IMPROVING PATIENT THROUGHPUT: GROWING ORGANIZATIONAL CAPACITY THROUGH PROJECT MANAGEMENT AND PROCESS IMPROVEMENT



Similar documents
Healthcare Reform SQUEEZING WATER FROM A STONE: MAXIMIZE YOUR EXISTING RESOURCES AND ENHANCE YOUR PATIENT FLOW PROGRAM

Improving Pediatric Emergency Department Patient Throughput and Operational Performance

Unstoppable Report Removing a Barrier to Patient Flow by Nursing Process Redesign

Go With The Flow- From Charge Nurse to Patient Flow Coordinator. Donna Ojanen Thomas, RN, MSN Cynthia J. Royall, RN, BSN

BEHAVIORAL HEALTH AND DETOXIFICATION - MEETING DEMAND FOR SERVICES UNIVERSITY OF PITTSBURGH MEDICAL CENTER MERCY HOSPITAL Publication Year: 2013

Accident & Emergency Department Clinical Quality Indicators

Improvements Across the Continuum of Care at a National Top 10 Academic Medical Center

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

Performance Management Dashboard May 2015

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015

Introduction of a Dedicated Admissions Nurse to Improve Access to Care for Surgical Patients

A Discussion on Automating Patient Flow

Analysis One Code Desc. Transaction Amount. Fiscal Period

Eliminating inefficiencies with PerfectServe. SUCCESS STORY Elimination of delays in consultant care. perfectserve.com

The New Complex Patient. of Diabetes Clinical Programming

Elimination of delays in consultant care

A STAR is born. Collaborative Strategy that works!

Creating a Hospital Based Bedside Delivery Program to Enhance the Patient Experience at Cleveland Clinic s Community Hospitals

Emergency Department Directors Academy Phase II. The ED is a Business: Intelligent Use of Dashboards

Unifying Compensation:

Wolfson Children s Hospital Jacksonville, Florida

Benchmarks and Best Practices in the Emergency Department. Jeanne McGrayne Premier Consulting Solutions

Care Coordination at Frederick Regional Health System. Heather Kirby, MBA, LBSW, ACM Assistant Vice President of Integrated Care

Case 2:08-cv ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138. Exhibit 8

Care Management Can We Do It Better?

Improving ED Flow through the UMLN II

Optimal patient flow is vital in hospitals to achieve

P/T 2B: 2 nd Half of Term (8 weeks) Start: 25-AUG-2014 End: 19-OCT-2014 Start: 20-OCT-2014 End: 14-DEC-2014

P/T 2B: 2 nd Half of Term (8 weeks) Start: 26-AUG-2013 End: 20-OCT-2013 Start: 21-OCT-2013 End: 15-DEC-2013

P/T 2B: 2 nd Half of Term (8 weeks) Start: 24-AUG-2015 End: 18-OCT-2015 Start: 19-OCT-2015 End: 13-DEC-2015

Physician-Led Emergency Department Optimization Dashboard

Creating a Pull System in a Push Dominated Environment

Why Service Matters Susan Osborne RN, MSN, MBA Vice President Service Excellence

DISCHARGE FOCUS PUTS HOSPITAL CAPACITY ISSUE TO BED By Terry Maher, Healthcare Practice Leader, USC Consulting Group

Menu Case Study 3: Medication Administration Record

Jim Hoelz, MS, MBA, RN, CEN, FAEN Chief Nurse Executive Blue Jay Consulting, LLC

ASSISTED LIVING FACILITY EXECUTIVE SUMMARY

Acute Care Access and Flow Dashboard - MCH - DRAFT

Enhanced Vessel Traffic Management System Booking Slots Available and Vessels Booked per Day From 12-JAN-2016 To 30-JUN-2017

Web&ACTION Program: Improving Patient Flow Getting Started

Maximising Ability, Reducing Disability. Dr. Áine Carroll Clinical Lead Valerie Twomey Programme Manager

Fife NHS Board Activity NHS FIFE. Report to the Board 24 February 2015 ACTIVITY REPORT

Leveraging Streamlined Patient Flow to Improve Care Delivery and Financial Health

Academic Calendars. Term I (20081) Term II (20082) Term III (20083) Weekend College. International Student Admission Deadlines

OPTIMIZING THE USE OF VHA s FEE BASIS CLAIMS SYSTEM (FBCS)

Existing Barriers to Patient Flow from ED to the ward the ED experience

Consumer ID Theft Total Costs

Virtual Mentor American Medical Association Journal of Ethics November 2006, Volume 8, Number 11:

Restaurant Equipment Industry

GBMC HealthCare is Building a Better System of Care for Our Community. John B. Chessare MD, MPH President and CEO GBMC HealthCare System

The Power of Revenue Management

Rehabilitation Services Integration Initiative North York General Hospital and St. John s Rehab Hospital

Capacity Strategy: The Science of Improving Future Performance

REWRITING PAYER/PROVIDER COLLABORATION July 24, MIKE FAY Vice President, Health Networks

26 OI July August

Physician Revenue Cycle and Compliance Preparing for the OIG

Performance Monitoring and Dashboards for Hospitalists

Beyond Overcrowding: Western Canadian Forum on Innovation and Evidence-based Decision Making in Emergency Care. October 26 & 27, 2007

ENHANCEMENT OF ACUTE SERVICE IN KCC ON CLINICAL PATHWAY FOR GERIATRIC HIP FRACTURE. Elaine Wong WY Queen Elizabeth Hospital 7 May 2012

Effective Approaches in Urgent and Emergency Care. Priorities within Acute Hospitals

Lessons from McKesson s Approach to Maintaining a Mature, Cost-Effective Sarbanes-Oxley Program

Supporting a Continuous Process Improvement Model With A Cost-Effective Data Warehouse

Bed Management Solution

Discussion Assurance Approval Regulatory requirement Mark relevant box X X X

MEDICAL MANAGEMENT PROGRAM LAKELAND REGIONAL MEDICAL CENTER

Escalating volume for practice

EMR and ehr Together for patients and providers. ehealth Conference October 3-4, 2014

UAB HEALTH SYSTEM AMBULATORY EHR IMPLEMENTATION

Environmental Services Business Case Development. Presentation to CHICA Saskatchewan Mark Heller

Report to: Trust Board Agenda item: 13 Date of Meeting: 25 April 2012

Nurse Credentialing: How to Impact Patient Outcomes in the Marketplace

Important Dates Calendar FALL

Understanding Patient Satisfaction Reporting in the Era of HCAHPS Robert J. Ogden

Newark Beth Israel Medical Center Selected: DSRIP Project #8: The Congestive Heart Failure (CHF) Transition Program

MSH Quality Improvement Plans (QIP): Progress Report for 2013/14 QIP

Gloucestershire Health and Care Scrutiny Committee

Presentation Objectives

Texas Nursing: Our Future Depends on It

State of Vermont. Patrick Flood. Commissioner Vermont Department of Disabilities, Aging and Independent Living

Ten Overlooked Opportunities For Significant Performance Improvement and Cost Savings

The Power of Metrics Part Two. By Rob Borchert, CPAM Altarum Institute: Revenue Cycle Management Practice

Strathalbyn and District Health Service: How a Multidisciplinary team Works?

IBH continued to struggle with four critical areas of special focus:

Effective Discharge Begins at Admission A Patient Flow Logistics Coordination Model. Prepared by Ben Sawyer Patient Placement Systems

TRANSFORMING HEALTH SYSTEM WITH IT Ain Aaviksoo, MD MPH. Deputy Secretary General for eservices & Innovation Ministry of Social Affairs of Estonia

SEO Presentation. Asenyo Inc.

Subpart B--Conditions of Participation: Comprehensive Outpatient Rehabilitation Facilities

EDI Services helps healthcare network streamline workflow, increase productivity, and improve revenue cycle management.

Transcription:

IMPROVING PATIENT THROUGHPUT: GROWING ORGANIZATIONAL CAPACITY THROUGH PROJECT MANAGEMENT AND PROCESS IMPROVEMENT Stephen V. Bogar, Sr. Management Engineer Lehigh Valley Hospital Challenge/Background America s hospitals are reporting demand for inpatient services growing at a rate not seen in well over a decade. Beds are full, emergency departments are on divert and staff is in short supply. This change in the economics of hospital care has been swift, catching most of the industry off guard. Hospitals have exited an era of surplus and entered a period of prolonged and chronic shortage. Lehigh Valley Hospital was not immune. In 2000 and 2001, we saw ambulance diversions increasing, excessive waits in the emergency department, Transfer Center patients turned away, operating rooms (ORs) put on hold and daily patient logistic challenges. Physician and patient satisfaction suffered. We knew we did not have the physical and human capacity currently to maintain access in the face of rising and uneven patient demand. However, we believed through process improvement we could help the situation. To eliminate frustrating delays and provide a higher level of service to all seeking our care, we launched our Growing Organizational Capacity (GOC) project in July 2002. The project goal was: By December 2003, design and implement improvements to ensure open access to meet or exceed the forecasted volumes over 5 years (FY03-FY08) The Global Objective was to maximize throughput and create open access by focusing on the post-encounter, encounter and pre-encounter phases of hospitalization to meet capacity needs of the organization. Focus was placed on developing and enhancing Processes, People and Physical Space, using our internal resources to manage and execute the project. The GOC project grew out of several previous projects which were designed to fix ED patient flow problems. In 2000-2001, Clockwork ED focused on enhancing ED processes to reduce the length of ED patient visits. There was some success; however, ED patients LOS remained high, resulting in ED backlog, due to the inability to move patients to a hospital bed in a timely fashion. In June 2002, a middle-management retreat was held and ideas were generated as potential solutions to fix capacity and patient throughput problems. The newly formed GOC task force reviewed and prioritized the over 1,000 ideas generated at this retreat. Project Development The GOC project formally commenced in September 2002 with 10 sub-projects initiated to speed up the process of patient discharge and bed turnover (cleaning, readying for next patient). Much of GOC s success has been due to organizational support it has received Lehigh Valley Hospital gives permission to IIE to only print the referenced paper and slides in the 17th Annual Society for Heath Systems Management Engineering Forum proceedings. Lehigh Valley Hospital and Health Network 1

from our hospital s senior administrative and clinical leadership. The project sponsors included the Chief Operating Officer, President of the Medical Staff and Chair of Medicine have served as our champions; communicating with peers about the challenges and helping eliminate barriers. The project leaders, Senior Vice President, Clinical Services; Vice-Chair of Emergency Medicine and Vice President, Operations, have managed the identification, execution and implementation of the sub-projects. A large, dynamic interdisciplinary group of physicians, mid-level managers and staff, literally hundreds of employees, was engaged to develop and participate in the solutions. The GOC Project was executed in two phases, each lasting about 12 months in length. The sub-projects were carefully selected to impact the total patient flow process. Leaders and team members were selected to offer both functional and outside views of the sub-project charter. The GOC project structure created the formation of two teams to help in the identification, execution and implementation of the sub-projects; GOC Implementation Team and GOC Resource and Development Team. The GOC Implementation Team included the GOC Project Leaders, current GOC Sub-project team leaders, at-large members with functional responsibility in targeted areas and selected GOC Resource and Development members on an as needed basis. The GOC Resource and Development Team consisted of some of the wealth of internal resources at LVH including; Management Engineering, Organization Development, Care Management, Information Services, Center for Educational Services and Marketing. The GOC Resource and Development Manager served as the GOC Project Manager, an innovative role connecting project sponsorship, leadership and resources for streamlined communication. The first 10 sub-projects, that kicked off in the Fall of 2002, were completed by Summer of 2003 and included: Discharge Process (focus on the physician communication and nursing unit staff process of patient discharge) Transport Mechanics for Discharge (use of centralized Patient Transport for patient discharge) External Transport -- Centralized Ambulance (develop centralized ambulance function for expedient movement of patients to other care facilities) Discharge Bed Turnaround Time (focus on the communication and process of dirty bed cleaning) Bed Tracking Software (implementation of bed tracking software for the cleaning of dirty beds and the reporting of clean beds) Intra-Hospital Transfers (enhance process and communication of the transfer of patient within the hospital) Short Stay Hospital Implementation (implement a short stay unit for 1 and 2 day stay patients from Ambulatory Surgical Unit) Find-a-Bed Implementation ( opening licensed beds not in use) Expanded Express Admissions Unit Feasibility (determine the feasibility of the expansion of the Express Admissions Unit pilot) Observation Unit Feasibility (determine the feasibility of the operation of a universal unit for observation patients) Lehigh Valley Hospital gives permission to IIE to only print the referenced paper and slides in the 17th Annual Society for Heath Systems Management Engineering Forum proceedings. Lehigh Valley Hospital and Health Network 2

The second phase which began in Fall 2003 and continued until Summer 2004, included the following sub-projects: Ancillary Services Feasibility (determine the feasibility of expanding ancillary services hours for patient discharge facilitation) Patient Logistics Implementation (implementation of 6 of the above projects into a new department called Patient Logistics) Pull System (development and implementation of a pull system for patient admission and transfer) Surgical Smoothing Feasibility (feasibility study of identifying opportunities to smooth the flow of patients in and out of surgical areas) Timely Discharge (increase number of patient discharged by 11:00AM SOS Shorten Our Stay (identify LOS reduction opportunities in long LOS patients ED LOS Reduction (design ED process improvements to reduce ED LOS) A unique outcome of the first phase of GOC was the idea of stitching six interrelated subprojects into one recommendation for implementation. A workout session was held with the six sub-project leaders, functional area management and the GOC Resource and Development Team. The group worked on process development, implementation strategies and cost/benefit analyses to ensure the success of the solutions. The result was the formation of our Patient Logistics department. Solutions/Results Implemented over the past year, these sub-projects have had a significant effect on throughput, capacity and customer satisfaction. The successes include: 1) Patient Logistics department implementation. The patient logistics function began in April 2003 and was implemented over six months. Patient Logistics oversees each step of patient throughput from admission to discharge and consists of the former bed management activities and now includes: Centralized Patient Transport, Discharge Bed SWAT team, Patient Flow Coordinators and Centralized Ambulance Transport. Teletracking s TransportTracking, BedTracking and PreAdmitTracking software packages were installed and implemented. This has resulted in reducing bed turnover time (bed dirty to bed clean) from 210 minutes to around 60 minutes. Consistent patient transport times of 24 minutes per trip, better communication of the need and availability of beds for patients. 2) A seven-bed Express Admissions Unit (EAU) now accounts for more than 50 percent of all direct admissions to the hospital, improving physician and patient satisfaction. The EAU allows direct admissions to completely bypass the ED and give fast patient care, including medication administration, diagnostic testing and admissions paperwork completion, on arrival. Lehigh Valley Hospital gives permission to IIE to only print the referenced paper and slides in the 17th Annual Society for Heath Systems Management Engineering Forum proceedings. Lehigh Valley Hospital and Health Network 3

3) In the 12-bed short stay hospital medically stable elective surgery patients spend one or two nights, freeing up the main ORs for more complicated cases, emergencies and traumas. 4) Find-a-Bed reviewed the current bed complement and allowed us to put 37 new beds in service. 5) The Short Stay Hospital Unit opened in April 2003 and caters to patients undergoing elective procedures who require a one to two day length of stay. Located in the same facility as our ambulatory surgery unit, this unit has helped us deal with our capacity issues by shifting select cases from our primary site to an alternate location. Helping us to manage a 12% growth in surgical cases, this unit has been well-received by both patients and physicians in meeting their needs. 6) Patient Flow Coordinators (PFCs) were created to facilitate the movement of patients throughout the hospital system. Patient flow coordinators ensure that patients from the ED, PACU and EAU are promptly transferred to assigned ready beds. In addition, as RN s, they problem-solve patient placement issues and provide hands-on clinical assistance as needed. 7) A pull system was developed and implemented in the patient admission process. Patients to be admitted from the ED, EAU and PACU are now pulled their assigned unit, through changes in the admitting process. These changes include a new electronic nursing report and the use of PreAdmit Tracking to set signals (or kanbans) for nursing units when a patient is ready to be moved. This has resulted in a 33% reduction in the time it takes for a patient to occupy a clean bed. 8) There are now more ancillary services hours on the weekend with physician coverage. This has facilitated more weekend patient discharges, freeing up beds for surgical admissions early in the week. 9) The ED has implemented process changes that have decreased the LOS by over 15%. Two of the process changes with significant impact are the Lines and Alerts and Bedside Registration. Summary The overall result is that we have kept the access to LVH open to the community. We attained a 5.9% admissions growth (exceeding forecasted volumes) from FY2003 to FY2004 breaking record monthly admissions along the way. ED visit volume continues to grow, despite the off-loading of patients through the EAU. Transfer Center requests have increased 120% and Transfer Center acceptances have increased by 150%. The many successes of GOC have resulted in a fantastic, highly profitable FY2004 for LVH. In addition, Press Ganey scores in most areas are rising to their highest levels ever. These integrated, positive results have positioned LVH to prepare for capacity expansion and increased technology, resulting in better, more efficient patient care of the greater Lehigh Valley community. The success of GOC is attributed to the organizational involvement of the staff at LVH, strong positive project management, increased technology, focus on capacity/demand measurement and implementation of enhanced processes surrounding patient throughput. A project structure is being developed to address current and future capacity issues, by monitoring Lehigh Valley Hospital gives permission to IIE to only print the referenced paper and slides in the 17th Annual Society for Heath Systems Management Engineering Forum proceedings. Lehigh Valley Hospital and Health Network 4

capacity/demand metrics via a dashboard, performing process audits to ensure the process change and identifying the next capacity thing. Lehigh Valley Hospital gives permission to IIE to only print the referenced paper and slides in the 17th Annual Society for Heath Systems Management Engineering Forum proceedings. Lehigh Valley Hospital and Health Network 5

Improving Patient Throughput: Growing Organizational Capacity through Project Management and Process Improvement Stephen V. Bogar, Sr. Management Engineer Lehigh Valley Hospital and Health Network

Problem Statement LVHHN was experiencing unprecedented levels of rising community demand which challenged our ability to optimally care for our community. Lost admissions due to: Emergency Department (ED) diversions Transfer Center denials Operating Room (OR) holds, Extended ED wait times Daily patient logistic challenges related to thru-put

3 Days Until Admission Once You Reach This Point Lehigh Valley Hospital and Health Network

Growing Organizational Capacity - GOC 2000-2001 2001 Clockwork ED 2001 Clockwork LVH June 2002 Circling to Land: Leadership Retreat Sept 2002 GOC commenced Structure Focus Post-Encounter Encounter Pre-Encounter

GOC Project Goal By June 2004, design and implement improvements to ensure open access to meet or exceed the forecast volumes over 5 years (FY 03-FY 08) FY 08) Three Capacity P s Peopleeople Processrocess Physical hysical space Internal capability development

LVH GROWING ORGANIZATIONAL CAPACITY PROJECT STRUCTURE GOC Project Monitored Projects Authority for Implementation in functional area Division Chief VP, Operations GOC Sponsors COO GOC Leaders VP, Nursing GOC Implementation Team GOC Leaders Medical Chief Vice-Chair ED GOC Leaders GOC Sub-Project Leaders At-Large Members GOC Resource & Development Team Members GOC Sub-Project Leaders Ancillary Services Enhancement Feasibility LOS Reductions to Improve Throughput And Capacity Implementation Patient Logistics Implementation ED LOS Reduction Pull System Implementation Discharge Education Campaign Smoothing System Feasibility GOC Resource and Development Team Management Engineering, Organizational Development, Care Management Marketing, I/S, CEDS

GOC Sub-Projects Discharge Process Transport Mechanics for Discharge External Transport (Centralized Ambulance) Discharge Bed Turnaround Time (D BST) Bed Tracking Software Intra-Hospital Transfers 17 th Short Stay Hospital Implementation Find-a-Bed Implementation Expanded EAU Feasibility Observation Unit Feasibility Ancillary Services Feasibility Patient Logistics Implementation Pull System Surgical Smoothing Feasibility Timely Discharge SOS (Shorten Our patients Stays) ED LOS Reduction

GOC SubProject Implementation 6 subprojects were stitched together Supported the creation of Patient Logistics Automated Patient Transport Software for discharges Centralized bed cleaning (software) Patient Flow Coordinators Centralized Ambulance Transport Discharge Process Intra-Hospital Transfer

Patient Logistics Functional/Operational Structure DBST In-patient Registration In-patient Bed Assignment Patient Transport PFC Patient Logistics Command Center Transfer Center Mini Electronic Bedboards Ambulance Transport Clinical Services Case Management Decedent Affairs

LVH-CC Bed Swat Team LVH-CC DBST Bed Turnaround Time Dirty to Clean May 2003 Implementation 220 200 Turnaround Time (minutes) 180 160 140 120 100 80 60 40 20 0 FY02Q1 FY02Q2 FY02Q3 FY02Q4 FY03Q1 FY03Q2 FY03Q3 FY03Q4 FY04Q1 FY04Q2 FY04Q3 FY04Q4* Month Goal: 60 minutes

LVH Pull System Design and implement a Pull System for admitting patients Demand for inpatient bed is anticipated by unit staff Kanbans or signals sent via Electronic Bed Board

LVH-CC Pull System ED Admissions Clean Bed to Patient Occupy Time 160 126 119 115 Avg Time (min) 120 80 40 106 100 101 107 97 100 92 84 Threshold Target Maximum 0 Nov-03 Dec-03 Jan-04 Feb-04 Mar-04 Apr-04 Month May-04 Jun-04 Jul-04 Aug-04 Sep-04

LVH-CC ED Length of Stay LVH-CC ED LOS Trend (FY02-FY05) 300 290 Variable Actual Fits 280 Time (Minutes) 270 260 250 240 230 220 Jan-02 Apr-02 Jul-02 Oct-02 Jan-03 Apr-03 Jul-03 Month Oct-03 Jan-04 Apr-04 Jul-04 Oct-04

LVH-CC ED Wait Times (Door to Seen) LVH-CC ED Door-to-Seen Trend (FY02-FY05) Time (Minutes) 90 85 80 75 70 65 60 55 50 45 40 Variable Actual Fits Jan-02 Apr-02 Jul-02 Oct-02 Jan-03 Apr-03 Jul-03 Month Oct-03 Jan-04 Apr-04 Jul-04 Oct-04

LVH-CC ED Wait Time for Inpatient Bed LVH-CC ED Wait Time for InPatient Bed (FY02-FY05) 220 Variable Actual Fits 200 Time (minutes) 180 160 140 120 100 Jan-02 Apr-02 Jul-02 Oct-02 Jan-03 Apr-03 Jul-03 Oct-03 Jan-04 Apr-04 Jul-04 Oct-04 Month

LVH-CC ED Diversion LVH-CC ED Diversion Trend 140 120 Variable Actual Fits 100 ED Diversion 80 60 40 20 0 Jan-02 Apr-02 Jul-02 Oct-02 Jan-03 Apr-03 Jul-03 Oct-03 Jan-04 Apr-04 Jul-04 Oct-04 Month

% of Discharges during Hour of Day 20.0% 18.0% 16.0% 14.0% 12.0% 10.0% 8.0% 6.0% 4.0% 2.0% 0.0% Bed Availability LVH-CC Bed Availability - Discharges plus Bed TAT by Hour of Day 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Hour of Day FY02 Effect FY03 Effect FY04 Effect Take Away: GOC supported a shift in the capacity curve to earlier in the day; there are six more beds available at noon. LVH-M showed a similar capacity shift; yielding two more beds available at noon.

GOC Success LVH-CC Effective Occupancy 102.5% 100.0% 97.5% % Occupancy 95.0% 92.5% 90.0% 87.5% 85.0% 82.5% 80.0% FY02Q1 FY02Q2 FY02Q3 FY02Q4 FY03Q1 FY03Q2 FY03Q3 FY03Q4 Fiscal Year Quarter FY04Q1 FY04Q2 FY04Q3 FY04Q4 Actual No "GOC"

LVH Admissions Higher and Higher LVH Admissions vs Fiscal Quarter 10000 9750 9500 Admissions 9250 9000 8750 8500 8250 8000 FY02Q3 FY02Q4 FY03Q1 FY03Q2 FY03Q3 FY03Q4 FY04Q1 Fis c a l Qua r t e r FY04Q2 FY04Q3 FY04Q4 FY05Q1 Take Away: We have exceeded admissions budget and forecast in FY03 and FY04

CC ED PressGaney Improvements FY 04 1Q - 3Q 77.9 to 83.9 (30% tile - 85% tile) Overall Assessment Overall Rating 70.5 to 76.8 (20% tile - 60% tile) Arrival 74.7 to 83.7 (25% tile - 85% tile) Personal Issues 69.8 to 78.4 (20% tile - 83% tile) Personal/ Insur. Info. 83.2 to 87.0 (35% tile - 77% tile) Patients & Families 81.1 to 86.1 (35% tile - 85% tile) Nurses 83.0 to 89.8 (55% tile - 97% tile) Doctors & PAs Family/Friends Tests 82.7 to 86.2 (45% tile - 77% tile) 82.6 to 85.0 (40% tile - 70% tile)

GOC Next Steps Capacity Oversight Transition Team formed Audit process changes Monitor the processes (data) Make recommendations for future capacity subprojects

GOC Success High Level Organizational Support Committed Staff Internal Resources Use of Technology