Palomar Community College District Data Center Disaster Recovery Plan
|
|
|
- Elfreda Hart
- 10 years ago
- Views:
Transcription
1 Palomar Community College District Data Center Disaster Recovery Plan Revised December 2009 Page 1
2 Table of Contents Sections 1.0 Introduction 1.1 Authority 1.2 Distribution 2.0 Basic Recovery Plan Requirements 2.1 Disaster Recovery Team 2.2 Offsite Storage of System Backup Tapes 2.3 Backup Facility 3.0 Recovery Plans 3.1 Disaster Preparation 3.2 Emergency Response 3.3 Recovery Procedures Recovery Time Table 4.0 Disaster Recovery Plan Review Appendixes A Disaster Recovery Team B Data Backup Tape Procedure C Backup Data Center D Recovery Team and Vendor Contact Information E Data Center Applications F Emergency Telephone List The Information Services Department gratefully acknowledges the model and selected text from the Disaster Recovery Plan of Glenville State College and the Administrative Information Systems Disaster Recovery Plan of Syracuse University, Southern West Virginia Community, and Macalester College. Revised December 2009 Page 2
3 1.0 Introduction The personnel, equipment, software systems, and databases, which comprise the District s Data Center, are necessary in order for the District to function in an effective manner. The Data Center is located on the main campus at 1140 West Mission Road, San Marcos, CA. The purpose of this plan is to provide guidance in recovering from a disaster which might befall Data Center services to minimize downtime and to assist users in accommodating their critical processing requirements. 1.1 Authority The decision to implement disaster recovery operational procedures is the responsibility of the Director of Information Services or his/her designee in consultation with the Vice President, Finance and Administrative Services. The Disaster Recovery Team will convene as soon as possible after a disaster has occurred to assess damages and make recommendations to the Director. It is the responsibility of the Director to report this information and the decision to the Vice President, Finance and Administrative Services. 1.2 Distribution This plan will be distributed to and used by those persons (identified in Appendix A) responsible for its implementation and operation. This document will be maintained and updated by the Information Services Department whenever significant changes occur. 2.0 Basic Recovery Plan Requirements The basic requirements for the Recovery plan are as follows: Disaster recovery team Disaster recovery documentation Backup computer facilities 2.1 Disaster Recovery Team The Disaster Recovery Team (see Appendix A) has been established and organized to assess the damage to the computer facility, to control and coordinate recovery/backup actions, and to make recommendations to the Director of Information Services. The team will consist of a cross section of persons responsible for one or more of the following functions: Recovery administration (insurance notification, supplies, organization) Systems software Application software Communications Operations Facilities Hardware Revised December 2009 Page 3
4 The Director of Information Services serves as the Chair and in the Director s absence, the Manager of Systems and Programming is to serve as the Chair. If both are absent, the chair assignment will be made by the Vice President, Finance and Administrative Services. The disaster recovery team shall meet annually to discuss the recovery plan and make recommendations for changes in order to keep it current. All changes must be agreed upon by the majority of the team before they become part of the plan. It will be the responsibility of the Chair to make the necessary changes and distribute the new document to the appropriate individuals. In the event of a disaster or major failure, the team should convene with as many team members as available. All members of the team should assess damages and report to the Chair at the earliest opportunity. The Vice President, Finance and Administrative Services will be notified of the steps to be taken and subsequent outcomes, who will then report to the President. 2.2 Offsite storage of system backup tapes In the event that disaster befalls the current Data Center, having backup tapes stored off-site is critical. Daily differential and weekly full backups of system data are stored in the Data Center and the most current full system backup, as defined in Appendix B, is stored off-site for safety in case of fire or flood. The District s system data backup tape procedures ensure data which may be lost during a disaster can be recovered. Off-site storage of system data backup tapes is provided by Cor-o-van Records Management and their storage facility is located in Poway, CA. 2.3 Backup facility In the case of fire or natural disaster it may become necessary to move the Data Center to a backup location. The District s backup facility (see Appendix B) is in Room 814 of the Escondido Center located at: 1951 East Valley Parkway, Escondido, CA. This site was selected for the following reasons: Property: The Escondido Center is owned by the District. Technology: The Escondido Center is the largest remote site connected to the District network. As a result it has a dedicated 20 MB fiber connection to the Data Center and its own CENIC connection to the Internet. Facility: Room 814 which serves as the IDF room for the center s 800-wing was enlarged in October 2009 and designed to be the District s backup Data Center. 3.0 Recovery Plans Several recovery plans have been identified for use, depending upon the circumstances. Disaster Preparation: Being ready and planning ahead is the easiest way to be sure the District can quickly and fully recover from a disaster. As a result, this Disaster Recovery Plan and the accompanying System Continuity Manual have been prepared. Revised December 2009 Page 4
5 Emergency Response: These are the first actions taken in an emergency situation, designed to bring the computer systems back to operation, even if not at full capacity or in a degraded state. Appendix D provides key personnel and vendor contact information. Recovery Procedures: These are the procedures designed to return the computer systems to a fully operational state, or degraded state, including bringing up the backup facility. Appendix E provides the priority in which the Data Center applications should be brought back online and the System Continuity Manual provides the detailed information needed in order to recover. 3.1 Disaster Preparation This section outlines the minimum steps needed in order to ensure the District can fully recover from a disaster. The disaster plan must be kept current and all personnel on the recovery team must be made aware of any plan changes and fully trained to perform their assigned tasks. The offsite storage area should be inspected annually to ensure it is clean, organized and that the correct backups are in storage. The fire fighting system in the computer room should be inspected annually. Department heads should be aware of the consequences of a disaster and develop alternate data processing procedures while recovery is in progress. The Facilities department maintains and distributes the District s Emergency Telephone Numbers List of pertinent personnel to contact in case of an emergency. Procedures and lead times for replacement equipment and communications should be established. All computing personnel should be informed of the proper emergency and evacuation procedures. The Communications department is responsible for informing the campus community of the disaster and the steps being taken to remedy the situation. In the event that there is warning of an impending disaster, e.g. potential flood situations, earthquake activity in the immediate area, fire or potential building damage, the following steps should be taken: Notice should be given to as many recovery team members as possible. The Director of Information Services or designee should be briefed and a decision should be made whether to shut down the systems. Revised December 2009 Page 5
6 The recovery team should convene and review whatever actions may be necessary. 3.2 Emergency Response This section details the basic actions that need to be taken in the event of a disaster situation. The Director of Information Services or designee should be notified as soon as possible. The disaster recovery team should be notified and assembled as soon as reasonable under the circumstances. Team members should assess damages to their individual areas of expertise. The recovery procedures should include an estimated timeline for restoration of specific services based on the service priority described in Appendix E. The estimate can include alternative interim solutions for specific services during the reconstruction of permanent solutions. Team members should advise the Director of Information Services as to the extent of damage and recovery procedures necessary so that the decision to move the Data Center can be made after the assessment of the damage to the current facility has been determined. Pertinent vendors should be contacted and negotiations should be made for the delivery of equipment, delivery time should be noted. (See Appendix D) All department heads should be informed of the decision and given an estimated time for the return to either full or degraded services. Each member of the disaster recovery team should supervise his or her own area of expertise. The computer facility should be secured. 3.3 Recovery Procedures Recovery from a complete failure to a degraded mode of services may be necessary. In this case it may be possible to bring up individual departments on a priority basis. The decision to operate in a degraded mode and the order in which departments are to be brought back into service should be made by the Director of Information Services in consultation with team members and the Vice President, Finance and Administrative Services. With Information Services support, the Payroll Department developed a Payroll Recovery Procedure that is not dependent on Data Center processing and the materials are stored off-site with the system backup tapes. As a result, it is likely that Payroll would be able to issue Revised December 2009 Page 6
7 paychecks to faculty, staff and students on the scheduled pay dates without interruption. A required cash fund transfer to the San Diego County Office of Education could also be handled. If it is decided to transfer Data Center operations to the backup facility located at Escondido Center it is assumed that the basic emergency procedures have been followed as detailed in section 3.2. An inventory of the status of existing equipment and files should be compiled. The Director of Information Services should coordinate the move of facility. Vendors (see Appendix C) should be contacted to initiate delivery of replacement equipment to the Escondido Center backup facility. The estimated time of delivery should be noted. A new offsite (backup) storage facility should be located and used immediately, if necessary. All facility systems should be verified operational at this time. Systems should be tested and loaded as soon as the vendors release them to the District. Communications, networking, operations and applications software personnel should be prepared to install and or setup their individual function in the appropriate order. All department heads should be made aware of progress and or setbacks on a regular basis. Existing safety and emergency procedures at the backup facility should be examined for their adequacy as a computer room Recovery Timetable The following timetable is estimated and does not take into account the amount of time required to input data held on hardcopy during the recovery period, or re-inputting data which may have been lost during recovery. Day 1 Day 2-4 Convene the disaster recovery team, ascertain the extent of the damage and evaluate potential consequences, notify department heads, contact vendors, discuss options. Release formal communication to the campus community. At the disaster site, carry-out a safety inspection, inventory status of existing equipment and files, make a full evaluation of the damage, provide detailed accounting for insurance claims, and retrieve vital documents and reusable equipment. At the Escondido Center, prep the backup facility, set up Revised December 2009 Page 7
8 administrative support services, make arrangements for staff work space, compile an inventory of surviving equipment and assess communications (voice/data) and network capabilities. Define priorities for restoring minimal network services and Data Center operations, order new equipment and estimate the emergency mode processing time frame. Test the Payroll Recovery Procedure, expedite authorization of recovery expenditures, record the costs, and notify regulatory authorities of the work place change. Day 5-12 Day Obtain system data backup tapes and ensure all relevant documentation is retrieved from the offsite storage facility for restoration of network services and information systems. Take delivery and install new equipment. Restore programs and data, and test integrity of programs and data. Reconfigure communications network equipment and ensure that the reinstated communications environment is operable and tested. Make priority determination of data processing and systems, restore partial operation to priority departments, enforce current computer and information systems security standards, Before undertaking any processing, transfer security copies of all files and programs to offsite storage location. Restore full communications and networking capabilities. Work with departments to verify data and operation of application. Start processing in accordance with prepared production schedules. 4.0 Disaster Recovery Plan Review The following steps will be taken to ensure that the Disaster Recovery Plan is current, feasible and effective: Every year the Disaster Recovery Team will be convened to review the Plan and Appendices. Updates or revisions will be made at this time. The Director of Information Services or designee will subject the contents of the off-site disaster backup tape storage to unannounced periodic audits. Results of the audit will be documented and filed with the Disaster Recovery Plan addenda materials. Revised December 2009 Page 8
9 Appendix A Disaster Recovery Team Vice President, Finance and Administrative Services Director, Information Services Director, Facilities Director, Fiscal Services Director, Business and Contract Services Information Services: Manager, Systems & Programming Information Services: Manager, Network &Technical Services Information Services: Database Administrator Information Services: Senior Network Specialist Revised December 2009 Page 9
10 Appendix B Data Backup Tape Procedure 1) Backup strategy The Information Services tape library contains all the required tape sets for the weekly Differential Backups. There are 5 backup sets, WEEK1, WEEK2, WEEK3, WEEK4, and LAST with 12 tapes per set. This device is a Dell LTO4 Tape Library that is downward compatible to the LTO2 tapes Offsite Backup tapes are rotated on a four (4) week cycle. All Offsite Backup tapes are stored at the Cor-o-van data storage facility. 2) Backup tape sets: Differential Backups - Contains system data files changed since the last Full Backup Full Backups - Contains all system data files maintained in the Data Center Offsite Backups Full Backup for Offsite storage Semi-Annual Backups - Another Full Backup twice a year in June and December 3) Backup tape schedule: Differential Backups - Scheduled Sunday Thursday nights Full Backups - Scheduled Friday nights Offsite Backups - Scheduled Saturday nights Semi-Annual Backup 1- December Semi-Annual Backup 2 - June 4) Backup software and media rotation: Symantec Backup Exec version 12 is used to backup the servers. The software has been very effective in backing up data and restoring lost data and it is upgraded by the Information Services staff when new updates are made available. Sunday starts the new backup week and the tapes will be rotated automatically using job policies for each server within the Backup Exec software. The Offsite containers are delivered every Thursday to the Information Services Helpdesk and inserted into the tape library for the upcoming cycle. The tapes are removed every Monday morning and retrieved by Cor-o-van that same afternoon for offsite storage. Any changes to the schedule due to holidays are made in advance with Cor-o-van for both deliveries and pickup dates. EZ-BACK is used to backup hard drive information (Desktop, My Documents, Favorites) on faculty and staff desktop computers to the SAN backup share drive. This drive is part of the nightly Backup Exec backups, but the user must run the EZ- BACK application because it does not run automatically. Revised December 2009 Page 10
11 Appendix C Backup Data Center (Room 814) Revised December 2009 Page 11
12 Appendix D Recovery Team and Vendor Contact Information Recovery Team Home Phone Cell Phone Bonnie Ann Dowd Don Sullins Mike Ellis Phyllis Laderman Ken Jay Scott McClure Jose Vargas Leonora Carandang Mike Dimmick Vendors Name Office Phone Cell Phone Abtech Systems Robby Wright (pager) AT&T Robert DeGuire Cor-o-van Tracey Reber ext.1228 Cisco Systems Emily Diaz CPT Systems Sean Murphy Dell Bob Monagan Nexus Chad Williams Oracle Susan Medici Veritas Software Tracy lee Revised December 2009 Page 12
13 Appendix E Data Center Applications Information Services reviewed the business functions supported by the applications running in the District s Data Center and recommend the following priorities: BUSINESS FUNCTION APPLICATION PRIORITY Telecommunications /Voic Cisco Unified Communications Cisco Unity Critical & Archiving Microsoft Exchange & SQL Server EMC SAN & Xtender Critical Internet CENIC/ Microsoft Windows Critical District Websites & Departmental Folders Microsoft Windows/ EMC SAN Critical Registration and Student Records PeopleSoft SA/HR & eservices Essential Financial Aid PeopleSoft SA/HR & eservices Essential Payroll & Human Resources PeopleSoft SA/HR & eservices Essential Courses and Term Schedule PeopleSoft SA/HR & eservices Essential Fiscal Accounting, Purchasing, Budgeting PeopleSoft Financials & Accounts Payable Essential Online Courses & Content Blackboard Essential Counseling SARS GRID Important Assessment Testing COMPASS Important Earth Science ESRI ArcGIS Important Graphics FTP Server Important Helpdesk Remedy Convenient Asset Management Vertere Convenient Document Imaging Hershey Convenient Library Database SirsiDynix Convenient Health Services MedPro Convenient Revised December 2009 Page 13
14 Appendix F Emergency Telephone List (Attach most current list here) Revised December 2009 Page 14
How To Handle A Disaster Recovery Plan
Page 1 of 9 Policy Statement CSB Policy And Procedures The equipment, software systems, and databases that comprise the ephi System are critical components that enable the [CSB] to function in an effective
Riverhead Central School District
Riverhead Central School District Data Disaster Recovery Plan The following pages outline the data recovery process for the Riverhead Central School District **This document should be kept in paper form**
SUBJECT: Information Technology Disaster Recovery Plan
SUBJECT: Information Technology Disaster Recovery Plan The Circumstances The Louisiana Delta Community College Disaster Recovery plan will be invoked after an incident which has impaired or disabled the
1. Backup and Recovery Policy
POLICY TITLE: POLICY #: IT - 2 DATE DRAFTED: 09/23/05 APPROVED DATE: 09/23/05 REVISION DATE: BRIEF DESCRIPTION: Backup and Recovery Policy Minimum requirements for the creation and retention of computer
North Florida Community College
North Florida Community College Technology Plan Table of Contents Executive Summary... 3 Technology Vision... 5 Annual Initiatives... 6 2010 Data Center Expansions... 6 The Next 3 Years... 6 Technology
Disaster Recovery Plan Documentation for Agencies Instructions
California Office of Information Security Disaster Recovery Plan Documentation for Agencies Instructions () November 2009 SCOPE AND PURPOSE The requirements included in this document are applicable to
Jacksonville University Information Technology Department Disaster Recovery Plan. (Rev: July 2013)
Jacksonville University Information Technology Department Disaster Recovery Plan (Rev: July 2013) Table of Contents Introduction 3 Objectives/Constraints 4 Assumptions 4 Critical Systems 5 Incidents Requiring
Disaster Recovery Plan
Disaster Recovery Plan This guide sets forth items to consider in the review of the firm s disaster recovery plan. You should form a committee to assess the plan and should assign activities under the
Technology Recovery Plan Instructions
State of California California Information Security Office Technology Recovery Plan Instructions SIMM 5325-A (Formerly SIMM 65A) September 2013 REVISION HISTORY REVISION DATE OF RELEASE OWNER SUMMARY OF
About Backing Up a Cisco Unity System
CHAPTER 4 Introduction This chapter describes in general terms backing up a Cisco Unity system. When you back up a Cisco Unity server (and one or more Exchange servers) you need to consider the same issues
Planning a Backup Strategy
Planning a Backup Strategy White Paper Backups, restores, and data recovery operations are some of the most important tasks that an IT organization performs. Businesses cannot risk losing access to data
APPENDIX 7. ICT Disaster Recovery Plan
APPENDIX 7 ICT Disaster Recovery Plan This policy was approved and ratified by the Governing Body of Cox Green School on 15 th October 2013 Signed: Chair of Governors Date: Ratified: Oct 2013 Review: Sep
14/03/12 Updated Annex 1 to refer to current backup details. 15/03/12 Included section detailing NetApp filer data storage
System and File Restore Policy Document Status Security Classification Version 1.1 Level 4 - PUBLIC Status DRAFT Approval Life 3 Years Review By June 2012 Owner Change History System Support Group Manager
Massachusetts Institute of Technology. Functional Area Recovery Management Team Plan Development Template
Massachusetts Institute of Technology Functional Area Recovery Management Team Plan Development Template Public Distribution Version For further information, contact: Jerry Isaacson MIT Information Security
Disaster Recovery and Business Continuity Plan
Disaster Recovery and Business Continuity Plan Table of Contents 1. Introduction... 3 2. Objectives... 3 3. Risks... 3 4. Steps of Disaster Recovery Plan formulation... 3 5. Audit Procedure.... 5 Appendix
DISASTER RECOVERY AND CONTINGENCY PLANNING CHECKLIST FOR ICT SYSTEMS
Appendix L DISASTER RECOVERY AND CONTINGENCY PLANNING CHECKLIST FOR ICT SYSTEMS I. GETTING READY A. Obtain written commitment from top management of support for contingency planning objectives. B. Assemble
Enterprise Backup Solution Vendor Questions
Enterprise Backup Solution Vendor Questions What is the size of a single full back up? If Backups comprise 28% of the 19TB, can we assume that a single full (not compressed) is approximately 6TB? The approximate
Audit of. District s Information Technology Disaster Recovery Plan
Audit of District s Information Technology Disaster Recovery Plan April 11, 2014 Report #2014-03 MISSION STATEMENT The School Board of Palm Beach County is committed to providing a world class education
Data Center Assistance Group, Inc. DCAG Contact: Tom Bronack Phone: (718) 591-5553 Email: [email protected] Fax: (718) 380-7322
Business Continuity and Disaster Recovery Job Descriptions Table of Contents Business Continuity Services Organization Chart... 2 Director Business Continuity Services Group... 3 Manager of Business Recovery
APPENDIX 7. ICT Disaster Recovery Plan
APPENDIX 7 ICT Disaster Recovery Plan This policy was approved and ratified by the Governing Body of Cox Green School on 20 th October 2015 Signed: Chair of Governors Date: Version Authorisation Approval
BACKUP AND RECOVERY PLAN MS SQL SERVER
BUREAU OF INFORMATION & TELECOMMUNICATIONS BACKUP AND RECOVERY PLAN MS SQL SERVER Page 1 of 5 Revisions & Addendums Log: Instructions: Changes and Addendum can be sent to: James R. Douglas, Technical Analyst
NH-HMIS Disaster Recovery Plan
NH-HMIS Disaster Recovery Plan Page 1 of 7 NH-HMIS Disaster Recovery Plan 3/2014 Table of Contents On-Site Power Outage or Service Interruption... 3 Network Data Recovery... 3 Database Tape Backups...
Service Level Documentation April, 2015
Service Level Documentation April, 2015 Purpose of the Service Level Document The purpose of this Service Level Document is to outline the relationship and responsibilities between Information Technology
15 Organisation/ICT/02/01/15 Back- up
15 Organisation/ICT/02/01/15 Back- up 15.1 Description Backup is a copy of a program or file that is stored separately from the original. These duplicated copies of data on different storage media or additional
CLIENT. Report of Remote Backup Service
CLIENT Report of Remote Backup Service Summary Report from May 1, 2006 to May 31, 2006 Page: 2 of 5 31 May 06 Backup Process SafeComs utilizes the proven industry standard backup rotation strategy known
Symantec Backup Exec 2010
Reliable Backup and Recovery Designed for Your Growing Business Overview delivers market leading backup and recovery protection from server to desktop. Easily protect more data while you reduce storage
INFORMATION TECHNOLOGY SERVICES TECHNICAL SERVICES June 2012
INFORMATION TECHNOLOGY SERVICES TECHNICAL SERVICES June 2012 Program Description Network Services is a service unit in Information Technology Services responsible for designing, acquiring, deploying, operating,
San Francisco Chapter. Information Systems Operations
Information Systems Operations Overview Operations as a part of General Computer Controls Key Areas of focus within Information Systems Operations Key operational risks Controls generally associated with
Tailored Technologies LLC
685 Third Avenue New York, NY 10017 Tel: (212) 503-6300 Fax: (212) 503-6312 Date: January 9, 2014 To: The Audit File of the Hugh L. Carey Battery Park City Authority From: Tailored Technology Observations
DISASTER RECOVERY PLANNING GUIDE
DISASTER RECOVERY PLANNING GUIDE AN INTRODUCTION TO BUSINESS CONTINUITY PLANNING FOR JD EDWARDS SOFTWARE CUSTOMERS www.wts.com WTS Disaster Recovery Planning Guide Page 1 Introduction This guide will provide
Wiley College Information Technology (IT) Disaster Recovery Plan
Wiley College Information Technology (IT) Disaster Recovery Plan Dr. Haywood L. Strickland President and CEO Submitted by: Nathaniel E. Hewitt, III Vice President for Information Systems and Technology
85-01-55 Overview of Business Continuity Planning Sally Meglathery Payoff
85-01-55 Overview of Business Continuity Planning Sally Meglathery Payoff Because a business continuity plan affects all functional units within the organization, each functional unit must participate
RPI Employee s Federal Credit Union Business Continuity/Disaster Recovery Plan. January 23, 2012
RPI Employee s Federal Credit Union Business Continuity/Disaster Recovery Plan January 23, 2012 Purpose and Objectives 2 Disaster Recovery Organizational Structure 3 Appendices: Disaster Recovery Emergency
Birkenhead Sixth Form College IT Disaster Recovery Plan
Author: Role: Mal Blackburne College Learning Manager Page 1 of 14 Introduction...3 Objectives/Constraints...3 Assumptions...4 Incidents Requiring Action...4 Physical Safeguards...5 Types of Computer Service
MARQUIS DISASTER RECOVERY PLAN (DRP)
MARQUIS DISASTER RECOVERY PLAN (DRP) Disaster Recovery is an ongoing process to plan, develop, test and implement changes, processes and procedures supporting the recovery of the critical functions in
The University of Iowa. Enterprise Information Technology Disaster Plan. Version 3.1
Version 3.1 November 22, 2004 TABLE OF CONTENTS PART 1: DISASTER RECOVERY EXPECTATIONS... 3 OVERVIEW...3 EXPECTATIONS PRIOR TO AN INCIDENT OCCURRENCE...3 EXPECTATIONS PRIOR TO A DISASTER OCCURRENCE...4
UNIVERSITY INFORMATION TECHNOLOGY SERVICES (UITS) & INFORMATION WAREHOUSE FUNCTIONAL ANNEX 13
UNIVERSITY INFORMATION TECHNOLOGY SERVICES (UITS) & INFORMATION WAREHOUSE FUNCTIONAL ANNEX 13 Revision: December 19, 2012 Supersedes: June 9, 2009 Effective Date: January 30, 2012 OBJECTIVES The primary
Symantec Backup Exec 11d for Windows Small Business Server
Symantec Backup Exec 11d for Windows Small Business Server End-User Call Script for Sales This document is intended as a simple call structure to help get you started when selling Backup Exec 11d for Windows
Creating a Business Continuity Plan. What We ll Cover... What is a BCP? Micky Hogue, CRM
Creating a Business Continuity Plan Micky Hogue, CRM Sandia National Laboratories Albuquerque, NM 505-844-6640 [email protected] What We ll Cover... What is a Business Continuity Plan Why create a BCP?
ACS Backup and Restore
Table of Contents Implementing a Backup Plan 3 What Should I Back Up? 4 Storing Data Backups 5 Backup Media 5 Off-Site Storage 5 Strategies for Successful Backups 7 Daily Backup Set A and Daily Backup
Clovis Municipal School District Information Technology (IT) Disaster Recovery Plan
Clovis Municipal School District Information Technology (IT) Disaster Recovery Plan Revision History REVISION DATE NAME DESCRIPTION Draft 1.0 Eric Wimbish IT Backup Disaster Table of Contents Information
Disaster Recovery Plan Checklist
Disaster Recovery Plan Checklist Your guide for setting up or updating a Disaster Recovery Plan for your business. ArcSource Disaster Recovery Plan Checklist 1. Compile Your Internal Contacts Information
EXAM - E20-027. nterprise Backup Recovery Design Exam for Data Center Architects Exam. http://www.examskey.com/e20-027.html
EMC EXAM - E20-027 nterprise Backup Recovery Design Exam for Data Center Architects Exam TYPE: DEMO http://www.examskey.com/e20-027.html Examskey Cisco E20-027 exam demo product is here for you to test
BUSINESS CONTINUITY PLAN
BUSINESS CONTINUITY PLAN Business Name: Phone # Cell # Emergency Contact Information: Dial 9-1-1 in an Emergency Non-Emergency: Police: Fire: Insurance Provider: Emergency Planning Team: I. CRITICAL OPERATIONS
C I T Y O F W E S T L I N N
C I T Y O F W E S T L I N N JOB DESCRIPTION Job Title: DESKTOP TECHNICIAN II GENERAL FUNCTION: Position is responsible for: 1) providing administration and support for all City desktop and peripheral hardware,
The Weill Cornell Medical College and Graduate School of Medical Sciences. Responsible Department: Information Technologies and Services (ITS)
Information Technology Disaster Recovery Policy Policy Statement This policy defines acceptable methods for disaster recovery planning, preparedness, management and mitigation of IT systems and services
Best Practices for Using Symantec Online Storage for Backup Exec
WHITE PAPER: xxxxxx Data Protection [00-Cover_Bar] Best Practices for Using Symantec Online Storage for Backup Exec Confidence in a connected world. White Paper: Data Protection Best Practices for Using
State of Oklahoma <Insert Agency Name Here> Business Continuity Plan Template DRAFT
State of Oklahoma Template DRAFT Version 1.0 Page 2 of 56 Table of Contents DOCUMENT CHANGE CONTROL... 6 SECTION I: INTRODUCTION... 7 A. How to Use This Plan... 7 B. Objectives...
Symantec Backup Exec 2012
Better backup for all Data Sheet: Backup and Disaster Recovery Overview is one integrated product that protects virtual and physical environments, simplifies both backup and disaster recovery, and recovers
Local Government Cyber Security:
Local Government Cyber Security: Guidelines for Backing Up Information A Non-Technical Guide Essential for Elected Officials Administrative Officials Business Managers Multi-State Information Sharing and
SOUTH LAKELAND DISTRICT COUNCIL INTERNAL AUDIT FINAL REPORT IT 11-02. IT Backup, Recovery and Disaster Recovery Planning
SOUTH LAKELAND DISTRICT COUNCIL INTERNAL AUDIT FINAL REPORT IT 11-02 IT Backup, Recovery and Disaster Recovery Planning Executive Summary Introduction As part of the 2011/12 Audit Plan and following discussions
DISASTER RECOVERY. Omniture Disaster Plan. June 2, 2008 Version 2.0
DISASTER RECOVERY Omniture Disaster Plan June 2, 2008 Version 2.0 CHAPTER 1 1 Disaster Recovery Plan Overview In the event that one of our data collection environments are unavailable due to an event,
Backup and Redundancy
Backup and Redundancy White Paper NEC s UC for Business Backup and Redundancy allow businesses to operate with confidence, providing security for themselves and their customers. When a server goes down
Solution Overview: Data Protection Archiving, Backup, and Recovery Unified Information Management for Complex Windows Environments
Unified Information Management for Complex Windows Environments The Explosion of Unstructured Information It is estimated that email, documents, presentations, and other types of unstructured information
1. Storeroom supplies -- For items stocked in the Palmer storeroom, use the Requisition for Supplies Form.
DISBURSEMENT PROCESSES Millersville University uses the Accounts Payable module of Banner Finance System to process vendor payments. After payroll, payments for goods and/or services represent the second
Identify and Protect Your Vital Records
Identify and Protect Your Vital Records INTRODUCTION The Federal Emergency Management Agency s Federal Preparedness Circular 65 states The protection and ready availability of electronic and hardcopy documents,
How To Virtualize A Server At Swic
Implementing Server Virtualization At Southwestern Illinois College (Case Study) Submitted by Christine Leja, CDP/CCP Background Southwestern Illinois College (SWIC) is a community college started in 1946
ENTERPRISE DATA CENTER BACKUP AND RECOVERY OVERVIEW
BACKUP AND RECOVERY OVERVIEW Version 2.15 Date: 09/16/2014 SECURITY WARNING The information contained herein is proprietary to the Commonwealth of Pennsylvania and must not be disclosed to un-authorized
Putnam/Northern Westchester BOCES Internal Audit Report on Information Technology
6G Putnam/Northern Westchester BOCES Internal Audit Report on Information Technology TABLE OF CONTENTS Page Report on Internal Controls Related to Information Technology Network and Network Security 1
ICT & Communications Services Disaster & Recovery Plan
ICT & Communications Services Disaster & Recovery Plan Advanced IT Services with George Spencer Academy www.aitn.co.uk Advanced IT Services - Arthur Mee Road, Stapleford, Nottingham. NG9 7EW Email: [email protected]
WHITE PAPER THE BENEFITS OF CONTINUOUS DATA PROTECTION. SYMANTEC Backup Exec 10d Continuous Protection Server
WHITE PAPER THE BENEFITS OF CONTINUOUS DATA PROTECTION SYMANTEC Backup Exec 10d Continuous Protection Server 1 TABLE OF CONTENTS EXECUTIVE SUMMARY...3 Current Situation...3 The New Opportunity...3 The
Data Sheet: Backup & Recovery Symantec Backup Exec 12.5 for Windows Servers The gold standard in Windows data protection
The gold standard in Windows data protection Overview Symantec Backup Exec 12.5 delivers market-leading backup and recovery protection from server to desktop, providing complete data protection for the
Backup and Recovery 1
Backup and Recovery What is a Backup? Backup is an additional copy of data that can be used for restore and recovery purposes. The Backup copy is used when the primary copy is lost or corrupted. This Backup
Backup Exec 15: Protecting Microsoft SQL
TECHNICAL BRIEF: BACKUP EXEC 15: PROTECTING MICROSOFT SQL........................................ Backup Exec 15: Protecting Microsoft SQL Who should read this paper Technical White Papers are designed
REQUEST FOR PROPOSAL
CITY OF MUKILTEO 11930 Cyrus Way Mukilteo, Washington 98275 425-263-8030 www.ci.mukilteo.wa.us REQUEST FOR PROPOSAL IT SERVICES ACQUISTION SCHEDULE The Acquisition Schedule is as follows, with all times
Appendix A Statement of Work: Digitization, Archiving and Digital Documents Management System
Page 1 Appendix A Statement of Work: Digitization, Archiving and Digital Documents Management System 1 Page 2 Table of Contents Table of Contents... 2 TERMS AND ABBREVIATIONS... 3 Statement of Work Overview...
Archiving, Backup, and Recovery for Complete the Promise of Virtualization
Archiving, Backup, and Recovery for Complete the Promise of Virtualization Unified information management for enterprise Windows environments The explosion of unstructured information It is estimated that
Introduction. Ease-of-Use
Remote Data Backup Introduction Computers are the default storage medium for most businesses and virtually all home users. Because portable media is quickly becoming an outdated and expensive method for
More enhanced features.
More enhanced features. Saves time and lowers cost. Upgrade today for complete data and system protection across your virtual and physical server environments. Symantec Backup Exec 12.5 NEW agents for
SVA Backup Plus Features
1221 John Q. Hammons Drive Madison, WI 53717 P.O. Box 44966, Madison, WI 53717 P: 608.826.2400 TF: 800.366.9091 F: 608.831.4243 www.sva.com Introduction Computers are the default storage medium for most
Contingency Planning and Disaster Recovery Plan
Contingency Planning and Disaster Recovery Plan Introduction In response to Homeland Security concerns and following sound business practices, agencies were asked to develop a Continuity of Operations
Disaster Recovery Planning
Disaster Recovery Planning This is a brief guide, with a suggested table of contents, to help you get started with putting together your Disaster Recovery Plan (DRP) Pensar can assist you in completing
Version: 1.5 2014 Page 1 of 5
Version: 1.5 2014 Page 1 of 5 1.0 Overview A backup policy is similar to an insurance policy it provides the last line of defense against data loss and is sometimes the only way to recover from a hardware
ICT Policies. ELFT Backup & Recovery Procedure
ICT Policies ELFT Backup & Recovery Procedure Version 1.2 Document Control Summary Document Title Document Purpose File References Status ELFT Backup & Recovery Procedure To set out the Trusts procedure
CHAPTER 15 DISASTER COST RECOVERY PROCEDURES
Kern County Policy and Administrative Procedures Manual CHAPTER 15 DISASTER COST RECOVERY PROCEDURES 1501. General Statement... 1 1502. Disaster Relief Claim Procedures... 1 1503. Responsibilities... 2
Portable Media. BackupAssist Quick-Start Guide for. BackupAssist installation, configuration and setup. www.backupassist.com. Contents.
BackupAssist Quick-Start Guide for Portable Media BackupAssist installation, configuration and setup Contents 1.1 Introduction... 2 2.1 Before you begin... 2 Applies to Tape 3.1 Installation... 2 4.1 Initial
Business Continuity. Disaster Recovery Plan
Business Continuity Disaster Recovery Plan Emergency Contact Persons Phyllis Hollis, President & CEO O: (212) 916 3888 Cell: (917) 804 8021 Email: [email protected] Kinchen Bizzell, Managing Director,
