BGE Service Application Guidelines Residential Modification/Relocation Projects



Similar documents
BGE Service Application Guidelines Commercial & Industrial Projects

Please Refer to Attached Sample Form

How To Get A Power Line Extension

REQUEST FOR ELECTRIC SERVICE Commercial

Please Refer to Attached Sample Form

INSTRUCTIONS FOR PREPARING APPLICATIONS FOR ELECTRIC SERVICE & METER

Internet Application for New Multi-Family Electric Service Builders/Developers Fax to: (800) or call (800) Date Faxed: 1

Applying For New or Revised Electric Service

CONSTRUCTION PERMIT APPLICATION AND INSTRUCTIONS (Permit Application follows instructions)

Natural gas and electric service guide

Builder/developer gas service application

STATE OF SOUTH CAROLINA RESIDENTIAL PROPERTY CONDITION DISCLOSURE STATEMENT

MLGW Contact Numbers. Memphis Light, Gas and Water Division P.O. Box 430. Memphis, TN

Contractor Information 2011

BUILDING PERMIT RESIDENTIAL BASEMENT FINISH

Botetourt County, Virginia. Frequently Asked Questions

- Natural Gas Service Application Checklist -

BASIC NEC CODE RULES AND DESIGN PRACTICE

How To Get A Building Permit In Florida

Upper Southampton Township Department of Licenses and Inspections 939 Street Rd. Southampton, Pa Phone: Fax:

City of Elk River BASEMENT Office Use Only

ATTACHMENT A Town of Lakeside Fee Schedule. ANIMALS Annual pet registration fee per animal limit 4 animals $ 8.00 each

DPIE FY2016 Fee Schedule (Effective July 1, 2015)

COUNTY OF LOS ANGELES BUILDING AND SAFETY DIVISION ELECTRICAL CODE FEE SCHEDULE (Title 27 of the County of Los Angeles Code, Ord No.

Building Code Inspections and Fees

Step 1: Application Instructions

Electric Service Guide for Residential Construction

Four Point Inspection

BUILDING PERMITS. Santa Rosa County Building Inspection

BUILDERS AND CONTRACTORS GUIDE FOR ELECTRIC SERVICE

Connecticut Standardized Municipal Instructions for Solar Photovoltaic (PV) Permitting Process Town of Pomfret

GAS CONVERSION PROJECT ˆAn Alternative to Oil

Figure. 1 - Split Phase 240/120V circuit (180 phase shift)

HOMEOWNER S PERMIT GUIDE

Your energy costs. A room-by-room guide. P.O. Box San Diego, CA Connect at sdge.com

Building Permits: When are they required?

ELECTRIC WATER HEATER CREDIT

Application for. Commercial New Service

ALL STAR ELECTRIC COMPANY 10,000 Trumbull SE, Suite #F Albuquerque, NM (505) voice & fax NM License

Heating & Cooling Efficiency

PREPARED DATE: SIGNATURE AND SEAL INSPECTION REPORT PREPARED BY: PRINT NAME: REGISTRATION NUMBER: MAILING ADDRESS:

Contents. Section 1 General Information 2. 1.A Introduction 3 1.B Overview 3 1.C Pricing, Billing, and Payment Policies 6

Rhode Island Residential Heating Program from National Grid

How To Wire A Three Phase, Single Phase, Wye Transformer

Schedule B to By-law

Homeowner Information Guide Electrical Safety. British Columbia Safety Authority

Scope of Work Class I Contractor s Licenses. Putnam County Ordinance Section 17. Types of Authorized Contractor Licenses.

- Natural Gas Service Application Checklist -

forair optimal air environments ResidentialPresentation

Current Programs available to Limited Income Customers. Residential and Multifamily

SCHUYLER DEPARTMENT OF UTILITIES SCHUYLER, NEBRASKA ELECTRIC RATES

SINGLE PACKAGE VERTICAL AIR CONDITIONERS

NIPSCO AIR CONDITIONER (AC) CYCLING PROGRAM. Frequently Asked Questions. 1. Can I really make a difference by participating?

4. REQUEST FOR ELECTRIC SERVICE. 4.1 General Service Information

Center for Energy Education Laboratory

Electric Service Guide for Commercial Construction

RESIDENTIAL UTILITY PERMITS APPLICATION PACKET

3. TYPES OF SERVICE AVAILABLE. 3.1 Scope

Building Permit Application

EXPRESS PERMITS (No Plan Check Required)

SERVICE MANUAL FOR 6535 SERIES TWO TON HIGH EFFICIENCY PACKAGED HEAT PUMPS

Temporary Electric Service

Real Property Title 10. Sales of Property Subtitle 6. New Home Warranties

NOTICE OF INTENT Department of Revenue Policy Services Division. Income Tax Credits for Wind or Solar Energy Systems (LAC: 61:I.

BVCAA inc HVAC Service Bid Sheet Item Description. Materials Labor Total 3/24/2015

Saving Water and Energy in Residential Hot Water Distribution Systems. Gary Klein California Energy Commission

I NI NP R Inspected Items

T-100-R Installation Guide

Local Dealer:

City of Riverside Building & Safety Division Residential Electric Vehicle (EV) Charger Guidelines

Circuit breaker panel. Power supply for condensing unit. Power supply for furnace. Air handler (Furnace)

TENT AND STAGE CUSTOMER ASSISTANCE GUIDE

Accela Automation User Manual for Gwinnett County Automated Inspection Request System (IVR)

Annual Service Agreement

Unitil Energy Systems, Inc. Interconnection Standards For Inverters Sized Up To 100 kva

CONTRACT FOR SALE OF REAL ESTATE

A Residential Owner s Guide to PERMITS. Elgin CITY OF PLANNING & NEIGHBORHOOD SERVICES

The formula for finding CFM is: CFM = BTUH OUTPUT_ Temp Rise (ACF)* *Altitude correction factor below 1000ft = 1.08

Load Management Wiring Guide

VertiCool Space Saver 2 to 15 tons Water-Cooled and Chilled Water

Photovoltaic Incentive Program

Hanna delivers the technical and marketing expertise needed to produce a car wash that meets the car wash customer's expectations.

york air-conditioning products Residential & VRF News 2015


Install Guide 3M-50. Caution. Caution

Certified Residential Energy Auditor (REA) Study Guide

APPLICATION FOR NEW CONSTRUCTION

HEATING AND COOLING SYSTEMS THAT FIT COMFORTABLY WITHIN YOUR BUDGET.

Electrical Engineering

Three-phase AC circuits

HV AC CODE CHECKLISTS

2015 Service Guide XCEL ENERGY. Minnesota North Dakota South Dakota Natural Gas and Electric Installation Information for Residential Contractors

How To Get A Better Deal On Power From Powerline Power From Pse

The City of Basehor, Kansas

Transcription:

BGE Service Application Guidelines Residential Modification/Relocation Projects To the Customer Following is important information to assist you in applying for BGE gas and/or electric modification or relocation of equipment, and completing the BGE Service Application for Modification/Relocation Projects of the following types of facilities: Residential rehab Increase in residential service Relocation of any residential BGE equipment, such as poles, guy wires, meters, service wires, etc. Completing the Service Application In order for BGE to meet your requested service date, we strongly recommend that you submit the service application as early as possible in your planning process. It is very important that you complete all the requested information on the service application. Do not skip or omit any of the items. This may cause unnecessary delay of your project. Jobs are subject to cancellation if you do not respond to requests for information or if initial site work does not progress. In addition, it is essential that you enter your company s name accurately on the service application. When you are asked for the Legal Name of Company, please provide the official name of your company as it appears on file with the State of Maryland Attorney General s Office. Your company s legal name will also appear on your Charter or Articles of Incorporation. Meter Location and Traffic Protection Requirements When selecting your desired electric and/or gas meter location, it is necessary to follow BGE s meter configuration and traffic protection requirements. For these requirements, please consult the BGE Gas & Electric Metering Manual or the Customer Information Booklet. These publications are available online at www.bge.com under the heading of <Business> and <New Construction Services>. Your BGE representative will also discuss these requirements with you. Submitting Other Important Information To ensure the proper processing of your service application, it is necessary for BGE to receive the following information: A completed copy of the BGE Service Application for Residential Modification/Relocation Projects A Site Plan to scale* (1 = 100 at a minimum) showing the following: All on-site utilities (water, sewer, septic area, storm drain, etc.) Proposed meter location (gas and/or electric); see BGE Gas & Electric Metering Manual at www.bge.com Existing BGE poles and pole numbers Driveway and property lines * If no site plan exists, draw your proposed work in the Sketch Area provided. You may also submit photos of your project. More important information is continued on the next page. REV. 4/2015

You may submit a hard copy of the Site Plan, an electronic file on diskette, or a CD-ROM in one of four BGE approved formats: Microstation (.dgn) (all releases) AutoCAD (.dwg) (releases prior to Version 14).dxf format.pdf format BGE s Outdoor Lighting Program If street lighting is required or you are interested in BGE s private area lighting program, visit www.bge.com/outdoorlighting. Please complete and submit the application. Small Generator Connection If your project entails small generator interconnection (solar panels, wind turbines, interconnected generators, etc.) visit www.bge.com/energychoices - Small Generator Interconnection. Please complete and submit the Interconnection Request Application in addition to this application. Working Near Power Lines The law requires that before anyone begins work that may bring people, equipment, or other objects within 10 feet of overhead power lines, they must notify BGE at 410-685-0123. Please refer to www.bge.com under the heading of <Business> and <New Construction Services> then <Additional Resources> for information on the Maryland High Voltage Line Act. In order to prevent any scheduling delays once you submit your service request, please submit a complete set of site plans with your service application as soon as possible. With regard to Verizon, CATV or other non-bge equipment relocation, contact the appropriate utility for procedures and costs. If you would like additional information about applying for BGE Service, visit New Construction Services at www.bge.com. Also available online are the BGE Gas & Electric Metering Manual and the Customer Information Booklet. REV. 4/2015 2

BGE Service Application for Residential Modification/Relocation Projects Today s Date: Requested Service Date: Service Request #: (mm/dd/yy) (mm/dd/yy) (For BGE internal use) Lead time for an individual job will vary depending on the scope of the work and weather conditions. Within 10 days of receipt of this application, the BGE representative assigned to your job will contact you to discuss the project. Please print or type. 1. Project Address: Address(es): County: ADC Map Page: ADC Grid: 2. Owner/Contractor/Builder Information: Name and/or Legal Name of Company: Mailing Address: _ 3. Person BGE will contact to discuss the Project and send communications regarding changes affecting the status of the job: Name: Title: First MI Last Legal Name of Company: Address: 4. Person responsible for Construction Charges: Name: Title: First MI Last Legal Name of Company: Address: Federal Tax ID #: REV. 4/2015

5. Person responsible for electric and/or gas monthly Consumption/Service Billing: Name: Title: First MI Last Legal Name of Company: Address: Do you currently have a BGE account? q Yes: Account # q No Have you ever had service with BGE in the past? q Yes q No If yes, at what address? 6. Project Information: Type of Building (check one): q Existing q Rehab q Single Home q Townhouse q Mobile Home Type of Service: q Electric Only q Gas Only q Gas & Electric Service Required: q Permanent q Relocation q Increase Total number of meters to be set/changed/relocated: Electric Gas 7. Please Provide a Detailed Description of Your Project: REV. 4/2015 2

8. Sketch Area: Please show existing and proposed locations of utilities. You may also submit photos of your project. REV. 4/2015 3

9. Load Information: If your project is a rehab and/or an increase in service, complete the following: Existing Building Area Sq. Footage: Existing Size of Main Disconnect: amps Electric Voltage Requirements (check one): Proposed Building Area Sq. Footage: Proposed Size of Main Disconnect: (check one) q 100 amps q 150 amps q 200 amps q 400 amps q 120/240V 1φ, 3 wire q 120/208V 3φ, 4 wire q 240V Delta 3φ, 3 wire (limited availability) Gas Delivery Pressure (check one): q Standard (1/4 PSIG) q 2 PSIG NOTE: Verify with your BGE representative that the available gas main pressure will support a 2 PSIG interior piping system. Connected Loads Include both your existing electrical loads and any new electrical loads you may be adding. Electric Type of Load Proposed New or Additional Electric Load (Do not include existing load) Existing Electric Load Total Electric Load (Proposed new or additional plus existing electric load) 1. Indoor Lighting kw kva kw kva kw kva 2. Outdoor Lighting kw kva kw kva kw kva 3. Comfort Heat kw kva kw kva kw kva 4. Heat Pump Compressor kw ton kw ton kw ton 5. Heat Pump Aux. Heat kw kva kw kva kw kva 6. Electric Baseboard (# of thermostats) kw kva kw kva kw kva 7. Air Conditioning kw ton kw ton kw ton 8. Range kw kva kw kva kw kva 9. Water Heater kw kva kw kva kw kva 10. Tankless Water Heater kw kva kw kva kw kva 11. Dryer kw kva kw kva kw kva 12. Dishwasher kw kva kw kva kw kva 13. Air Compressor kw Hp kw Hp kw Hp 14. Motors kw Hp kw Hp kw Hp Gas Type of Load Proposed New or Additional Gas Load (Do not include existing load) Existing Gas Load Total Gas Load (Proposed new or additional plus existing gas load) 1. Comfort Heat Btu Btu Btu 2. Heat Pump Aux. Heat Btu Btu Btu 3. Range Btu Btu Btu 4. Water Heater Btu Btu Btu 5. Tankless Water Heater Btu Btu Btu 6. Dryer Btu Btu Btu 7. Pool Heater Btu Btu Btu 8. Generator Btu Btu Btu 9. Gas Fireplace Btu Btu Btu 10. Outdoor Grill Btu Btu Btu 11. Other: Btu Btu Btu Btu Btu Btu Btu Btu Btu REV. 4/2015 4

10. If there is any other information that BGE needs to know about your project, please note below: 11. Summary: To ensure that BGE can quickly and easily process your service application, please provide the following: 4 Load information 4 A complete set of plans including (electronic version, if available): All on-site utilities (water, sewer, septic area, storm drain, etc.) Proposed meter location (gas and/or electric); see BGE Gas & Electric Metering Manual at www. bge.com Driveway and property lines Mail service application and complete set of plans to: Have questions? BGE - Customer Planning Department Call the BGE New Business Department Service Application Unit 800-233-1854 1068 N. Front Street, Room 501 Or visit the BGE website at www.bge.com PO Box 1475 Baltimore, MD 21203-1475 REV. 4/2015 5