APPLICATION OF PRIMAVERA ENTERPRISE IN ELECTRIC POWER DISTRIBUTION OF BELGRADE
|
|
|
- Leonard Atkinson
- 10 years ago
- Views:
Transcription
1 APPLICATION OF PRIMAVERA ENTERPRISE IN ELECTRIC POWER DISTRIBUTION OF BELGRADE Milan ŠMIGIĆ Centar za upravljanje projektima CPM, Beograd, Serbia and Monte Negro Goran ŽIVADINOVIĆ Elektrodistribucija Beograd - EDB, Beograd, Serbia and Monte Negro INTRODUCTION This paper describes the implementation of Primavera Enterprise software for Project Management in Electric Power Distribution Company of Belgrade, Serbia (EDB - Elektrodistribucija Beograd) based on the real-life investment project examples from fiscal year 2003 and Primavera Enterprise is comprehensive, multiproject planning and control software, built on SQL, Oracle, and InterBase server databases for enterprise wide project management implementations. EDB BUSINESS NEED AND PM IT SOLUTION PLATFORM In today s complex business environment in Serbia, electric utility organizations (like EDB in Belgrade) often have multiple projects underway at the same time, sharing the same resources. To ensure that projects are completed on time and within budget, executives, project managers, and other members of the project team need to be able to see both summary and detail information about all aspects of all projects in the enterprise - both planned and in progress. For EDB Primavera Enterprise platform has provided the enterprise structure needed to manage multiple projects-from the highest levels of the organization to the individuals that perform specific tasks. Primavera Enterprise Project Management Solution includes Primavera Project Planner for the Enterprise (abbreviated P3e), which can be used as stand alone for project and resource management, or it can be used with other PM companion products. For example, Primavera Progress Reporter enables Web-based team communication and time keeping, Primavera Portfolio Analyst provides project analysis across the enterprise, and Primavision allows users to access project management data via the Internet. P3e is a multiuser, multiproject system with scheduling and resource control capabilities supporting complex project hierarchies, durations and scheduling in time units as small as minutes, resource scheduling with a focus on roles and skills, recording of actual data, customizable views, and userdefinable data. In EDB P3e was ideal IT solution because it fit the need to simultaneously manage multiple project and support multiuser access across a department or across the entire enterprise. It supports an enterprise project structure (EPS) with an unlimited number of project, activities, baselines, resources, work breakdown structures (WBS), organizational breakdown structure (OBS), user-defined codes, and critical-path-method scheduling and resource levelling. On the other hand it also provides centralized resource management. This includes resource timesheet approval and ability to communicate with project resources who use Progress Reporter, Primavera Enterprise/s Web-based timesheet management, issue tracking, and management by threshold. MANAGING CAPITAL PROJECTS IN EDB Before implementing P3e to schedule projects, team members and other project participants were thoroughly trained to understand the processes involved in project management and the associated recommendations that help smooth implementation of the software that supports corporate mission. Simply stated, all key stakeholders had to understand that project management is the process of achieving goals within the constraints of time, budget, and staffing restrictions and not some software tool reserved for IT managers or engineers. The key point for putting project managers on the same page was the fact that project management allows project managers to get the most out of company available resources. For Top Executives company resources were easily defined as: People, Materials, Money, Equipment, Information, Facilities and Knowledge. But the hardest thing to describe and prove was that Project Management across the enterprise factors in all of these variables across multiple projects, enabling project managers and company executives to see an accurate picture of how project/s resource use affects other projects. The process of project management in EDB was finally defined based on three key principles: Planning Controlling Managing
2 Planning a project The first step in EDB capital project management process is to define a project. It includes the following questions and answers set: What is the scope of the project? What is the project duration? What resources are available to the project? Who will perform what tasks? How much will the project cost? What is the estimated budget? The answers to these questions form the framework of a project to EDB managers. Controlling a project Once the management has built the project and estimated the budgeting needs, Project Manager provides to management detailed project plan and after his/her plan is approved saves his/her original plan as a baseline to help himself/herself control the project in the next phase. A baseline provides a solid point of reference as project schedule changes over time. It allows project manager to compare the original schedule to the current one and identifies significant changes and develops contingency plans. EDB Project manager on weekly basis collect and compare all project actuals (time, scope, costs) in order to keep project heading in the right direction. Effective project control in EDB reaps many benefits. It allows Project Manager to keep a close eye on possible problems before they become critical (and costly). And it also enables the project team and senior management to view real-time cost and scheduling timeframes based on the reality of the actual schedule. Managing a project Dates on which activities started or finished Quantities of resources consumed Changes to scope Unit price changes EDB SINGLE PROJECT MANAGEMENT IMPLEMENTATION PROCESS Utilization of Primavera Enterprise Project Management Solution in Sector for Capital Investments of EDB will be explained using the example of pilot project»district network in suburban area Borca Greda«. Definitions and explanations of this particular investment project, planned and executed in 2003, will be given simultaneously with definitions commonly used in Primavera Project Management software solution. Enterprise Project Structure (EPS) In EDB, typically top management users in an enterprise will have access to a large database that contains all the projects and project-related information from the field. The information this database contains must be structured in a way that allows individuals to access the project data they need, quickly and accurately. In P3e, database of projects is arranged in a hierarchy called the enterprise project structure (EPS). The EPS is further subdivided into 3 main levels or nodes as needed for efficient project analyses from the enterprise perspective. The 3 main EPS nodes are Projects Planned, Project in Execution and Project Completed. Part of the Enterprise Project Structure of EDB projects is shown in Fig. 1. It is not the complete EPS of EDB company s projects but it rather represents the PM s perspective of it. The seven projects in the first subdivision of EPS are in planned status, meaning that these projects are not in a progress state in a given instance of time. FIGURE 1 The part of EDB EPS structure This process, as defined by EDB management, is the process of guiding a project from start to finish and this process is the shared responsibility of functional and project manager. A good project manager wears many hats, acting at various times as a motivator, communicator, coordinator, and advisor to the project team. On the other hand EDB functional manager is always there to help if resources became scarce or the specific knowledge and know-how becomes unavailable to the project team. On the end of the day, as the project s progress is being monitored weekly, it is the Project Manager s job to keep the project team aware of changes to the schedule and scope. Effective project management also requires consistency on when to engage the upper management regarding the project details. This project communication issue has been resolved in EDB by regular daily on-line update based on Primavera software solution that includes baseline and progress of all major project values such as:
3 Organization Breakdown Structure (OBS) Organizational Breakdown Structure (abbreviated OBS). In EDB, the organizational breakdown structure is a global hierarchy that represents the managers responsible for the projects in an enterprise. The OBS reflects the management structure of an organization, from top-level personnel down through the various levels constituting department managers. When specific responsible manager is associated with an EPS node, any project added to the branch of this EPS is assigned to that managers responsibility by default. OBS hierarchy is also used to grant user s specific access privileges to project level data and project WBS level data. Activity network A detailed list of activities can be added for each WBS element on the lowest hierarchical level. This process is shown on the left-hand side of Figure 3. Therefore, WBS element (Prethodne aktivnosti) is subdivided into 9 activities, each of them having Activity Code (»A2490«for example) and Activity Name (»Revidovanje Projekta - Interno«). Original Duration Column shows the duration of each activity. So, original duration of A2490 activity is 1 day. FIGURE 3 Activity table and Gantt chart Work Breakdown Structure (WBS) A Work Breakdown Structure (WBS) is a hierarchical arrangement of the products and services produced during the project. The project is the highest level of the WBS while an individual activity required creating a product or service is the lowest level. Each project in the Enterprise Project Structure has its own WBS. When creating a project in P3e, the project manager typically develops the WBS first, assigns reference documents to each WBS element, and then defines activities for performing the element's work. As it can be seen from Figure 2, Work Breakdown Structure begins with the node of highest level. So, in the root of the tree is the name of the project. The WBS subdivision nodes on lower level are commonly used in EDB Company for TS 10/0.4 kv. This arrangement can also be available for some other type of projects. In the example of project which is considered in this paper only the Realization is subdivided in three parts on the lowest hierarchical level: Preliminary Activities, Building Activities and Final Activities. For each hierarchical level (node) a Responsible Manager is defined. For example Goran Živadinović is the Responsible Manager at the root of the WBS, and Lidija Stanković for WBS element called Prethodne aktivnosti, and so forth. FIGURE 2 An example of WBS The right-hand side of Fig. 3 graphically shows the duration of activities and Timescale. All activities have its planned start and planed finish, which are displayed with the Primary Baselines. So the planned finish of activity A2480 is 23 May 03. Actual finish of that activity is 26 May 03. Duration of an activity is separated on two parts: Actual Work and Remaining Work. For example the remaining duration of A2500 activity is 6 days. Gantt Chart shows the state of all activities at some particularly instant of time called Data Date. In our example Data Date is 04-June-03. Activity Network is shown in Fig. 4. To create an activity network all relationships between activities must be first defined. FIGURE 4 The part of the activity network showing activities that belong to WBS-element Građenje objekta
4 EDB ENTERPRISE WIDE PROJECT MANAGEMENT IMPLEMENTATION PROCESS Implementation of Primavera Enterprise software was started at the beginning of The team, whose members were engineers from Sector for Capital Investment, was formed in order to define and execute The Project of Enterprise wide PM Implementation. As a first result of this team work, two models of typical projects that are commonly managed in Sector for Investment were established. Although, the Activity Networks for different projects are not the same, it helped us in planning the particular projects. Thus, the project»district network in suburban area Borca Greda«differs from the Model of project of that type in some elements, but not completely. After the PM Methodology training, CPM consulting team has also implemented Primavera software setup and training. When basic platform had been finished, Pilot-Project based on the previously defined model was introduced, and managing some of the projects of Sector for Investment has been started. Here are the most important experiences and considerations based on utilizing Enterprise wide Project Management in EDB. Maturing the PM tools and the PM processes Given the renewed EDB focus on project management as the delivery system for corporate capital and maintenance projects, it is natural for organizations to seek a method of ascertaining the maturity of their current project management processes. Therefore in the first phase of this project CPM consulting team and the authors have thoroughly analyzed a standard PMI Project Management Capability Maturity Model (PMCMM) and applied it within an EDB. This process has gained the endorsement of the company s management and buy-in by the rank and file employees. Even more to the point and used in conjunction with the requisite training and reinforcement, the CPM team has help EDB management to produce significant positive results within only a few months after initial application. This section will therefore focus on the following: 1. Outline the development of PM tools that the authors have recently employed to help organizations assess their project status, 2. Indicate how go-forward plans were developed and reviewed 3. Indicate the potential application of PM tools toward other projects in the region. First, we would like to describe the experience in utilizing PM tools from the management point of view. Utilizing specific PM tools affects the following items: 1. Procedures applying in process of execution of projects have become transparent to all project participants, 2. Project Management process is now comprehensively defined for all users, 3. Enterprise wide PM tools support a big picture in managing projects from top management perspective, that is allows top managers to view the project details all at once in on-line manner, 4. Teamwork in planning and responsibility in controlling and managing project activities needs to be established and supported at the Department level and generally in a Company as a whole. In the past for many EDB projects, project-team was commonly not been formed. Thus the WBS elements and corresponding Activity Networks were not planned by the responsible managers (PM) or the members of the team but usually only one man has acted all the roles. The project planning was a typical One man show. For many companies in utility sector in Serbia this is a serious problem that can dramatically reduce all other benefits of using PM tools enterprise wide. Here are some of the best practice experiences of CPM consulting team that helped implementation of PM tools in EDB. The initial task list for the consulting team supporting the implementation of PM tools is as follows: 1. To fully understand the organizational culture and processes of the client. 2. To educate the core management team. 3. To use PM maturity tools to objectively evaluate the client s project management processes and IT infrastructure against measurable criteria. 4. To provide a written report and review with the client s top management level. 5. To recommend changes to both IT infrastructure and PM processes To get the Project Management Maturity to the next level, From Author s working experience on several similar projects, these initial methodology steps provide the most accurate and useful information basis regarding both the PM processes and the organizational PM maturity with the least risk of significant implementation errors in the future (delays, budget changes, unsatisfied client, scope creep etc.). Learning about the existing PM norms and skills before implementing any new PM software tools authors have improved understanding of EDB s existing PM maturity and therefore enabled successful project implementation.
5 LESSONS LEARNED During the course of this project Top Management was kept totally involved and engaged, first by presentation and approval of a proposed consultation scope of work, and later by a constantly updated WBS and a schedule (yes, there was considerable scope creep ) with Earned Value criteria so that the client always knew where it had been, where it was going, and (more to the point!) how much the consulting project was going to cost. The initial report of the preliminary interview/survey was reviewed with the client and it was explained where differences existed between what was designed (client s designed process) and what existed (what the client s PMO and supporting personnel actually thought and were doing). These differences were further explained in terms of improvement goals that were achievable at various levels. Since CPM had also performed a statistical analysis, we were also able to present the degree of correlation achieved for each individual survey question and for the survey process overall. The client comments (or push back ) were then analyzed, responded to, and (where applicable) integrated into the final or formal report. One of the most striking benefits of this overall PM implementation process was the change in corporate culture. Although the project managers were defined by the effective process as accountable for costs (generally defined as both being responsible and possessing requisite authority ), there was no infrastructure to provide cost reporting and forecasting, nor did they possess or exercise any significant control over project expenditures. There are many more such examples that could be cited of an observed delta between designed and actual processes, but these will suffice to convey the degree of change in attitude and corporate culture that was required and is even now progressing in EDB. In general, the overall results of the more specific recommendations have been positive and particularly very positive in the areas as follows: REFERENCES 1. Goulet, Douglas R Measuring the Success of Project Management and the Capability Maturity Model Using the Parking Lot Metric. Proceedings of the Project Management Institute Annual Seminars & Symposium. Newtown Square, PA: Project Management Institute. 2. Kerzner,Harold Strategic Planning for Project Management Using a Project Management Maturity Model. New York: John Wiley & Sons. 3. Kwak, Young H., and William C. Ibbs Calculating Project Management s Return on Investment. Project Management Journal (June): Moore, Thomas J An Evolving Program Management Maturity Model: Integrating Program and Project Management. Proceedings of the Project Management Institute Annual Seminars & Symposium.Newtown Square, PA: Project Management Institute. 5. Project Management Institute A Guide to the Project Management Body of Knowledge, Figure 2-11, p. 22. Newtown Square, PA: Project Management Institute. 6. Rosenstock, Christian, Robert S. Johnston, and Larry M. Anderson Maturity Model Implementation and Use: A Case Study. 7. Proceedings of the Project Management Institute Annual Seminars & Symposium. Newtown Square, PA: Project Management Institute. 8. Software Engineering Institute, (1994). The Capability Maturity Model: Guidelines for Improving the Software Process. Reading, MA: Addison Wesley Longman, Inc. 9. Proceedings of the Project Management Institute Annual Seminars & Symposium November 1 10, 2001 Nashville,Tenn.,USA 1. In the area of team building and communication. 2. The client has revamped their old paper-based scheduling system and upgraded to a more robust enterprise scheduling tool (P3e) that provides the requisite level of response. 3. An automated cost tracking, reporting, and forecasting system has been developed and is being implemented. 4. Material expediting and tracking, once a function belonging almost solely to the overworked field construction engineers, has been taken over by a new material tracking and expediting functionality over to the EDB from the Resource manager.
LECTURE -08 INTRODUCTION TO PRIMAVERA PROJECT PLANNER (P6)
LECTURE -08 INTRODUCTION TO PRIMAVERA PROJECT PLANNER (P6) GOAL In this lecture, we ll learn: Background of Primavera Project Planner (P6) Getting Started P6 Interface Basic Navigation and Operation Setting
Oracle Primavera P6 Enterprise Project Portfolio management Overview Programme Reference # 201A
Oracle Primavera P6 Enterprise Project Portfolio management Overview Programme Reference # 201A Programme Description: Dedicated one full day training module in a structured and professional manner to
CA PA for CA Clarity PPM 14.2: Project and Investment Management 200
CA PRODUCTIVITY ACCELERATOR CONTENT DESCRIPTION CA PA for CA Clarity PPM 14.2: Project and Investment Management Content Overview PRODUCT RELEASE CA Clarity PPM 14.2 DURATION & COURSE CODE Three (3) Hours
ARTEMIS VIEWS ADVANCED PLANNING. With ProjectView
ARTEMIS VIEWS ADVANCED PLANNING With ProjectView ADVANCED PLANNING Advanced Planning is a powerful role-based project and resource management application. Designed for project managers, project planners
ROI Building The Business Case For Professional Services Automation
ROI Building The Business Case For Professional Services Automation Robert D. Anderson, CPA Director Specialized Services Hitachi Consulting Kimberly McDonald Baker Vice-President, Sales and Marketing
PBL: Project Management. Competency: Project Definition
Competency: Project Definition 1. Define project management and the context of modern project management. 2. Describe how to manage projects throughout the five major process groups. 3. Define the characteristics
The Amazing History of Primavera Software
The Amazing History of Primavera Software (as told by a Complete Outsider) By Ron Winter, PSP Schedule Analyzer Software History? There is nothing new in the world except the history you do not know. Harry
PMO Metrics Recommendations
Introduction The purpose of this document is to recommend metrics to be used by the Project Management Office (PMO) to measure and analyze their project and PMO success. The metrics are divided into Project
Primavera Project Manager for the Enterprise Version 6.1 Custom Training Manual
Primavera Project Manager for the Enterprise Version 6.1 Custom Training Manual Course Contents June 27, 2003 This publication is produced as a custom training document for The University of North Carolina.
Primavera P6 Enterprise Project Portfolio Management Certified Implementation Specialist
Oracle 1z0-535 Primavera P6 Enterprise Project Portfolio Management Certified Implementation Specialist Version: 6.0 QUESTION NO: 1 Select the true statement regarding Global Preferences in Primavera P6
PROJECT MANAGEMENT IN PRIMAVERA P6 WEB ACCESS REL 7
PROJECT MANAGEMENT IN PRIMAVERA P6 WEB ACCESS REL 7 Duration: 03 days INTRODUCTION This course provides hands-on training for Primavera s web-based solution. Participants will create a project, add activities
Project Control System Manual. Jefferson Science Associates, LLC. 200 Organization. Project Control System Manual Revision 7 - 7 -
Jefferson Science Associates, LLC 200 Organization Project Control System Manual Revision 7-7 - 200 Organization This section of the JSA Project Control System Manual describes the organizational elements
Description of Program Management Processes (Initiating, Planning) 2011 PROGstudy.com. All rights reserved
Description of Program Management Processes (Initiating, Planning) Topics Covered Program Management Process Groups salient features Description of all processes in Initiating Process Group: Initiate Program
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects
State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement
WelcomRisk. For organizations looking to improve project performance through proactive risk management.
Welcom For organizations looking to improve project performance through proactive risk management. Improved Project Performance Through Better Management. All projects are exposed to varying degrees of
Project Management Certificate (IT Professionals)
Project Management Certificate (IT Professionals) Whether your field is architecture or information technology, successful planning involves a carefully crafted set of steps to planned and measurable goals.
Preplanning And Scheduling Of Road Construction By Using PPM
Preplanning And Scheduling Of Road Construction By Using PPM 1 T.Subramani, M.Sekar 2 1Professor & Dean, Department of Civil Engineering, VMKV Engg. College, Vinayaka Missions University, Salem, India
Oracle s Primavera P6 Enterprise Project Portfolio Management
Oracle s Primavera P6 Enterprise Project Portfolio Management Oracle s Primavera P6 Enterprise Project Portfolio Management is the most powerful, robust and easy-to-use solution for prioritizing, planning,
Project Management Concepts
Project Management Concepts Day Workshop Course PM12 PM12 - Project Management Concepts Course ID: PM12 Credits: 21 PDUs Course Duration: 3 days Course Level: Basic 3 Days 21 PDUs Course Description: In
CA Clarity Project & Portfolio Manager
CA Clarity Project & Portfolio Manager Project Management User Guide v12.1.0 This documentation and any related computer software help programs (hereinafter referred to as the "Documentation") are for
The History of Primavera Scheduling Software Copyright February 10, 2013 by Ron Winter, PSP
The History of Primavera Scheduling Software Copyright February 10, 2013 by Ron Winter, PSP Please Note: This is paper is the result of an independent project by Ron Winter Consulting LLC. The information
1 Start a new project
Project Management Quick Reference Guide for Microsoft Project 2010 Before beginning a new project, an organization must determine whether the project fits its strategic goals. Executives should classify
Using Primavera Software in Resource Allocation and Project Evaluation of Construction Projects
Using Primavera Software in Resource Allocation and Project Evaluation of Construction Projects Hamed Ziaidoostan 1, Hamidreza Ghaneh 2, Matin Amanin 3, Mohamadmahi Gholipoor 4 1,2,3,4-M A Student of Business
Oracle Primavera. P6 Dashboards Demo Script
Oracle Primavera P6 Dashboards Demo Script Script Team Information Role Name Email Primary Author L. Camille Frost [email protected] Contributor Reviewer Richard Ring [email protected] Manager
CA Clarity PPM. Project Management User Guide. v13.0.00
CA Clarity PPM Project Management User Guide v13.0.00 This documentation, which includes embedded help systems and electronically distributed materials, (hereinafter referred to as the Documentation )
Primavera P6 Enterprise Project Portfolio Management
Primavera P6 Enterprise Project Portfolio Chris Sala Director, Primavera GBU Federal/A&D Sales Oracle Primavera Provides Platform for Enterprise Program Capture, institutionalize
A collection of Safran Project report samples for project professionals
A collection of Safran Project report samples for project professionals Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger www.safran.com Contents Introduction... 2 About the Reports
Work Breakdown Structure (WBS)
Work Breakdown Structure (WBS) The building blocks of a schedule start with a Work Breakdown Structure (WBS). The WBS is a hierarchical reflection of all the work in the project in terms of deliverables.
Project Management Professional (Certified by PMI)
Project Management Professional (Certified by PMI) PMI certified Project Management Professional credential is the most important industryrecognized certification for project managers. This recognition
Glossary. Release 13.3.00
Glossary Release 13.3.00 This Documentation, which includes embedded help systems and electronically distributed materials, (hereinafter referred to as the Documentation ) is for your informational purposes
Guidelines: Project Schedule Project Management Office (PMO)
Guidelines: Project Schedule Project Management Office (PMO) Process The project Schedule outlines the tasks and activities of the project; the duration; start and end dates for each individual task and
PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited
PROJECT TIME MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT WHAT DOES THE TIME MANAGEMENT AREA ATTAIN? Manages the project schedule to ensure timely completion of
Methodology Management. Reference Manual
Methodology Management Reference Manual 1997-2005 Primavera Systems, Inc. All rights reserved. Unless otherwise noted, this software is the property of Primavera Systems, Inc. (Primavera) or its licensors
Chapter 6. (PMBOK Guide)
Chapter 6 Project Time Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: [email protected] ir Homepage:
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction
Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects Puian Masudifar, Deputy CEO, VIRA Consulting Engineers Fereydoun Fardad, Aryana Project Management
Project Management Framework
Project Management Framework Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
Project Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
Project Management Guidebook
METHOD 12 3 empowering managers to succeed Project Management Guidebook ISBN 0-473-10445-8 A bout this e-book This e-book was created by Method123 (see www.method123.com) to help provide you with a simple
PROJECT MANAGEMENT TECHNIQUES FOR NON-PROJECT MANAGERS. Session 2
PROJECT MANAGEMENT TECHNIQUES FOR NON-PROJECT MANAGERS Session 2 Agenda Introduction Project Management Overview Project Management Concepts Project Management Techniques BC Technology Summary Q&A Introduction
Using Project and Resource Management with Clarity
Using Resource and Project Management with Clarity Using Project and Resource Management with Clarity Self Paced Training Course Page 1 of 112 Using Resource and Project Management with Clarity Module
http://metalink.oracle.com/ http://support.oracle.com/
P3 to P6 Professional Migration Guide Release 8.1 May 2011 Copyright Oracle Primavera P3 to P6 Professional Migration Guide Copyright 1999, 2011, Oracle and/or its affiliates. All rights reserved. The
Develop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by
Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Paul E Harris Administration Evacuation Timings, meals and facilities Mobile phones
CA Clarity PPM. Glossary. Release 13.1.00
CA Clarity PPM Glossary Release 13.1.00 This Documentation, which includes embedded help systems and electronically distributed materials, (hereinafter referred to as the Documentation ) is for your informational
Collaborative Scheduling using the CPM Method
MnDOT Project Management Office Presents: Collaborative Scheduling using the CPM Method Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE Table of Contents Introduction...3-1 Overview...3-1 The Process and the Project Plan...3-1 Project Objectives and Scope...3-1 Work Breakdown Structure...3-1
Is Your Schedule Correct? Common Scheduling Mistakes and How to Avoid Them
Sponsored by Is Your Schedule Correct? Common Scheduling Mistakes and How to Avoid Them Joseph A. Lukas PMP, CSM, CCP, PE White Paper 1-888-762-3683 www.pmcentersusa.com Joe Lukas & PM Centers USA, LLC
PeopleSoft Program Management
PeopleSoft Program Management Large enterprises and project-based organizations have long recognized the value of leveraging project knowledge across multiple projects. Yet today, 50 percent of IT projects
A Project Manager s Guide to Tracking Time and Resources
A Project Manager s Guide to Tracking Time and Resources Contents A Project Manager s Guide to Tracking Time and Resources...3 Project Management Methodologies...3 Project Management Body of Knowledge
Oracle Project Portfolio Management Integration Pack for Primavera P6 and Oracle E-Business Suite 3.1 - Implementation Guide
Oracle Project Portfolio Management Integration Pack for Primavera P6 and Oracle E-Business Suite 3.1 - Implementation Guide Release 3.1 Part No. E20507-02 June 2011 Oracle Project Portfolio Management
Project Initiation and Revision Training Manual. Table of Contents
for Engineering and Construction v.4.1 Project Initiation and Revision Training Class Conducted by Evans Technology June 2005 Table of Contents Introduction to Primavera... 3 Project Management (P3eC)...
Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time
Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Computer Scheduling Critical path method (CPM) requires numerous computations to determine activity start and finish dates,
Reading Sample. Integration Scenarios with Other Project Management Tools. Contents. Index. The Author. Project Management with SAP Project System
First-hand knowledge. Reading Sample SAP Project System s innovative design allows for cross-platform usage. This is good news for companies who manage projects through different programs and software.
Project Scope Management in PMBOK made easy
By Dr. TD Jainendrakumar The main objective of any project is to fulfill the scope of the project on time and within the budget. What is Project Scope? Scope refers to all the work involved in creating
Unit 4: Time Management (PMBOK Guide, Chapter 6)
(PMBOK Guide, Chapter 6) The questions on this topic focus heavily on scheduling techniques, network diagrams, Gantt charts, the critical path, compressing the schedule, PERT, and float. You may or may
Assessing the Appropriate Level of Project, Program, and PMO Structure
PMI Virtual Library 2011 Daniel D. Magruder Assessing the Appropriate Level of Project, Program, and PMO Structure By Daniel D. Magruder, PMP Executive Summary Does your organization have in-flight projects
Laboratory 1 Initiating a Project
Laboratory 1 Initiating a Project Outline What is a project? What is project management? Initiating a project. Getting Starting with Project 2007? What Is a Project? A project is an activity that has a
Manual on Training Preparation
Project on Improvement of Local Administration in Cambodia Three Steps of Training Preparation Step 1: Work Breakdown Structure Step 2: Schedule Step 3: Budget Table of Contents Three Steps of Training
300 Scheduling and Budgeting
Jefferson Science Associates, LLC 300 Scheduling and Budgeting Project Control System Manual Revision 7-16 - 300 Scheduling and Budgeting This chapter of the JSA Project Control System Manual describes
Stefan Glatzmaier, Michael Sokollek. Project Portfolio Management with SAP. RPM and cprojects. Bonn Boston
Stefan Glatzmaier, Michael Sokollek Project Portfolio Management with SAP RPM and cprojects Bonn Boston Contents Acknowledgements... 9 Introduction... 11 1 Overview of Project Portfolio Management with
Chapter 4. The IM/IT Portfolio Management Office
Chapter 4 The IM/IT Portfolio Management Office Learning Objectives Identify some of the primary causes of IM/IT project failures. Describe the main differences between IM/IT project management, IM/IT
TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain *
TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT Hazar Hamad Hussain * 1. Introduction The definition of Project as a temporary endeavor... refers that project has to be done within a limited
MANAGING PROJECT MANAGEMENT
1-01-15 INFORMATION MANAGEMENT: STRATEGY, SYSTEMS, AND TECHNOLOGIES MANAGING PROJECT MANAGEMENT Nancy Blumenstalk Mingus INSIDE Project Management Methodologies and Life Cycles; Selecting Project Management
PROJECT COST MANAGEMENT
7 PROJECT COST MANAGEMENT Project Cost Management includes the processes required to ensure that the project is completed within the approved budget. Figure 7 1 provides an overview of the following major
The Project Planning Process Group
3 The Project Planning Process Group............................................... Terms you ll need to understand: Activity Activity attributes Activity list Activity on arrow diagram (AOA) Activity
Dashboards and Reporting for Program Management
MnDOT Project Management Office Presents: Dashboards and Reporting for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will
IT Project Portfolio Management Doing The Right Things Right
IT Project Portfolio Management Doing The Right Things Right What is IT Project Portfolio Management? The Project Management Institute (PMI) defines Project Portfolio Management (PPM) as the centralized
What is Costrac? Approval of Budget against WBS. Feasibility Study Completed. Define & Map WBS. Approval of WBS. Estimate
The outcome of any venture is most often affected by the ready availability of useful information on which timely decisions can be taken. For project success, the need is therefore to know where you re
PROJECT TIME MANAGEMENT
6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity
Primavera P6 Enterprise Project Portfolio Management 8 Essentials (1Z0-567) Exam Study Guide
Primavera P6 Enterprise Project Portfolio Management 8 Essentials (1Z0-567) Exam Study Guide Margy Girdzius Director, Partner Enablement WWA&C Objective & Audience Objective Help you prepare to take the
APPLYING PROJECT MANAGEMENT TECHNIQUES TO QEHS
APPLYING PROJECT MANAGEMENT TECHNIQUES TO QEHS Mary F. McDonald, CQA President/Principal Consultant Individual Solution Options/Quality Services (ISO/QS), Inc. Austin, TX 78739 Tel: (512) 282-0181 E-mail:
PROJECT MANAGEMENT COURSE CATALOG
PROJECT MANAGEMENT COURSE CATALOG CATALOG GUIDE PROJECT MANAGEMENT FUNDAMENTALS 3 CAPM AND PMP CERTIFICATION - PREPARATORY COURSE 4 RISK MANAGEMENT 5 QUALITY MANAGEMENT 6 PLANNING AND CONTROL USING PRIMAVERA
See What's Coming in Oracle Project Portfolio Management Cloud
See What's Coming in Oracle Project Portfolio Management Cloud Release 9 Release Content Document Table of Contents GRANTS MANAGEMENT... 4 Collaborate Socially on Awards Using Oracle Social Network...
How to Develop Work Breakdown Structures
How to Develop Work Breakdown Structures Michael D. Taylor Copyright 2003-2009 by Michael D. Taylor All Rights Reserved. No part of this work covered by the copyright hereon may be reproduced or used in
SCHEDULING AND TIME MANAGEMENT. Project Management and Leadership 2015D, PhD, PMP
SCHEDULING AND TIME MANAGEMENT Project Management and Leadership 2015D, PhD, PMP Our PROGRAMME: 1. INTRODUCTION TO PROJECT MANAGEMENT 2. STARTING A PROJECT 3. WORK MOTIVATION 4. COMMUNICATION 5: TEAMS
Chapter 2: Project Time Management
Chapter 2: Project Time Management Learning Objectives o o o o Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules.
PROMASTAR Instructor-led Professional Training Services
PROMASTAR Instructor-led Professional Training Services Primavera P6 Professional Fundamentals Rel 8.3 Primavera P6 Professional Fundamentals Rel 8.3 Page 1 Oracle Primavera Learning Experience Learning
Project Management Guidelines
Project Management Guidelines Overview Section 86-1506 (5) directs the NITC to adopt guidelines regarding project planning and management. The goal of project management is to achieve the objectives of
Training Seminars. Description. Core Courses: The core courses consist of the following:
Training Seminars Description The POI consists of training courses known as core. The purpose of the core courses is to provide a principles or foundation knowledge baseline to the student in the fundamentals
EXAMPLE <PROJECT NAME> DATE
EXAMPLE DATE TABLE OF CONTENTS 1. EXECUTIVE SUMMARY... 2 1.1. Issue... 2 1.2. Anticipated Outcomes... 2 1.3. Recommendation... 2 1.4. Justification... 3 2. BUSINESS CASE ANALYSIS TEAM...
INFORMATION CONNECTED
INFORMATION CONNECTED Business Solutions for the Utilities Industry Primavera Project Portfolio Management Solutions Achieve Operational Excellence with Robust Project Portfolio Management Solutions The
PROJECT PLANNING & SCHEDULING USING PRIMAVERA P6 TM. in an PAUL EASTWOOD HARRIS
PROJECT PLANNING & SCHEDULING USING PRIMAVERA P6 TM For all industries including Versions 4 to 6 Planning and Progressing Project Schedules With and Without Roles and Resources in an Established Enterprise
Leveraging SharePoint for Project, Program, and Portfolio Management
Leveraging SharePoint for Project, Program, and Portfolio Management Addressing the Challenges of Communicating, Coordinating, Controlling, and Complying Delivered by Dean W. Farmer, MMS, PMP at the SIUE
Business ByDesign. The SAP Business ByDesign solution helps you optimize project management
SAP Functions in Detail SAP Solutions for Small Businesses and Midsize Companies Efficient Project Management Drive Project Success with SAP Business ByDesign The SAP Business ByDesign solution helps you
Module 11. Software Project Planning. Version 2 CSE IIT, Kharagpur
Module 11 Software Project Planning Lesson 29 Staffing Level Estimation and Scheduling Specific Instructional Objectives At the end of this lesson the student would be able to: Identify why careful planning
PORTFOLIO MANAGEMENT TRAINING
PORTFOLIO MANAGEMENT TRAINING OBJECTIVE To qualify students in the portfolio management, one of the main strategic alignment tools between the project management and the organizational strategy. TRAINING
pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
Program Lifecycle Methodology Version 1.7
Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated
A Step-by-Step Approach for Planning Your Small Project
A Step-by-Step Approach for Planning Your Small Project Dohn Kissinger, MBA, PhD, PMP Planning for a small project is difficult. The PMBOK Guide (PMI, 1996) is an impressive document, which thoroughly