Project Management Procedures SECTION 3 PROCUREMENT

Size: px
Start display at page:

Download "Project Management Procedures SECTION 3 PROCUREMENT"

Transcription

1 Property & Campus Services Project Management Procedures SECTION 3 PROCUREMENT Maintainer: pcs-project-office@unimelb.edu.au Page: 1 of 8

2 3.1 TABLE OF CONTENTS 3.2 INTRODUCTION SELECTION OF TENDERERS CONTRACT DOCUMENTS RETENTION TENDERS FOR SERVICES AND OTHER SPECIALIST TRADES TENDER RECEIPT TENDER EVALUATION AND RECOMMENDATION INDUCTION OF CONTRACTORS PREAWARD MINUTES SAFE WORK METHOD STATEMENTS (SWMS) PROJECT APPROVAL BUILDING WORKS COMMENCEMENT NOTIFICATION BUILDING PERMIT EH&S ASSESSMENT...7 RELATED DOCUMENTS...8 RESPONSIBLE OFFICER... Error! Bookmark not defined. IMPLEMENTATION OFFICER... Error! Bookmark not defined. REVIEW... Error! Bookmark not defined. VERSION HISTORY... Error! Bookmark not defined. POLICY LIBRARY REQUIREMENTS... Error! Bookmark not defined. Maintainer: Page: 2 of 8

3 3.2 INTRODUCTION The Project Manager is responsible for: Procurement of the works by whatever delivery method is selected, meets the University s requirements as detailed in University s Building Tendering and Purchasing Policy UOM0385 Compliance with the University s Tendering Guidelines for calling and reviewing tenders for all contracts required to deliver projects. Co-ordinating the various resources to complete the project within specified constraints of time, cost and quality and becomes the single point of contact for the client during the course of the project. Maintaining hard copy and electronic files for all projects in up-to-date condition in the format prescribed by the Director, Project Delivery. Progressively entering all relevant information into the Property & Campus Services (PCS) Project Reporting Database. 3.3 SELECTION OF TENDERERS On all projects, the Project Manager shall ensure that a list of tenderers is prepared, in conjunction with the Design Team, for approval by the Construction Manager (refer to Tender Report). Contractors shall be selected to tender for a specific project on the basis of the following criteria:- Previous experience in similar projects Experience working for the University of Melbourne Technical capacity Financial capacity Quality Assurance Time performance Environment, Health and Safety Human resources management Skill formation Price The selection of Contractors to tender shall be made from the Property & Campus Services Contractor Panel for the appropriate category. If it is proposed to invite a Contractor to tender who is not on the Contractor Panel, the Construction Manager may give interim approval whilst the Contractor becomes registered with Property & Campus Services. The Construction Manager shall maintain a list of tenderers, and shall ensure that an appropriate number and range of tenderers are sought for all projects. Procurement Guidelines are to be followed unless otherwise approved by the Construction Manager. Where the guidelines are not followed, reasons must be stated on the Tender Report. 3.4 CONTRACT DOCUMENTS General Conditions of Contract will depend on the project value (refer to Procurement Guidelines), and will be nominated by the Project Manager in consultation with the Design Team and approved by the Construction Manager. The following templates are provided to assist: Maintainer: pcs-project-office@unimelb.edu.au Page: 3 of 8

4 Letter of Acceptance - Consultancy Services Letter of Acceptance - Trade Contractor Minor Works Contract The Procedure for Contracts details the procedure for preparation and signing of formal contracts related to building works. The General Conditions of Contract for formal contracts will be nominated by the Design Team and approved by the Construction Manager. Reference shall be made in the Contract Documents to the following standard University Documents: Special Conditions of Contract Requirements for Working in University of Melbourne Sites 3.5 RETENTION The University s requirements for retention sums, whether cash, bank guarantee as detailed in Procedure for Contracts. 3.6 TENDERS FOR SERVICES AND OTHER SPECIALIST TRADES For building contracts two alternative tendering methods are acceptable. The decision as to which method is adopted shall be made by the Design Team. ALTERNATIVE 1 SUBCONTRACTORS PROPOSED BY TENDERERS Tenderers will be required to propose Subcontractors with the appropriate skills, experience and capacity to deliver the Services and Specialist Trades in accordance with the detailed and coordinated Tender Documents prepared by the Design Team. This Alternative 1 requires that the Design Consultants are very diligent in completing their design and documentation work so as to avoid the need for variations during the Contract. The Contractor will be fully responsible for the performance of the Subcontractors under this Alternative 1. Alternative 2 SUBCONTRACTORS PROPOSED BY UNIVERSITY A list of approved trade contractors shall be included in the tender documents and the Builder must select from the list for his tender to conform. The services and specialist trades shall be a subcontractor to the builder. An example of the appropriate clause to be included in the tender documents is: The following is a list of approved trade contractors for <<Mechanical Services, Electrical Services, Security Services, Voice & Data, Lift Services etc. - insert trade contractor list as appropriate.>> For a tender to be conforming, tenderers must select from the approved list. The Builder may submit an alternative tender using trade contractors not on the list, provided a conforming tender is submitted. Such alternative tender must nominate the proposed alternate trade contractor, and the benefit to the University in approving the alternative trade contractor. The University reserves the right to accept or not to accept an alternative tender. Maintainer: pcs-project-office@unimelb.edu.au Page: 4 of 8

5 In this Alternative 2 the Contractor accepts full responsibility for the performance of the Subcontractors but the University bears some responsibility as a result of having provided the list of trade contractors to the tenderers. Alternative 3 SEPARATE CONTRACTS BY UNIVERSITY Tenders are called by the University be called separately for services or other specialist trades. Tenders shall be assessed by the Services Consultant and the University nominates the successful tenders as subcontractors to tenderers of the building works and the tenderers include the Nominated Subcontracts in their tenders prior to closing of building tenders. In this Alternative 3 the Contractor accepts full responsibility for the performance of the Subcontractors but the University still bears some responsibility as a result of having tendered the work of the Nominated Subcontractors without input from the Building Contractor. 3.7 TENDER RECEIPT All Tenders for projects must be delivered to: The Tender Box Reception Property & Campus Services Ground Floor, Swanston St University of Melbourne, Carlton Vic 3053 Upon receipt of tender submissions, the Project Manager is required to complete the Tender Box Closing Form. Tenders shall be opened in accordance with the Procurement Guidelines and the Tender Report completed and signed. 3.8 TENDER EVALUATION AND RECOMMENDATION A thorough evaluation of each tender shall be carried out, normally by the Principal Consultant with input from the Design Team, and a tender report submitted to the Project Manager. Tender evaluations shall ensure that:- Late tenders are only considered the approval of the Construction Manager AFTER all conforming tenders have been evaluated AND no conforming tender is considered to be acceptable; All clarifications and qualifications in the received tenders must be withdrawn, priced or adjusted to ensure comparison is like for like; All schedules in the tender documents are completed. Successful AND unsuccessful tenderers shall be advised, in writing, of the decision by the Principal Consultant or the Project Manager after a tender has been accepted. Refer to the Draft Reply to Unsuccessful Tenderers. 3.9 INDUCTION OF CONTRACTORS Only University of Melbourne inducted contractors are permitted to work on building or construction projects. The inductions are conducted in accordance with the University of Melbourne Property & Campus Services Specific Induction (Parkville Campus) booklet. Maintainer: pcs-project-office@unimelb.edu.au Page: 5 of 8

6 Individual contractors who are not on the list of inducted contractors may be separately inducted by the Project Manager by following the induction booklet format and forwarding the completed forms to the Construction Manager. The name of the contractor will be added to the list of inducted contractors. Should any contractor give cause to be removed from the list of inducted contractors, the Project Manager shall advise the Construction Manager, who shall determine whether or not the cause warrants removal. An induction is only valid for a maximum of 2 years PREAWARD MINUTES Prior to the award of any contract in excess of $10, the contractor must attend a Pre- Award Interview meeting and sign the minutes. Refer to Pre-Award Interview Minutes template. For projects less than $10, where a unique EH&S hazard has been identified the Pre- Award Interview meeting is also required SAFE WORK METHOD STATEMENTS (SWMS) Safe Work Method Statements (SWMS) are required for all building works and shall be completed and signed by the Contractor and forwarded to the Project Manager prior to commencing the related work. The Project Manager shall, in consultation with the EH&S department, review the SWMS and return the SWMS to the Contractor for revision and resubmission as required. The SWMS shall be a description of the work methods employed by the Contractor to mitigate or minimise the EH&S hazards, and the control measures employed to ensure compliance with the Safe Work Method Statement PROJECT APPROVAL The Project Manager shall obtain the approval of the authorised delegate by submitting the completed BR file to the authorised delegate. To determine appropriate authorised delegate refer to the University s Building Tendering and Purchasing Policy UOM0385 The Tender Report and the Project Budget shall be completed and attached. On all projects the Project Approval Form shall be completed and attached to the BR file. On projects in excess of $400, the Project Approval Form together with a Project Approval Summary shall be submitted to the Major Tender Board for approval BUILDING WORKS COMMENCEMENT NOTIFICATION Prior to commencement of building works, the Project Manager shall complete and distribute the Building Works Commencement Notification by , using the Projects Notification List (PCS_ConProjectNotification) plus Client Department. Refer to Project Works Commencement Notification for proforma BUILDING PERMIT Maintainer: pcs-project-office@unimelb.edu.au Page: 6 of 8

7 Prior to commencement of building works, the Project Manager shall ensure Building Permit has been obtained SAFETY MANAGEMENT PLANS Prior to commencement of building works, the Project Manager shall ensure the relevant Safety Management Plan (SMP) is obtained from the Principal Contractor and has been reviewed by the EHS Department. Maintainer: Page: 7 of 8

8 DOCUMENT CONTROL Approvals Version No. Approval Date Name Title Signature/ ref /04/ /06/2012 Leo Fincher-Johnson Construction Manager, Major Projects 26 Jun 2012 L. Fincher- Johnson Review history Version No. Review Date Name Title /06/2012 Brendan Jordan Project Manager Version history Version No. Version Date Summary of Changes Prepared by: /04/2012 Robert Pollock /06/2012 New format and content amendments from Robert Pollock's _ProjectManagementProcedures_2012_Ver8.doc Tania Robinson Maintainer: Page: 8 of 8

Project Sizing Guide. Property & Campus Services

Project Sizing Guide. Property & Campus Services Purpose This document is intended to assist in deciding what sort of management overheads would be justified for a proposed project. Instructions for Use 1. Evaluate the proposed work against each of the

More information

Revision: 3. Author: J McGuire Department: Company. Category: Contract Management. Appr. Signature: CONTENTS 1.0 PURPOSE... 1 2.0 SCOPE...

Revision: 3. Author: J McGuire Department: Company. Category: Contract Management. Appr. Signature: CONTENTS 1.0 PURPOSE... 1 2.0 SCOPE... POLICY Title: QAL Contract Management Policy Policy No: P801.001 Issue: 2 Revision: 3 Operative Date: 10/11/2009 Author: J McGuire Department: Company Sect./Classification: Company Category: Contract Management

More information

GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities

GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities Office of Government Procurement Building Control (Amendment) Regulations 2014 Procurement

More information

REQUEST FOR QUOTE. RFQ Reference Number: RFQ <<INSERT e.g SWR 03-11/12>> <<Enter Course Name>>

REQUEST FOR QUOTE. RFQ Reference Number: RFQ <<INSERT e.g SWR 03-11/12>> <<Enter Course Name>> REQUEST FOR QUOTE RFQ Reference Number: RFQ Date of Issue: Name of Business Unit: Address: Contact Person: Telephone: Email:

More information

Procedures for Tenders and Contracts. October 2014. Huon Valley Council Procedures for Tenders and Contracts October 2014 Page 1 of 14

Procedures for Tenders and Contracts. October 2014. Huon Valley Council Procedures for Tenders and Contracts October 2014 Page 1 of 14 Procedures for Tenders and Contracts October 2014 Huon Valley Council Procedures for Tenders and Contracts October 2014 Page 1 of 14 Huon Valley Council Procedures for Tenders and Contracts October 2014

More information

Procurement of Goods, Services and Works Policy

Procurement of Goods, Services and Works Policy Procurement of Goods, Services and Works Policy Policy CP083 Prepared Reviewed Approved Date Council Minute No. Procurement Unit SMT Council April 2016 2016/0074 Trim File: 18/02/01 To be reviewed: March

More information

Mitchell Shire Council

Mitchell Shire Council ATTACHMENT Mitchell Shire Council Ordinary Council Meeting CONTRACT MANAGEMENT POLICY AND TENDERING POLICY Contract Management Policy 25 March 2013 Attachment 1 Pages 12 CORPORATE SERVICES DOCUMENT NUMBER

More information

CONTRACTOR SAFETY MANAGEMENT PROCEDURE

CONTRACTOR SAFETY MANAGEMENT PROCEDURE CONTRACTOR SAFETY MANAGEMENT PROCEDURE Version 1.0 TRIM file number Short description Relevant to Authority Responsible officer Responsible office Date introduced July 20, 2015 Date(s) modified June 11,

More information

Tender for. Provision of Risk Management Services for the Eyre Peninsula Local Government Association and Member Associations

Tender for. Provision of Risk Management Services for the Eyre Peninsula Local Government Association and Member Associations Tender for Provision of Risk Management Services for the Eyre Peninsula Local Government Association and Member Associations Select request for tenders Table of Contents Page No 1. Structure of this RFT...

More information

POLICY CONTRACT MANAGEMENT POLICY POLICY STATEMENT

POLICY CONTRACT MANAGEMENT POLICY POLICY STATEMENT POLICY CONTRACT MANAGEMENT POLICY POLICY STATEMENT The intent of this policy is to establish a University-wide governance structure for managing contracts and other legally binding documents. The Policy

More information

Code of Practice for Agents Undertaking Renovation Grants

Code of Practice for Agents Undertaking Renovation Grants Code of Practice for Agents Undertaking Renovation Grants July 1998 Contents Introduction Page 1 Approved List of Agents Page 1 Procurement Page 2 Approval Page 5 Works in Progress Page 6 Completion Page

More information

WHS Contractor Management Procedure

WHS Contractor Management Procedure Wudinna District Council 1. Overview Wudinna District Council as part of its commitment under its Policy recognises its obligation to: Ensure, so far as is reasonably practicable, the health and safety

More information

Disposal Schedule for Functional records of the Electricity Supply Industry Expert Panel

Disposal Schedule for Functional records of the Electricity Supply Industry Expert Panel Disposal Schedule for Functional records of the Electricity Supply Industry Expert Panel Disposal Authorisation No. 2370 TABLE OF CONTENTS INTRODUCTION page4 Archives legislation page 4 Schedule elements

More information

PREQUALIFICATION DOCUMENT FOR PROVISION OF WEBSITE HOSTING AND MAINTENANCE SERVICES - TENDER NO KENAS NO/19/2013/2015

PREQUALIFICATION DOCUMENT FOR PROVISION OF WEBSITE HOSTING AND MAINTENANCE SERVICES - TENDER NO KENAS NO/19/2013/2015 PREQUALIFICATION DOCUMENT FOR PROVISION OF WEBSITE HOSTING AND MAINTENANCE SERVICES - TENDER NO KENAS NO/19/2013/201 KENYA ACCREDITATION SERVICE P.O BOX 47400-00100 NAIROBI KENYA Tel: 0787 39 679 or 072

More information

STANDARD PRE-QUALIFICATION DOCUMENT FOR THE PROCUREMENT OF WORKS (MAJOR CONTRACTS)

STANDARD PRE-QUALIFICATION DOCUMENT FOR THE PROCUREMENT OF WORKS (MAJOR CONTRACTS) STANDARD PRE-QUALIFICATION DOCUMENT FOR THE PROCUREMENT OF WORKS (MAJOR CONTRACTS) Pre-qualification Ref: Issue Date: [Insert Title of Project] [Insert Reference] [Insert Date] Public Procurement Authority

More information

香 港 特 別 行 政 區 政 府. The Government of the Hong Kong Special Administrative Region. Development Bureau Technical Circular (Works) No.

香 港 特 別 行 政 區 政 府. The Government of the Hong Kong Special Administrative Region. Development Bureau Technical Circular (Works) No. 香 港 特 別 行 政 區 政 府 The Government of the Hong Kong Special Administrative Region 政 府 總 部 發 展 局 工 務 科 香 港 添 馬 添 美 道 2 號 政 府 總 部 西 翼 1 8 樓 Works Branch Development Bureau Government Secretariat 18/F, West

More information

Briefing Session (SWD/T008/2013) Social Welfare Department 7 January 2016. This briefing will introduce part of the Tender Documents.

Briefing Session (SWD/T008/2013) Social Welfare Department 7 January 2016. This briefing will introduce part of the Tender Documents. Briefing Session Invitation to Tender For the Provision of Two Year Full- time Enrolled Nurse (General) and Enrolled Nurse (Psychiatric) Training Programmes for the Welfare Sector for the Social Welfare

More information

WHS CONTRACTOR MANAGEMENT PROCEDURE

WHS CONTRACTOR MANAGEMENT PROCEDURE 1. Overview The Port Augusta City Council as part of its commitment under its WHS Contractor Management policy, recognises its obligation to: Ensure, so far as is reasonably practicable, the health and

More information

PREQUALIFICATION INFORMATION

PREQUALIFICATION INFORMATION Department of Planning, Transport and Infrastructure Building and Construction Project Prequalification System (Edition 2012) PREQUALIFICATION INFORMATION General Building Contractor Residential Building

More information

SourceIT User Notes. Specific Clauses. Licence and Support Contract Commercial off-the-shelf Software RELEASE VERSION 2.

SourceIT User Notes. Specific Clauses. Licence and Support Contract Commercial off-the-shelf Software RELEASE VERSION 2. SourceIT User Notes Specific Clauses Licence and Support Contract Commercial off-the-shelf Software RELEASE VERSION 2.3 DECEMBER 2012 AGIMO is part of the Department of Finance and Deregulation SourceIT

More information

15 For clarification and other details Please contact: 1. Asst. Manager - 8978027919 Please Note:

15 For clarification and other details Please contact: 1. Asst. Manager - 8978027919 Please Note: TENDER NOTICE 1 Name of the work and place Electrical works at sbi.intouch BRANCH (KADAPA), Y.S.R. District, Andhra Pradesh. 2 Estimated Cost Rs.9,51,186/- 3 Date of issue of tender through 23/06/16 Bank

More information

Contents: 1 General. 1 General. 2 Tenderer s obligations. 3 The Procuring Department s undertakings. Republic of Botswana. OF TENDER Feb 2006

Contents: 1 General. 1 General. 2 Tenderer s obligations. 3 The Procuring Department s undertakings. Republic of Botswana. OF TENDER Feb 2006 PUBLIC PROCUREMENT AND ASSET DISPOSAL BOARD STANDARDISED CONDITIONS OF TENDER Feb 2006 Contents: 1 General 2 Tenderer s obligations 3 The Procuring Department s undertakings 1 General Actions 1 The Procuring

More information

香 港 特 別 行 政 區 政 府. The Government of the Hong Kong Special Administrative Region. Development Bureau Technical Circular (Works) No.

香 港 特 別 行 政 區 政 府. The Government of the Hong Kong Special Administrative Region. Development Bureau Technical Circular (Works) No. 政 府 總 部 發 展 局 工 務 科 香 港 特 別 行 政 區 政 府 The Government of the Hong Kong Special Administrative Region Works Branch Development Bureau Government Secretariat 香 港 添 馬 添 美 道 2 號 政 府 總 部 西 翼 1 8 樓 18/F, West

More information

LGRF. Procurement Probity Plan. July 2012

LGRF. Procurement Probity Plan. July 2012 LGRF July 2012 When to develop a : A probity plan is best used for any procurement of medium complexity and size and above. A probity plan can be implemented without use of a probity advisor/auditor. Description

More information

-17 2015 OUTSOURCING POLICY

-17 2015 OUTSOURCING POLICY Outsourcing Policy TABLE OF CONTENTS EXECUTIVE SUMMARY... 3 Aim & Introduction... 3 POLICY PARAMETERS... 4 Key Terms... 4 Outsourcing Agreement Requirements... 5 MATERIAL OUTSOURCING AGREEMENTS... 6 Board

More information

ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES

ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES CAPITAL GRANTS PROGRAM / BUILDING GRANTS ASSISTANCE SCHEME Background Non government schools accepting the

More information

STANDARD CONTRACT PROVISIONS ROADS

STANDARD CONTRACT PROVISIONS ROADS STANDARD CONTRACT PROVISIONS ROADS Volume 3 MINOR WORKS CONTRACT SYSTEM (MW) MANUAL FOR MINOR WORKS CONTRACTS Standard Contract Provisions Roads Volume 3 Department of Transport and Main Roads for Minor

More information

Management Plan. Contractor Management

Management Plan. Contractor Management Management Plan Contractor Management Doc ID No. Version No. Owner Next Review Date Management Plan Contractor Management Risk Statement: High This document will be reviewed on a one yearly basis, unless

More information

Management of Contractors and Suppliers Procedure

Management of Contractors and Suppliers Procedure Management of Contractors and HSE P1101 Table of Content 1 DOCUMENT CONTROL... 2 2 PURPOSE... 3 3 SCOPE... 3 4 DEFINITIONS... 3 5 ROLES AND RESPONSIBILITIES... 5 6 PROCESS DETAILS... 9 6.1 Confirm Need

More information

Department of Health PFU & PPP Forum. Benchmarking and market testing in NHS PFI projects. Code of Best Practice

Department of Health PFU & PPP Forum. Benchmarking and market testing in NHS PFI projects. Code of Best Practice Department of Health PFU & PPP Forum Benchmarking and market testing in NHS PFI projects Code of Best Practice This Code of Best Practice provides guidance and advice on good practice to NHS Trusts, Project

More information

To be used in conjunction with the Invitation to Tender for Consultancy template.

To be used in conjunction with the Invitation to Tender for Consultancy template. GUIDANCE NOTE Tendering for, choosing and managing a consultant Using this guidance This information is not intended to be prescriptive, but for guidance only. Appointing consultants for relatively small

More information

Government of the Kingdom of Lesotho. Ministry of Public Works and Transport. Principal Building Agreement

Government of the Kingdom of Lesotho. Ministry of Public Works and Transport. Principal Building Agreement Government of the Kingdom of Lesotho Ministry of Public Works and Transport Project Employer Contractor Contract Date Contract No Principal Building Agreement MINISTRY OF PUBLIC WORKS & TRANSPORT BUILDING

More information

Australian Standard. General conditions of contract for design and construct. AS 4300 1995 (Incorporating Amendment No. 1)

Australian Standard. General conditions of contract for design and construct. AS 4300 1995 (Incorporating Amendment No. 1) AS 4300 1995 (Incorporating Amendment No. 1) Australian Standard General conditions of contract for design and construct This Australian Standard was prepared by Committee OB/3, General Conditions of Contract.

More information

Procedure. Work Health and Safety Contractor Management. Document number: PRO-00808. Rev no. Description Process Owner Approved for issue

Procedure. Work Health and Safety Contractor Management. Document number: PRO-00808. Rev no. Description Process Owner Approved for issue Procedure Work Health and Safety Contractor Management Document number: PRO-00808 This document is the property of Seqwater. It must not be copied or reproduced in any way whatsoever without the authority

More information

[Project Name] NZTA Contract No. [Contract Number] Schedule of Prices

[Project Name] NZTA Contract No. [Contract Number] Schedule of Prices [Project Name] NZTA Contract No. [Contract Number] Schedule of Prices Schedule of Prices SP1

More information

DIRECTORATE OF ESTATES & FACILITIES

DIRECTORATE OF ESTATES & FACILITIES DIRECTORATE OF ESTATES & FACILITIES PROCEDURE AND INFORMATION MANUAL EPM PM4 Client Representative (University Project Manager) for Capital Projects Scope of Services Document Originated: April 2006 By:

More information

Appendix 18 NEC3 Options

Appendix 18 NEC3 Options Appendix 18 NEC3 Options December 2007 Page 449 Appendix 18 NEC3 Options NEC3 Main Options There are six main options as set out below. The Contractor carries the greatest risk under options A and B, and

More information

Community Learning and Skills Service. Contract Management 2015/16. Guidance for providers. Slough and RBWM

Community Learning and Skills Service. Contract Management 2015/16. Guidance for providers. Slough and RBWM Community Learning and Skills Service Contract Management 2015/16 Guidance for providers Slough and RBWM CONTENTS 1. Purpose... 3 2. About East Berkshire Community Learning and Skills Service... 4 3.

More information

A GOOD PRACTICE GUIDE FOR EMPLOYERS

A GOOD PRACTICE GUIDE FOR EMPLOYERS MITIGATING SECURITY RISK IN THE NATIONAL INFRASTRUCTURE SUPPLY CHAIN A GOOD PRACTICE GUIDE FOR EMPLOYERS April 2015 Disclaimer: Reference to any specific commercial product, process or service by trade

More information

Overview of the Transfer of Undertakings (Protection of Employment) Regulations 2006

Overview of the Transfer of Undertakings (Protection of Employment) Regulations 2006 TUPE Overview of the Transfer of Undertakings (Protection of Employment) Regulations 2006... 1 Service Provision Changes... 1 Employer Liability Information... 2 Liability for Failure to Inform and Consult

More information

Procurement, Contracting and Contract Management Policy

Procurement, Contracting and Contract Management Policy Procurement, Contracting and Contract Management Policy Corporate policy 8.4 Responsible Officer: Group Manager Accounting and Taxation Policy Custodian: Chief Finance Officer Division: Finance and Resources

More information

Supplier prequalification Document

Supplier prequalification Document Table of Contents Part 1 Invitation to Applicants Invitation Notice Statement of Requirements Part 2 Application Procedures Section 1 Instructions to Applicants Section 2 Application submission control

More information

Procurement Services Document Control Sheet

Procurement Services Document Control Sheet Procurement Services Document Control Sheet Document Reference: Standing Orders for Contracts 2010 Log of Changes Issue Date Originator Authorisation V0.1 September Rebecca Document came into place 2010

More information

Schedule of Prices. Project Name Contract No. Contract Number

Schedule of Prices. Project Name Contract No. Contract Number Schedule of Prices Project Name Contract No. Contract Number C3-LS-BP-Issue 2 SP Page 1 Printed 1 March 2011 >: 1. When preparing the schedule

More information

Date: 7 February 2013

Date: 7 February 2013 Item No. Report title: Classification: Open Ward(s) or groups affected: From: Date: 7 February 2013 Meeting Name: Deputy Leader and Cabinet Member for Housing Management GW2: Leasehold and Ancillary Properties

More information

RTO Delegations Guidelines

RTO Delegations Guidelines RTO Delegations Guidelines ISBN 0 7594 0389 9 Victorian Qualifications Authority 2004 Published by the Victorian Qualifications Authority This publication is copyright. Apart from any use permitted under

More information

Australian National Audit Office. Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO

Australian National Audit Office. Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO Australian National Audit Office Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO Commonwealth of Australia 2002 ISBN 0 642 80678 0 10 December 2002 Dear Mr

More information

Guide Document for Development of WHS Management Plans

Guide Document for Development of WHS Management Plans DISCLAIMER: THIS DOCUMENT IS PROVIDED AS GUIDANCE TO ASSIST CONTRACTORS IN MEETING THEIR OBLIGATIONS UNDER THE WHS LAW AND NTG CONTRACTS. NTG DOES NOT ACCEPT ANY RESPONSIBILITY FOR THE CONTENTS OF CONTRACTORS

More information

Procedure: OHS CONTRACTOR MANAGEMENT

Procedure: OHS CONTRACTOR MANAGEMENT Procedure: OHS CONTRACTOR MANAGEMENT. Purpose This procedure outlines the occupational health and safety (OHS) requirements for the management of contractors engaged to perform tasks or services for Greater

More information

2013 Training Calendar

2013 Training Calendar 2013 Training Calendar Newcastle Office Level 1, 165 Lambton Road Broadmeadow NSW 2292 Ph: 02 4953 9400 Fax: 02 4953 9433 Website: www.newcastle-mba.com.au Structured MBA Training for Professional Development

More information

G2 Contract Management Plan Date: July 2014 Edition 1 / Revision 0

G2 Contract Management Plan Date: July 2014 Edition 1 / Revision 0 G2 Contract Management Plan Date: Edition 1 / Revision 0 REVISION REGISTER Ed/Rev Number Ed 1 / Rev 0 Clause Number All G2.1 G2.2 G2.3 G2.4 G2.5 G2.5 G2.6.1 G2.6.2 G2.6.3 G2.6.4 G2.6.5 G2.6.6 G2.6.7 G2.7

More information

GUIDELINE NO. 22 REGULATORY AUDITS OF ENERGY BUSINESSES

GUIDELINE NO. 22 REGULATORY AUDITS OF ENERGY BUSINESSES Level 37, 2 Lonsdale Street Melbourne 3000, Australia Telephone.+61 3 9302 1300 +61 1300 664 969 Facsimile +61 3 9302 1303 GUIDELINE NO. 22 REGULATORY AUDITS OF ENERGY BUSINESSES ENERGY INDUSTRIES JANUARY

More information

SERVICE CONTRACT NOTICE. Development of a sustainable information system for MAFWM Location - Serbia

SERVICE CONTRACT NOTICE. Development of a sustainable information system for MAFWM Location - Serbia Ref. Ares(2013)2579227-05/07/2013 Public document to be completed by the Contracting Authority SERVICE CONTRACT NOTICE Development of a sustainable information system for MAFWM Location - Serbia 1. Publication

More information

Terms and Conditions of Offer and Contract (Works & Services) Conditions of Offer

Terms and Conditions of Offer and Contract (Works & Services) Conditions of Offer Conditions of Offer A1 The offer documents comprise the offer form, letter of invitation to offer (if any), these Conditions of Offer and Conditions of Contract (Works & Services), the Working with Queensland

More information

APPENDIX B: FINANCIAL PLANNING AND CONTROL OF RESOURCES

APPENDIX B: FINANCIAL PLANNING AND CONTROL OF RESOURCES APPENDIX B: FINANCIAL PLANNING AND CONTROL OF RESOURCES 1 PERFORMANCE PLANS 1.1 The key controls for performance plans are: (a) to ensure that all relevant plans are produced and that they are consistent

More information

A Guide to Small Works. A brief explanation

A Guide to Small Works. A brief explanation A Guide to Small Works A brief explanation A Guide to House Extensions/Small Works - a brief explanation Small works are an ongoing, cherished part of DDC's activity and restricted only by distance. Here

More information

3. Specification. Tender No. 1716 Tender Name: Panel for External Printing Services 49

3. Specification. Tender No. 1716 Tender Name: Panel for External Printing Services 49 3. Specification Tender Name: Panel for External Printing Services 49 Specification 1. Introduction The Port Phillip City Council ( the Council ) invites tenders from suitably experienced organisation(s)

More information

CLIENT / PROJECT MANAGER AGREEMENT

CLIENT / PROJECT MANAGER AGREEMENT Authorship of this work is claimed by The Association of Construction Project Managers and any unauthorised reproduction constitutes an infringement in terms of the Copyright Act No 98 of 1978. CLIENT

More information

1.1 An initial request to enter into a contractual arrangement may be initiated by either Massey University or another party (Other Party).

1.1 An initial request to enter into a contractual arrangement may be initiated by either Massey University or another party (Other Party). CONTRACT MANAGEMENT PROCEDURE Section Risk Management Contact Risk Manager Last Review February 2013 Next Review February 2016 Approval Not required Procedures Contract Initiation Request Mandatory Guidance

More information

Page 5. The Adult Social Services and Health Committee. The Strategic Director of Adult Social Services, Housing and Health

Page 5. The Adult Social Services and Health Committee. The Strategic Director of Adult Social Services, Housing and Health Page 5 Agenda Item 5 Report to: The Adult Social Services and Health Committee Date: 20 th November 2012 Report of: The Strategic Director of Adult Social Services, Housing and Health Ward Location: All

More information

STANDARD PROCUREMENT PREQUALIFICATION DOCUMENT. (Works, Heavy Equipment, Supply and Installation Contracts)

STANDARD PROCUREMENT PREQUALIFICATION DOCUMENT. (Works, Heavy Equipment, Supply and Installation Contracts) STANDARD PROCUREMENT PREQUALIFICATION DOCUMENT (Works, Heavy Equipment, Supply and Installation Contracts) Table of Contents Page INTRODUCTION 3 SECTION I - Invitation for prequalification... 4 SECTION

More information

Subvented Social Welfare Non-Governmental Organisations Procurement Procedures

Subvented Social Welfare Non-Governmental Organisations Procurement Procedures Subvented Social Welfare Non-Governmental Organisations Procurement Procedures Corruption Prevention Department Independent Commission Against Corruption March 2001 CONTENTS Pages Introduction 1 The Basic

More information

REQUEST FOR EXPRESSIONS OF INTEREST

REQUEST FOR EXPRESSIONS OF INTEREST REQUEST FOR EXPRESSIONS OF INTEREST RISK ASSESSMENT SOFTWARE & CONSULTANCY SERVICES EYRE PENINSULA LOCAL GOVERNMENT ASSOCIATION (referred to as "EPLGA" or the "Association") ABN 90 992 364 300 TABLE OF

More information

Derbyshire Trading Standards Service Quality Manual

Derbyshire Trading Standards Service Quality Manual Derbyshire Trading Standards Service Quality Manual This Quality Manual has been developed to give a broad outline of how the Trading Standards Division s range of services comply with the requirements

More information

38. Project Management

38. Project Management Draft 1 - RGU: Master Retention Schedule (MaRS) November 2008 38. Project Management The function of managing projects. The original copy of the records in this section will be held by and. Some records

More information

STANDARD TENDER DOCUMENT FOR PROCUREMENT OF INSURANCE SERVICES

STANDARD TENDER DOCUMENT FOR PROCUREMENT OF INSURANCE SERVICES STANDARD TENDER DOCUMENT FOR PROCUREMENT OF INSURANCE SERVICES Table of Contents Page INTRODUCTION.. 3 Section I INVITATION FOR TENDERS... 4 Section II INSTRUCTION TO TENDERERS Appendix to instructions

More information

RDTL Procurement Best Practice Guide 7: Managing Contracts. RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS

RDTL Procurement Best Practice Guide 7: Managing Contracts. RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS 1 RDTL Procurement Guidelines The Procurement Legal Regime Decree Law sets out new procurement processes which must

More information

Brighton Hill Community School. Staff Absence

Brighton Hill Community School. Staff Absence Staff Absence Contents of this policy: Rationale Purpose Aim GUIDELINES for ABSENCE due to sickness 1. Reporting Procedure 2. Certification Procedures 3. Time off for medical appointments 4. Return to

More information

Policy Number: 3-804 Policy Name: Professional Services and Construction Services Procurement

Policy Number: 3-804 Policy Name: Professional Services and Construction Services Procurement Page 1 3-804 Professional Services and Construction A. Project Delivery Methods 1. A university may procure design services, construction and construction services, as applicable, under any of the following

More information

Business Continuity Policy and Business Continuity Management System

Business Continuity Policy and Business Continuity Management System Business Continuity Policy and Business Continuity Management System Summary: This policy sets out the structure for ensuring that the PCT has effective Business Continuity Plans in place in order to maintain

More information

Suppliers Guide to Tendering Products and Services. Guide to Tendering with Western Australian Public Authorities. (January 2015)

Suppliers Guide to Tendering Products and Services. Guide to Tendering with Western Australian Public Authorities. (January 2015) Suppliers Guide to Tendering Products and Services Guide to Tendering with Western Australian Public Authorities (January 2015) Tendering Guide Products and Services Department of Finance Optima Centre,

More information

Professional Practice Commission: March 2013. Alternative Project Delivery Systems

Professional Practice Commission: March 2013. Alternative Project Delivery Systems Professional Practice Commission: March 2013 Alternative Project Delivery Systems UIA Accord Building project delivery systems. Definition Building project delivery systems are defined as the contractual

More information

REQUEST FOR QUOTATION (RFQ) FOR PROVISION OF GENDER PANEL SERVICES

REQUEST FOR QUOTATION (RFQ) FOR PROVISION OF GENDER PANEL SERVICES Appendix A Request for Quotation Template Dear REQUEST FOR QUOTATION (RFQ) FOR PROVISION OF GENDER PANEL SERVICES [INSERT NAME OF DEPARTMENT OR AGENCY] is seeking a service provider for the provision of

More information

ASBESTOS MANAGEMENT PLAN

ASBESTOS MANAGEMENT PLAN ASBESTOS MANAGEMENT PLAN PREPARED BY: Scott Gregory: Estates - Property Services DATE: 18/04/2014 STATUS: Draft ISSUE: 2014 (02) September 2014 NEXT REVISION DATE: April 2014 Contents 1.0 Introduction

More information

DRAFT PROCUREMENT AND TENDERING PROCEDURES. (Revised October 2006)

DRAFT PROCUREMENT AND TENDERING PROCEDURES. (Revised October 2006) DRAFT PROCUREMENT AND TENDERING PROCEDURES (Revised October 2006) Contents Page 1. Purpose of Document 2 2. Objectives of Procedures 2 3. Procurement of Supplies and Services 2 4. Invoice Processing 4

More information

www.portsmouth.gov.uk Part 3D - Officers' Employment Procedure Rules 1

www.portsmouth.gov.uk Part 3D - Officers' Employment Procedure Rules 1 Part 3D - Officers' Employment Procedure Rules 1 These rules determine procedures to be followed in the recruitment of senior officers of the council and in any disciplinary action which may become necessary

More information

Edith Cowan University. Document and Records Management Procedure. Safety and Employment Relations..

Edith Cowan University. Document and Records Management Procedure. Safety and Employment Relations.. Document and Records Management Procedure Procedure Owner: Director Human Resources Services Centre Keywords: 1) Document 2) Records 3) Health and Safety TABLE OF CONTENTS 1. INTENT... 1 2. ORGANISATIONAL

More information

Request for Tender (RFT)

Request for Tender (RFT) 1 of 12 Request for Tender (RFT) Philippines Australia Human Resource and Organisational Development Facility Organisation: Department of Social Welfare and Development Activity Title: Enhancing the DSWD

More information

Page 97. Executive Head of Asset Planning, Management and Capital Delivery

Page 97. Executive Head of Asset Planning, Management and Capital Delivery Page 97 Agenda Item 7 Report to: Strategy and Resources Committee Date: 16 December 2013 Report of: Executive Head of Asset Planning, Management and Capital Delivery Ward Location: Not applicable Author

More information

Draft Service Level Agreement. for IT consultancy for advice, studies, software development and software maintenance Framework service contract

Draft Service Level Agreement. for IT consultancy for advice, studies, software development and software maintenance Framework service contract Draft Service Level Agreement for IT consultancy for advice, studies, software development and software maintenance Framework service contract Publication Reference: : OJ/25/06/2014-PROC/2014/023 TIME

More information

Asset Protection Agreement Templates - Customer Explanatory Notes. Explanatory Notes on Asset Protection Agreement

Asset Protection Agreement Templates - Customer Explanatory Notes. Explanatory Notes on Asset Protection Agreement Asset Protection Agreement Templates - Customer Explanatory Notes Explanatory Notes on Asset Protection Agreement Clause Heading Background The Asset Protection Agreement is intended for use where the

More information

Guide. Minister s Guide to Auditing for Building Surveyors. April 2014

Guide. Minister s Guide to Auditing for Building Surveyors. April 2014 Guide Minister s Guide to Auditing for Building Surveyors April 2014 Guide Minister s Guide to Auditing for Building Surveyors April 2014 Department of Planning, Transport and Infrastructure 136 North

More information

Guidance Notes for the NEC Engineering and Construction Contract

Guidance Notes for the NEC Engineering and Construction Contract The first objective of the Risk Register is to identify the risks inherent in a project. Some of these risks are generic, and will apply to whatever work is carried out. An example is the risk of errors

More information

TfNSW Standard Requirements TSR T Technical Management

TfNSW Standard Requirements TSR T Technical Management Template Applicable to: Transport Projects Quality Management System Status: Division: Approved Transport Projects Version: 5.0 Desksite No.: 3455797_1 Date of issue: 1 July 2014 Effective date: 1 July

More information

REQUEST FOR BIDS. Project Management Technical Services

REQUEST FOR BIDS. Project Management Technical Services REQUEST FOR BIDS Project Management Technical Services SECTION 1: GENERAL INSTRUCTIONS TO BIDDERS 1. Bids must be submitted in the form specified in this invitation, if any, and sealed in an envelope or

More information

2. Subject to any special rules applied by the College's funding bodies, the tendering procedures will be applicable to:

2. Subject to any special rules applied by the College's funding bodies, the tendering procedures will be applicable to: HARPER ADAMS UNIVERSITY COLLEGE Code of Tendering Practice Introduction 1. The following guidelines are to be used in the conduct of tendering and contracting of major services and supplies commissioned

More information

QUALITY MANAGEMENT PLAN

QUALITY MANAGEMENT PLAN QUALITY MANAGEMENT PLAN Project Name EfW CHP Facility, North Yard, Devonport Project Number: C1005 Location: North Yard, Devonport Dockyard, Plymouth Approved by: Dated: Signed: KIER Project Manager Reviewed

More information

Contract Standing Orders and Procedure - A Guide For Council Employees

Contract Standing Orders and Procedure - A Guide For Council Employees Hampshire County Council Constitution Part 3:F Contract Standing Orders 1. Interpretation 2. Status of, and Compliance with, Contract Standing Orders 3. Approval to Commence Procurement 4. Contract Value

More information

Accounting standards support to English college finance staff

Accounting standards support to English college finance staff Accounting standards support to English college finance staff Invitation to Tender for Consultant Contract for Accounting Standards Support to further education (FE) College and Sixth Form College finance

More information

inform practice note SUBCONTRACTING ARRANGEMENTS Content Synopsis: Practice Note # 7 May 2007 (Version 1 - May 2007) construction industry development

inform practice note SUBCONTRACTING ARRANGEMENTS Content Synopsis: Practice Note # 7 May 2007 (Version 1 - May 2007) construction industry development construction industry development inform practice note Issued by the Construction Industry Development Board Development through partnership construction procurement and delivery SUBCONTRACTING ARRANGEMENTS

More information

UNSOLICITED PROPOSALS

UNSOLICITED PROPOSALS UNSOLICITED PROPOSALS GUIDE FOR SUBMISSION AND ASSESSMENT January 2012 CONTENTS 1 PREMIER S STATEMENT 3 2 INTRODUCTION 3 3 GUIDING PRINCIPLES 5 3.1 OPTIMISE OUTCOMES 5 3.2 ASSESSMENT CRITERIA 5 3.3 PROBITY

More information

KITCHEN CONTRACT FOR WORK OVER $5000 COMPANY NAME: ADDRESS: DATE: CONTRACT PRICE: Please read all attached information and terms.

KITCHEN CONTRACT FOR WORK OVER $5000 COMPANY NAME: ADDRESS: DATE: CONTRACT PRICE: Please read all attached information and terms. KITCHEN CONTRACT FOR WORK OVER $5000 COMPANY NAME: ADDRESS: DATE: CONTRACT PRICE: Please read all attached information and terms. Page 1 of 14 OWNER CHECKLIST (To be completed by the owner prior to signing

More information

Reference Check Review Guidelines

Reference Check Review Guidelines Reference Check Review Guidelines P a g e 2 Overview The purpose of these guidelines is to provide clarity on implementation of the Province of British Columbia s internal reference check requirements

More information

Prequalification Document for Procurement of Works

Prequalification Document for Procurement of Works STANDARD PROCUREMENT DOCUMENT Prequalification Document for Procurement of Works Caribbean Development Bank September 2007 ii Foreword This Standard Procurement Document Prequalification Document for Procurement

More information

Air Traffic Service Providers Entry Control Procedures Manual 2. Approval Procedures for ATS Providers

Air Traffic Service Providers Entry Control Procedures Manual 2. Approval Procedures for ATS Providers 2.1 Approval Procedures for ATS Providers Flowchart POTENTIAL ATS PROVIDER Contacts CASA re process in provision of ATS CASA TO DESPATCH INFORMATION PACK CONTAINING : Covering letter outlining application

More information

Highlands and Islands Broadband Pathfinder Project - Background

Highlands and Islands Broadband Pathfinder Project - Background ITEM: 22(a) PAGE: 1 REPORT TO: The Moray Council on 5 July, 2006 SUBJECT: BY: Highlands and Islands Broadband Pathfinder Project - Background Chief Executive 1. Reason for Report 1.1 The Pathfinder Broadband

More information

PROFESSIONAL SERVICES SPECIFICATION

PROFESSIONAL SERVICES SPECIFICATION R64 - PAVEMENT MARKING August 1996 PROFESSIONAL SERVICES SPECIFICATION PM2 PROJECT MANAGEMENT PLAN Date JUNE 2012 Department 1 DOT Spec R64 of Infrastructure, Energy and Resources Index DEPARTMENT of INFRASTRUCTURE,

More information

Wharton Construction Ltd. Quality Manual. Kellaw Road Yarm Road Business Park Darlington DL1 4YA

Wharton Construction Ltd. Quality Manual. Kellaw Road Yarm Road Business Park Darlington DL1 4YA Quality Manual Kellaw Road Yarm Road Business Park Darlington DL1 4YA MANUAL IDENTIFICATION This document is a controlled/uncontrolled copy. Copy Number:...of... Issued to... Title... Holders of controlled

More information

Newsletter. Opening letter from Chair, Jeremy Newman

Newsletter. Opening letter from Chair, Jeremy Newman Newsletter Opening letter from Chair, Jeremy Newman Dear Stakeholders Happy New Year to you all. 2015 is shaping up to be a very exciting and challenging year for the SSRO. Hopefully you will be aware

More information

CONTRACT, PROJECT BIDDING AND MANAGEMENT AND PARTNERSHIP PROCEDURE. Date - February 2011

CONTRACT, PROJECT BIDDING AND MANAGEMENT AND PARTNERSHIP PROCEDURE. Date - February 2011 CONTRACT, PROJECT BIDDING AND MANAGEMENT AND PARTNERSHIP PROCEDURE Date - February 2011 CONTRACT & PROJECT BIDDING & MANAGEMENT PROCESS CONTENTS 1 Introduction 2 Pre-Bid 3 Project Bid Submission 4 Accepted

More information