EMBA in Management & Finance. Corporate Finance. Eric Jondeau
|
|
- Vincent Fletcher
- 8 years ago
- Views:
Transcription
1 EMBA in Management & Finance Corporate Finance
2 EMBA in Management & Finance Lecture 5: Capital Budgeting For the Levered Firm
3 Prospectus Recall that there are three questions in corporate finance. The first regards what long-term investments the firm should make (the capital budgeting question). The second regards the use of debt (the capital structure question). This chapter considers the nexus of these questions. EMBA 3/29
4 Outline 1. Adjusted Present Value Approach 2. Flows to Equity Approach 3. Weighted Average Cost of Capital Method 4. Comparison of the APV, FTE, and WACC Approaches 5. Capital Budgeting when the Discount Rate Must Be Estimated 6. APV Example 7. Beta and Leverage 8. Summary and Conclusions EMBA 4/29
5 1. Adjusted Present Value Approach The value of a project to the firm can be thought of as the value of the project to an unlevered firm (NPV) plus the present value of the financing side effects (NPVF): APV = NPV + NPVF There are four side effects of financing: The Tax Subsidy to Debt The Costs of Issuing New Securities The Costs of Financial Distress Subsidies to Debt Financing EMBA 5/29
6 APV Example Consider a project of the Pearson Company. The timing and size of the incremental after-tax cash flows for an all-equity firm are: $1,000 $125 $250 $375 $ The unlevered cost of equity is r 0 = 10%: NPV $125 $250 $375 $500 = $1, (1.10) (1.10) (1.10) (1.10) 10% NPV 10% = $56.50 The project would be rejected by an all-equity firm: NPV < 0. EMBA 6/29
7 APV Example (continued) Now, imagine that the firm finances the project with $600 of debt at r B = 8%. Pearson s tax rate is 40%, so they have an interest tax shield worth τ C r B B = $600 = $19.20 each year. The net present value of the project under leverage is: APV = NPV + NPV APV APV = $ debt tax shield So, Pearson should accept the project with debt. 4 t= 1 $19.20 t (1.08) = $ = $7.09 EMBA 7/29
8 APV Example (continued) Note that there are two ways to calculate the NPV of the loan. Previously, we calculated the PV of the interest tax shields. Now, let s calculate the actual NPV of the loan: NPV NPV loan loan 4 $ (1 0.4) $600 = $600 t (1.08) (1.08) = $63.59 t= 1 4 APV = NPV + NPVF APV = $ = $7.09 which is the same answer as before. EMBA 8/29
9 2. Flow to Equity Approach Discount the cash flow from the project to the equity holders of the levered firm at the cost of levered equity capital, r S. There are three steps in the FTE Approach: Step One: Calculate the levered cash flows Step Two: Calculate r S. Step Three: Valuation of the levered cash flows at r S. EMBA 9/29
10 Step 1: Levered Cash Flows for Pearson Since the firm is using $600 of debt, the equity holders only have to come up with $400 of the initial $1,000. Thus, CF 0 = $400. Each period, the equity holders must pay interest expense. The after-tax cost of the interest is (1 τ C ) r B B = (1 0.40) 0.08 $600 = $28.80 CF 1 = $ CF 3 = $ CF 2 = $ CF 4 = $ $400 $96.20 $ $ $ EMBA 10/29
11 Step 2: Calculate r S for Pearson B rs = r0 + (1 τ C )( r0 rb ) S To calculate the debt to equity ratio, B/S, start with B/V PV PV 4 $125 $250 $375 $ t (1.10) (1.10) (1.10) (1.10) t= 1 (1.08) = = $ $63.59 = $1, B = $600 when V = $1, so S = $ $600 r S = (1 0.40)( ) = 11.77% $ EMBA 11/29
12 Step 3: Valuation for Pearson Discount the cash flows to equity holders at r S = 11.77% $400 $96.20 $ $ $ PV $96.20 $ $ $ = $ (1.1177) (1.1177) (1.1177) (1.1177) PV = $28.56 EMBA 12/29
13 3. WACC Approach S B rwacc = rs + rb (1 τ C ) S + B S + B To find the value of the project, discount the unlevered cash flows at the weighted average cost of capital. Suppose Pearson s target debt to equity ratio is 1.50 B = 1.50 B = 1.5S S B 1.5S 1.5 S = = = 0.60 = = 0.40 S + B S + 1.5S 2.5 S + B r r WACC WACC = (0.40) (11.77%) + (0.60) (8%) (1 0.40) = 7.58% EMBA 13/29
14 Valuation for Pearson Using WACC To find the value of the project, discount the unlevered cash flows at the weighted average cost of capital NPV $125 $250 $375 $500 = $1, (1.0758) (1.0758) (1.0758) (1.0758) NPV 7.58% = $6.68 EMBA 14/29
15 4. Comparison of the APV, FTE, and WACC Approaches All three approaches attempt the same task: Valuation in the presence of debt financing. Guidelines: Use WACC or FTE if the firm s target debt-to-value ratio applies to the project over the life of the project. Use the APV if the project s level of debt is known over the life of the project. In the real world, the WACC is the most widely used by far. EMBA 15/29
16 Comparison of the APV, FTE, and WACC Approaches APV WACC FTE Initial Investment All All Equity Portion Cash Flows UCF UCF LCF Discount Rates r 0 r WACC r S PV of financing effects Yes No No Which approach is best? Use APV when the level of debt is constant Use WACC and FTE when the debt ratio is constant WACC is by far the most common FTE is a reasonable choice for a highly levered firm EMBA 16/29
17 5. Capital Budgeting When the Discount Rate Must Be Estimated A scale-enhancing project is one where the project is similar to those of the existing firm. In the real world, executives would make the assumption that the business risk of the non-scale-enhancing project would be about equal to the business risk of firms already in the business. No exact formula exists for this. Some executives might select a discount rate slightly higher on the assumption that the new project is somewhat riskier since it is a new entrant. EMBA 17/29
18 6. APV Example Worldwide Trousers, Inc. is considering replacing a $5 million piece of equipment. The project will generate pretax savings of $1,500,000 per year, and not change the risk level of the firm. The initial expense will be depreciated straight-line to zero salvage value over 5 years; the pretax salvage value in year 5 will be $500,000. The firm can obtain a 5-year $3,000,000 loan at 12.5% to partially finance the project. If the project were financed with all equity, the cost of capital would be 18%. The corporate tax rate is 34%, and the risk-free rate is 4%. The project will require a $100,000 investment in net working capital. Calculate the APV. EMBA 18/29
19 APV Example: Cost Let s work our way through the four terms in this equation: APV = Cost + PV + PV + PV unlevered depreciation interest project tax shield tax shield The cost of the project is not $5,000,000. We must include the round trip in and out of net working capital and the after-tax salvage value. NWC is riskless, so we discount it at r f. Salvage value should have the same risk as the rest of the firm s assets, so we use r , , 000 (1 0.34) Cost = $5.1m (1 + r ) (1 + r ) = $4,873, f 0 EMBA 19/29
20 APV Example: PV unlevered project Turning our attention to the second term, APV = $4,873, PV + PV + PV unlevered depreciation interest project tax shield tax shield PVunlevered project is the present value of the unlevered cash flows discounted at the unlevered cost of capital, 18%. PV UCF $1.5 m (1 0.34) t (1 ) (1.18) 5 5 t unlevered = = t project t= 1 + r0 t= 1 = $3, 095,899 EMBA 20/29
21 APV Example: PV depreciation tax shield Turning our attention to the third term, APV = $4,873, $3,095,899 + PV + PV depreciation tax shield interest tax shield PVdepreciation tax shield is the is the present value of the tax savings due to depreciation (D) discounted at the risk free rate: r f = 4% PV = 5 depreciation tax shield t= 1 t= 1 D τ C t f (1 + r ) 5 $1m 0.34 = = t $1,513,619 (1.04) EMBA 21/29
22 APV Example: PV interest tax shield Turning our attention to the last term, APV = $4,873, $3,095,899 + $1,513,619 + PV interest tax shield PVinterest tax shield is the present value of the tax savings due to interest expense discounted at the firm s debt rate: r B = 12.5% PV 5 5 C B interest = = t tax shield t= 1 + rb t= ,500 = = 453, t (1.125) t= 1 τ r $3m $3m t (1 ) (1.125) EMBA 22/29
23 APV Example: Adding It All Up Let s add the four terms in this equation: APV = Cost + PV + PV + PV unlevered depreciation interest project tax shield tax shield APV = $4,873, $3, 095,899 + $1,513, $453, = $189,930 Since the project has a positive APV, it looks like a go. EMBA 23/29
24 7. Beta and Leverage Recall that an asset beta would be of the form: β = Cov( UCF, R ) Asset 2 σ Market Market EMBA 24/29
25 Beta and Leverage: No Corporate Taxes In a world without corporate taxes, and with riskless corporate debt, (β Debt = 0) it can be shown that the relationship between the beta of the unlevered firm and the beta of levered equity is: β Asset Equity = Asset β Equity In a world without corporate taxes, and with risky corporate debt, it can be shown that the relationship between the beta of the unlevered firm and the beta of levered equity is: Debt Equity β = β + β Asset Asset Asset Debt Equity EMBA 25/29
26 Beta and Leverage: With Corporate Taxes In a world with corporate taxes, and riskless debt, it can be shown that the relationship between the beta of the unlevered firm and the beta of levered equity is: Debt β Equity = 1 + (1 τ C ) β Equity Unlevered firm Debt Since 1 + (1 τ C ) must be more than 1 for a Equity levered firm, it follows that β Equity > β Unlevered firm EMBA 26/29
27 Beta and Leverage: With Corporate Taxes If the beta of the debt is non-zero, then: β = β + (1 τ ) ( β β ) Equity Unlevered firm C Unlevered firm Debt B S L EMBA 27/29
28 8. Summary and Conclusions 1. The APV formula can be written as: APV UCFt = + Additional Initial t (1 + r ) effect of debt investment t= The FTE formula can be written as: FTE t= 1 ( Initial Amount ) LCFt = t (1 + r ) investment borrowed S 3. The WACC formula can be written as UCFt NPV Initial WACC = t (1 + r ) investment t= 1 WACC EMBA 28/29
29 Summary and Conclusions 4. Use the WACC or FTE if the firm's target debt to value ratio applies to the project over its life. WACC is the most commonly used by far. FTE has appeal for a firm deeply in debt. 5 The APV method is used if the level of debt is known over the project s life. The APV method is frequently used for special situations like interest subsidies, LBOs, and leases. 6 The beta of the equity of the firm is positively related to the leverage of the firm. EMBA 29/29
Discount rates for project appraisal
Discount rates for project appraisal We know that we have to discount cash flows in order to value projects We can identify the cash flows BUT What discount rate should we use? 1 The Discount Rate and
More informationGESTÃO FINANCEIRA II PROBLEM SET 5 SOLUTIONS (FROM BERK AND DEMARZO S CORPORATE FINANCE ) LICENCIATURA UNDERGRADUATE COURSE
GESTÃO FINANCEIRA II PROBLEM SET 5 SOLUTIONS (FROM BERK AND DEMARZO S CORPORATE FINANCE ) LICENCIATURA UNDERGRADUATE COURSE 1 ST SEMESTER 2010-2011 Chapter 18 Capital Budgeting and Valuation with Leverage
More informationThe Adjusted Present Value Approach to Valuing Leveraged Buyouts 1
Chapter 17 Valuation and Capital Budgeting for the Levered Firm 17A-1 Appendix 17A The Adjusted Present Value Approach to Valuing Leveraged Buyouts 1 Introduction A leveraged buyout (LBO) is the acquisition
More informationThe Adjusted Present Value Approach to Valuing Leveraged Buyouts 1 Introduction
Chapter 18 Valuation and Capital Budgeting for the Levered Firm 18A-1 Appendix 18A The Adjusted Present Value Approach to Valuing Leveraged Buyouts 1 Introduction A leveraged buyout (LBO) is the acquisition
More informationThe Assumptions and Math Behind WACC and APV Calculations
The Assumptions and Math Behind WACC and APV Calculations Richard Stanton U.C. Berkeley Mark S. Seasholes U.C. Berkeley This Version October 27, 2005 Abstract We outline the math and assumptions behind
More informationThe Adjusted-Present-Value Approach to Valuing Leveraged Buyouts 1)
IE Aufgabe 4 The Adjusted-Present-Value Approach to Valuing Leveraged Buyouts 1) Introduction A leveraged buyout (LBO) is the acquisition by a small group of equity investors of a public or private company
More informationBA 351 CORPORATE FINANCE. John R. Graham Adapted from S. Viswanathan LECTURE 10 THE ADJUSTED NET PRESENT VALUE METHOD
BA 351 CORPORATE FINANCE John R. Graham Adapted from S. Viswanathan LECTURE 10 THE ADJUSTED NET PRESENT VALUE METHOD FUQUA SCHOOL OF BUSINESS DUKE UNIVERSITY 1 THE ADJUSTED NET PRESENT VALUE METHOD COPING
More informationCost of Capital and Project Valuation
Cost of Capital and Project Valuation 1 Background Firm organization There are four types: sole proprietorships partnerships limited liability companies corporations Each organizational form has different
More informationCHAPTER 14 COST OF CAPITAL
CHAPTER 14 COST OF CAPITAL Answers to Concepts Review and Critical Thinking Questions 1. It is the minimum rate of return the firm must earn overall on its existing assets. If it earns more than this,
More informationPractice Exam (Solutions)
Practice Exam (Solutions) June 6, 2008 Course: Finance for AEO Length: 2 hours Lecturer: Paul Sengmüller Students are expected to conduct themselves properly during examinations and to obey any instructions
More informationCHAPTER 12 RISK, COST OF CAPITAL, AND CAPITAL BUDGETING
CHAPTER 12 RISK, COST OF CAPITAL, AND CAPITAL BUDGETING Answers to Concepts Review and Critical Thinking Questions 1. No. The cost of capital depends on the risk of the project, not the source of the money.
More informationMM1 - The value of the firm is independent of its capital structure (the proportion of debt and equity used to finance the firm s operations).
Teaching Note Miller Modigliani Consider an economy for which the Efficient Market Hypothesis holds and in which all financial assets are possibly traded (abusing words we call this The Complete Markets
More informationCost of Capital. Katharina Lewellen Finance Theory II April 9, 2003
Cost of Capital Katharina Lewellen Finance Theory II April 9, 2003 What Next? We want to value a project that is financed by both debt and equity Our approach: Calculate expected Free Cash Flows (FCFs)
More informationWACC and APV. The Big Picture: Part II - Valuation
WACC and APV 1 The Big Picture: Part II - Valuation A. Valuation: Free Cash Flow and Risk April 1 April 3 Lecture: Valuation of Free Cash Flows Case: Ameritrade B. Valuation: WACC and APV April 8 April
More informationFinance 2 for IBA (30J201) F. Feriozzi Re-sit exam June 18 th, 2012. Part One: Multiple-Choice Questions (45 points)
Finance 2 for IBA (30J201) F. Feriozzi Re-sit exam June 18 th, 2012 Part One: Multiple-Choice Questions (45 points) Question 1 Assume that capital markets are perfect. Which of the following statements
More informationCOST OF CAPITAL. Please note that in finance, we are concerned with MARKET VALUES (unlike accounting, which is concerned with book values).
COST OF CAPITAL Cost of capital calculations are a very important part of finance. To value a project, it is important to discount the cash flows using a discount rate that incorporates the debt-equity
More informationChapter 14 Capital Structure in a Perfect Market
Chapter 14 Capital Structure in a Perfect Market 14-1. Consider a project with free cash flows in one year of $130,000 or $180,000, with each outcome being equally likely. The initial investment required
More informationFinancial Markets and Valuation - Tutorial 6: SOLUTIONS. Capital Structure and Cost of Funds
Financial Markets and Valuation - Tutorial 6: SOLUTIONS Capital Structure and Cost of Funds (*) denotes those problems to be covered in detail during the tutorial session (*) Problem 1. (Ross, Westerfield
More informationLeverage. FINANCE 350 Global Financial Management. Professor Alon Brav Fuqua School of Business Duke University. Overview
Leverage FINANCE 35 Global Financial Management Professor Alon Brav Fuqua School of Business Duke University Overview Capital Structure does not matter! Modigliani & Miller propositions Implications for
More informationt = 1 2 3 1. Calculate the implied interest rates and graph the term structure of interest rates. t = 1 2 3 X t = 100 100 100 t = 1 2 3
MØA 155 PROBLEM SET: Summarizing Exercise 1. Present Value [3] You are given the following prices P t today for receiving risk free payments t periods from now. t = 1 2 3 P t = 0.95 0.9 0.85 1. Calculate
More informationEMBA in Management & Finance. Corporate Finance. Eric Jondeau
EMBA in Management & Finance Corporate Finance EMBA in Management & Finance Lecture 4: Capital Structure Limits to the Use of Debt Outline 1. Costs of Financial Distress 2. Description of Costs 3. Can
More informationOn the Applicability of WACC for Investment Decisions
On the Applicability of WACC for Investment Decisions Jaime Sabal Department of Financial Management and Control ESADE. Universitat Ramon Llull Received: December, 2004 Abstract Although WACC is appropriate
More informationDUKE UNIVERSITY Fuqua School of Business. FINANCE 351 - CORPORATE FINANCE Problem Set #4 Prof. Simon Gervais Fall 2011 Term 2.
DUK UNIRSITY Fuqua School of Business FINANC 351 - CORPORAT FINANC Problem Set #4 Prof. Simon Gervais Fall 2011 Term 2 Questions 1. Suppose the corporate tax rate is 40%. Consider a firm that earns $1,000
More informationUse the table for the questions 18 and 19 below.
Use the table for the questions 18 and 19 below. The following table summarizes prices of various default-free zero-coupon bonds (expressed as a percentage of face value): Maturity (years) 1 3 4 5 Price
More informationCAPITAL STRUCTURE [Chapter 15 and Chapter 16]
Capital Structure [CHAP. 15 & 16] -1 CAPITAL STRUCTURE [Chapter 15 and Chapter 16] CONTENTS I. Introduction II. Capital Structure & Firm Value WITHOUT Taxes III. Capital Structure & Firm Value WITH Corporate
More informationDUKE UNIVERSITY Fuqua School of Business. FINANCE 351 - CORPORATE FINANCE Problem Set #7 Prof. Simon Gervais Fall 2011 Term 2.
DUKE UNIVERSITY Fuqua School of Business FINANCE 351 - CORPORATE FINANCE Problem Set #7 Prof. Simon Gervais Fall 2011 Term 2 Questions 1. Suppose the corporate tax rate is 40%, and investors pay a tax
More information1 Pricing options using the Black Scholes formula
Lecture 9 Pricing options using the Black Scholes formula Exercise. Consider month options with exercise prices of K = 45. The variance of the underlying security is σ 2 = 0.20. The risk free interest
More information] (3.3) ] (1 + r)t (3.4)
Present value = future value after t periods (3.1) (1 + r) t PV of perpetuity = C = cash payment (3.2) r interest rate Present value of t-year annuity = C [ 1 1 ] (3.3) r r(1 + r) t Future value of annuity
More informationCorporate Finance & Options: MGT 891 Homework #6 Answers
Corporate Finance & Options: MGT 891 Homework #6 Answers Question 1 A. The APV rule states that the present value of the firm equals it all equity value plus the present value of the tax shield. In this
More informationCorporate Finance: Final Exam
Corporate Finance: Final Exam Answer all questions and show necessary work. Please be brief. This is an open books, open notes exam. For partial credit, when discounting, please show the discount rate
More informationTPPE17 Corporate Finance 1(5) SOLUTIONS RE-EXAMS 2014 II + III
TPPE17 Corporate Finance 1(5) SOLUTIONS RE-EXAMS 2014 II III Instructions 1. Only one problem should be treated on each sheet of paper and only one side of the sheet should be used. 2. The solutions folder
More informationDiscount Rates and Tax
Discount Rates and Tax Ian A Cooper and Kjell G Nyborg London Business School First version: March 1998 This version: August 2004 Abstract This note summarises the relationships between values, rates of
More informationVALUE OF ASSETS OF PRZEDSIĘBIORSTWO ROBÓT KOMUNIKACYJNYCH W KRAKOWIE S.A. WITH REGISTERED OFFICE IN CRACOW AS AT 1 JULY 2013
VALUE OF ASSETS OF PRZEDSIĘBIORSTWO ROBÓT KOMUNIKACYJNYCH W KRAKOWIE S.A. WITH REGISTERED OFFICE IN CRACOW AS AT 1 JULY The document has been prepared at the request of ZUE S.A. Warsaw, 12 August 1 CONTENTS
More informationAPractitionersToolkitonValuation
APractitionersToolkitonValuation Part I: (Un)Levering the Cost of Equity and Financing Policy with Constant Expected Free Cash Flows: APV, WACC and CFE Frans de Roon, Joy van der Veer 1 Introduction Valuation
More informationWeek- 1: Solutions to HW Problems
Week- 1: Solutions to HW Problems 10-1 a. Payback A (cash flows in thousands): Annual Period Cash Flows Cumulative 0 ($5,000) ($5,000) 1 5,000 (0,000) 10,000 (10,000) 3 15,000 5,000 4 0,000 5,000 Payback
More informationCopyright 2009 Pearson Education Canada
The consequence of failing to adjust the discount rate for the risk implicit in projects is that the firm will accept high-risk projects, which usually have higher IRR due to their high-risk nature, and
More information( ) ( )( ) ( ) 2 ( ) 3. n n = 100 000 1+ 0.10 = 100 000 1.331 = 133100
Mariusz Próchniak Chair of Economics II Warsaw School of Economics CAPITAL BUDGETING Managerial Economics 1 2 1 Future value (FV) r annual interest rate B the amount of money held today Interest is compounded
More informationChapter 18. Web Extension: Percentage Cost Analysis, Leasing Feedback, and Leveraged Leases
Chapter 18 Web Extension: Percentage Cost Analysis, Leasing Feedback, and Leveraged Leases Percentage Cost Analysis Anderson s lease-versus-purchase decision from Chapter 18 could also be analyzed using
More informationLeverage and Capital Structure
Leverage and Capital Structure Ross Chapter 16 Spring 2005 10.1 Leverage Financial Leverage Financial leverage is the use of fixed financial costs to magnify the effect of changes in EBIT on EPS. Fixed
More informationThe value of tax shields is NOT equal to the present value of tax shields
The value of tax shields is NOT equal to the present value of tax shields Pablo Fernández * IESE Business School. University of Navarra. Madrid, Spain ABSTRACT We show that the value of tax shields is
More informationChapter 14 Multinational Capital Structure and Cost of Capital
Sample Exam: Part IV Chapters 12-17 Butler / Multinational Finance (5e) Multiple Choice Choose the best answer Chapter 12 Foreign Market Entry and Country Risk Management 1. Much of the 1990 s growth in
More informationCorporate Finance: Final Exam
Corporate Finance: Final Exam Answer all questions and show necessary work. Please be brief. This is an open books, open notes exam. 1. DayTop Inns is a publicly traded company, with 10 million shares
More informationNIKE Case Study Solutions
NIKE Case Study Solutions Professor Corwin This case study includes several problems related to the valuation of Nike. We will work through these problems throughout the course to demonstrate some of the
More informationSOLUTIONS. Practice questions. Multiple Choice
Practice questions Multiple Choice 1. XYZ has $25,000 of debt outstanding and a book value of equity of $25,000. The company has 10,000 shares outstanding and a stock price of $10. If the unlevered beta
More informationChapter 17 Does Debt Policy Matter?
Chapter 17 Does Debt Policy Matter? Multiple Choice Questions 1. When a firm has no debt, then such a firm is known as: (I) an unlevered firm (II) a levered firm (III) an all-equity firm D) I and III only
More informationProblem 1 Problem 2 Problem 3
Problem 1 (1) Book Value Debt/Equity Ratio = 2500/2500 = 100% Market Value of Equity = 50 million * $ 80 = $4,000 Market Value of Debt =.80 * 2500 = $2,000 Debt/Equity Ratio in market value terms = 2000/4000
More informationCHAPTER 7 MAKING CAPITAL INVESTMENT DECISIONS
CHAPTER 7 MAKING CAPITAL INVESTMENT DECISIONS Answers to Concepts Review and Critical Thinking Questions 1. In this context, an opportunity cost refers to the value of an asset or other input that will
More informationUSING THE EQUITY RESIDUAL APPROACH TO VALUATION: AN EXAMPLE
Graduate School of Business Administration - University of Virginia USING THE EQUITY RESIDUAL APPROACH TO VALUATION: AN EXAMPLE Planned changes in capital structure over time increase the complexity of
More informationLecture 16: Capital Budgeting, Beta, and Cash Flows
Lecture 16: Capital Budgeting, Beta, and Cash Flows eading: Brealey and Myers, Chapter 9 Lecture eader, Chapter 15 Topics: Final topics on basic CPM Debt, Equity, and sset Betas Leveraged Betas Operating
More informationLecture: Financing Based on Market Values II
Lecture: Financing Based on Market Values II Lutz Kruschwitz & Andreas Löffler Discounted Cash Flow, Section 2.4.4 2.4.5, Outline 2.4.4 Miles-Ezzell- and Modigliani-Miller Miles-Ezzell adjustment Modigliani-Miller
More informationHomework Solutions - Lecture 2
Homework Solutions - Lecture 2 1. The value of the S&P 500 index is 1286.12 and the treasury rate is 3.43%. In a typical year, stock repurchases increase the average payout ratio on S&P 500 stocks to over
More informationProjecting Consistent Debt and Interest Expenses
WEB EXTENSION26A Projecting Consistent Debt and Interest Expenses Projecting financial statements for a merger analysis requires explicit assumptions regarding the capital structure in the post-merger
More informationCHAPTER 15 FIRM VALUATION: COST OF CAPITAL AND APV APPROACHES
0 CHAPTER 15 FIRM VALUATION: COST OF CAPITAL AND APV APPROACHES In the last two chapters, we examined two approaches to valuing the equity in the firm -- the dividend discount model and the FCFE valuation
More informationCapital Cash Flows: A Simple Approach to Valuing Risky Cash Flows
Capital Cash Flows: A Simple Approach to Valuing Risky Cash Flows Richard S. Ruback Graduate School of Business Administration Harvard University Boston, MA 02163 email: rruback@hbs.edu ABSTRACT This paper
More informationEquity Analysis and Capital Structure. A New Venture s Perspective
Equity Analysis and Capital Structure A New Venture s Perspective 1 Venture s Capital Structure ASSETS Short- term Assets Cash A/R Inventories Long- term Assets Plant and Equipment Intellectual Property
More informationThe Tangent or Efficient Portfolio
The Tangent or Efficient Portfolio 1 2 Identifying the Tangent Portfolio Sharpe Ratio: Measures the ratio of reward-to-volatility provided by a portfolio Sharpe Ratio Portfolio Excess Return E[ RP ] r
More informationIf you ignore taxes in this problem and there is no debt outstanding: EPS = EBIT/shares outstanding = $14,000/2,500 = $5.60
Problems Relating to Capital Structure and Leverage 1. EBIT and Leverage Money Inc., has no debt outstanding and a total market value of $150,000. Earnings before interest and taxes [EBIT] are projected
More informationLECTURE- 4. Valuing stocks Berk, De Marzo Chapter 9
1 LECTURE- 4 Valuing stocks Berk, De Marzo Chapter 9 2 The Dividend Discount Model A One-Year Investor Potential Cash Flows Dividend Sale of Stock Timeline for One-Year Investor Since the cash flows are
More informationBA 351 CORPORATE FINANCE. John R. Graham Adapted from S. Viswanathan LECTURE 5 LEASING FUQUA SCHOOL OF BUSINESS DUKE UNIVERSITY
BA 351 CORPORATE FINANCE John R. Graham Adapted from S. Viswanathan LECTURE 5 LEASING FUQUA SCHOOL OF BUSINESS DUKE UNIVERSITY 1 Leasing has long been an important alternative to buying an asset. In this
More informationCHAPTER 2 How to Calculate Present Values
CHAPTER How to Calculate Present Values 0. Mr. Basset is buying a security worth $0,000 now, which is its present value. The unknown is the annual payment. Using the present value of an annuity formula,
More informationCHAPTER 8. Problems and Questions
CHAPTER 8 Problems and Questions 1. Plastico, a manufacturer of consumer plastic products, is evaluating its capital structure. The balance sheet of the company is as follows (in millions): Assets Liabilities
More informationCHAPTER 15 Capital Structure: Basic Concepts
Multiple Choice Questions: CHAPTER 15 Capital Structure: Basic Concepts I. DEFINITIONS HOMEMADE LEVERAGE a 1. The use of personal borrowing to change the overall amount of financial leverage to which an
More informationCapital Budgeting Formula
apital Budgeting Formula Not in the book. Wei s summary If salvage value S is less than U n : If salvage value S is greater than U n : Note: IF t : incremental cash flows (could be negative) )(NW): change
More informationCHAPTER 7: NPV AND CAPITAL BUDGETING
CHAPTER 7: NPV AND CAPITAL BUDGETING I. Introduction Assigned problems are 3, 7, 34, 36, and 41. Read Appendix A. The key to analyzing a new project is to think incrementally. We calculate the incremental
More informationChapter 17 Corporate Capital Structure Foundations (Sections 17.1 and 17.2. Skim section 17.3.)
Chapter 17 Corporate Capital Structure Foundations (Sections 17.1 and 17.2. Skim section 17.3.) The primary focus of the next two chapters will be to examine the debt/equity choice by firms. In particular,
More informationWorking Paper. WP No 549 March, 2004. Pablo Fernández *
CIIF Working Paper WP No 549 March, 2004 EQUIVALENCE OF TEN DIFFERENT DISCOUNTED CASH FLOW VALUATION METHODS Pablo Fernández * * Professor of Financial Management, PricewaterhouseCoopers Chair of Finance,
More informationMBA 8230 Corporation Finance (Part II) Practice Final Exam #2
MBA 8230 Corporation Finance (Part II) Practice Final Exam #2 1. Which of the following input factors, if increased, would result in a decrease in the value of a call option? a. the volatility of the company's
More informationTax-adjusted discount rates with investor taxes and risky debt
Tax-adjusted discount rates with investor taxes and risky debt Ian A Cooper and Kjell G Nyborg October 2004 Abstract This paper derives tax-adjusted discount rate formulas with Miles-Ezzell leverage policy,
More informationCompany Share Price Valuation using Free Cash Flow To Equity
Financial Modeling Templates Company Share Price Valuation using Free Cash Flow To Equity http://spreadsheetml.com/finance/valuation_freecashflowtoequity.shtml Copyright (c) 2009-2014, ConnectCode All
More informationNumbers 101: Taxes, Investment, and Depreciation
The Anderson School at UCLA POL 2000-20 Numbers 101: Taxes, Investment, and Depreciation Copyright 2002 by Richard P. Rumelt. In the Note on Cost and Value over Time (POL 2000-09), we introduced the basic
More informationChapter 13 Capital Budgeting: Estimating Cash Flow and Analyzing Risk ANSWERS TO END-OF-CHAPTER QUESTIONS
Chapter 13 Capital Budgeting: Estimating Cash Flow and Analyzing Risk ANSWERS TO END-OF-CHAPTER QUESTIONS 13-3 Since the cost of capital includes a premium for expected inflation, failure to adjust cash
More informationMidland Energy/Sample 2. Midland Energy Resources, Inc.
Midland Energy Resources, Inc. Midland Energy Resources, Inc. is a global energy company that operates in oil and gas exploration and production (E&P), refining and marketing (R&M), and petrochemicals.
More informationExam (Correction) Exercise 1: Market efficiency
Executive MA Program Pr. Eric Jondeau orporate Finance Exam (orrection) Exercise 1: Market efficiency (10 points) Answer the following questions in a few lines. a) TransTrust orp. has changed how it accounts
More informationCash Flow, Taxes, and Project Evaluation. Remember Income versus Cashflow
Cash Flow, Taxes, and Project Evaluation Of the four steps in calculating NPV, the most difficult is the first: Forecasting cash flows. We now focus on this problem, with special attention to What is cash
More informationCHAPTER 8 STOCK VALUATION
CHAPTER 8 STOCK VALUATION Answers to Concepts Review and Critical Thinking Questions 5. The common stock probably has a higher price because the dividend can grow, whereas it is fixed on the preferred.
More informationTax-adjusted discount rates with investor taxes and risky debt
Tax-adjusted discount rates with investor taxes and risky debt Ian A Cooper and Kjell G Nyborg October 2005, first version October 2004 Abstract This paper derives tax-adjusted discount rate formulas with
More informationNapoli Pizza wants to determine its optimal capital structure
Napoli Pizza wants to determine its optimal capital structure ABSTRACT Brad Stevenson Daniel Bauer David Collins Keith Richardson This case is based on an actual business decision that was made by a small,
More informationHomework Assignment #1: Answer Key
Econ 497 Economics of the Financial Crisis Professor Ickes Spring 2012 Homework Assignment #1: Answer Key 1. Consider a firm that has future payoff.supposethefirm is unlevered, call the firm and its shares
More informationCapital Budgeting Further Considerations
Capital Budgeting Further Considerations For 9.220, Term 1, 2002/03 02_Lecture10.ppt Lecture Outline Introduction The input for evaluating projects relevant cash flows Inflation: real vs. nominal analysis
More informationChapter 15: Debt Policy
FIN 302 Class Notes Chapter 15: Debt Policy Two Cases: Case one: NO TAX All Equity Half Debt Number of shares 100,000 50,000 Price per share $10 $10 Equity Value $1,000,000 $500,000 Debt Value $0 $500,000
More informationISSUES ON USING THE DISCOUNTED CASH FLOWS METHODS FOR ASSET VALUATION
ISSUES ON USING THE DISCOUNTED CASH FLOWS METHODS FOR ASSET VALUATION CRISTINA AURORA BUNEA-BONTAŞ 1, MIHAELA COSMINA PETRE 2 CONSTANTIN BRANCOVEANU UNIVERSITY OF PITESTI, FACULTY OF MANAGEMENT-MARKETING
More informationValuation Mobile networks
ITU EXPERT-LEVEL TRAINING ON NETWORK COST MODELING FOR ASIA AND PACIFIC COUNTRIES LEVEL II Valuation Mobile networks Bangkok, Thailand, 15-19 November 2010 Note: The views expressed in this paper are those
More informationChapter 09 - Using Discounted Cash-Flow Analysis to Make Investment Decisions
Solutions to Chapter 9 Using Discounted Cash-Flow Analysis to Make Investment Decisions 1. Net income = ($74 $42 $10) [0.35 ($74 $42 $10)] = $22 $7.7 = $14.3 million Revenues cash expenses taxes paid =
More informationWACC and a Generalized Tax Code
WACC and a Generalized Tax Code Sven Husmann, Lutz Kruschwitz and Andreas Löffler version from 10/06/2001 ISSN 0949 9962 Abstract We extend the WACC approach to a tax system having a firm income tax and
More informationCHAPTER 8: ESTIMATING CASH FLOWS
CHAPTER 8: ESTIMATING CASH FLOWS 8-1 a. Straight line depreciation = ($15 - $3)/10 = $1.20 Annual Tax Savings from Depreciation = $ 1.2 (0.4) = $0.48 Present Value of Tax Savings from Depreciation = $
More informationChapter 20 Lease Financing ANSWERS TO END-OF-CHAPTER QUESTIONS
Chapter 20 Lease Financing ANSWERS TO END-OF-CHAPTER QUESTIONS 20-1 a. The lessee is the party leasing the property. The party receiving the payments from the lease (that is, the owner of the property)
More informationCHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA
CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA Basic 1. To calculate the payback period, we need to find the time that the project has recovered its initial investment. After two years, the
More informationFIN 413 Corporate Finance. Capital Structure, Taxes, and Bankruptcy
FIN 413 Corporate Finance Capital Structure, Taxes, and Bankruptcy Evgeny Lyandres Fall 2003 1 Relaxing the M-M Assumptions E D T Interest payments to bondholders are deductible for tax purposes while
More informationReal Estate Investment Analysis using Excel
Graduate Certificate in Real Estate Finance (GCREF) course Real Estate Investment Analysis using Excel Sing Tien Foo Department of Real Estate 22 August 2014 2 Lecture Outline Investing in real estate
More informationValuing Companies. Katharina Lewellen Finance Theory II May 5, 2003
Valuing Companies Katharina Lewellen Finance Theory II May 5, 2003 Valuing companies Familiar valuation methods Discounted Cash Flow Analysis Comparables Real Options Some new issues Do we value assets
More informationFundamentals Level Skills Module, Paper F9
Answers Fundamentals Level Skills Module, Paper F9 Financial Management June 2008 Answers 1 (a) Calculation of weighted average cost of capital (WACC) Cost of equity Cost of equity using capital asset
More informationBank Valuation: Comparable Public Companies & Precedent Transactions
Bank Valuation: Comparable Public Companies & Precedent Transactions Picking a set of comparable companies or precedent transactions for a bank is very similar to what you d do for any other company here
More informationThings to do before the first class meeting
FINANCE 351 Corporate Finance John Graham Things to do before the first class meeting C Read the Gifford and Brealey and Myers material (see class schedule) C Read over the syllabus and class schedule.
More informationChoice of Discount Rate: Basic Theory
Choice of Discount Rate Discussion in 2 Parts 1. Basic Theory 2. A Common Practical Approach: Weighted Average Cost of Capital Massachusetts Institute of Technology Choice of Discount Rate Slide 1 of 24
More informationForecasting and Valuation of Enterprise Cash Flows 1. Dan Gode and James Ohlson
Forecasting and Valuation of Enterprise Cash Flows 1 1. Overview FORECASTING AND VALUATION OF ENTERPRISE CASH FLOWS Dan Gode and James Ohlson A decision to invest in a stock proceeds in two major steps
More informationA Test Of The M&M Capital Structure Theories Richard H. Fosberg, William Paterson University, USA
A Test Of The M&M Capital Structure Theories Richard H. Fosberg, William Paterson University, USA ABSTRACT Modigliani and Miller (1958, 1963) predict two very specific relationships between firm value
More informationMGT201 Solved MCQs(500) By
MGT201 Solved MCQs(500) By http://www.vustudents.net Why companies invest in projects with negative NPV? Because there is hidden value in each project Because there may be chance of rapid growth Because
More informationChapter 11 Cash Flow Estimation and Risk Analysis ANSWERS TO SELECTED END-OF-CHAPTER QUESTIONS
Chapter 11 Cash Flow Estimation and Risk Analysis ANSWERS TO SELECTED END-OF-CHAPTER QUESTIONS 11-1 a. Cash flow, which is the relevant financial variable, represents the actual flow of cash. Accounting
More informationValuing the Debt Tax Shield
INSTITUTT FOR FORETAKSØKONOMI DEPARTMENT OF FINANCE AND MANAGEMENT SCIENCE FOR 15 2007 ISSN: 1500-4066 MARCH 2007 Discussion paper Valuing the Debt Tax Shield BY IAN COOPER AND KJELL G. NYBORG This paper
More information