Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation



Similar documents
USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

The International Workshop on Micropiles, 2007

UNDERPINNING OF NEW STUDENT HOUSING BUILDING USING MICROPILES, NORTH CAROLINA USA

PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE

Safe & Sound Bridge Terminology

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

SECTION 1 GENERAL REQUIREMENTS

Design and Construction of Auger Cast Piles

System. Stability. Security. Integrity. 150 Helical Anchor

METHOD OF STATEMENT FOR STATIC LOADING TEST

LEGACY REPORT ER ICC Evaluation Service, Inc. Reissued November 1, Legacy report on the 1997 Uniform Building Code

Outline MICROPILES SUBJECT TO LATERAL LOADING. Dr. Jesús Gómez, P.E.

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations

ITEM # OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils

Stability. Security. Integrity.

SECTION 411 DRILLED PIERS

How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No May 15, 2013

IH-635 MANAGED LANES PROJECT, SEG. 3.2

How to Design and Build a Fence/G traverse Bridge or Graffiti Project

SECTION ABANDONMENT OF SEWER MAINS

Section 2100-Trenching and Tunneling

Dr. Jesús Gómez, P.E. 36th Annual Conference on Deep Foundations, Boston, MA

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM

CHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE

GEORGE J. CAMBOURAKIS, P.E., C. ENG. PRESIDENT & CHIEF STRUCTURAL ENGINEER

Comprehensive Design Example 2: Foundations for Bulk Storage Facility

Section Installation of pipe and casing for sanitary sewer by methods of augering.

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

Pro-Lift Steel Pile Foundation Repair

SUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors.

Page B-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2014 LOAD TESTS

SECTION SHEETING, SHORING AND BRACING

Load Testing of Drilled Shaft Foundations in Limestone, Nashville, TN Dan Brown, P.E., Ph.D.

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

VERTICAL MICROPILE LATERAL LOADING. Andy Baxter, P.G.

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska

High Strain Dynamic Load Testing of Drilled Shafts

SECTION SUPPORT OF EXCAVATION

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

US 51 Ohio River Bridge Engineering and Environmental Study

MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS

California Department of Transportation Doyle Drive Test Program Contract No. 04A3362

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge.

MICROPILE FOUNDATIONS IN KARST: STATIC AND DYNAMIC TESTING VARIABILITY

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

ATLAS RESISTANCE Pier Foundation Systems

GLOSSARY OF TERMINOLOGY

6 RETROFITTING POST & PIER HOUSES

San Antonio Water System Standard Specifications for Construction ITEM NO SLIP-LINING SANITARY SEWERS

BRIDGES ARE relatively expensive but often are

SECTION 10 WATER WELL SUPPLY SCOPE OF WORK

Methods of Soft Ground Improvement

Informational Workshop Public Meeting Kanawha Falls Bridge Project

REHABILITATION PACKAGE 1-a

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL

The unit costs are based on the trend line of the 3 low bids for the average quantity.

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT

DESIGNING STRUCTURES IN EXPANSIVE CLAY

SECTION ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section Submittals.

San Francisco Oakland Bay Bridge East Span Seismic Safety Project

HIGH TENSION CABLE BARRIER

Rehabilitation of the Red Bank Road Bridge over Hoover Reservoir. Presented By: Doug Stachler, P.E.

FY08 SEWER POINT REPAIRS BID TABULATION

Design of Bridges. Introduction. 3 rd to 4 th July Lecture for SPIN Training at the University of Dar es Salaam

High Capacity Helical Piles Limited Access Projects

SECTION PUBLIC STORM UTILITY DRAINAGE PIPING

Step 11 Static Load Testing

Dead load (kentledge) A structure over the test pile. Ground anchorage either by tension piles or ground anchors. Bi-directional (Osterberg-cell)

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13)

STATIC PILE LOAD TEST MANUAL. GEOTECHNICAL CONTROL PROCEDURE GCP-18 Revision #4

Wastewater Capital Projects Management Standard Construction Specification

ENGINEERED FOUNDATIONS. Department of Public Works Jeff Hill, PE

The Installation and Load Testing of Drilled Shafts

San Antonio Water System Standard Specifications for Construction ITEM NO POINT REPAIRS AND OBSTRUCTION REMOVALS

LS 2540 SEWER LATERALS AND INSPECTION TEES

SECTION 700 STRUCTURES SECTION 701 DRIVEN PILING MATERIALS Materials Materials shall be in accordance with the following:

Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair

DIVISION 4300 STORM DRAINAGE

Sewer Rehabilitation Design Requirements

San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS

Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI

Ecoflex Wall Penetration Systems: An efficient, sustainable solution for penetrating concrete or block walls

Emergency repair of Bridge B421

SECTION EARTH MOVING

ENCE 4610 Foundation Analysis and Design

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)

Geotechnical Building Works (GBW) Submission Requirements

1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona

Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC October 27, 2015 Session 26

Chapter 3 Pre-Installation, Foundations and Piers

Moving Small Mountains Vesuvius Dam Rehab

TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe

High Density Polyethylene Liners for Rehabilitation of Corroded Pipelines

Transcription:

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 JRHill@HaywardBaker.com Aaron C. Kober, P.E. Modjeski & Masters, Inc. 804 North First Street St. Louis, MO 63102 314-588-8115 ACKober@Modjeski.com Background & Geotechnical Profile The Merchant Railroad Bridge crosses the Mississippi River in St. Louis, Missouri and has been in continuous service since its construction in the 1890s. In order to extend its life for another century, the Owner has implemented plans for rehabilitation and reconstruction of the structure. This work includes immediate replacement of the East and West Approach deck truss spans with new deck girder spans supported atop concrete piers and founded on deep foundations with rock sockets. Foundation and substructure work was required to be completed without removing the existing spans in order to reduce the amount of track down time. The initial design called for concrete drilled shaft foundations, extending to bedrock. However, since the new foundation work had to be performed beneath the existing structure with available headroom of less than 30 feet, drilled shafts presented an expensive foundation option. The geotechnical profile, typical of soil conditions along the Mississippi River at the North side of St. Louis, consists of: 0 to 40 ft: Silty alluvial-deposited sands/clays (very loose) 40 to 80 ft: Sands (denser with depth) 80 to 85 ft: Weathered Limestone 85: Solid Limestone bedrock Micropile Value Engineering Proposal The micropile contractor, working closely with the Owner and their structural engineer, proposed the use of micropiles as an economic alternative to drilled shaft foundations for the replacement structures. Micropiles offered several advantages over drilled shafts at this site. Micropile drill rigs are specifically designed for working in low headroom and tight access conditions. Consequently, the ability to work with low headroom proved to be very beneficial for this project. Micropiles can economically drill through debris such as urban fill more easily than drilled shafts. Micropiles can also be installed with rock cutting bits, which will drill the rock sockets more efficiently than coring with a 36-inch diameter core barrel. One final advantage offered by the micropiles is that the smaller diameter enables installation in closer proximity to existing utilities.

At certain micropile locations on this site, installation of a drilled shaft would have required either the relocation of additional utilities or enlargement of the pile cap. Micropile construction is not affected by high groundwater tables or running soil conditions, which were possible at this location, thus resulting in improved constructability and an accelerated schedule. Drilled shaft installation would have required the use of low-overhead drilling equipment, requiring the use of casing and laborious slurry drilling methods at this site. The micropile casing is the drill string and is often left in place, eliminating concern for final quality of the foundation element related to installation or removal of a temporary casing. Leaving the casing in place also reduces the risk of subsidence of the existing structure or adjacent utilities. Scope of Work The lengths of the structural replacement zones are 462 feet for the East approach, and 507 for the West approach. Six pile caps were constructed on each side of the river. Micropiles were installed under five consecutive of the six bents for each approach, incorporating an overall total of 146 micropiles supporting ten bents. The initial design provided by the Micropile Contractor used approximately one micropile for each drilled shaft. At each pile cap located immediately adjacent to the Mississippi River, low headroom was not an issue and drilled shafts were installed as originally proposed. Figure 1. Extent of rehabilitation work at East and West approach spans.

Figure 2. West and East approach locations, Merchant RR Bridge. Pre-Production Probe Drilling beneath West Approach Prior to production work, the micropile contractor performed probe drilling near Bents W3, W4, and W6 of the West Approach. The size and shape of the West Approach pier caps, as well as the exact location of the micropiles at those bents was contingent upon the exact location of several existing site obstructions, which could not be easily relocated. These obstructions included 48- inch and 108-inch diameter sewer lines at an approximate depth of 20 feet, a high-pressure gas line, a fiber optic line, a water line, and an in-service rail line. The Micropile Contractor advanced the probe drill string with water flush in an effort to accurately locate several of the underground obstructions. After locating the obstructions, several of the projected micropile locations were probed in the same manner to double-check their dodging of underground obstructions during production work. Where obstructions were identified as miscellaneous urban fill, the micropile contractor was able to use core bits to core through such obstructions. Micropile Installation Following probe drilling, two drill rigs were mobilized to the East Approach to begin installation. To meet production schedule requirements, up to four drill rigs were used at certain times during the project. With headroom of 18 feet, 10 foot pieces of casing were used to make up the micropiles. Threaded casings eliminated the need for welding in the field. In some locations, the general contractor was able to perform partial excavation in order to increase the available headroom. In other locations, a drill rig requiring only 14 feet of headroom was used to install the micropiles. The micropile contractor drilled the casing (9.625 inch OD x 0.545 inch wall) to depth using rotary drilling with external water flush. Water from the Mississippi River was used for the

drilling operation. The micropiles were advanced through the soils on site, including fill, looseto-dense sands, and weathered rock. They were then socketed a minimum of five feet into solid limestone. Drill water and spoil was returned to the surface through the annular space. Depending on the individual load conditions of the pile cap and the existing site obstructions, the micropiles were either installed vertically or battered at 1.5 on 12. This battering was designed to carry the longitudinal rail loads as provided by the structural engineer. Once each micropile was socketed, a tremie pipe was lowered to the bottom of the casing and the casing was filled with neat cement grout. An on-site colloidal mixer, specifically designed for neat cement grout, was used to provide a uniform and consistent grout. The volume of grout placed in each micropile was recorded to ensure full grouting of the casing. After tremie grouting each micropile, a pressure cap was fitted to the top of the micropile, and additional grout was pumped into the pile to a minimum pressure of 150 psi. Pressure grouting of the rock socket is performed to fill any voids or fissures in the rock and provide structural contact between the micropile drill tooling and the solid dolomitic bedrock. Following installation of the micropiles at each pile cap, the general contractor excavated to the planned bottom elevation of the footing. The micropile contractor then cut the micropiles to a specified elevation. Steel bearing caps were then placed on each micropile, and the micropiles were cast into a reinforced pile cap provided by the General Contractor. Installation procedures for the East and West approaches were identical. Figure 3. Typical micropile and subsurface profile at the Merchant Railroad Bridge site.

Figure 4. Micropile locations adjusted due to utilities conflict at Bent 6 (West approach). Figure 5. Typical micropile layout for East and West approaches.

Figure 6. Micropile installation at Bents 2 and 3 beneath the East approach. Figure 7. Micropile installation in 17 ft of headroom. Figure 8. Micropile installation at Bent 3 (West approach).

Quality Control Documentation Driller s logs recorded all drilling parameters during operations. Grout Strength Testing Independent laboratory tests of 3 x 6 cylinders confirmed that the minimum 28 day unconfined compressive strength of 5,000 psi was achieved. Grout samples were taken daily. Steel Properties Independent laboratory testing of random coupons of the micropile casing material were used to confirm the structural properties of the casing. The casing material is API Grade N80, with a tensile strength of 80 ksi. Load Testing The micropiles were designed to carry 325 kips and were tested to 650 kips using ASTM D 1143 Quick Load test Procedure. One load test was completed on the west side of the river and one load test was completed on the east side of the river. Both load tests were completed on production micropiles. Production micropiles were also used as the reaction anchors for the load test. Earthquake design loads were not considered. Figure 9. Load test setup on production micropile.

Figure 10. Detail A from Figure 9. Figure 11. Load test setup.

0.00 Total Movement vs Load 0 100 200 300 400 500 600 700 800-0.50-1.00 Deflection (in) -1.50-2.00-2.50-3.00-3.50 Merchants Bridge Micropile Load Test by Hayward Baker Elastic Deflection vs. Load 9.625 OD x 0.545 Wall DL = 300 Kips Length of Pile = 90' ASTM D1143 Quick Load Test Test Date 9/22/04 E d B i i R k Load (kip) Average Total Deflection Theoretical Elastic Deflection Tip Movement Linear (Average Total Deflection) Linear (Tip Movement) Figure 12. Total Movement vs. Load. Test preformed on production micropile. Conclusion Micropiles offer an economical alternative to drilled shafts where tight access, low headroom, or urban fill adversely affects the construction schedule of a schedule critical project. The micropile alternative not only shortened the foundation rehabilitation schedule by several weeks, but realized a significant cost savings for the Owner. Acknowledgements The authors extend their appreciation to the following parties for helping make this project a success: Terminal Railroad Association (Owner), St. Louis Bridge Company (GC), Keeley & Sons, Inc. (JV), and Midwest Testing (Engineer).