CITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General



Similar documents
CLEANING, INSPECTION, AND TESTING OF SEWERS

CHAPTER 6 - SANITARY SEWER

SECTION IV - TESTS AND INSPECTIONS PART 1 - GENERAL Testing - General

SANITARY SEWER SPECIFICATIONS

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.

Section SEWER PIPE INSTALLATION AND TESTING

SEWER CLEANING, INSPECTION AND ASSESSMENT

SANITARY GRAVITY SEWER LINE TESTING. B. Section CCTV Inspection of Gravity Sewer Lines

SECTION ACCEPTANCE TESTING FOR SANITARY SEWERS

City of Regina Standard Construction Specification SECTION 1320 SEWERMAIN TESTING

INSTALLATION OF INSITUFORM LINER

CCTV INSPECTION OF SEWER LINES. A. Section Sanitary Gravity Sewer Lines. B. Section Sanitary Gravity Sewer Line Testing

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)

Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

SECTION 9.02 BUILDING SUBSURFACE DRAINS (PERIMETER, ETC.)

San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION

SECTION ABANDONMENT OF SEWER MAINS

CITY OF COLFAX REQUIREMENTS AND STANDARDS FOR CLOSED CIRCUIT TELEVISION SEWER LATERAL INSPECTIONS

SECTION CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE

Section 402. STORM SEWERS

1. General General Requirements Gravity Sanitary Sewer Testing Requirements...3

Wastewater Capital Projects Management Standard Construction Specification

SECTION 724 PIPE CULVERTS

SECTION GRAVITY SANITARY SEWERS

53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines:

STANDARD SPECIFICATIONS SECTION SEWER MAIN AND LATERAL CONNECTION SEALING BY CHEMICAL GROUT

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.

DESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES SITE UTILITIES

REHABILITATION OF UNDERGROUND SEWER LATERAL PIPES WITH CURED-IN-PLACE-PIPE LINER SECTION 02542

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

San Antonio Water System Standard Specifications for Construction ITEM NO SLIP-LINING SANITARY SEWERS

SECTION 21 REHABILITATION OF SANITARY SEWER MAINS BY THE PIPE BURSTING AND TRENCHLESS PIPE REPLACEMENT METHOD

LS 2540 SEWER LATERALS AND INSPECTION TEES

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION STORM DRAIN SYSTEMS PART 1 - GENERAL

SECTION ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section Submittals.

LOGAN TOWNSHIP MUNICIPAL UTILITIES AUTHORITY DESIGN, CONSTRUCTION, INSPECTION AND TESTING MANUAL

STANDARD SPECIFICATIONS SECTION INSTALLATION OF GRAVITY SEWER PIPELINES. 1. Trenching, Backfilling and Compacting: 02223

SECTION PRECAST CONCRETE UTILITY STRUCTURES

SECTION STORM DRAIN SYSTEM

ATTACHMENT 2: SPECIFICATION FOR SEWER CCTV VIDEO INSPECTION

SECTION POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

STANDARD SPECIFICATIONS SECTION CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS

Special Specification 7021 Water Main and Sewer Line Replacements

Exhibit A. Rules and Regulations for House Connections and Sewer Extensions

STANDARD SPECIFICATIONS SECTION CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS

CORPORATION OF THE CITY OF BURLINGTON SPECIFICATION INDEX FOR CCTV VIDEO INSPECTION OF PROPOSED STORM SEWERS (SPEC. NO. SS7) 1. Scope of Work SS7-1

Beacon Hill Sewer District Standard Specifications

SECTION 603 SANITARY SEWER FORCE MAINS

San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS

Storm Sewer Trenchless Upgrade Alternatives and Recommendations

Sewer Water Pipeline Replacement with CERTA LOK RESTRAINED JOINT PVC PIPE

DIVISION 4300 STORM DRAINAGE

SECTION 802 GRAVITY SEWER PIPE

SECTION CEMENT-MORTAR LINED AND COATED STEEL PIPE

Sewer Line Rehabilitation

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING

SECTION SANITARY SEWER PIPE

Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe

Section 5 Sanitary Sewer

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

San Antonio Water System Standard Specifications for Construction ITEM NO POINT REPAIRS AND OBSTRUCTION REMOVALS

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

ARTICLE II (2) ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH Purpose and Application.

ASTM C76, Class III, Wall B, except as modified herein. Clean natural sand, ASTM C33. Artificial or manufactured sand will not be permitted.

SECTION POLYVINYL CHLORIDE (PVC) PIPE

SECTION STORM DRAINAGE SYSTEM

Section 4. Sewer Testing

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.

VERIFICATION TESTING GUIDELINES FOR CONTRACTORS

OAR52 A-1 (September, 1981)

SECTION ASBESTOS CEMENT PIPE REPAIRS, DEMOLITION, AND DISPOSAL

VIDEO INSPECTION AND LASER PROFILING IN FLORIDA. AASHTO SOC Conference Larry Ritchie, FDOT August 14, 2013

Specifications for Residential Property Owners Connection to New Public Sewer

SECTION NONREINFORCED CONCRETE SEWER PIPE

PART 6 - STANDARD DESIGN AND CALCULATION FORMS 6.1 SANITARY SEWER DATA SHEET

SECTION 1 GENERAL REQUIREMENTS

Learning Objectives. History of Vacuum Testing for Precast. Vacuum Testing. Terminology and purpose

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS

Section 2100-Trenching and Tunneling

STANDARD SPECIFICATIONS SECTION CLEANING AND LINING WATER MAINS

SECTION 7 UNDERDRAIN SERVICE

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

SECTION XXXXXX TECHNICAL SPECIFICATIONS FOR INSTALLATION OF PROTECTIVE COATINGS FOR MANHOLES, WETWELLS, AND OTHER SANITARY SEWER STRUCTURES

SECTION BUILDING SEWERS. B. Connection of building sanitary drainage system to municipal sewers.

GENERAL SPECIFICATIONS AND GUIDELINES FOR INSTALLATION MASTERLINER CURED-IN-PLACE PIPE SYSTEMS

SEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER

The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm:

City of West Linn Public Works Standard Construction Specifications. Table of Contents

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

Waste Collection Systems

Transcription:

General All sanitary sewers, manholes and force mains shall be acceptance tested, as hereinafter specified in the presence of a City representative. Acceptance testing shall be performed after backfilling is completed. The Contractor shall make any and all necessary repairs required to pass the acceptance test, at no additional cost to the City. Each section of sewer between manholes shall be cleaned, tested and inspected. All repairs shown to be necessary by the tests are to be made promptly. Broken or cracked pipe shall be replaced and all deposits removed. The sewer pipe shall be set into position true to the line and grade and entirely cleaned out. Testing of Gravity Sewers All gravity sewer pipes shall be inspected manhole-to-manhole and tested by inducing low-pressure air into the pipe. The air shall be slowly introduced into the pipe and the pressures shall be gradually increased with the test section to 5.0 psi. The air test shall be conducted by the Contractor under the supervision of the City s representative and shall be performed with equipment manufactured specifically for air testing of pipe. The Contractor may desire to perform an air test for his or her own purposes prior to backfilling; however, the acceptance air test shall be performed after backfilling has been completed. Each section of the sewer being tested shall be temporarily sealed-off by means of suitable plugs. In addition, all wyes, tees, or ends of lateral stubs shall be sealed with suitable removable caps securely fastened to withstand internal test pressure. All such pipe to be tested shall be required to sustain 5.0 psi test pressure without loss or drop in pressure for a time period of 5 minutes. In the event that a loss does occur, appropriate repairs or reconstruction shall be made and the test procedure shall be rerun until the test criteria (5.0 psi for 5 minutes) are successfully accomplished. In the event where ground water elevations prevail higher than the top of the sewer pipe that is being tested, 0.5 psi per foot of hydrostatic head above the top of the sewer pipe shall be added to the test pressure. City of Beverly Massachusetts Revised February 2010 1

The pressurizing equipment shall have a safety gauge, which shall limit the loading on the sewer line to ten (10) psi. In addition, the calibration on all pressure gauges shall be no greater than 0.10 psi. All PVC pipes shall also be tested for pipe deflection. Said tests shall not be performed until the backfill has been in place for at least 60 days. The maximum acceptable deflection shall be five (5%) percent of the vertical internal diameter as defined in ASTM Specification D-3034. Said testing shall be performed with a mandrel similar or equal to that manufactured by Cherne Industries, Inc. Mandrels are to bear ASTM certification for the pipe size being tested. It is required that deflection-testing equipment receives the prior approval of the City. The Contractor is permitted to attach a mandrel to the camera, for a camera so equipped, to perform the television inspection and mandrel test simultaneously. The City will lamp each section of the sewer pipe between manholes by placing a light at one end and observing the pipe at the other end. Sewers not constructed on uniform line and grade, and therefore not showing a full circle of light during lamping, will not be accepted by the City. If the pipe installation fails to meet these requirements, the Contractor shall determine at his own expense the source or sources of leakage, and he or she shall repair or replace all defective materials and workmanship. Hydrostatic Testing of Force Mains All force mains shall be hydrostatically tested for leakage after installation is completed. Said testing shall be performed in accordance with the applicable sections of the AWWA C standards. Prior to performance of the testing work the Contractor shall submit to the City Engineer the following: A testing schedule. A listing of equipment intended to be used, including general information on the pump, pressure gauge, pressure relief and water meter. Certification that the pressure gauge has been calibrated to 0.1 psi within the past three months. City of Beverly Massachusetts Revised February 2010 2

The Contractor will provide the water required for testing purposes and shall provide all required temporary fittings to complete testing prior to the existing force main including temporary removal of air relief valves for testing purposes. Each section of pipe to be tested shall be slowly filled with water during which time air shall be expelled from the pipeline through the air release valves (where high points in the line exist at which there are no air release valves, Contractor shall install corporation cocks for that purpose). After all air is expelled, the air release devices shall be closed and line pressures shall be raised to the test pressure directed by the Engineer. Test pressures shall be 1.5 times the expected working pressure predicated upon the elevation of the lowest point on the line, corrected to the elevation of the lowest point in the line, corrected to the evaluation of the test gauge. Any joint, cracked pipe or other appurtenances revealing leakage during the pressure test shall be corrected after which the pressure test shall be rerun. Pressure tests shall be conducted for a 30-minute time period. After performance of the successful pressure test, a leakage test shall be performed over a duration period of two hours at a pressure to be determined by the Engineer. Leakage is defined as the quantity of water supplied to the test section of pipe, which is required to maintain pressure within 5 psig of said test pressure during the entire testing period. Pipe construction so tested shall be deemed to have failed the leakage test if the leakage resulting is greater than 10 gallons per inch diameter per mile of pipe per day. Vacuum Testing of Manholes After erection of the manholes, connection of the sewer and placement of the backfill to approximately the finished ground elevation, each manhole shall be vacuum-tested for water tightness. Connecting pipes shall be securely plugged and an approved vacuum-testing device shall be placed and sealed within the manhole frame/cover section. Lift holes, if any, shall be plugged with an approved, non-shrinkable grout prior to testing. If a coating or lining is to be applied to the interior of the manhole the vacuum test must not be performed until the coating or lining has been cured according to the manufacturer s recommendations. Vacuum testing shall be according to ASTM C1244, except as specified otherwise herein. City of Beverly Massachusetts Revised February 2010 3

A vacuum of ten (10) inches of mercury (Hg) shall be drawn on the manhole after which the vacuum pump shall be shut off. If the indicated vacuum pressure drops to below nine (9) inches in less than three (3) minutes, the test apparatus shall be removed and appropriate repairs/plugging shall be performed. The test shall be repeated, as necessary, until a time period of minimum of three (3) minutes occurs before the vacuum pressure drops one (1) inch and/or there is no visual indication of water leakage. Appropriate repairs/plugging is defined as sealing the grade rings and inside joints with Parsons Epoxy Compound, Parsonpoxy FG, or approved equivalent. Television and Inspection After cleaning and at the direction of the City, and prior to acceptance of the sewers by the City, sewer sections shall be visually inspected by the Contractor, Engineer, and City by means of closed-circuit television for final inspection. The inspection shall be done one manhole-to-manhole section of pipe at a time. The Contractor is permitted to attach a mandrel to the camera, for a camera so equipped, to perform the television inspection and mandrel test simultaneously. The television camera used for the inspection shall be one specifically designed and constructed for such inspection and shall be capable of pan and tile direction movement to lateral view connections and deflects. Lighting for the camera shall be suitable to allow a clear color picture of the entire periphery of the pipe. The camera shall be operative in 100% humidity conditions. The camera, television monitor, and other components of the video system shall be capable of producing a color picture quality to the satisfaction of the City; and if unsatisfactory, equipment shall be removed and no payment will be made for an unsatisfactory inspection. The camera shall be utilized to record the condition of all manhole interior conditions. The camera shall be moved through the line in either direction at a moderate rate, stopping when necessary and at lateral connections and shall tilt and pan each lateral connection to permit proper documentation of the sewer s condition. In no case will the television camera be pulled at a speed greater than 30 feet per minute. City of Beverly Massachusetts Revised February 2010 4

Manual winches, power winches, TV cable, and powered rewinds or other devices that do not obstruct the camera view or interfere with proper documentation of the sewer. If, during the inspection operation, the television camera will not pass through the entire manhole section, the Contractor shall set up his equipment so that the inspection can be performed from the opposite manhole. Any section of gravity sewer that is found by internal TV inspection to be defective; to contain silt and/or debris; or to be otherwise unacceptable to the City, shall be corrected and re-televised at the expense of the Contractor. When manually operated winches are used to pull the television camera through the line, telephones or other suitable means of communication shall be set up between the two manholes of the section being inspected to ensure good communications between members of the crew. The importance of accurate distance measurements is emphasized. Measurement for location of deflects shall be above ground by means of a meter device. Marking on the cable or the like, which would require the interpolation for depth of manhole, will not be allowed. Accuracy of the distance meter shall be checked by use of a walking meter, roll-a-tape, or other suitable device, and the accuracy shall be satisfied to the City. Documentation of the television results shall be as follows: Television Inspection Logs: Printed location records shall be kept by the Contractor and will clearly show the location in relation to and adjacent manhole of each infiltration point observed during inspection. In addition, other points of significance such as locations of building sewers, unusual conditions, broken pipe, and other discernible features will be recorded and a copy of such records will be supplied to the City. Digital Video Recordings: Digital video recording shall be provided at the discretion of the City and shall be either color DVD or mpeg compatible. City of Beverly Massachusetts Revised February 2010 5