1 Test Estimation Tools and techniques for realistic predictions of your test effort by Rex Black As a test manager, development manager, or test lead, at the beginning of many projects, you probably find yourself confronted with the question, How long will it take and what resources do you need to test this system? Maybe your boss asked you. Or maybe your boss just gave you an end date, and you re wondering if you can actually hit that date. Or maybe you re bidding on a project for an important client. Or maybe you are putting together a proposal for a new in-house project, and the stakeholders for that project need to know how long the testing will take. No matter what the impetus, it is important to know how to estimate testing projects. An estimate should accurately predict and guide the project s future. Such an estimate is 1. Realistic. It includes all the tasks that you can reasonably anticipate. It forecasts what, based on our current knowledge, is most likely to happen. It reveals the risks to a test project so you can take steps to mitigate them. 2. Actionable. I want clear ownership of tasks by committed individual contributors. I want to see assigned resources and known dependencies. 3. Flexible. What if deadline and resources constraints are immovable? The estimate must accommodate project realities. Some Estimation Terminology Project: Temporary endeavor undertaken to create or provide service or product. Test subproject: The subset of the project performed by the test team to provide test services to the project. Project schedule (a.k.a., work-breakdown-structure): Hierarchical decomposition of project into phases, activities, and tasks with resources and dependencies. Check the Project Management Institute s Web site ( for more useful definitions and ideas about project management and estimation. Divide and Conquer One excellent estimation tool is a work-breakdown-structure. A work-breakdownstructure (WBS) is a hierarchical decomposition of a project (in this case, the test effort) into stages, activities, and tasks. For testing projects, start with the following stages: Test Estimation Copyright Rex Black 2002 All Rights Reserved Page 1 of 12
2 Planning Staffing (if applicable) Test environment acquisition and configuration Test development Test execution (including find/fix/retest cycles) Those with programming backgrounds may be familiar with the technique divide and conquer. A WBS works in a similar way. Once you have determined the stages, divide them into ever-smaller chunks of work, ultimately down to the level of one person over a short period of time (one to five business days.) Then conquer the estimation problem by understanding how long (duration) and how much work (effort) each task will take. Because the overall effort and duration estimate derives from the lowest-level constituent tasks, such calculations are called bottom-up estimates. To measure when tasks are completely finished during the project, it helps to ensure that each task produces a key deliverable, or at least a first draft or some measurable piece of a key deliverable. These deliverables may be internal to the test team, like test cases, test tools, or test data. They may be deliverables in to the test team, like the first feature-complete test release, the unit test results, or the configuration of the test environments. They may be deliverables out to the project team, like test plans, bug reporting systems, and test results. These deliverables are often inputs to subsequent tasks. Let s use a hypothetical case study to bring these dry ideas to life. Step into the shoes of the Test Manager on the Grays and Blues project. This project team is building an exciting, first-person action game based on the history of the United States Civil War. Your Test Team consists of two skilled test engineers and five junior but eager test technicians. You will run the System Test phase of the project the Development Team owns the Component and Integration Phases which is proceeding under the V model software development lifecycle methodology. (I talk more about testing and development lifecycles in my book, Managing the Testing Process.) The test strategy is to use scripted, manual test cases with some automated load and reliability tests. As the test manager, you sit down to create a WBS for the Grays and Blues test project. You can use a project management tool like Microsoft Project, or you can tape 3x5 index cards (or stick Post-It Notes ) to a white board. (Often, people who use the index card technique will enter their estimates into a project management tool after they re done.) Initially, you might come up with the WBS shown in Figure 1. Test Estimation Copyright Rex Black 2002 All Rights Reserved Page 2 of 12
3 Figure 1: An Initial Work-Breakdown-Structure Unite and Estimate Decomposing the work into tasks can be done alone, but accurate predictions about how long those tasks will take requires the collective wisdom of the technically competent people on the team: those who know how long the tasks really take because they ve done them before. (Some managers like to gather the team together to develop the initial WBS; others bring the team a first draft WBS that serves as a springboard for the discussion. It's up to you.) Using the whole team leverages varied and extensive experience. On a teambuilding note, involving the team in estimation sends a powerful message of trust and collegiality. It also builds commitment to the estimate. There are three major techniques for team estimation. One is the Delphic Oracle, where each team member estimates how long each task will take. During estimate review, the high and low estimators for each task explain their reasoning. The low estimator may point out an optimization or trick that can speed up a task, like using a random number generator, a spreadsheet, and cutand-paste to generate large amounts of test data rather than entering it by hand. The high estimator may point out a likely delay, like the process of getting imported hardware prototypes through customs. The estimation process is then repeated twice more, taking the high and low estimators points into account each time. The average for each task at the end of the last iteration is the estimate. Test Estimation Copyright Rex Black 2002 All Rights Reserved Page 3 of 12
4 The next approach, called the Three Point, involves asking people not for one estimate, but for three estimates of each task. The first number is the best case estimate; i.e., assume everything goes well. The second number is the worst-case estimate; i.e., assume our worst fears are realized. The third number is the expected-case estimate. The average of the expected cases is the final estimate, but the best case and worst-case estimates are documented to understand the accuracy of the estimate and to feed into the test planning and risk management processes. Finally, the combination of Delphic Oracle and Three Point techniques is called the Wideband technique. Team members give three numbers. The low and high estimators for each of the three numbers on each task explain their estimate. The process is repeated twice, then the averages of the expected case estimates become the final estimate. The average best- and worst-case numbers for each task become the range. Names like Delphic Oracle serve as reminders that you are trying to foretell the future. Risky business, that. As the project proceeds, you will learn new things that would have affected the estimate. Changes will happen. Flaky new technology won t work right the first time. So, it s a good idea to include some contingency time some slack into your schedule, especially the riskiest tasks. A rule of thumb that s worked for me is 20%, but you ll want to look back at past estimates and see how far off initial estimates were from final end dates to come up with a good rule of thumb for you. Hop back into your Grays and Blues shoes again. Suppose you sit down with your team and go through the WBS, assigning durations and effort to each task using the Wideband technique. In the process, you find a missing activity, Smoke Test. In addition, the exercise of discussing the highest worst-case estimates identifies a number of key risks to the testing project that you will want to put contingency plans in place for. The sized estimate is shown in Figure 2. Test Estimation Copyright Rex Black 2002 All Rights Reserved Page 4 of 12
5 It Depends Figure 2: An Estimate with Tasks Sized Using the Wideband Technique The project shown in Figure 2 looks very strange. It seems like, given enough people and other resources, it could finish in fifteen days, the length of the longest task, Write LCV/Reliability (LCV is an abbreviation in this figure for Load, Capacity, and Volume.). But are resources the only constraint on your schedule? Of course not! Some tasks have dependencies on other tasks. The tasks that come before are called predecessor tasks, and the ones that follow are successor tasks. Successor tasks cannot start or at least cannot complete until their predecessor task(s) are at some stage of completion. Of course some deliverables cannot be started or finished until others are finished. Dependencies often arise through the deliverables. For example, you might want a completed, approved test plan before you start test development. This is an internal test team deliverable, and is called a finish-to-start dependency. As another example, suppose you decide that you want to continue system testing three weeks beyond both the completion of new feature development and also the delivery of the last major change for testing. In that case, you have a finish-to-finish dependency. If you re using the 3x5 or PostIt Note method, you and the team can use the following approach to identify the dependencies: Test Estimation Copyright Rex Black 2002 All Rights Reserved Page 5 of 12
6 1. Stick all the tasks that have no dependencies to the whiteboard first, at the far left edge. 2. Now, add the tasks that depend in some way on the tasks currently on the whiteboard (and only those tasks). Tape or stick them to the right of those tasks upon which they depend. With a marker, draw a line representing the dependency that connects the successor and predecessor tasks. Identify what kind of dependency it is. 3. Repeat step two until you and the team have identified all dependencies. For small projects, you might rather have everyone huddle around a PC and plug the data directly into the project management tool. If you have used the 3x5/whiteboard approach, now is the time to enter the information into a project management tool, because the next step is to look at the critical paths. The critical paths are those sequences where delay, slippage, or exceeding the allotted time for any task along the sequence will cause a day-forday delay in the project end date. Near critical paths are those where a delay of a day or two might not affect the schedule, but significant delays will. For example, those tasks that affect phase entry or exit criteria are often on the critical path, as many dependencies tend to converge around phase entry and exit dates. External dependencies are another frequent source of delay for projects. Analyzing the critical paths identifies those tasks that are at the highest risk of delaying the schedule. Such tasks require careful management and attention during the project. No Free Lunch As part of the team estimation exercise, resources are assigned to tasks (some managers come to the team estimation meeting with pre-determined resources for some tasks). The exact set of resources required is very project-specific, of course, but generally fall into the categories of people test environments test tools and testware. People resources include test engineers and test technicians, whether contractors or employees, as well as outside test resources like test labs and vendor test groups. Remember that using a less-skilled person to accomplish a particular task due to a shortage of a particular skillset, perhaps will increase the effort and duration of that task, so be ready to revise the estimate based on the people assigned. Also, keep in mind that a person s skill with a given task or tool determines the accuracy of the estimate. Unless, for each task on your schedule, Test Estimation Copyright Rex Black 2002 All Rights Reserved Page 6 of 12
7 you have at least one person on your team who knows how to perform that task, the estimate will be subject to delays for those tasks for which skilled people are unavailable. If you find yourself understaffed or without skilled people in certain areas, you ll need to talk to your manager about hiring a new tester, bringing in a contractor, or reducing the scope of the test effort. Test environment resources include hardware, software, networks, facilities, and so forth. You needn t account for every pen and piece of paper, usually, but it s especially important to include expensive or long-lead-time items like large servers and lab space. Test tools and testware include custom (new or reused) test data, test cases, test scripts (manual or automated), and test harnesses, along with the widely-known commercial test tools. In many cases, test tools and testware are deliverables from the early stages of the test project. Back in the land of Grays and Blues, our WBS with dependencies and resources assigned might appear as shown in Figure 3. As the test manager for Grays and Blues, you ve taken care to avoid some common estimation pitfalls, like assuming that two people can finish a task in half the time of one. overloading test tools (e.g., insufficient licenses) or the test environment (e.g., performance and load testing on the same systems as functional testing). forgetting to include time and resources to set up and support the environments and tools. These mistakes can cause lengthy delays on projects when critical dependencies delay successor tasks. Test Estimation Copyright Rex Black 2002 All Rights Reserved Page 7 of 12
8 Figure 3: A WBS with Dependencies and Resources Assigned Estimating Test Execution The test execution stage is often particularly hard to estimate. How long it will take to finish running the tests is really a function of two questions: 1) how long will it take to run each planned test (scripted or exploratory) at least once, and 2) when will we be done finding bugs, fixing them, and confirming they re fixed? To deal with the first question first, you have to know three things to estimate the planned test time. 1. How many total person-hours of testing have you planned? Suppose you have estimated the number of hours required for each Gray and Blue test case. You come up with a total of 280 hours of effort. 2. How many raw person-hours of staff time do you have available per week? Our Gray and Blue test team includes 7 people, and let s assume they work 40 hours per week, so we have 280 person-hours available. 3. What percentage of the time a tester is on site is spent, on average, running test cases? (Testers often must attend meetings, confirm bug closure, update test scripts, read , and do other productive things that are not related to planned test execution during each week.) Assuming our Gray and Blue testers spend 50% of their time testing, we have 140 person-hours of testing per week. Test Estimation Copyright Rex Black 2002 All Rights Reserved Page 8 of 12
9 This would mean that we need two weeks to run each test once. Now to the harder question: How long to find all the bugs? Stephen Kan in Metrics and Models in Software Quality Engineering and Pankoj Jalote in CMM in Practice both advance what are known as defect removal models (see StickyNotes for more on those references). A simplified version of building such a model is as follows. First, we need to have some prediction of the total number of bugs. Function point and lines of code counts are commonly used, but might be beyond your process capability. Suppose you have the total number of person-hours estimated for the project. If so, can you look back at previous projects and see how many personhours were estimated, and how many bugs you ultimately found? If not, maybe you have some other historical data you can use, like the average number of defects found per feature or per programmer. The idea is to create a simple mathematical model using a spreadsheet, say that calculates, using a metric or two that you have during the estimation period, the total number of bugs ultimately found during testing. Second, given a prediction of the total number of bugs, how long will it take to find them? Again, with historical data, perhaps we can calculate what percentage of the remaining bugs are typically found each week during system test. Now, how long to fix them all and confirm them fixed? Again, based on historical data, what percentage of the open bugs get fixed each week? As you derive absolute numbers from the percentages, take care to check these numbers against the capability of the test and development teams. If you project a peak bug find rate of 200 per week for your Gray and Blue team of 7, ask yourself, Can the testers really report over five bugs per day? Now, add this information to your spreadsheet, building a simple model for the cumulative bug open and close numbers. If, as the Grays and Blues test manager, you come up with a defect removal model that predicts the find and fix rates shown in Figure, then the test execution schedule in Figure 3 is reasonable. The more historical data you have for projects like your current project, the more accurate these predictions will be. For instance, using historical data, one of my clients predicts total bug reports with 10% accuracy on projects as long as two years. (You can download the spreadsheet used to generate this chart from my Web site as part of the templates that accompany Managing the Testing Process. See StickyNotes for details.) Test Estimation Copyright Rex Black 2002 All Rights Reserved Page 9 of 12
10 Figure 4: A Predicted Find/Fix Chart, Based on Historical Data Factors that Influence Testing Estimates System engineering including the testing is a complex, high-risk, human endeavor. As such, it s important to combine good estimation techniques with an understanding of the factors that can influence effort, time, dependencies, and resources. Some of these factors processes, tools, test environment, skills, team composition and management can act to slow down or speed up the schedule, while others, when present, can only slow things down. When preparing a test estimate, it s important for the test manager and those on the test team who help with estimation to consider how each of these factors will affect the estimate. Forgetting just one of these factors can turn a realistic estimate into an unrealistic one. For an explanation of factors that can effect test estimates, see my article Factors affecting test estimation, published on StickyMinds.com. But We Don t Have Until April 30 th! Suppose you propose your realistic, actionable schedule to management, and they say, Make it shorter! We don t have that long! Now what? Reluctantly or petulantly accept a date from management? That s not a good plan. How about some other options? Test Estimation Copyright Rex Black 2002 All Rights Reserved Page 10 of 12
11 One thing you could do is relax your entry criteria for testing a bit. Oftentimes, people define entry criteria as, "one phase must end before the next begins." But suppose you waive the feature complete entry criteria for system testing and accept an almost complete release. If you did this in the Grays and Blues example, you could pull in your estimated test completion date by two weeks. That s good; but people must understand that this overlap can increase risks to system quality. For one thing, can developers really fix bugs and finish the system at same time? If not, what will suffer, bugs or features? For another thing, testing an unready system often is less efficient, which might result in less and less thorough testing. Another solution is to add staff. Suppose you can increase the test team and programming team staff so that you can run test passes in a week and fix bugs twice as fast, too? In the Grays and Blues example, this would pull in the estimated end date by five weeks. Now March 26 is the new end date, which is 40% earlier. But the human resource cost would increase significantly, perhaps even doubling. Furthermore, it s not certain that you could hire new people and ramp up them up in time to make a positive contribution to this project. An oft-proposed solution to schedule crunches is an arbitrary reduction in test execution time. Hmm, people think, maybe we can accept a lesser level of quality? Okay, suppose you cut test execution in half? This eliminates the scary staffing budget increase, but will you really be done testing? Cutting test execution is the most risky strategy for schedule compression. In terms of schedule, what if the system is not good enough at end date? Now you have a schedule slip right at the end. In terms of budget, this schedule slip occurs when the project s daily cost is at the highest point. In terms of quality, bugs will be found late in testing, leaving no time to remove them. You might have to drop buggy functions late in the game, after you ve already expended most of the time and money to implement those features. If you re going to take risks with quality, take those risks with your eyes open. To do so, carefully consider the comparative levels of risk associated with reducing the testing effort. One option is to eliminate whole areas of test coverage. Identify the lowest-risk areas in the scope of testing, and then either drop coverage or test in those areas only if you can leverage other testing that brings you to that area anyway. Another option is to reduce the extent of testing across the board. Identify the least risky of the highest-risk areas, and adopt a balanced (broad, not deep) test approach. You can also postpone automation of some tests or use outsourcing, especially test labs, to reduce test environment costs. Whatever technique you choose, the idea is to pick creative techniques in a proactive way to reduce the time required for testing. Instead of cutting testing, you could cut the features in the product. For Grays and Blues, suppose you drop significant chunks of game functionality, like Test Estimation Copyright Rex Black 2002 All Rights Reserved Page 11 of 12
12 multiplayer and arcade, Mac, and Linux platforms? This reduces the test effort by about 25%. So, depending on effect on development, you could be done by March 26. This can work, but it s also true that releasing lots of small releases increases the quality risks related to regression. (The limited amount of testing time associated with a small maintenance release makes missing bugs in unchanged areas more likely.) Therefore, these features should be bundled with next regular release. What Not to Propose While there are a few other approaches to dealing with schedule pressure, I don t recommend any of them. One is weekend or overtime work. If people were machines, you could use 7-day workweeks to shrink schedules by 40%. Now, people will have to work weekends and overtime occasionally. However, it should seldom be part of the schedule or estimate, but rather an attempt to catch up if you fall behind at some point. As Tom DeMarco suggested in The Deadline, extended overtime will burn people out and reduce their productivity. The only benefit of long periods of overtime is the cynical one, which is to make managers appear blameless when schedules are missed. Another risky estimation technique is setting a tight schedule as a stretch goal for testers. To have a 50/50 chance of on-time project completion, each task (especially critical and near-critical path tasks) must have a 50/50 chance of finishing on time. Otherwise, you will probably fall further and further behind. Tight schedules only make sense if you believe in what s called Theory X management. This theory says that people will only do their best work if cajoled, exhorted, and pressured by their manager. As an alternative, consider Theory Y. This theory says that people want to do their best work, and it s the manager s job to enable, support, and nurture that work. If theory Y applies to your team, then stretch goals are a losing strategy. Also, as a practical matter, even if heroics and sacrifice lead to on-time delivery for one project, what are the long-term quality and motivation impacts? Realistic, Actionable Estimates In a successful project, schedule, budget, features, and quality the four moving parts in a system development effort converge as the release date approaches. Realistic, actionable estimates lay the foundation for this kind of project success. The best practices of project estimation and management can help you develop a good estimate. Such an estimate is complete and accurate, captures and balances risks, has committed team and individual ownership, and takes into account dependencies and critical path. Such an estimate gives executives and the project management team options that allow them to balance competing risks. Working together, through smart trade-offs in the context of a good estimate, you can guide your project to success. Test Estimation Copyright Rex Black 2002 All Rights Reserved Page 12 of 12
The Project Planning Process Group
3 The Project Planning Process Group............................................... Terms you ll need to understand: Activity Activity attributes Activity list Activity on arrow diagram (AOA) Activity
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects
Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
Unit 4: Time Management (PMBOK Guide, Chapter 6)
(PMBOK Guide, Chapter 6) The questions on this topic focus heavily on scheduling techniques, network diagrams, Gantt charts, the critical path, compressing the schedule, PERT, and float. You may or may
added to the task, using Project, it will automatically calculate the schedule each time a new resource is added.
Chapter 3 Effort Driven Task Type By now, you will be getting sick of my repetition of the effort driven formula: Resource Units X Duration = Work I make no apologies, as it needs to be engraved in the
CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012
King Saud University College of Computer & Information Sciences Department of Computer Science CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012 1- Decomposing
Step by Step Project Planning
Step by Step Project Planning Contents Introduction The Planning Process 1 Create a Project Plan...1 Create a Resource Plan...1 Create a Financial Plan...1 Create a Quality Plan...2 Create a Risk Plan...2
THE PROJECT MANAGEMENT KNOWLEDGE AREAS
THE PROJECT MANAGEMENT KNOWLEDGE AREAS 4. Project Integration Management 5. Project Scope Management 6. Project Time Management 7. Project Cost Management 8. Project Quality Management 9. Project Human
Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072
Chapter 6: Project Time Management King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Learning Objectives Understand the importance of project schedules Define
INTRODUCTION: Plan and Schedule Development Create a Work Breakdown Structure (WBS) The detailed guidelines and examples start on the following page.
What This Is INTRODUCTION: Plan and Schedule Development Create a Work Breakdown Structure (WBS) The detailed guidelines and examples start on the following page. First of a series of guidelines for project
Chapter 2: Project Time Management
Chapter 2: Project Time Management Learning Objectives o o o o Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules.
WORK PROGRAM GUIDELINES
Project Managed Change Program WORK PROGRAM GUIDELINES JABATAN KERJA RAYA MALAYSIA Cawangan Pengurusan Projek Kompleks (PROKOM) Ibu Pejabat JKR Malaysia 2 Document Ownership Section No Section Amendment
Project Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
Project Scheduling & Tracking
Project Scheduling & Tracking Traditional Techniques: Work Breakdown Structure (WBS) Gantt Charts Precedence Diagrams Earned Value Planning It is the mark of an instructed mind to rest satisfied with the
15 Principles of Project Management Success
15 Principles of Project Management Success Project management knowledge, tools and processes are not enough to make your project succeed. You need to get away from your desk and get your hands dirty.
WHITE PAPER. The extensive outsourcing checklist
WHITE PAPER The extensive outsourcing checklist INTRODUCTION When it s time to find an outsourcing provider, many companies just call up the old RFP (Request for Proposal) file on the computer, change
Develop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
SWEN 256 Software Process & Project Management
SWEN 256 Software Process & Project Management Plan: Identify activities. No specific start and end dates. Estimating: Determining the size & duration of activities. Schedule: Adds specific start and end
Project Management Planning
Overview of Resource Planning Every organization has a limited number of resources to perform tasks. A project manager's primary role is to find a way to successfully execute a project within these resource
How to Outsource Without Being a Ninnyhammer
How to Outsource Without Being a Ninnyhammer 5 mistakes people make when outsourcing for profit By Jason Fladlien 2 Introduction The way everyone does outsourcing is patently wrong, and this report is
Developing a Load Testing Strategy
Developing a Load Testing Strategy Michele Ruel St.George Bank CMGA 2005 Page 1 Overview... 3 What is load testing?... 4 Scalability Test... 4 Sustainability/Soak Test... 4 Comparison Test... 4 Worst Case...
Project Management Glossary
Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project
Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu
Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project schedules and good project time management Define activities as the basis for developing project
(Refer Slide Time: 01:52)
Software Engineering Prof. N. L. Sarda Computer Science & Engineering Indian Institute of Technology, Bombay Lecture - 2 Introduction to Software Engineering Challenges, Process Models etc (Part 2) This
Test Plan Template (IEEE 829-1998 Format)
Test Plan Template (IEEE 829-1998 Format) Test Plan Identifier Some type of unique company generated number to identify this test plan, its level and the level of software that it is related to. Preferably
Chapter 4: Project Time Management
Chapter 4: Project Time Management Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
NEDARC POSITION PAPER
Which Database Will Serve Your Needs? National EMSC Data Analysis Resource Center Central to any EMS, public health, or large healthcare organization is the collection, storage, retrieval, and analysis
Object-Oriented Analysis. with the Unified Process. John W. Satzinger Southwest Missouri State University. Robert B. Jackson Brigham Young University
Object-Oriented Analysis and Design with the Unified Process John W. Satzinger Southwest Missouri State University Robert B. Jackson Brigham Young University Stephen D. Burd University of New Mexico ALL
SYSTEMS ANALYSIS AND DESIGN DO NOT COPY
Systems Analysis and Design in a Changing World, Fourth Edition -488-6-5 Copyright 7 Thomson Course Technology. All rights reserved. FOURTH EDITION SYSTEMS ANALYSIS AND DESIGN IN A C HANGING W ORLD John
Establishing your Automation Development Lifecycle
Establishing your Automation Development Lifecycle Frequently I engage clients in assessing and improving their automation efforts. The discussion normally starts from a position of frustration We ve invested
The Plan s Journey From Scope to WBS to Schedule
The Plan s Journey From Scope to WBS to Schedule Presented by: Rick Clare, CBAP, PMP, OCP, CSM PM Centers USA, LLC. 2013 Company Background Consulting and Training (Virtual, Public and Private Training)
Noorul Islam College of Engineering M. Sc. Software Engineering (5 yrs) IX Semester XCS592- Software Project Management
Noorul Islam College of Engineering M. Sc. Software Engineering (5 yrs) IX Semester XCS592- Software Project Management 8. What is the principle of prototype model? A prototype is built to quickly demonstrate
WHY BUSINESS CONTINUITY PLANS FAIL
WHY BUSINESS CONTINUITY PLANS FAIL 12 COMMON CAUSES AND HOW TO PREVENT THEM By Keith Erwood The ProtectEr, CEO and Principal Consultant The Continuity Co., LLC All material in this report is the property
Chapter 11: Integrationand System Testing
Object-Oriented Software Engineering Using UML, Patterns, and Java Chapter 11: Integrationand System Testing Integration Testing Strategy The entire system is viewed as a collection of subsystems (sets
TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain *
TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT Hazar Hamad Hussain * 1. Introduction The definition of Project as a temporary endeavor... refers that project has to be done within a limited
SOFTWARE SELECTION GUIDE. How to Find the Right Software for Your Organization
SOFTWARE SELECTION GUIDE How to Find the Right Software for Your Organization 1. Table of Contents Introduction 4 Step 1: Define Your Needs Business Goals Requirements List Step 2: Determine Your Options
Five Steps to Getting Started with Contract Management
Five Steps to Getting Started with Contract Management White Paper (281) 334-6970 [email protected] www.prodagio.com Contracts play a major role in your daily interactions with clients and suppliers alike.
Is Your Schedule Correct? Common Scheduling Mistakes and How to Avoid Them
Sponsored by Is Your Schedule Correct? Common Scheduling Mistakes and How to Avoid Them Joseph A. Lukas PMP, CSM, CCP, PE White Paper 1-888-762-3683 www.pmcentersusa.com Joe Lukas & PM Centers USA, LLC
TEST PLAN OUTLINE (IEEE 829 FORMAT)
TEST PLAN OUTLINE (IEEE 829 FORMAT) 1) Test Plan Identifier 2) References 3) Introduction 4) Test Items 5) Software Risk Issues 6) Features to be Tested 7) Features not to be Tested 8) Approach 9) Item
Service Virtualization:
Service Virtualization: Reduce the time and cost to develop and test modern, composite applications Business white paper Table of contents Why you need service virtualization 3 The challenges of composite
CRUSH WHITE PAPER HOW TO BUILD A KILLER STRATEGIC ACCOUNT PLAN. The guide every salesperson needs to read before creating a strategic account plan.
CRUSH WHITE PAPER HOW TO BUILD A KILLER STRATEGIC ACCOUNT PLAN The guide every salesperson needs to read before creating a strategic account plan. CRUSH PAPER: HOW TO BUILD A KILLER STRATEGIC ACCOUNT PLAN!!
Testing, What is it Good For? Absolutely Everything!
Testing, What is it Good For? Absolutely Everything! An overview of software testing and why it s an essential step in building a good product Beth Schechner Elementool The content of this ebook is provided
Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose
1 2 Author s Preface The Medialogist s Guide to Project Time Management is developed in compliance with the 9 th semester Medialogy report The Medialogist s Guide to Project Time Management Introducing
How To Manage Project Management
CS/SWE 321 Sections -001 & -003 Software Project Management Copyright 2014 Hassan Gomaa All rights reserved. No part of this document may be reproduced in any form or by any means, without the prior written
Fundamentals of Measurements
Objective Software Project Measurements Slide 1 Fundamentals of Measurements Educational Objective: To review the fundamentals of software measurement, to illustrate that measurement plays a central role
The purpose of this course is to provide practical assistance for defining and managing project scope.
Scope Definition and Scope Management Purpose - To provide practical assistance for defining and managing project scope. This course will focus on tips for creating a scope statement rather than a step-by-step
PHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The ning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
REWARD System For Even Money Bet in Roulette By Izak Matatya
REWARD System For Even Money Bet in Roulette By Izak Matatya By even money betting we mean betting on Red or Black, High or Low, Even or Odd, because they pay 1 to 1. With the exception of the green zeros,
ADAPTING SCHEDULE ADHERENCE MEASUREMENT TO IMPROVE PERFORMANCE Product No. 10039
ADAPTING SCHEDULE ADHERENCE MEASUREMENT TO IMPROVE PERFORMANCE Adapting Schedule Adherence Measurement to Improve Performance Abstract If you are implementing schedule adherence metrics, reading this groundbreaking
APPLYING PROJECT MANAGEMENT TECHNIQUES TO QEHS
APPLYING PROJECT MANAGEMENT TECHNIQUES TO QEHS Mary F. McDonald, CQA President/Principal Consultant Individual Solution Options/Quality Services (ISO/QS), Inc. Austin, TX 78739 Tel: (512) 282-0181 E-mail:
Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa
Project Creation and Gantt Chart Design Using Microsoft Project R. Baker The University of Tampa What is Microsoft Project? Microsoft Project is a software package designed help managers manage a variety
How to Select and Implement an ERP System
How to Select and Implement an ERP System Prepared by 180 Systems Written by Michael Burns 180 Systems WHAT IS ERP?... 3 ANALYSIS... 4 VENDOR SELECTION... 6 VENDOR DEMONSTRATIONS... 8 REFERENCE CALLS...
The ROI of Test Automation
The ROI of Test Automation by Michael Kelly www.michaeldkelly.com Introduction With the exception of my first project team out of college, in every project team since, I ve had to explain either what automated
Smarter Balanced Assessment Consortium. Recommendation
Smarter Balanced Assessment Consortium Recommendation Smarter Balanced Quality Assurance Approach Recommendation for the Smarter Balanced Assessment Consortium 20 July 2012 Summary When this document was
PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited
PROJECT TIME MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT WHAT DOES THE TIME MANAGEMENT AREA ATTAIN? Manages the project schedule to ensure timely completion of
Work Breakdown Structure (WBS) Emanuele Della Valle http://emanueledellavalle.org
Planning and Managing Software Projects 2011-12 Class 7 Work Breakdown Structure (WBS) Emanuele Della Valle http://emanueledellavalle.org Credits 2 This slides are largely based on Prof. John Musser class
WBS, Estimation and Scheduling. Adapted from slides by John Musser
WBS, Estimation and Scheduling Adapted from slides by John Musser 1 Today Work Breakdown Structures (WBS) Estimation Network Fundamentals PERT & CPM Techniques Gantt Charts 2 Estimation Predictions are
Learning Objectives. Learning Objectives (continued) Importance of Project Schedules
Chapter 6: Project Time Management Information Technology Project Management, Fifth Edition Learning Objectives Understand the importance of project schedules and good project time management Define activities
Managing Successful Software Development Projects Mike Thibado 12/28/05
Managing Successful Software Development Projects Mike Thibado 12/28/05 Copyright 2006, Ambient Consulting Table of Contents EXECUTIVE OVERVIEW...3 STATEMENT OF WORK DOCUMENT...4 REQUIREMENTS CHANGE PROCEDURE...5
THE THREE ASPECTS OF SOFTWARE QUALITY: FUNCTIONAL, STRUCTURAL, AND PROCESS
David Chappell THE THREE ASPECTS OF SOFTWARE QUALITY: FUNCTIONAL, STRUCTURAL, AND PROCESS Sponsored by Microsoft Corporation Our world runs on software. Every business depends on it, every mobile phone
Introduction to Software Engineering. 9. Project Management
Introduction to Software Engineering 9. Project Management Roadmap > Risk management > Scoping and estimation > Planning and scheduling > Dealing with delays > Staffing, directing, teamwork 2 Literature
Topics. Project plan development. The theme. Planning documents. Sections in a typical project plan. Maciaszek, Liong - PSE Chapter 4
MACIASZEK, L.A. and LIONG, B.L. (2005): Practical Software Engineering. A Case Study Approach Addison Wesley, Harlow England, 864p. ISBN: 0 321 20465 4 Chapter 4 Software Project Planning and Tracking
Project Knowledge Areas
From Houston S: The Project Manager s Guide to Health Information Technology Implementation. Chicago: HIMSS; 2011; pp 27 39. This book is available on the HIMSS online bookstore at www. himss.org/store.
The Performance Marketer s Guide to Email Marketing: Engaging Your Subscribers
Fluent 2016 Page 5 The Performance Marketer s Guide to Email Marketing: Engaging Your Subscribers You ve cleared the initial hurdle of acquiring new prospects for your email marketing campaigns, but now
Basic Project Management & Planning
Basic Project Management & Planning Dr. David K. Potter Director & Don Pether Chair in Engineering and Management [email protected] 1 What is Project Management? A set of principles, methods, tools, and
Lecture 6: Project Time Management By: Prof. Lili Saghafi. Information Technology Project Management, Fifth Edition
Lecture 6: Project Time Management By: Prof. Lili Saghafi Information Technology Project Management, Fifth Edition Learning Objectives 2 Understand the importance of project schedules and good project
SharePoint Project Management: The Key to Successful User Adoption
SharePoint Project Management: The Key to Successful User Adoption Leanne M. Bateman, PMP February 2012 Leanne Bateman, 2012. All rights reserved. Table of Contents ABSTRACT... 3 ABOUT THE AUTHOR... 3
PHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The Planning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
Chapter 11 Project Management
Chapter 11 Project Management Managing and Using Information Systems: A Strategic Approach by Keri Pearlson & Carol Saunders Introduction What are the elements of a good project? Why do so many IT projects
Top 5 Mistakes Made with Inventory Management for Online Stores
Top 5 Mistakes Made with Inventory Management for Online Stores For any product you sell, you have an inventory. And whether that inventory fills dozens of warehouses across the country, or is simply stacked
Work Breakdown Structure (WBS)
Work Breakdown Structure (WBS) The building blocks of a schedule start with a Work Breakdown Structure (WBS). The WBS is a hierarchical reflection of all the work in the project in terms of deliverables.
Software Project Management Part 2: Work Breakdown Structures
Software Project Management Part 2: Work Breakdown Structures Introduction into Software Engineering Lecture 20 Bernd Bruegge Applied Software Engineering Technische Universitaet Muenchen 1 Where are we?
ZCorum s Ask a Broadband Expert Series:
s Ask a Broadband Expert Series: The Advantages of Network Virtualization An Interview with Peter Olivia, Director of Systems Engineering ZCorum 1.800.909.9441 4501 North Point Parkway, Suite 125 Alpharetta,
Agile Power Tools. Author: Damon Poole, Chief Technology Officer
Agile Power Tools Best Practices of Agile Tool Users Author: Damon Poole, Chief Technology Officer Best Practices of Agile Tool Users You ve decided to transition to Agile development. Everybody has been
9 Keys to Effectively Managing Software Projects
9 Keys to Effectively Managing Software Projects Introduction Can managing software development be as simple as reading a brief to-do/not-to-do list? No. All evidence indicates that software development
OUTSOURCING PRODUCTION SUPPORT
WHITE PAPER Managed Global Software Teams OUTSOURCING PRODUCTION SUPPORT How to Engage a Remote Team with Minimum Risk THE SITUATION You re slammed. The list of projects and requests keeps growing. You
PROJECT RISK MANAGEMENT
PROJECT RISK MANAGEMENT DEFINITION OF A RISK OR RISK EVENT: A discrete occurrence that may affect the project for good or bad. DEFINITION OF A PROBLEM OR UNCERTAINTY: An uncommon state of nature, characterized
Rolling Wave Planning: Manage Projects Without Going Under
Rolling Wave Planning: Manage Projects Without Going Under Rolling Wave Planning: Manage Projects Without Going Under W. Charles Slaven MBA PMP CSSBB CPA (inactive) Director, Lean Deployment and Continuous
Project Management Guidebook
METHOD 12 3 empowering managers to succeed Project Management Guidebook ISBN 0-473-10445-8 A bout this e-book This e-book was created by Method123 (see www.method123.com) to help provide you with a simple
How to Study Mathematics Written by Paul Dawkins
How to Study Mathematics Written by Paul Dawkins Before I get into the tips for how to study math let me first say that everyone studies differently and there is no one right way to study for a math class.
Introduction to Project Management ECE 480. Erik Goodman
Introduction to Project Management ECE 480 Erik Goodman What is Project Management? a method for organizing tasks a structured framework to help a group work productively tools to aid in task sequencing,
Involve-Project Manager
Involve-Project Manager This article will describe: What is Project Management Why is Project Management so important to community and voluntary organisations The Key Phases of Project Management: o Initiation
CHAPTER 3: MANAGING IMPLEMENTATION PROJECTS
Chapter 3: Managing Implementation Projects CHAPTER 3: MANAGING IMPLEMENTATION PROJECTS Objectives Introduction The objectives are: Describe common problems that occur in implementation projects. Describe
Adapted from slides by John Musser
Adapted from slides by John Musser 1 What s the difference? Plan Identify activities. No specific start and end dates. Estimate Determine the size and duration of activities. Schedule Add specific start
Would You Like To Earn $1000 s With The Click Of A Button?
Would You Like To Earn $1000 s With The Click Of A Button? (Follow these easy step by step instructions and you will) This Version of the ebook is for all countries other than the USA. If you need the
ECDL. European Computer Driving Licence. Project Planning Project Management Software BCS ITQ Level 2. Syllabus Version 1.0
ECDL European Computer Driving Licence Project Planning Project Management Software BCS ITQ Level 2 Using Microsoft Project 2013 Syllabus Version 1.0 This training, which has been approved by BCS, The
SPECIFICATION BY EXAMPLE. Gojko Adzic. How successful teams deliver the right software. MANNING Shelter Island
SPECIFICATION BY EXAMPLE How successful teams deliver the right software Gojko Adzic MANNING Shelter Island Brief Contents 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Preface xiii Acknowledgments xxii
PMP Exam Preparation Answer Key
Chapter 2 Answers 1) d) They are all of equal importance unless otherwise stated The Triple Constraint of Project Management is that Scope, Time, and Cost are all equal unless otherwise defined as such.
Schedule Risk Analysis Simplified 1 by David T. Hulett, Ph.D.
Schedule Risk Analysis Simplified 1 by David T. Hulett, Ph.D. Critical Path Method Scheduling - Some Important Reservations The critical path method (CPM) of scheduling a project is a key tool for project
Identifying and Managing Project Risk, Second Edition 2008 Tom Kendrick. The PERIL Database
The PERIL Database Good project management is based on experience. Fortunately, the experience and pain need not all be personal; you can also learn from the experience of others, avoiding the aggravation
INTRODUCTION TO PROJECT MANAGEMENT
INTRODUCTION TO PROJECT MANAGEMENT OVERVIEW The purpose of presentation is to provide leaders and team members of projects, committees or task forces with advanced techniques and practical skills for initiating,
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE Table of Contents Introduction...3-1 Overview...3-1 The Process and the Project Plan...3-1 Project Objectives and Scope...3-1 Work Breakdown Structure...3-1