Prof. Olivier de Weck



Similar documents
Techniques: CPM-PERT

Project Planning and Scheduling

Operational Research. Project Menagement Method by CPM/ PERT

Schedule Risk Analysis Simulator using Beta Distribution

ESD.36 System Project Management. Lecture 6. - Introduction to Project Dynamics. Instructor(s) Dr. James Lyneis. Copyright 2012 James M Lyneis.

Scheduling Resources and Costs

CPM-200: Principles of Schedule Management

Application Survey Paper

10 Project Management with PERT/CPM

Amajor benefit of Monte-Carlo schedule analysis is to

Quantitative Risk Analysis with Microsoft Project

Project management: a simulation-based optimization method for dynamic time-cost tradeoff decisions

MECH 896 Professional Development for MEng Students. Homework Discussion. Scheduling Overview. Winter 2015: Lecture #5 Project Time Management

CISC 322 Software Architecture. Project Scheduling (PERT/CPM) Ahmed E. Hassan

Chapter 11 Monte Carlo Simulation

Project Management SCM Pearson Education, Inc. publishing as Prentice Hall

Cambridge International AS and A Level Computer Science

Project Scheduling and Gantt Charts

Chapter 4: Project Time Management

ME 407 Mechanical Engineering Design Spring 2016

Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014

Lecture 4. Prof. Olivier de Weck

Scheduling Glossary Activity. A component of work performed during the course of a project.

PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM)

Project Time Management

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza

22 Project Management with PERT/CPM

Project Management Chapter 3

INT 3 Schedule Risk Analysis

Scheduling. Anne Banks Pidduck Adapted from John Musser

A UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST

Lecture 26 CPM / PERT Network Diagram

Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration

SE351a: Software Project & Process Management

Network Calculations

Project Scheduling: PERT/CPM

The work breakdown structure can be illustrated in a block diagram:

PROGRAM EVALUATION AND REVIEW TECHNIQUE (PERT)

USER S GUIDE for DSM@MIT

Chapter 6 (part 1) Project Time Management. (Project Scheduling)

Project Time Management

PROJECT RISK MANAGEMENT

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072

PROJECT COMPLETION PROBABILITY AFTER CRASHING PERT/CPM NETWORK

Project Scheduling: PERT/CPM

Schedule Risk Analysis Simplified 1 by David T. Hulett, Ph.D.

MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc.

Goals of the Unit. spm adolfo villafiorita - introduction to software project management

Project Management DISCUSSION QUESTIONS

Chapter 6: Project Time Management

Learning Objectives. Learning Objectives (continued) Importance of Project Schedules

Software Project Scheduling under Uncertainties

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

Lecture 6: Project Time Management By: Prof. Lili Saghafi. Information Technology Project Management, Fifth Edition

8. Project Time Management

SCHEDULING AND TIME MANAGEMENT. Project Management and Leadership 2015D, PhD, PMP

Network analysis: P.E.R.T,C.P.M & Resource Allocation Some important definition:

Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi

CRASHING-RISK-MODELING SOFTWARE (CRMS)

Module 11. Software Project Planning. Version 2 CSE IIT, Kharagpur

Project Time Management

MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc.

Should I Resource Load My Schedule?

SYSM 6304: Risk and Decision Analysis Lecture 5: Methods of Risk Analysis

Collaborative Scheduling using the CPM Method

Chapter 2: Project Time Management

PROJECT TIME MANAGEMENT

7. PROJECT MANAGEMENT

pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

Module 3: The Project Planning Stage

Chapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False

Use project management tools

State-Based Probabilistic Scheduling Using STROBOSCOPE s CPM Add-On

Scope management can be defined as controlling what is and what is not a part of the project.

Project Scheduling. Introduction

PERT/CPM. Network Representation:

A SIMULATION MODEL FOR RESOURCE CONSTRAINED SCHEDULING OF MULTIPLE PROJECTS

Dashboards and Reporting for Program Management

Application of Critical Path Method scheduling to research plan and management of graduate students research project in engineering education

A. O. Odior Department of Production Engineering University of Benin, Edo State.

CRASHING PERT NETWORKS: A SIMULATION APPROACH

B D E F

Chapter-6. Developing a Project Plan

Project Management Glossary

A Robustness Simulation Method of Project Schedule based on the Monte Carlo Method

Project Time Management

A Generalized PERT/CPM Implementation in a Spreadsheet

PMP : Project Management Professional Study Guide Kim Heldman

Network Planning and Analysis

Risk Review Process Basics

PROJECT PROPOSAL: PROJECT BLUE ZUMA

Simulation and Lean Six Sigma

CSSE 372 Software Project Management: Software Project Scheduling

Time Management. Part 5 Schedule Development. Richard Boser

02 Project planning. There are two approaches to identifying the components of a project: productbased and work- or activity-based.

Transcription:

ESD.36 System Project Management + Lecture 9 Probabilistic Scheduling Instructor(s) Prof. Olivier de Weck Dr. James Lyneis October 4, 2012

Today s Agenda Probabilistic Task Times PERT (Program Evaluation and Review Technique) Monte Carlo Simulation Signal Flow Graph Method System Dynamics 2

Task Representations Tasks as Nodes of a Graph Circles Boxes A,5 Tasks as Arcs of a Graph Tasks are unidirectional arrows ID:A Nodes now represent states of a project KelleyWalker form ES LS EF Dur:5 LF broken A, 5 fixed 3

Task Times Detail Task i ES(i) LS(i) Duration t(i) Total Slack TS(i) FS(i) Free Slack EF(i) Duration t(i) ES(j) LF(i) j is the immediate successor of i with the smallest ES j>i Free Slack (FS) is the amount a job can be delayed without delaying the Early Start (ES) of any other job. FS<=TS always 4

How long does a task take? Conduct a small inclass experiment Fold MIT paper airplane Have sheet & paper clip ready in front of you Paper airplane type will be announced, e.g. A1B1C1D1 Build plane, focus on quality rather than speed Note the completion time in seconds +/ 5 [sec] Plot results for class and discuss Submit your task time online, e.g. 120 sec We will build a histogram and show results 5

MIT Paper Airplane Courtesy of Steven D. Eppinger. Used with permission. Credit: Steve Eppinger 6

Concept Question 1 How long did it take you to complete your paper airplane (round up or down)? 25 sec 50 sec 75 sec 100 sec 125 sec 150 sec 175 sec 200 sec 225 sec > 225 sec 7

MIT Class Results (2008) Beta Distribution parameters: a=2.27, b=5.26 8

Discussion Point 1 Job task durations are stochastic in reality Actual duration affected by Individual skills Learning curves what else? Why is the distribution not symmetric (Gaussian)? Project Task i 15 Frequency 10 5 0 10 15 20 25 30 35 40 completion time [days] 9

Today s Agenda Probabilistic Task Times PERT (Program Evaluation and Review Technique) Monte Carlo Simulation Signal Flow Graph Method System Dynamics 10

PERT PERT invented in 1958 for U.S Navy Polaris Project (BAH) Similar to CPM Treats task times probabilistically 10 B t=4 mo A t=3 mo 20 30 t=1 mo t=3 mo Original PERT chart used activityonarc convention C E t=2 mo D F 40 50 t=3 mo Image by MIT OpenCourseWare. 11

CPM vs PERT Difference how task duration is treated: CPM assumes time estimates are deterministic Obtain task duration from previous projects Suitable for implementation type projects PERT treats durations as probabilistic PERT = CPM + probabilistic task times Better for uncertain and new projects Limited previous data to estimate time durations Captures schedule (and implicitly some cost) risk 12

PERT Task time durations are treated as uncertain A optimistic time estimate minimum time in which the task could be completed everything has to go right M most likely task duration task duration under normal working conditions most frequent task duration based on past experience B pessimistic time estimate time required under particularly bad circumstances most difficult to estimate, includes unexpected delays should be exceeded no more than 1% of the time 13

AMB Time Estimates Project Task i Range of Possible Times 15 Frequency 10 5 0 10 15 20 25 30 35 40 times completion time [days] Time A Time M Time B Assume a Betadistribution 14

BetaDistribution All values are enclosed within interval As classes get finer arrive at bdistribution Statistical distribution pdf: t A, B Beta function: x 0,1 15

MIT Class Results (2008) Beta Distribution parameters: a=2.27, b=5.26 16

Expected Time & Variance Estimated Based on A, M & B Mean expected Time (TE) TE Time Variance (TV) 2 B A TV t 6 Early Finish (EF) and Late Finish (LF) computed as for CPM with TE Set T=F for the end of the project A 4 M B Example: A=3 weeks, B=7 weeks, M=5 weeks > then TE=5 weeks 6 2 17

What Can We Do With This? Compute probability distribution for project finish Determine likelihood of making a specific target date Identify paths for buffers and reserves 18

Probability Distribution for Finish Date PERT treats task times as probabilistic Individual task durations are bdistributed Simplify by estimating A, B and C times Sums of multiple tasks are normally distributed Normal Distribution for F See draft textbook Chapter 2, second half, for details of calculations. Time E[EF(n)]=F 19

Probability of meeting target? Many Projects have target completion dates, T Interplanetary mission launch windows 34 days Contractual delivery dates involving financial incentives or penalties Timed product releases (e.g. Holiday season) Finish construction projects before winter starts Analyze expected Finish F relative to T Normal Distribution for F Probability that project will be done at or before T T E[EF(n)]=F Time 20

Probabilistic Slack Target date for a tasks is not met when SL(i)<0, i.e. negative slack occurs Put buffers in paths with high probability of negative slack Normal (Gaussian) Distribution for Slack SL(i) SL(i) Time 21

Experiences with PERT? 22

Today s Agenda Probabilistic Task Times PERT (Program Evaluation and Review Technique) Monte Carlo Simulation Signal Flow Graph Method System Dynamics 23

Project Simulation (from Lecture 5) Panel Design Panel Data Die Design Image removed due to copyright restrictions. Die Geometry Manufacturability Evaluation Verification Data Analysis Results Analysis Results Surface Data Prototype Die Production Die Die Geometry Verification Data Surface Data Surface Data Surface Modeling Die Design and Manufacturing Highly Iterative Process how often is each task carried out? how long to complete? Steven D. Eppinger, Murthy V. Nukala, and Daniel E. Whitney. "Generalised Models of Design Iteration Using Signal Flow Graphs", Research in Engineering Design. vol. 9, no. 2, pp. 112123, 1997. 24

Signal Flow Graph Model: Stamping Die Development 25

Computed Distribution of Die Development Timing 30 25 36.97 Simulation: 100 Runs Estimate likely completion time 20 Occurences 15 10 What else can we do with the simulation? 5 0 0 20 40 60 80 100 120 Project Duration [days] 26

Process Redesign/Refinement Die Prelim. M fg. Die Prelim. M fg. D ie Start 0.75 z 2 z 2 z 1 z 3 Design1 z 3 Eval.1 Design2 Eval.2 Design3 1 2 3 4 5 6 0.25 z 1 0.25 z 2 Init. Surf. M odeling 7 0. 7 5 z 2 0.1 z 1 1 z Most likely path 0.9 z 3 0. 5 Final Surf. M odeling z 7 0.5 8 9 10 Final M fg. Eval. Finish 27

Whatif analysis Spend more time on die design (1): Increase time spent on initial die design (1) from 3 to 6 days Increase likelihood of going to Initial Surface Modeling (7) from 0.25 to 0.75 Is this worthwhile doing? Original E[F]=37 days New E[F]= 37 days no real effect! Why? Spend more time on final surface modeling (8): Increase time for that task from 7 to 10 days Increase likelihood of Finishing from 0.5 to 0.75 New E[F] = 30.8 days Why is this happening? 28

New Project Duration 500 Simulation: 1000 Runs 450 400 Occurences 350 300 250 200 30.796 New distribution of Finish time 150 100 50 0 20 30 40 50 60 70 80 90 100 110 120 Project Duration [days] 29

Applying Project Simulation to HumLog Distribution Center Project (From Lecture 4) Source unknown. All rights reserved. This content is excluded from our Creative Commons license. For more information, see http://ocw.mit.edu/fairuse. 30

0 4 1 2 0 4 Start Simulation Application to HumLog DC 4 6 6 14 3 2 4 6 4 2 APlanning (14) Simplify project into 7 major steps 5 8 DStaffing (7) 14 18 6 7 8 9 10 11 4 2 1 2 2 3 32 34 28 32 44 44 22 FCommissioning (5) BContracting (9) 18 20 20 21 21 23 23 25 23 29 13 6 29 30 19 1 43 44 21 1 34 36 15 16 18 20 2 14 12 4 17 2 2 1 36 39 4 3 39 43 CConstruction (11) 25 28 34 36 34 35 EInstallation (5) 31

Signal Flow Graph (with iterations) Add uncertain rework loops replanning loop Construction 0.2z 3 Installation 0.25z 7 0.25z 11 Start A B z 9 4 z C 11 5 z 5 1 6 0.8z D 5 7 fix construction errors loop z 14 2 3 D E Planning Contracting 0.5z 7 Staffing End Commissioning sequential staffing state in red 32

HumLog Simulation Results Expected Duration: 56 weeks Shortest Duration: 44 weeks In some cases duration can exceed 100 weeks! 33

Concept Question 2 What is your opinion of these long tails in project schedule distributions? I don t think they are real. This is a simulation artifact. Yes, they exist. I have experienced this. This is only relevant for projects that deal with very new products or extreme environments. I m not sure. I don t care. 34

System Dynamics Simulation Can carry out MonteCarlo Simulations with System Dynamics Vary key model parameters such as fraction correct and complete, productivity, rework discovery fraction, number of staff etc Assume distributions for these parameters Obtain insights into potential distribution of Time to completion, required staffing levels, error rates, project cost Improve planning and adaptation of projects, and confidence in claim numbers 35

Example Model without project control from last class and HW#3 Probabilistic Simulations: Normal Productivity uniform distribution (0.9 1.1) Normal Fraction Correct and Complete uniform distribution (0.75 0.95) 36

Results for project finish Individual simulations Confidence bounds Class3 Q on Q Probabilistic Work Done 1,000 Class3 Q on Q Probabilistic 50% 75% 95% 100% Work Done 1,000 750 750 500 500 250 250 0 0 15 30 45 60 Time (Month) 0 0 15 30 45 60 Time (Month) Distribution skewed to later finish 37

Results for project cost Individual simulations Confidence bounds Class3 Q on Q Probabilistic Cumulative Effort Expended 4,000 Class3 Q on Q Probabilistic 50% 75% 95% 100% Cumulative Effort Expended 4,000 3,000 3,000 2,000 2,000 1,000 1,000 0 0 15 30 45 60 Time (Month) 0 0 15 30 45 60 Time (Month) 38

Monte Carlo and SD Use in planning and adaptation: Size and timing (fraction compete) of buffers Timing of project milestones Important use in specifying confidence bands in a claim situation for distribution of cost overrun due to client (owner) Fit constrained only simulations which fit the data can be accepted Graham AK, Choi CY, Mullen TW. 2002. Using fitconstrained Monte Carlo trials to quantify confidence in simulation model outcomes. Proceedings of the 35th Annual Hawaii Conference on Systems Sciences. IEEE: Los Alamitos, Calif. (Available on request) 39

Usefulness of PERT and Simulation Account for task duration uncertainties Optimistic Schedule Expected Schedule Pessimistic Schedule Helps set time reserves (buffers) Compute probability of meeting target dates when talking to management, donors Identify and carefully manage critical parts of the schedule 40

Reading List Project Management Book Systems Engineering: Principles, Methods and Tools for System Design and Management de Weck, Crawley and Haberfellner (eds.), Springer 2010 (draft) textbook to support SDM core classes at MIT About 200 pages Selected Article Steven D. Eppinger, Murthy V. Nukala, and Daniel E. Whitney. "Generalised Models of Design Iteration Using Signal Flow Graphs", Research in Engineering Design. vol. 9, no. 2, pp. 112123, 1997. For this lecture, please read: Chapter Network Planning Techniques Second Half of Chapter 41

MIT OpenCourseWare http://ocw.mit.edu ESD. Fall 2012 For inforation about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms.