P.O. Box 416 Winlock WA 98596 360-880-8804 http://jstridpe.com julius10@mac.com

Similar documents
C O N S U L T A N T S RESUME

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

Meeting the Challenge of Pipeline Emergency Repair

Cost Estimating Procedures for Raw Sewage Overflow Control Program

WEFTEC.06. Kent Von Aspern,* Collins Orton** *Carollo Engineers 2700 Ygnacio Valley Rd Suite 300 Walnut Creek, CA 94598

SECTION POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

Annular Space Grouting of Slipline Products

CCU Engineering Specifications. Section PRECAST CONCRETE PRODUCTS

ENGINEERED FOUNDATIONS. Department of Public Works Jeff Hill, PE

RESUME Lee A. Knuppel, P.E.

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

Emerging Technologies in Wastewater Collection Systems

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils

Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair

Beacon Hill Sewer District Standard Specifications

Moving Small Mountains Vesuvius Dam Rehab

SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT

SECTION STORM DRAIN SYSTEM

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

LOWER NORTH OUTFALL SEWER AND NORTH OUTFALL SEWER REHABILITATION USING AMERON S T HAB METHOD

Dewatering - Time and Cost Relief by way of Trenchless Construction

See Appendix A for additional information, or contact ASTM directly.

Jackson Gulch Outlet Canal Rehabilitation Project

High-Rate Retention Treatment Facility for CSO Control in Windsor Riverfront East

SECTION STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

The Manitoba Water Services Board SECTION Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11

Technical Memorandum Cost Criteria for 2010 System Capacity Plan

CHAPTER VII CONSTRUCTION QUALITY CONTROL INSPECTION PROGRAM 1

Wastewater Capital Projects Management Standard Construction Specification

Tunnelling and underground works in PPC hydro projects: Contracting practices & construction management Ioannis Thanopoulos Dr.

ONSITE SEWAGE TREATMENT AND DISPOSAL SYSTEM REQUIREMENTS

Table 4.9 Storm Drain Inlet Protetion Applicable for

STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION

BUTE Department of Construction Management and Technology

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

Ameren Callaway Energy Center-Water Treatment Plant Sedimentation Basins #5 &#6, MO , Construction Permit No. CP , Callaway County

SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA (7300 Short Road, Serene Lakes)

4.3 Cisterns and Rain Barrels

CHAPTER 8 CIVIL DESIGN

Repairs Made With Under Pressure Installations Can Offer Reduced Risks And Expenses

Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

Stormwater/Wetland Pond Construction Inspection Checklist

PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE

BLADDER SURGE CONTROL SYSTEM

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

How To Install An Overhead Sewer

Source Water Protection Practices Bulletin Managing Sanitary Sewer Overflows and Combined Sewer Overflows to Prevent Contamination of Drinking Water

ITEM # OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

Well Records and Maintenance Guidelines

BEFORE THE PHILADELPHIA WATER, SEWER AND STORMWATER RATE BOARD DIRECT TESTIMONY OF STEPHEN J. FURTEK

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM

How To Build The New Irvington Tunnel

The Donut Hole Sunset The San Francisco-Pacifica Exclusion Zone

Section 2100-Trenching and Tunneling

How To Preserve Trees

Baton Rouge Foundation Repair

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

A HOMEOWNERS GUIDE ON-SITE SEWAGE MANAGEMENT SYSTEMS

San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS

APPENDIX M-2 SANITARY SEWER TECHNICAL MEMORANDUM. Stadium Reconstruction EIR

Los Angeles County Department Of Public Works. Land Development Division. Bond Calculation Sheets

SECTION ABANDONMENT OF SEWER MAINS

Geotechnical Building Works (GBW) Submission Requirements

Contractor of the Year

CHAPTER 11 STORM DRAINAGE

APPENDIX F. Baker County. Mason Dam Hydroelectric Project FERC No. P Turbidity Monitoring Plan

Pipe Bursting. Case Study at Zeeland, MI Collections Seminar September 6, Presentation Agenda. What is Pipe Bursting? What is Pipe Bursting?

Tunnelling & Underground. Specialists

Type of Sewer Systems. Solomon Seyoum

Installation of Large Diameter Buried Pipes

SUFFOLK COUNTY DEPARTMENT OF HEALTH SERVICES TOXIC/HAZARDOUS MATERIAL TRANSFER FACILITY DESIGN GUIDELINES

Index. protection. excavated drop inlet protection (Temporary) Block and gravel inlet Protection (Temporary)

Section Installation of pipe and casing for sanitary sewer by methods of augering.

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge.

SECTION EARTH MOVING

FY08 SEWER POINT REPAIRS BID TABULATION

Suffolk County Department of Health Services. Division of Environmental Quality

DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY. a guide to PREVENTING SEWER BACKUPS AND FLOODING

IH-635 MANAGED LANES PROJECT, SEG. 3.2

San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION

Wastewater Collection Practice Test #3 Page 1 of 15

Specifications for Residential Property Owners Connection to New Public Sewer

Glen Hills Area: Septic System and Public Sewer Q & A Information Sheet Page 1

COLORADO DEPARTMENT OF TRANSPORTATION STORMWATER FIELD INSPECTION REPORT - ACTIVE CONSTRUCTION

SECTION PUBLIC STORM UTILITY DRAINAGE PIPING

DEPARTMENT OF ENVIRONMENTAL QUALITY

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING

WHO WE ARE FOUNDATION REPAIR

SE-10 STORM DRAIN INLET PROTECTION. Objectives

Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects

Transcription:

P.O. Box 416 Winlock WA 98596 360-880-8804 http://jstridpe.com julius10@mac.com Education: B.S., Mining Engineering, South Dakota School of Mines, 1980 Registration: Registered Engineer Washington State, Past registrations Oregon and Arizona Affiliations/Certifications: Member, American Society of Mining Engineers (AIME/SME) Member, American Society of Civil Engineers (ASCE) Publications: Setting the Owner s Budget A Guideline ; P. Gribbon, J. Strid, NAT Portland, June 2010. Risk Management to Make Informed Contingency-Based CIP Decisions ; P. Gribbon, G. Colzani, C. Overby, J. Strid. NAT Portland, June 2010. Portland, Oregon s Alternative Contract Approach A Final Summary ; P. Gribbon, G. Colzani, J. Strid, J. McDonald, RETC Toronto, June 2007. Tunneling at Hollywood Reservoir ; G. Colzani, J. Strid, S. Cole, D. Olsen, RETC, San Diego, June 2001. Construction of the Hollywood Water Quality Improvement Project ; J. Strid, S. Cole, R. Harasick, E. Hartman, G. Colzani, R. Miller, North American Tunneling 2000, Boston. Overcoming Difficult Ground Conditions in San Francisco The Richmond Transport Tunnel San Francisco County, California ; S. Klein, M. Kobler, J. Strid, Engineering Geology Practice in Northern California 2001. Keys to Successful Construction Management in Underground Engineering, G. Sherry, R. Henn, J. Strid, North American Tunneling, 1996 Balkema, Rotterdam Richmond Transport [San Francisco] ; J. Strid, M. Kobler, S. Maiolini, World Tunneling, London, March 1995, pp. N5-N8. " Page 1 of 6

Years of Experience: 32 Julius Strid has over 30 years of practical on-site experience in heavy construction for tunnels, dams, mining, and airport construction. His extensive tunnel experience includes both soft and hard ground tunneling using shields, tunnel boring machines, drill and blast, and conventional hand mining. Julius Strid has been involved with dispute resolution, primarily through problem solving at project level, but also as an expert witness, project DRBs, and negotiations of changes. Julius M. Strid, P.E. - Consultant Expert Witness - Expert review and testimony of damages portion of claim on the Brightwater Tunnel, King County, Seattle, WA. Warranty Work - Construction Manager for repair of flex couplings on the Swan Island Pump Station, City of Portland, Bureau of Environmental Services. Quality Assurance - New Irvington Tunnel, San Francisco PUC. Willamette River CSO Tunnel Program $1.4 billion: Swan Island Pump Station Phase 2 $9 million, 2009-2011 Construction Manager: This is the second phase of construction for the very large 210 MGD underground Swan Island Pump Station. Phase 2 consisted of installing 3 large pumps, motors, VFDs, and the associated piping, and mechanical and electrical equipment necessary to complete the pump station. The shaft and first phase pumps were completed previously as part of the West Side CSO Tunnel. As the construction manager, supervised the QA system for the owner including coordination of inspection for certified welding of steel piping at the fabricators, shored excavation, installation of the piping and valves, structural pipe supports, structural steel, mechanical systems, electrical system, instrumentation and controls. ESCSO Tunnel, Portland, OR, $450 million, 2005-2011 Project Estimator/Project Controls Manager: Responsibilities are similar to those for the WSCSO, see below. The project used the same contract model, Cost-Reimbursable- Fixed-Fee as done for the WSCSO. This is a unique alternate contract method suitable for high-risk construction projects which successfully eliminated all claims and disputes for both projects. The entire program was completed on-time and under-budget with no outstanding contractual issues and no claims. The project contains 6 miles of 22-ft diameter sewage conveyance/storage tunnel and 6,000 linear feet of small diameter tunnels. The Eastside CSO tunnel tops the Westside CSO tunnel as the largest slurry boring machine excavated tunnel in North America. The project includes 7 large shafts and several very difficult connections to live sewers. The pre-construction phase contract began in July 2005. The project was completed in December 2011. " Page 2 of 6

WSCSO Tunnel, Portland, OR, $300 million, 2001-2006 Project Estimator/Project Controls Manager: Responsible for estimating during the preconstruction phase for the City of Portland. Responsibilities during construction were management of the controls system for this cost-reimbursable-fixed-fee project. The City selected this style of contract due to the difficult nature of the ground conditions and potential risks. The contractor was selected by qualifications and the construction contract price was based upon and estimated reimbursable cost. As controls manager, confirmed actual work quantities with the inspectors and monitored the projects costs of the QA and QC system. The project involves 18,000 linear feet of large diameter sewage conveyance/storage tunnel, 8,000 linear feet of small diameter tunnels, very large diameter shafts, appurtenant drop structures, gravity conduits, force mains, and a large wastewater pump station. Ground conditions were saturated alluvial soils next to the Willamette River. This is one of the most difficult soft ground tunnel projects ever attempted in North America and was the largest slurry boring machine excavated tunnel in North America at the time. The project includes 5 large shafts in saturated sands and gravels, including the 130-foot deep, 160-foot diameter pump station shaft housing the Swan Island Pump Station. The construction contract began in 2002 and was completed on time and on budget in 2006. Port of Seattle, SeaTac Airport, SeaTac, WA, several projects $5,000 to $200,000 2001 Construction Manager: Construction Manager for the Port Construction Services division of the Port of Seattle. This owner run construction department is a part of the Port of Seattle that constructs small projects for the airport and marine port. The Construction Services division does about $20 million in construction each year. Responsible for several projects associated with the $6 billion expansion of the SeaTac Airport, including the US Airways Baggage Office and the South Security Gate reconstruction, which were a part of the South Terminal Expansion Project. Hollywood Water Quality Improvement Project, Los Angeles, CA, $ 110 million, 1998-2001 Project Engineer: Performed construction management services for this $110 million reservoir tank and tunnel project. Responsible for the construction management staff representing the Department of Water and Power, including all change order estimates for negotiations. This project is in the heart of urban Hollywood in a very environmentally sensitive area. The tanks are world-class size underground water storage tanks, 30 million gallons each. The tank excavation site was shored with an extensive system of soldier piles and tiebacks and a slurry wall. The total volume of excavations for the tanks was 1 million cubic yards. There are 6 tunnels on the project, the largest 10-foot diameter, 1 mile long, with a shaft and underground connection to an existing feeder tunnel. The ground conditions were Topanga Formation consisting of inter-bedded, faulted, and folded sandstones and shales and intrusive basalt. All of the tunnels were successfully driven using tunnel-boring machines, except for the hand- " Page 3 of 6

mined Weid connection tunnel and the storm drain tunnel. Responsible for the inspection team quality assurance including coordination of certified welding inspection of the 72-inc steel pipe, inspection of the manufacture and coating of the steel pipe at the fabricator, inspection of the tunnel excavation, installation of the shoring system, concrete structures, and installation of very large steel piping and valves. Priest Reservoir Bypass Tunnel, Moccasin, CA, $10 million, 1997 Tunnel Engineer: Provided peer design review for a 2,500-linear foot hard rock drill and blast tunnel and three shafts for construction of a bypass on the Hetch Hetchy water supply system for the City and County of San Francisco. Responsibilities also included cost estimates and schedules preparations. Thomas Shaft Sampling Wells, San Francisco, CA, $1 million, 1997 Tunnel Engineer: Responsible for the preparation of target cost and contract schedule. This project consisted of design for a sampling well tying into the Coast Range Tunnel to monitor water quality. This well was designed to be installed from the ground surface using state-of-the-art directional drilling methods to make a blind connection the tunnel. The depth to the tunnel crown is 300 feet through Franciscan Formation sandstones and shales. Zoo Wet Weather Lift Station, San Francisco, CA, $8 million, 1996-1997 Resident Engineer: Responsible for inspection and contract administration of the pump station. This project contained a tunnel in saturated beach sands driven by dewatering, pipe jacking and the use of a TBM. The lift station was a large underground concrete structure containing 5 large submersible pumps. An above ground utility building was constructed to house the electrical and mechanical systems for the pumps. Seacliff Slope Restoration and Sewer Repair, San Francisco, CA, $6 million, 1997 Resident Engineer: Managed the design and construction during emergency repair of a 100-year-old brick sewer. The work consisted of design and construction of an underground vortex drop shaft, deareation structure and tie-in to the existing tunnel. The 50-foot deep excavation was supported using extensive soldier pile walls tied back at three levels. The $6-million fast-track construction project was completed in three months during a tight schedule controlled by the need to complete the repair before the next wet weather season. Supervised the field inspection team during excavation, installation of fiber reinforced piping, reinforced concrete pipe, and a large underground concrete connection structure. Richmond Transport Facilities, San Francisco, CA, $33 million, 1994-1996 Resident Engineer: Responsible for field and office engineering, project management, cost estimating and construction scheduling, processing of contractor submittals, change orders and contractor progress payments. Supervised the inspection team during construction of the cast-in-place concrete tunnel lining, connection structures, and piping systems. " Page 4 of 6

This project consisted of 10,200-feet of 14-foot diameter tunnel driven through hard rock, fill dune sands and Colma formation sands. The soft ground portion of the tunnel was mined using an open-faced digger shield, in conjunction with chemical and compaction grout to control surface settlement. The hard rock section utilized a fully shielded tunnel-boring machine to mine through brecciated shales, sandstone, serpentinite, chert, and gouge material. Drill and blast methods were used to mine 800- feet of 12-foot horseshoe incline and decline tunnel and an overflow chamber. Over 6,000 linear feet of 36-inch, 42-inch and 120-inch RCP sewer line were installed, along with concrete structures and weirs. Lake Merced Transport, San Francisco, CA, $22 million, 1993 Project Engineer/Senior Inspector: Responsibilities included office engineering and inspection during the construction of 8,500 linear feet of 14-foot diameter tunnel in saturated beach and dune sands, Colma formation and Merced formation using an open-faced shield. Inspected the rebar installation and setting of forms for the cast-inplace concrete tunnel lining. The project also included hand mining a 10-foot diameter; steel rib and spiling supported tunnel, construction of a transition structure, an overflow structure and an architectural building. Duties included processing submittals, change order estimates and progress payments, inspecting and reporting construction activities and monitoring of instrumentation and dewatering programs. Mr. Strid was responsible for inspection of final concrete lining. The concrete was batched on-site for all of the lining and structures. Also responsible for all closeout claims and change orders. Consultant Engineer - Various Projects, 1990-1992 WA, FL, NV, AZ, WV Claim resolution, expert witness. Mine design Floridin Mine, Big Mike Mine. Surface Water runoff retention system, Superintendent conveyor system. Mt. St. Helens Sediment Retention Dam, Toutle, WA, $70 million, 1987-1989 Project Engineer/Contract Administrator: Responsible for development of claims for differing site conditions, embankment engineer, grout plan and implementation, scheduling, progress payments, change orders, blasting engineer and structures engineer. This project was a $70 million dam constructed for the Army Corps of Engineers to trap volcanic sediment from Mt. St. Helens. The dam is composed of 15 million cubic yards of silty clay impervious core and andesitic basalt rock embankment and 80,000 cubic yards of concrete outlet works. Papago Storm Drain Tunnels, Phoenix, AZ, $70 million, 1984-1987 Assistant Resident Engineer: Provided construction administration, inspection and project engineering for three large tunnels ranging from 14-ft to 26-ft diameter. All were driven with shielded machines through soft ground composed of sands, gravels, and cobbles. Duties included construction management and contract administration for all phases of the project. This included developing computer documentation methods, coordination inspection, overseeing survey of control, incorporating change order " Page 5 of 6

estimates, value engineering, development of state of the art compaction grouting methods, analyzing claims, evaluation of geological conditions and interpreting geotechnical instrumentation data. Engineer - Various Tunnel Projects, Rockville, MD, 1983-1984 Tunnel Engineer: Worked on design and construction claims evaluation for several tunnels. Three Rivers Water Quality Management Program, Atlanta, GA, $30 million, 1982-1983 Office Engineer: Responsible for office engineering duties and assisted in evaluation of contractor claims. This project entailed 6-miles of tunnels and 2,000-feet of large diameter pipeline. The tunnel was 10-feet in diameter with the majority driven through hard rock with a TBM. A 2-mile portion was mixed face and mined using drill and blast methods. Antelope Valley Raw Water Intake Tunnel and Shafts, Beulah, ND, $15 million, 1980-1982 Office Engineer: Responsible for all office engineering duties during change of contractors for this lake-tap tunnel and shafts project. The shafts were 300-feet deep, the off-shore shaft was constructed in 70-feet of water. The on-shore shaft included a large 100-foot deep caisson and, at the time, the world s largest auger bored shaft (12 ft diameter). The 3,000 linear feet of single-pass segmental concrete lined tunnel was constructed in soft ground using a fully shielded TBM. " Page 6 of 6