JISC DEVELOPMENT PROGRAMMES Project Document Cover Sheet PROGRESS REPORT

Size: px
Start display at page:

Download "JISC DEVELOPMENT PROGRAMMES Project Document Cover Sheet PROGRESS REPORT"

Transcription

1 Project JISC DEVELOPMENT PROGRAMMES Project Document Cover Sheet PROGRESS REPORT Project Acronym VERSIONS Project ID Project Title Versions of Eprints user Requirements Study and Investigation of the Need for Standards Start Date July 2005 End Date January 2007 Lead Institution Project Director Project Manager & contact details Partner Institutions Project Web URL Programme Name (and number) Programme Manager London School of Economics and Political Science Jean Sykes, Librarian & Director of IT Services, LSE Frances Shipsey British Library of Political and Economic Science, London School of Economics and Political Science, 10 Portugal Street, London WC2A 2HD. Tel: +44(0) ; Fax: +44(0) ; Nereus Project Consortium ( Digital Repositories Programme Neil Jacobs Document Document Title Progress Report Reporting Period July 2005 to January 2006 Author(s) & project role Frances Shipsey, Project Manager Date 3 April 2006 Filename VERSIONS Project Progress Report Jan06 v1b.doc URL if document is posted on project web site Access Project and JISC internal General dissemination Document History Version Date Comments 0a 21 February Final draft version submitted for approval by Project Director a 28 February Final version submitted to JISC and to project partners b 3 April 2006 Final accepted version for general dissemination Page 1 of 12

2 Overview of Project Grant Statement Please confirm that the project is being conducted under the terms agreed with JISC in the letter of grant and the JISC Terms and Conditions attached to it. Note any changes to the original award, including any extensions or alterations granted. The project is being conducted under the terms agreed with JISC in the letter of grant dated 13 May Two adjustments have been agreed with the JISC Programme Manager: Before the project started, a one-month no-cost extension was agreed by on 23 May 2005, so that the Project start and end dates were adjusted to July 2005 to December 2006 (from June 2005 to November 2006) In January 2006, a one-month no-cost extension was agreed in response to a two-month vacancy in the full-time Project Officer post from November 2005-January Aims and Objectives Explain any changes to the original aims/objectives outlined in the project plan. List the targets set for this reporting period and explain if they have been met. There are no changes to the original aims and objectives outlined in the project plan. Targets set for this reporting period were as follows: Target Status Comments WP1: Project website created Met WP1: Recruitment of full-time Project Officer Met Two rounds of recruitment took place, one in July 2005 and one in December 2005 WP1: Detailed Project Plan submitted Met WP1: Project meetings Met July and October 2005, January 2006 VERSIONS Project meetings; August and November 2005, VERSIONS telephone conference calls held with partners. January 2006 VERSIONS Steering Committee (held in Leuven) approved Project Plan and Financial Report WP1: Consortium agreement Partly met Agreement drafted and some signed copies received. WP2: Research interview questions prepared WP2: Interviews held in Nereus partner libraries WP2: Interview notes written up Met Almost completely met Almost completely met Interviews held at KU-Leuven, Universite Libre de Bruxelles, WU- Wien, University of Maastricht, ZBW- Kiel during October to December. Interviews at LSE begun, December to January, with several interviews remaining to be held in February 2006 Notes mostly written up, with remaining interviews to write up in February. Notes to be anonymised during February. Page 2 of 12

3 WP3: Publication lists assembled Met Lists received from all 6 partners in the reporting period. WP5: Mailing lists for the project assembled Met Two private jiscmail lists set up: versions-sc@jiscmail.ac.uk and versions-og@jiscmail.ac.uk 3. Overall Approach Explain any changes to the overall approach outlined in the project plan. There are two additions to the overall approach outlined in the project proposal, though these have been included in the final detailed project plan: Creating scenarios Holding an evaluation workshop 4. Project Outputs Summarise progress during the reporting period and milestones/deliverables achieved. Progress during the reporting period has been fair though slower than anticipated, owing to a staffing vacancy described in Sections 7 and 12. Progress on the project management milestones and deliverables is as outlined in Sections 2 and 15. Most of these deliverables have been met, though there is more work to do on obtaining signed copies of the Consortium Agreement. Progress on the other work packages is outlined in Section 2 and Section Project Outcomes Summarise achievement against objectives, list outcomes and findings to date, and any interim conclusions. How do you see the project developing? Has progress changed the project in any way, and are there implications for the programme? What lessons have been learned that could be passed on to other projects or applied elsewhere? The interviews held during the reporting period have contributed significant information to the Project objectives on: Researchers understanding of different versions in the lifecycle of an academic paper Researchers attitudes towards secure storage and open access availability of papers at different stages Researchers current practices regarding retention of their own author versions Information gathered will feed into the following activities during the next reporting period: Creation of scenarios Interim findings report Questionnaire design Interim findings suggest that: Economists produce many versions of their work from first idea to final published journal article (up to 70); more versions tend to be produced when a work is co-authored Personal resource management strategies vary according to individual working practices and to some extent, local IT infrastructure Although most of the multiple versions produced are personal or private draft version, several milestone public versions and/or finished versions can generally be identified, eg Conference paper, Conference Presentation, Working paper, Submitted version to journal, Report (eg to Page 3 of 12

4 funding agency or government body), Final submitted version to journal (post print), Journal article Repository managers will need to develop policies on managing versions and revisions in order to provide a service to their researchers and to integrate with researchers own workflows Terminology used to describe different versions varies and may not on its own prove a useful tool in version identification In economics, the working paper often remains valuable to researchers even after publication of the journal article version has taken place. The working paper is a fuller more elaborated version, which may be referred to by the author in the journal article itself Citation of the journal article is important both for researchers citing others and for cited authors Researchers are not so concerned with minor variations between versions of papers though these variations are of concern to librarians and repository managers when describing the resources Researchers want to be able to establish quickly and easily when there is a substantive difference between versions, of which they should take account The nature of relationships between versions and the substance of any differences can most easily be explained by the authors, as soon as possible after the date of creation Descriptions of any differences between a final author manuscript version (postprint) and the published journal article are particularly important Researchers are not generally aware of publisher policies on self-archiving of author postprints and are interested in hearing about the ROMEO website Interim conclusions are that although the development of terminology could be useful as one tool in identifying versions, establishing guidelines for expressing the details of differences in the content of versions could be of more practical use to researchers and repository administrators. At present there is no straightforward way to establish the extent of difference other than by a visual comparison and this is time consuming. In terms of providing guidance to researchers in the form of a toolkit, the interim findings confirm that guidance could be useful in the following areas: identifying and describing their own work, negotiations with publishers over copyright assignment and knowledge of rights to self-archive, personal resource management including obtaining/retaining a final author version During the next reporting period the Project intends to obtain further information from the student community through the questionnaire and from other stakeholders by a formal invitation to contribute views. 6. Stakeholder Analysis Summarise the project s engagement with stakeholders including users. 6.1 Project partners The Project has engaged with immediate project partners at Project Module meetings held as part of the Nereus Consortium meetings as follows: July 2005, Dublin October 2005, Brussels January 2006, Leuven In addition there have been two telephone conference calls between partners in August and November Two jiscmail mailing lists were established in October 2005 for communications with partners versions-sc for the Steering Committee and versions-og for the Operational Group of Nereus. 6.2 JISC The project has been represented at the following JISC meetings and events: Page 4 of 12

5 JISC Joint Programmes Meeting, Cambridge, July 2005 JISC Digital Repositories Programme Meeting, Glasgow, October 2005 JISC Training Day on Use Cases and Scenarios, Bath, November Other Digital Repositories Projects and Studies VERSIONS has had informal contacts with other DRP projects at the above meetings and by . For example we were interested to see what the RepoMMan survey had discovered about researchers current practice of storing different versions of research material in various locations. This topic has now been identified as a theme of interest to several projects and usefully named personal resource management by Sarah Currier, Programme Support Officer. LSE Library and the VERSIONS Project were approached by Rightscom Ltd about a potential partnership. Rightscom is leading the RIVER project, a short-term scoping study for the JISC Scholarly Communications Group on version identification. VERSIONS Project staff and LSE Library staff are partners in the study along with Oxford University Computing Services (including staff from the JISC DRP Project ASK). The VERSIONS Project responded to an invitation to contribute views by questionnaire to the Linking UK Repositories Scoping Study, led by University of Hull and other partners. 6.4 Users The project has engaged with users during the reporting period by means of interviews with academic researchers and repository managers/librarians. 31 individual interviews have been held with: Professors Heads of academic departments Lecturers/researchers PhD students Research support service manager Repository managers, assistants and technical staff Other library staff In addition, LSE economics researchers who have been involved in the Economists Online economics subject repository pilot have been informed about the VERSIONS project by means of individual and in some cases individual meetings and discussions. 6.5 Other Engagement with other stakeholders such as representatives of the metadata and software development communities has consisted of informal discussions at opportune meetings such as JISC events, during the reporting period. A list of stakeholders to approach was drawn up in October and this activity will be stepped up and formalised during the coming reporting period. 7. Risk Analysis Summarise any problems that have occurred and any mitigating actions taken. A full-time Project Officer was appointed during July 2005 and started work on schedule in September Unfortunately however, the Project Officer left in mid-november. Mitigating actions taken were: Repeat round of recruitment carried out and completed in December 2005 with new Project Officer appointed and in post by 23 January 2006 Request for no-cost extension to project agreed by Programme Manager in January 2006 Temporary WP operator staff recruited during January 2006 to assist with typing up interview notes 8. Standards Note any changes in the standards to be used and the reasons. There is nothing to report under this heading. Page 5 of 12

6 9. Technical Development Note any changes in the development approach or technologies to be used and the reasons. There is nothing to report under this heading. 10. Intellectual Property Rights Summarise progress clearing any third-party rights. There is nothing to report under this heading. Project Resources 11. Project Partners Explain any changes to the institutional project partners or subcontractors, and any impacts this has/will have on the project or schedule. What other institutions or organisations are you or do you plan to collaborate with? The Nereus Consortium expanded from 6 to 15 members during the period since the grant award. New members joining Nereus up to September 2005 are also members of the VERSIONS Project. Some of these new partners have participated by hosting interviews with researchers. Newer members joining Nereus since September 2005 have been invited to join the VERSIONS Project if they wish. As reported in Section 6, LSE Library and the VERSIONS Project are collaborating with Rightscom Ltd and with Oxford University Computing Services and the ASK Project on a short-term scoping study on version identification for the JISC Scholarly Communications Group. 12. Project Management Note any changes in project staff or their roles since the last report. Briefly explain any problems or gaps with staffing and the effect this has had on the project schedule. As noted in Section 7, there was a two-month vacancy in the full-time Project Officer post. The effect on the project schedule has been: The timetables of interviews with researchers had already been drawn up, so these were largely kept on schedule with the Project Manager conducting the interviews during October to December There was a delay in writing up the full notes of the interviews and it was not possible to begin analysing the notes during the reporting period Research interviews with LSE staff were postponed until January-February 2006 Formal contacts with other stakeholders from the metadata, repository software development and publishing communities were not made during the reporting period owing to the vacancy. This will resume from February/March The work on the publications list analysis was postponed until recruitment of the new Project Officer. Louise Allsop took up post as Project and Communications Officer on 23 January Programme Support Summarise contact with/influence of the programme, e.g. with the programme manager, formal or informal links with other projects, or programme-related activities. What further support would you like from the programme, e.g. guidance, workshops, etc? Do you have any suggestions for improving the programme? Page 6 of 12

7 The Project has received site visits from JISC Programme staff as follows: Visit from Neil Jacobs, the Programme Manager, July 2005 Visit from Julie Allinson, one of the Programme Support Officers, January 2006 These were very useful opportunities to discuss progress and possible links with other projects. The Programme Manager and Support Officer have been helpful and supportive. The training in use cases and scenarios held in November 2005 was relevant and useful. VERSIONS Project Staff have also attended JISC meetings and events as reported in Section 6 and these have been useful occasions to meet other Project staff as well as JISC personnel. The programme wiki and the digital repositories discussion list have been good developments. 14. Budget Use the budget template to report expenditure against and attach as Appendix A. Explain the reasons for any significant overspend or underspend. Expenditure during the reporting period is attached as Appendix A. Detailed Project Planning 15. Workpackages Report progress against plan, noting key activities during the reporting period. Explain why any targets haven t been met. List objectives for the next reporting period, note if any changes to plan are needed, and explain why. Current reporting period: WP1: Project Management and Reporting Project plan Completed January 2006 Project website Completed September ; there was no expertise within the Project on website creation a freelance designer was hired. Some advice was provided by LSE Website Services Recruit Project Officer Completed July 2005 and Project meetings again in December 2005 July, October 2005 and January 2006; telephone conference calls August and November 2005 WP2: User Requirements Study and Repository Use Objectives for study and Completed October 2005 questioning route for interviews Arrange and conduct Interviews completed at interviews Nereus partner libraries by Conference calls were new to the Library at LSE Project staff have advised other Library colleagues on use of system and have had to spend some time on establishing charging procedures for the calls. In January 2006, the project plan, financial report and an oral progress report were approved at the VERSIONS Steering Committee meeting in Leuven. Agreed with Nereus partners at October meeting Some interviews remaining to be conducted at LSE during January- Page 7 of 12

8 Write up interview notes WP3: Publications List Analysis Define criteria and request publication lists from Nereus Economists Online partners December 2005 February 2006 Almost completed by January This milestone suffered from loss of 2006 Project Officer. Some ground was made up through use of temporary staff during January to type up transcripts Lists supplied by Nereus partners by January 2006 WP4: Guidelines and Standards no milestones were due in this period Make contact with stakeholders Literature review WP5: Dissemination and evaluation Maintain project website Discussion with partners during October-November led to clarification of information that would be available from partners some but not all could provide information about provenance of full text open access copies. Individual partners would provide the publications lists to LSE rather than obtaining the lists from the central EO repository. This activity suffered from the loss of the Project Officer. A preliminary list of stakeholders has been prepared and informal contacts made as the opportunity arose Work on this has begun The Project website has not been updated owing to the Project Officer vacancy. Establish mailing lists Completed October 2005 Initially a public jiscmail list for the VERSIONS Project was set up in addition to two lists for project partners. However, following the establishment of the open digitalrepositories list by the JISC DRP, the idea of a separate public mailing list has been dropped. Public communications will be carried out through the digital repositories list instead. Presentations and/or papers at relevant workshops and conferences Publish articles in appropriate journals and newsletters Next reporting period: Paper delivered at OAI4 in October 2005 No full articles as yet, but some news items issued. Objective Due date Changes to plan needed and reasons WP2: Interim findings report February 2006 Need to re-schedule this deliverable for March 2006 to allow time for review by Consortium partners; reason February timing was unrealistic given that interviews at LSE are continuing into February WP2: Develop questionnaire February 2006 WP2: Publicise and launch March 2006 Page 8 of 12

9 questionnaire WP2: Write scenarios February 2006 WP2: Analyse results of May 2006 questionnaire WP2: Report on findings of July 2006 user study incorporating results from publications list analysis WP3: Analysis of proportion of February 2006 papers available in full text WP3: Project partners who can February 2006 provide this, to send complete information about provenance of full text and reasons for nonavailability WP3: Consolidate lists and February 2006 provide cross-tabulation with Romeo status WP3: Analysis of findings February 2006 WP3: Report on findings of March 2006 publications list analysis WP4: Literature review March 2006 WP4: Develop guidelines on July 2006 version identification WP5: Maintain project website Ongoing WP5: Organise and report on June 2006 evaluation workshop 16. Evaluation Plan Report progress against plan, and note any evaluation results during the reporting period. List objectives for the next reporting period, note if any changes to plan are needed, and explain why. Current reporting period: There were no evaluation activities planned. Planning for an evaluation workshop on the user requirements study to be held in May 2006 has begun during the reporting period. Agreement has been reached with the project partners on the date and venue, 10 May 2006 at LSE. The date coordinates with a Nereus quarterly meeting taking place in the UK on May and will allow the Project to invite selected Nereus partners to participate in the workshop. Next reporting period: The online survey will be assessed to evaluate size of sample and range of respondents The publications list analysis will be evaluated in terms of completeness of data provided by partners The user requirements survey and publications lists analysis will be evaluated for validity of findings at an evaluation workshop 17. Quality Assurance Plan Report progress against plan, describe the QA procedures put in place, and any QA results during the reporting period. List objectives for the next reporting period, note if any changes to plan are needed, and explain why. Current reporting period: Page 9 of 12

10 Quality assurance procedures relating to the Project website were carried out during the reporting period. The website passed the W3C test but there were one or two issues relating to WCAG accessibility testing. LSE s Website Services staff advised the Project that these issues were relatively minor. Additional testing was carried out in LSE s suite for visually impaired readers which appeared to confirm this view. However, looking to the future, it is hoped that the new Project Officer may be able to address the outstanding issues and ensure full compliance, following training in FrontPage. The detailed project plan was approved by the Project Steering Committee. During the reporting period, Morag Greig of University of Glasgow (and the Daedalus Project) and Bill Hubbard of SHERPA and University of Nottingham kindly agreed to carry out peer review of some of the VERSIONS Project s written deliverables. Next reporting period: The interim findings report on the interviews will be reviewed by VERSIONS Consortium partners The online questionnaire for the user requirements study will be given a pilot testing and feedback will be incorporated The full findings report will be subject to peer review and the user requirements study will be evaluated at a workshop The publications lists analysis will be subject to peer review and review by VERSIONS Consortium partners A literature review will be subject to peer review The guidelines on versions will be subject to peer review 18. Dissemination Plan Report progress against plan, noting dissemination done, whether you feel it was successful, and any publicity the project received during the reporting period. List objectives for the next reporting period, note if any changes to plan are needed, and explain why. Current reporting period: There has been significant dissemination about the Project during the reporting period: Written items: Two brief items in the LSE internal online newsletter to staff LSE Briefing, July 2005 and January 2006 A4 Flyer about the project for Joint Programmes Meeting, Cambridge, July 2005 Project website, September 2005 and ongoing Brief news item on the VERSIONS Project in CURLNews, No. 16, January Key stakeholders in the Economics Department have been informed about the project and invited to participate in interviews Presentations: Short presentation to JISC DRP Projects at the Joint Programmes Meeting, Cambridge, July 2005 Versions in the lifecycle of academic papers - user requirements and guidelines for digital repositories, presentation at the CERN Workshop on Innovations in Scholarly Communication (OAI4), Geneva, October Short presentation on the VERSIONS Project to SHERPA Network Meeting, Glasgow, December 2005 (given by Sally Rumsey, LSE E-Services Librarian on behalf of the Project) Next reporting period: Page 10 of 12

11 The Project will aim to make further presentations and to seek opportunities for dissemination through written items, beginning with a presentation to CABI Publishers in Oxfordshire. 19. Exit/Sustainability Plan Report progress against plan, noting any issues related to archiving, preservation, maintenance, supporting documentation, etc. List objectives for the next reporting period, note if any changes to plan are needed, and explain why. Current reporting period: The setting up of the Project website was the first step in providing for project deliverables to be maintained during and after the Project. Next reporting period: There is nothing to report under this heading for the coming reporting period Page 11 of 12

12 Appendix A Project Budget for July 2005 to January 2006 Page 12 of 12

JISC DEVELOPMENT PROGRAMMES Project Document Cover Sheet PROGRESS REPORT

JISC DEVELOPMENT PROGRAMMES Project Document Cover Sheet PROGRESS REPORT Project JISC DEVELOPMENT PROGRAMMES Project Document Cover Sheet PROGRESS REPORT Project Acronym VERSIONS Project ID Project Title Versions of Eprints user Requirements Study and Investigation of the Need

More information

Versions of academic papers online - the experience of authors and readers

Versions of academic papers online - the experience of authors and readers Versions of academic papers online - the experience of authors and readers Thank you for your interest in the VERSIONS Project survey on writing, disseminating and accessing academic research papers. This

More information

The overall aim for this project is To improve the way that the University currently manages its research publications data

The overall aim for this project is To improve the way that the University currently manages its research publications data Project Plan Overview of Project 1. Background The I-WIRE project will develop a workflow and toolset, integrated into a portal environment, for the submission, indexing, and re-purposing of research outputs

More information

Response to Invitation to Tender: requirements and feasibility study on preservation of e-prints

Response to Invitation to Tender: requirements and feasibility study on preservation of e-prints Response to Invitation to Tender: requirements and feasibility study on preservation of e-prints A proposal to the JISC from the Arts and Humanities Data Service and the University of Nottingham, Project

More information

THE UNIVERSITY OF LEEDS. Vice Chancellor s Executive Group Funding for Research Data Management: Interim

THE UNIVERSITY OF LEEDS. Vice Chancellor s Executive Group Funding for Research Data Management: Interim THE UNIVERSITY OF LEEDS VCEG/12/274 Vice Chancellor s Executive Group Funding for Research Data Management: Interim SOME CONTENT HAS BEEN REMOVED FROM THIS PAPER TO MAKE IT SUITABLE FOR PUBLIC DISSEMINATION

More information

Project Plan DATA MANAGEMENT PLANNING FOR ESRC RESEARCH DATA-RICH INVESTMENTS

Project Plan DATA MANAGEMENT PLANNING FOR ESRC RESEARCH DATA-RICH INVESTMENTS Date: 2010-01-28 Project Plan DATA MANAGEMENT PLANNING FOR ESRC RESEARCH DATA-RICH INVESTMENTS Overview of Project 1. Background Research data is essential for good quality research, especially when data

More information

Progress Report Template -

Progress Report Template - Progress Report Template - Project Name Project Website Report compiled by Kultur, University of Southampton (lead institution) http://kultur.eprints.org Victoria Sheppard Reporting period Oct 07 Apr 08

More information

Project Information. EDINA, University of Edinburgh Christine Rees Sheila Fraser sheila.fraser@ed.ac.uk 0131 651 7715

Project Information. EDINA, University of Edinburgh Christine Rees Sheila Fraser sheila.fraser@ed.ac.uk 0131 651 7715 Project Acronym - Project Title Project Information Scoping Study: Aggregations of Metadata for Images and Time-based Media Start Date June 2010 End Date 17 September 2010 Lead Institution Project Director

More information

Institutional Repositories: Staff and Skills Set

Institutional Repositories: Staff and Skills Set SHERPA Document Institutional Repositories: Staff and Skills Set University of Nottingham 25 th August 2009 Circulation PUBLIC Mary Robinson University of Nottingham Introduction This document began in

More information

Progress Report Template -

Progress Report Template - Progress Report Template - Text in italics is explanatory and should be deleted in completed documents. Project Name Project Website Report compiled by CHARTER UNIVERSITY OF EXETER http://projects.exeter.ac.uk/charter/

More information

Resource Discovery Services at London School of Economics Library

Resource Discovery Services at London School of Economics Library Resource Discovery Services at London School of Economics Library Graham Camfield Abstract The paper describes some recent projects and developments at the Library of the London School of Economics and

More information

Optimising Data Management: full listing of deliverables. College storage approach

Optimising Data Management: full listing of deliverables. College storage approach Appendix 4: Optimising Data Management: full listing of deliverables Description Deliverables Notes Principles for data quality and re-use Identification of accountable person for key systems Establishment

More information

RESEARCH DATA MANAGEMENT AT THE UNIVERSITY OF WARWICK: RECENT STEPS TOWARDS A JOINED-UP APPROACH AT A UK UNIVERSITY

RESEARCH DATA MANAGEMENT AT THE UNIVERSITY OF WARWICK: RECENT STEPS TOWARDS A JOINED-UP APPROACH AT A UK UNIVERSITY Abstract RESEARCH DATA MANAGEMENT AT THE UNIVERSITY OF WARWICK: RECENT STEPS TOWARDS A JOINED-UP APPROACH AT A UK UNIVERSITY from Jenny Delasalle This paper charts the steps taken and possible ways forward

More information

JISC Project Plan. Project Information Project Identifier To be completed by JISC Project Title

JISC Project Plan. Project Information Project Identifier To be completed by JISC Project Title Contact: Chris Franks (chris.franks@ncl.ac.uk) Date: 29/02/12 JISC Project Plan Project Information Project Identifier To be completed by JISC Project Title RAPID (Raptor Informing Decisions) Project Hashtag

More information

HERON (No: 649690): Deliverable D.2.6 DATA MANAGEMENT PLAN AUGUST 2015. Partners: Oxford Brookes University and Università Commerciale Luigi Bocconi

HERON (No: 649690): Deliverable D.2.6 DATA MANAGEMENT PLAN AUGUST 2015. Partners: Oxford Brookes University and Università Commerciale Luigi Bocconi HERON (No: 649690): Deliverable D.2.6 DATA MANAGEMENT PLAN AUGUST 2015 Partners: Oxford Brookes University and Università Commerciale Luigi Bocconi Institutions: Low Carbon Building Group, Oxford Brookes

More information

UKSG Invitation to Develop Library Discovery Technologies

UKSG Invitation to Develop Library Discovery Technologies UKSG Invitation to Tender Assessing the Impact of Library Discovery Technology on Content Usage 1. UKSG, with the support of Jisc, invite tenders for a research study assessing the impact of library discovery

More information

Jean Sykes The UK Research Data Service Project

Jean Sykes The UK Research Data Service Project Jean Sykes The UK Research Data Service Project Keynote Item Original citation: Originally presented at ESRDS Social Science Week, 13 March 2009, London, UK. This version available at: http://eprints.lse.ac.uk/25373/

More information

Taking Forward The Curl Vision: The Year s Highlights

Taking Forward The Curl Vision: The Year s Highlights Annual Report 07-08 Annual Report 07-08 A N N U A L R E P O R T 0 7-0 8 6 Research Libraries UK Research Libraries UK 7 Taking Forward The Curl Vision: The Year s Highlights Communications Chair: Michele

More information

JISC Project Plan. Project Information. Project Title Project Hashtag. Bringing Corporate Data to Life

JISC Project Plan. Project Information. Project Title Project Hashtag. Bringing Corporate Data to Life JISC Project Plan Before completing this template please note: This template is for completion by JISC funded projects Text in blue italics is explanatory and should be deleted in completed documents.

More information

JISC Brief Progress Report Template

JISC Brief Progress Report Template JISC Brief Progress Report Template Project Document Cover Sheet Project Acronym Project Title eppsme Project Information An e-portfolio based Pedagogy for SMEs Start Date April 2009 End Date March 2011

More information

E N T R E P R E N E U R I A L S K I L L S P A S S P R O J E C T Q U A L I T Y A S S U R A N C E P L A N

E N T R E P R E N E U R I A L S K I L L S P A S S P R O J E C T Q U A L I T Y A S S U R A N C E P L A N E N T R E P R E N E U R I A L S K I L L S P A S S P R O J E C T Q U A L I T Y A S S U R A N C E P L A N Version 6.0 24/05/2014 Entrepreneurial Skills Pass V E R S I O N H I S T O R Y Version # Date Author

More information

What Are institutional Repositories and Their Function?

What Are institutional Repositories and Their Function? Open Access Budapest Open Access Initiative An old tradition and a new technology have converged to make possible an unprecedented public good... http://www.soros.org/openaccess/read.shtml High principals

More information

1 About This Proposal

1 About This Proposal 1 About This Proposal 1. This proposal describes a six-month pilot data-management project, entitled Sustainable Management of Digital Music Research Data, to run at the Centre for Digital Music (C4DM)

More information

JISC Project Plan. Leeds RoaDMaP (Leeds Research Data Management Pilot) #leedsrdm. University of Leeds

JISC Project Plan. Leeds RoaDMaP (Leeds Research Data Management Pilot) #leedsrdm. University of Leeds Date: 09/03/2012 JISC Project Plan Project Information Project Identifier To be completed by JISC Project Title Leeds RoaDMaP (Leeds Research Data Management Pilot) Project Hashtag #leedsrdm Start Date

More information

Supporting Digital Preservation and Asset Management in Institutions

Supporting Digital Preservation and Asset Management in Institutions Page 1 of 7 Issue 43 April 2005 Supporting Digital Preservation and Asset Management in Institutions Leona Carpenter describes a JISC development programme tackling the organisational and technical challenges

More information

Institutional Repositories: Staff and Skills requirements

Institutional Repositories: Staff and Skills requirements SHERPA Document Institutional Repositories: Staff and Skills requirements 8th August 2007 Circulation PUBLIC Mary Robinson Introduction This document began in response to requests received by the core

More information

Development of a retention schedule for research data at the London School of Hygiene & Tropical Medicine JISC final report

Development of a retention schedule for research data at the London School of Hygiene & Tropical Medicine JISC final report 1. Introduction Development of a retention schedule for research data at the London School of Hygiene & Tropical Medicine JISC final report 1.1 The London School of Hygiene & Tropical Medicine is a postgraduate

More information

JISC Progress Report Template - Full

JISC Progress Report Template - Full JISC Progress Report Template - Full Project Identifier Project Title Project Hashtag Project Information To be completed by JISC U-CARE: Universities Collaborative Approach to Reducing Energy Start Date

More information

Initiating an Arts Repository: the gateway to research at University College Falmouth

Initiating an Arts Repository: the gateway to research at University College Falmouth Kultivate Project Case Study Initiating an Arts Repository: the gateway to research at Tim Shear, Learning Technologist Tom Readings, Digital Resources Officer Doreen Pinfold, Head of Library and Information

More information

LIBER Case Study: University of Oxford Research Data Management Infrastructure

LIBER Case Study: University of Oxford Research Data Management Infrastructure LIBER Case Study: University of Oxford Research Data Management Infrastructure AuthorS: Dr James A. J. Wilson, University of Oxford, james.wilson@it.ox.ac.uk Keywords: generic, institutional, software

More information

Laurian Williamson, Research Data Management Service Developer Version 1.0 October 2012 Version 2.0 January 2013 Version 3.

Laurian Williamson, Research Data Management Service Developer Version 1.0 October 2012 Version 2.0 January 2013 Version 3. Information Services Roles, responsibilities and skills matrix for research data management (RDM) support ADMIRe working document Laurian Williamson, Research Data Management Service Developer Version

More information

Recommendations for the Implementation of Article 37 of the Spanish Science, Technology and Innovation Act: Open Access Dissemination SUMMARY

Recommendations for the Implementation of Article 37 of the Spanish Science, Technology and Innovation Act: Open Access Dissemination SUMMARY Recommendations for the Implementation of Article 37 of the Spanish Science, Technology and Innovation Act: Open Access Dissemination SUMMARY CC BY - 1 Publication date: October 2014 Index 1. Introduction

More information

Leadership, management and the part-time doctoral experience for second career researchers

Leadership, management and the part-time doctoral experience for second career researchers LF Small Development Project Leadership, management and the part-time doctoral experience for second career researchers End-of-Funding Report Dr Pauline Couper Dr Julie Evans 1 Contents 1. Project Details...

More information

LJMU Research Data Policy: information and guidance

LJMU Research Data Policy: information and guidance LJMU Research Data Policy: information and guidance Prof. Director of Research April 2013 Aims This document outlines the University policy and provides advice on the treatment, storage and sharing of

More information

PERARES PROJECT EVALUATIONS

PERARES PROJECT EVALUATIONS PERARES PROJECT EVALUATIONS The checklist and survey forms in the following pages are proposed for use in 2012 2014 by Perares partners in evaluation of projects they undertake within Perares or independently

More information

Human Resources Report 2014

Human Resources Report 2014 Item 7 Item # Council CounciRemunerationl 3 February Date19 2015 March 2013 Human Resources Report 2014 Purpose of paper Action Public/Private Corporate Strategy 2013-15 Decision Trail Recommendations

More information

Report on a deposit licence for E-prints

Report on a deposit licence for E-prints !74 0.94.:2039 Report on a deposit licence for E-prints Circulation: PUBLIC Gareth Knight Arts & Humanities Data Service Notes 1. For the purposes of this document, an e-print is defined as an electronic

More information

JISC Project Plan. Project Information. Project Title Project Hashtag. TraD: Training for Data Management

JISC Project Plan. Project Information. Project Title Project Hashtag. TraD: Training for Data Management JISC Project Plan Before completing this template please note: This template is for completion by JISC funded projects Text in blue italics is explanatory and should be deleted in completed documents.

More information

Green, Blue, Yellow, White & Gold A brief guide to the open access rainbow.

Green, Blue, Yellow, White & Gold A brief guide to the open access rainbow. Green, Blue, Yellow, White & Gold A brief guide to the open access rainbow. Part One -- The Basic Picture Bill Hubbard Repositories Support Project In looking at the options that are available for the

More information

Project reporting in FP6

Project reporting in FP6 Guidance notes for Integrated Projects, Networks of Excellence, Specific Targeted Research or Innovation Projects, Coordination Actions, Specific Support Actions, Co-operative Research Projects and Collective

More information

How To Work With Outside Trainers And Consultants

How To Work With Outside Trainers And Consultants Denbighshire Voluntary Services Council Your local county voluntary council 2. Running your organisation 2.14 Using freelance trainers and consultants Introduction The purpose of this information sheet

More information

Information Management

Information Management G i Information Management Information Management Planning March 2005 Produced by Information Management Branch Open Government Service Alberta 3 rd Floor, Commerce Place 10155 102 Street Edmonton, Alberta,

More information

DataShare & Data Audit. Lessons Learned. Robin Rice. Digital Curation Practice, Promise and Prospects

DataShare & Data Audit. Lessons Learned. Robin Rice. Digital Curation Practice, Promise and Prospects DataShare & Data Audit Framework 2007-09: 09: Lessons Learned Robin Rice University of Edinburgh, Scotland Digital Curation Practice, Promise and Prospects Chapel Hill, NC USA April 1-3 2009 A forum for

More information

Guideline. Records Management Strategy. Public Record Office Victoria PROS 10/10 Strategic Management. Version Number: 1.0. Issue Date: 19/07/2010

Guideline. Records Management Strategy. Public Record Office Victoria PROS 10/10 Strategic Management. Version Number: 1.0. Issue Date: 19/07/2010 Public Record Office Victoria PROS 10/10 Strategic Management Guideline 5 Records Management Strategy Version Number: 1.0 Issue Date: 19/07/2010 Expiry Date: 19/07/2015 State of Victoria 2010 Version 1.0

More information

Role and Skill Descriptions. For An ITIL Implementation Project

Role and Skill Descriptions. For An ITIL Implementation Project Role and Skill Descriptions For An ITIL Implementation Project The following skill traits were identified as fairly typical of those needed to execute many of the key activities identified: Customer Relationship

More information

Deliverable D2.2. MasterMind Website MASTERMIND

Deliverable D2.2. MasterMind Website MASTERMIND Deliverable D2.2 MasterMind Website MASTERMIND MAnagement of mental health disorders Through advanced technologyand services telehealth for the MIND GA no. 621000 Project co-funded by the European Commission

More information

EXECUTIVE EDUCATION PROGRAMME FACILITATOR

EXECUTIVE EDUCATION PROGRAMME FACILITATOR EXECUTIVE EDUCATION PROGRAMME FACILITATOR IfM Education and Consultancy Services Limited, Institute for Manufacturing, University of Cambridge THE MAIN PURPOSE OF THE JOB ROLE IS TO: Facilitate the development

More information

EPSRC Research Data Management Compliance Report

EPSRC Research Data Management Compliance Report EPSRC Research Data Management Compliance Report Contents Introduction... 2 Approval Process... 2 Review Schedule... 2 Acknowledgement... 2 EPSRC Expectations... 3 1. Awareness of EPSRC principles and

More information

Introduction The Co-Motion Data Management Plan draws upon guidance from the Centre for Housing Policy s Data

Introduction The Co-Motion Data Management Plan draws upon guidance from the Centre for Housing Policy s Data Co-Motion: Data Management Plan Design for Wellbeing: Ageing and Mobility in the Built Environment EPSRC Grant Reference: EP/K03748X/1 Principal Investigator: Dr Mark Bevan Contact Project Manager: co-motion@york.ac.uk

More information

Loughborough University Institutional Repository. This item was submitted to Loughborough University's Institutional Repository by the/an author.

Loughborough University Institutional Repository. This item was submitted to Loughborough University's Institutional Repository by the/an author. Loughborough University Institutional Repository Providing eective continuing professional development to United Kingdom academic librarians in the further education sector : outcomes from a national survey

More information

Inception Report. for. Cadastre & Registration FLOSS Project

Inception Report. for. Cadastre & Registration FLOSS Project Inception Report for Cadastre & Registration Version [1.1] Status [INITIAL DRAFT] Version date [30/07/2010] Document Id Cadastre & Registration FLOSS No. 1 Introduction Document Control Version Summary

More information

External Audit BV Performance Report: Delivering Change Management and Financial Sustainability

External Audit BV Performance Report: Delivering Change Management and Financial Sustainability CLACKMANNANSHIRE COUNCIL THIS PAPER RELATES TO ITEM 05 ON THE AGENDA Report to: Resources and Audit Committee Date of Meeting: 24 September 2015 Subject: External Audit BV Performance Report: Delivering

More information

SOCIAL MEDIA AND AUSTERITY: ONLINE PEER SUPPORT IN MENTAL HEALTH COMMUNITIES

SOCIAL MEDIA AND AUSTERITY: ONLINE PEER SUPPORT IN MENTAL HEALTH COMMUNITIES SOCIAL MEDIA AND AUSTERITY: ONLINE PEER SUPPORT IN MENTAL HEALTH COMMUNITIES Dr Ian Tucker (University of East London), Dr Lewis Goodings (University of Roehampton), Mr Brett Raymond-Barker (University

More information

PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:

PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: Project Name Project Management Plan Document Information Document Title Version Author Owner Project Management Plan Amendment History

More information

European Commission Green Public Procurement (GPP) Training Toolkit - Module 1: Managing GPP Implementation. Joint procurement.

European Commission Green Public Procurement (GPP) Training Toolkit - Module 1: Managing GPP Implementation. Joint procurement. European Commission Green Public Procurement (GPP) Training Toolkit - Module 1: Managing GPP Implementation Joint procurement Fact sheet Toolkit developed for the European Commission by ICLEI - Local Governments

More information

Community engagement: Developing a strategy

Community engagement: Developing a strategy Community engagement: Developing a strategy Some questions to help with planning... This guidance outlines some important things to consider when planning a community engagement strategy for your project

More information

Programme Specification. MRes Developmental Psychology. Valid from: September 2012 Faculty of Health & Life Sciences

Programme Specification. MRes Developmental Psychology. Valid from: September 2012 Faculty of Health & Life Sciences Programme Specification MRes Developmental Psychology Valid from: September 2012 Faculty of Health & Life Sciences SECTION 1: GENERAL INFORMATION Awarding body: Teaching institution and location: Final

More information

Deliverable D7.2: The project website

Deliverable D7.2: The project website Project acronym: TRACE Project title: Trafficking as A Criminal Enterprise Grant number: 607669 Programme: Seventh Framework Programme Security Research Objective: SEC-2013.6.1-3 Contract type: Coordination

More information

OpenAIRE Research Data Management Briefing paper

OpenAIRE Research Data Management Briefing paper OpenAIRE Research Data Management Briefing paper Understanding Research Data Management February 2016 H2020-EINFRA-2014-1 Topic: e-infrastructure for Open Access Research & Innovation action Grant Agreement

More information

UNIVERSITY OF SUSSEX. 1 Advertisement Ref: 861

UNIVERSITY OF SUSSEX. 1 Advertisement Ref: 861 UNIVERSITY OF SUSSE 1 Advertisement Ref: 861 Head of Content Delivery and Digital Strategy Permanent, full time Salary range: starting at 47,328 and rising to 54,841 per annum. It is normal to appoint

More information

Guide to choosing a Consultant

Guide to choosing a Consultant Guide to choosing a Consultant Contents 1. Background: about this resource... 1 2. The process of selecting, engaging and managing consultants... 1 Stage 1: Do we really need a consultant or contractor

More information

Research Data Management Support Service Jan June 2015 End Stage Report

Research Data Management Support Service Jan June 2015 End Stage Report Research Data Management Support Service Jan June 2015 End Stage Report Report Version Control Version Date Author Change Description 1.0 23/06/2015 Gareth Knight 1 1.1. Project Manager s Report This End

More information

Healthwatch Oxfordshire Board of Directors

Healthwatch Oxfordshire Board of Directors Healthwatch Oxfordshire Board of Directors Date of Meeting: October 14 th 2014 Paper No: 9 Title of Presentation: Amendments to contract with OCC This paper is for Discussion Decision x Information Purpose

More information

Library Impact Data Project

Library Impact Data Project Library Impact Data Project Summary This project aims to prove a statistically significant correlation between library usage and student attainment. Using activity data from three separate systems and

More information

JISC Project Plan - EVIE

JISC Project Plan - EVIE EVIE Project Plan Version 2.1 11.3.05 JISC Project Plan - EVIE Overview of Project 1. Background Researchers in all disciplines are increasingly expecting to be able to undertake a variety of researchassociated

More information

Project Management Framework

Project Management Framework Information Services Project Management Framework October 2003 Document ID No. Page 1 of 1 Contents 1. Introduction Page 3 2. Use of Framework Page 3 3. Project Register and Monitoring Page 4 4. Project

More information

ETIP Wind Steering Committee meeting Monday 7th March 2016 11:00 16:45 EWEA office, Rue d Arlon 80 6th floor Bruxelles AGENDA

ETIP Wind Steering Committee meeting Monday 7th March 2016 11:00 16:45 EWEA office, Rue d Arlon 80 6th floor Bruxelles AGENDA ETIP Wind Steering Committee Meeting: ETIP Wind Steering Committee meeting Monday 7th March 2016 11:00 16:45 EWEA office, Rue d Arlon 80 6th floor Bruxelles AGENDA 11:00 11:30 11:30 12:00 12:00-12:45 12:45

More information

Checklist for a Data Management Plan draft

Checklist for a Data Management Plan draft Checklist for a Data Management Plan draft The Consortium Partners involved in data creation and analysis are kindly asked to fill out the form in order to provide information for each datasets that will

More information

Jisc Research Data Discovery Service Project

Jisc Research Data Discovery Service Project 23 rd April 2015 First Workshop Jisc Research Data Discovery Service Project Christopher Brown Project Overview and Plan Walkthrough 2 Project Team Team Member Name Role Contact Details Rachel Bruce Deputy

More information

CALL FOR QUOTATION For COMMUNICATION SERVICES

CALL FOR QUOTATION For COMMUNICATION SERVICES CALL FOR QUOTATION For COMMUNICATION SERVICES Background EuroHealthnet invites tenders from communications agencies in order to establish a framework agreement for a maximum duration of 3 years, subject

More information

IBAPro Project Management Methodology

IBAPro Project Management Methodology IBAPro Project Management Methodology A description of the IBApps Project Management Methodology and Implementation Process Version 2.2, June 2013 Contents 1. Project Management... 3 2. Phases... 3 2.1.

More information

Appendix 1e. DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA. Performance Management Framework

Appendix 1e. DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA. Performance Management Framework Appendix 1e DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA Performance Management Framework DISTRIBUTION LIST Audit Team David Esling, Head of Audit and Assurance - Risk Management

More information

University of Edinburgh Knowledge Strategy Committee. 8 June 2012. Use of the Project Governance Toolkit for Shared Academic Timetabling

University of Edinburgh Knowledge Strategy Committee. 8 June 2012. Use of the Project Governance Toolkit for Shared Academic Timetabling University of Edinburgh Knowledge Strategy Committee 8 June 2012 Use of the Project Governance Toolkit for Shared Academic Timetabling Brief description of the paper Shared Academic Timetabling has been

More information

Managing Research Data: Research Data Management Training Materials

Managing Research Data: Research Data Management Training Materials Cover Sheet for Proposals (All sections must be completed) JISC Digital Infrastructure Programme Name of Programme Initiative: Managing Research Data: Research Data Management Training Materials Name of

More information

Nottingham Trent University. Creating a Learning Community using the Brightspace Content Management solution

Nottingham Trent University. Creating a Learning Community using the Brightspace Content Management solution Nottingham Trent University Creating a Learning Community using the Brightspace Content Management solution Overview Challenge Nottingham Trent University (NTU) is among the top 50 higher education providers

More information

The Real Project. Final Quality Report. Professor Michael Osborne

The Real Project. Final Quality Report. Professor Michael Osborne Recognition of Experiential & Accredited Learning (REAL) Project 527723-LLP-1-2012-1-UK-GRUNDTVIG-GMP The Real Project Introduction Final Quality Report Professor Michael Osborne This Final Evaluation

More information

Programme Specification MA MUSEUMS & GALLERIES IN EDUCATION. Awarding Institution Institute of Education University of London. Teaching Institution

Programme Specification MA MUSEUMS & GALLERIES IN EDUCATION. Awarding Institution Institute of Education University of London. Teaching Institution Programme Specification MA MUSEUMS & GALLERIES IN EDUCATION Awarding Institution Institute of Education University of London Teaching Institution Institute of Education University of London Name of final

More information

CDC UNIFIED PROCESS PRACTICES GUIDE

CDC UNIFIED PROCESS PRACTICES GUIDE Purpose The purpose of this document is to provide guidance on the practice called Project Close-Out and to describe the practice overview, requirements, best practices, activities, and key terms related

More information

Procedures for validation and accreditation

Procedures for validation and accreditation Procedures for validation and accreditation Published by the Quality and Academic Support Office, Directorate of Students and Education Support Latest Edition (March 2002, updated August 2009 and 2013

More information

Training and education framework for fertility nursing

Training and education framework for fertility nursing Training and education framework for fertility nursing Carmel Bagness November 2013 A training and education framework for fertility nursing: grant usage feedback report Contents Introduction 3 Background

More information

JISC data.bris project & EPSRC Platform project: progress against workplan (October 2012)

JISC data.bris project & EPSRC Platform project: progress against workplan (October 2012) Project Name : data.bris DBSG/5/2 JISC data.bris project & EPSRC Platform project: progress against workplan (October 2012) WORKPACKAGES Month: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Oct 11 Nov Dec

More information

PROJECT WEBSITE PROJECT WEBSITE

PROJECT WEBSITE PROJECT WEBSITE PROJECT WEBSITE published by the research team of the Horizon 2020 Project DiDIY Digital Do It Yourself in the context of WorkPackage 8 Dissemination, future roadmap and sustainability (WP Lead Partner:

More information

Nottingham Trent University. Creating a Learning Community using the Brightspace Content Management solution

Nottingham Trent University. Creating a Learning Community using the Brightspace Content Management solution Nottingham Trent University Creating a Learning Community using the Brightspace Content Management solution Overview Challenge Nottingham Trent University (NTU) is among the top 50 higher education providers

More information

Securing and using additional external resources to support Health Inequalities Strategy delivery

Securing and using additional external resources to support Health Inequalities Strategy delivery REQUEST FOR DIRECTOR DECISION DD537 Title: Securing and using additional external resources to support Health Inequalities Strategy delivery Executive Summary: The Greater London Authority Act 1999 requires

More information

Choosing & using a Lean Construction Consultant

Choosing & using a Lean Construction Consultant This is a response to the growing interest in lean construction and the growth in the use of lean construction consultants 1. It aims to help owners, clients, constructors and projects (who we will refer

More information

IPR issues facing open access

IPR issues facing open access Loughborough University Institutional Repository IPR issues facing open access This item was submitted to Loughborough University's Institutional Repository by the/an author. Citation: GADD, E., 2003.

More information

Copac Collection Management Tools Pilot

Copac Collection Management Tools Pilot Copac Collection Management Tools Pilot Final Report November 2011- July 2012 Partners: Mimas, RLUK, & the White Rose Consortium Associates: Universities of Manchester, Warwick, UCL & the V&A. Funded by

More information

Research and the Scholarly Communications Process: Towards Strategic Goals for Public Policy

Research and the Scholarly Communications Process: Towards Strategic Goals for Public Policy Research and the Scholarly Communications Process: Towards Strategic Goals for Public Policy A Statement of Principles March 2007 www.rin.ac.uk Research and the Scholarly Communications Process: Towards

More information

Measuring the Impact of Volunteering

Measuring the Impact of Volunteering Measuring the Impact of Volunteering Why is measuring the impact of volunteering important? It is increasingly important for organisations or groups to describe the difference that volunteering makes to,

More information

The Lifecycle Management of ETDs Project: Multi Stakeholders National Partnership

The Lifecycle Management of ETDs Project: Multi Stakeholders National Partnership The Lifecycle Management of ETDs Project: Multi Stakeholders National Partnership Shannon Stark Shannon.stark@unt.edu Daniel G. Alemneh Daniel.alemneh@unt.edu Stephen Eisenhauer Stephen.eisenhauer@unt.edu

More information

Programme Enhancement Plan (PEP) Template (Integrated Masters) Semester 1

Programme Enhancement Plan (PEP) Template (Integrated Masters) Semester 1 Academic Quality & Partnerships Office Programme Information Academic School: Programme Enhancement Plan (PEP) Template (Integrated Masters) Semester 1 What is the name of the award that this enhancement

More information

INFORMATION NOTICE No. 1 * 3. The work programme of the meeting will consist of the following substantive themes:

INFORMATION NOTICE No. 1 * 3. The work programme of the meeting will consist of the following substantive themes: INF.1 15 December 2011 ENGLISH ONLY UNITED NATIONS ECONOMIC COMMISSION FOR EUROPE CONFERENCE OF EUROPEAN STATISTICIANS Work Session on the Communication of Statistics (DISSCOM 2012) (Geneva, Switzerland,

More information

D1.3 Data Management Plan

D1.3 Data Management Plan Funded by the European Union s H2020 Programme D1.3 Data Management Plan 1 PROJECT DOCUMENTATION SHEET Project Acronym Project Full Title : TANDEM : TransAfrican Network Development Grant Agreement : GA

More information

WP1: Project Management

WP1: Project Management Objectives: Project Management WP1: Project Management Work Description (Methodology / Technical Approach): Work description This work package includes the execution and updating of the SCHEMA Management

More information

Project management & implementation activities

Project management & implementation activities Project management & implementation activities ZGURA-M Ltd. Aims: A1: To ensure that the project is established on a robust and secure organisational structure with clearly defined management functions.

More information

University of Oxford RCUK open access compliance report 2013-14

University of Oxford RCUK open access compliance report 2013-14 Introduction University of Oxford RCUK open access compliance report 2013-14 The University of Oxford has made considerable progress in all areas of its open access (OA) programme. The University is fully

More information

Internal Audit Quality Assessment Framework

Internal Audit Quality Assessment Framework Internal Audit Quality Assessment Framework May 2013 Internal Audit Quality Assessment Framework May 2013 Crown copyright 2013 You may re-use this information (excluding logos) free of charge in any format

More information

Benefits realisation. Gate

Benefits realisation. Gate Benefits realisation Gate 5 The State of Queensland (Queensland Treasury and Trade) 2013. First published by the Queensland Government, Department of Infrastructure and Planning, January 2010. The Queensland

More information

Managing and Sharing research Data

Managing and Sharing research Data Managing and Sharing research A Guide to Good Practice Louise Corti Veerle Van den Eynden Libby Bishop & Matthew Woollard Corti_ AW.indd 8 13/02/2014 14:00 00_Corti_et_al_Prelims.indd 3 2/25/2014 6:02:00

More information

ICT Project Management

ICT Project Management THE UNITED REPUBLIC OF TANZANIA PRESIDENT S OFFICE PUBLIC SERVICE MANAGEMENT ICT Project Management A Step-by-step Guidebook for Managing ICT Projects and Risks Version 1.0 Date Release 04 Jan 2010 Contact

More information