Cost With Payment Requisitions (cont.) Actual Costs are recorded on the activities assigned to the Payment Requisition. 33
Record Actual Cost With Payment Requisitions (cont.) Actual Costs can be viewed on the Expenses tab. 34
P6 R8.2 Web Dashboard 35
Access Contract, Cost & Schedule Data In P6 Web Add projects to the Personal Workspace to view Projects. Click on a project to access more detail 36
Access Contract, Cost & Schedule Data In P6 Web (cont.) Access the P6 schedule with the ability to modify activities in P6 Web. 37
Access Contract, Cost & Schedule Data In P6 Web (cont.) Access the Cost Worksheet from Contract Management in P6 Web. Click to open Contract Management from P6Web 38
P6 R8.2 Web Product Demonstration 39