CASE STUDY - OVERHEAD COSTS ANALYSIS
|
|
|
- Alisha Mason
- 10 years ago
- Views:
Transcription
1 CASE STUDY - OVERHEAD COSTS ANALYSIS Yong-Woo Kim 1 and Glenn Ballard 2 ABSTRACT Construction projects become complicated and fragmented so that many specialty contractors are involved. In such changed environments, a general contractor s overhead costs are increasing comparable to direct costs. In addition to an increase of volume, activities consisting of overhead costs play an important role in coordinating different participants who include different specialty contractors and client. This paper reviews traditional overhead control and critiques problems thereof through literature review, interviews with professionals, and data collection. It proposes a new overhead cost control method, called profit-point analysis (PPA) applying activitybased costing (ABC). It is followed by a case study presented to exemplify the new method. KEY WORDS Construction overhead costs, activity-based costing (ABC), profit point analysis (PPA), nurturing relationship 1 2 Ph. D. Candidate at University of California at Berkeley, [email protected] Research Director at Lean Construction Institute (LCI) and Associate Adjunct Professor at University of California at Berkeley, [email protected]
2 Yong-Woo Kim and Glenn Ballard 2 INTRODUCTION Construction projects become complicated and fragmented so that many specialty contractors are involved. In such altered environments, a general contractor s overhead costs increase comparable to direct costs. In addition to the increase of volume, activities contributed to overhead costs play an important role in coordinating different participants that include different specialty contractors and client. However, the construction industry has not changed the method of controlling overhead costs in construction projects. Traditionally, construction overhead uses resource-based costing and volume-based allocation (Kim and Ballard 2001, Holland and Hobson 1999). Resource-based costing is the method in which costs are assigned by each resource, and volume-based allocation is the method of cost allocation in which costs are allocated to cost objects in accordance with the volume of direct labor hours, direct labor costs or contract amount. This paper criticizes the traditional overhead costing in construction projects and proposes a new costing method as an application of activity-based costing. It is followed a case study to exemplify the new method. The study is confined to the perspectives of a general contractor, who is subcontracting most works. It is noted that numbers regarding a case study are modified because they are confidential to a company. PROBLEMS IN TRADITIONAL OVERHEAD COSTING The current method of overhead costing would result in the following problems: COST DISTORTION HINDERS PROFITABILITY ANALYSIS Construction projects have different cost codes for each resource such as project engineer or manager. They treat overhead costs separately and do not assign overhead costs to work divisions such as earthwork or to participants such as subcontractors. However, they assign overhead costs to work divisions in proportion to direct labor hours or direct labor costs when owners request the assignment of overhead costs (Sommer 2001). Such volume-based allocation results in cost distortion (Cokins 1996, Johnson and Kaplan 1987, Horngren et al. 1999). The problem of current practice regarding overhead assignment is that companies do not know real costs for each work division and those for each participants such as subcontractors because either they do not assign overhead costs or they use a uniform cost driver (i.e., direct labor costs) for assignment of overhead costs. Therefore, it is difficult to find where money is being made and lost because progress payments for each work division or building from clients contain overhead costs. In other words managements have difficulty in doing a profitability analysis. LITTLE MANAGEMENT ATTENTION TO ACTIVITIES OR PROCESSES OF EMPLOYEES Little management attention is paid to activities or processes since every cost is assigned and reported resource by resource. In other words, little management attention is paid to supporting activities. As a result, managements do not have information on how much resources and what services are provided to participants such as subcontractors. It does not help nurture relationships with the subcontractors.
3 Case Study - overhead costs analysis 3 PROFIT POINT ANALYSIS This study adopts activity-based accounting (ABC) tool because activity-based costing has been advocated as a means of overcoming the systematic distortions of traditional cost accounting and of bringing relevance back to managerial accounting. It is necessary to review activity-based costing because the proposed method is based on activity-based costing ACTIVITY-BASED COSTING Traditional cost accounting has been criticized for cost distortion and the lack of relevance during the last 20 years (Johnson and Kaplan 1987). A traditional system reports where and by whom money is spent on, but fails to report the cost of activities and processes (Miller 1996). Many organizations, including petroleum and semiconductor companies in the manufacturing industry, have adopted the new costing method, activitybased costing (ABC). There are two purposes of activity-based costing. The first is to prevent cost distortion. Cost distortion occurs because traditional costing combines all indirect costs into a single cost pool. This pool is allocated on the basis of some resource common to all of the company s products, typically direct labor. Cost distortion is prevented in ABC by adopting multiple cost pools (activities) and cost drivers. The second purpose is to minimize waste or non-value-adding activities by providing a process view. This objective can be achieved by activity analysis and (or) the function of monitoring activities. PROFIT POINT This study assumes that contracts between a client and a general contractor, and between a general contractor and subcontractors are fixed cost-based contracts. Suppose there is a general contractor who is using 100% outsourcing (specialty contracting) in performing a project. Project management costs under the assumed condition depend largely on how to manage different subcontractors, each of which performing one or a few work division(s). The suggested overhead costs analysis method would determine the costs (especially, management costs) at each point (we call it profit point ) where a company and subcontractors are interfaced. This would result in revealing the flow of costs and profits. A profit point is the point where organic relations between the participants are met, rather than neglected. It is noted, though, that the proposed cost analysis model does not take into account the relationship between subcontractors. PROFIT POINT ANALYSIS Profitability information compiles from a company s management activities, which will be collected at profit points in a construction site by using an activity form. Then the result of activity analysis is applied to multiple cost objects. In our model, management areas, work divisions / participants, and facilities are regarded as cost objects. Figure 1 shows a three-dimensional cost object in our model from the perspective of a project.
4 Yong-Woo Kim and Glenn Ballard 4 Subcontractors (Work Divisions) XYZ Contractor DEF Contractor ABC Contractor Quality Control Safety costs Scheduling Bldg #1 Bldg #2 Bldg #3 Bldg #4 Facilities Figure 1: Multiple Cost Objects In addition to cost information for work divisions, costs for each management area will also be known. It would give a company insight into the relationship between a company and its subcontractors because management areas such as safety control are the core of a company s business activities in a project. On the other hand, current accounting systems put every cost information to cost accounts which combine profit points. It might result in preventing a company from understanding the relationship with subcontractors. A case study was performed to find the usefulness and limitations of this analysis, which is discussed in the following section. CASE STUDY SUN MICROSYSTEMS PROJECT PHASE III PURPOSES There are three purposes of this case study, which are as follows: The case study is to test the feasibility of PPA (profit point analysis), The case study is performed to explore difficulties / limitations of implementation, and The case study is implemented to find usefulness of PPA results. METHODS AND PROCEDURES The case study lets each employee use the new method and collect data from employees. For the purpose of data collection, a database is made using Microsoft Access As a way to test and validate the new method, a set of information that the new method creates will be presented to several professionals. Then, professionals and researchers will be able to implement a qualitative analysis for evaluating the new method. There are six sequential procedures to meet the purpose of this case study, which are as follows: The first step is to identify the current practice with which overhead costs are controlled in the project. In this step we use document collection and interviews with a project manager.
5 Case Study - overhead costs analysis 5 The next step is to identify the drawbacks that our research is trying to solve with the tool (PPA) to be tested. Then as a consultant we give instructions and explanations regarding PPA tool to case study participants. Activity forms are to be distributed to participants and participants are required to fill out the forms (Data Collection). Data analysis using different queries in MS Access 2000 The results are discussed with participants, and participants are interviewed on difficulties and improvement areas, etc. (Qualitative Analysis) PROJECT BACKGROUND The project selected for the case study is Sun Microsystems Phase IIIA located in Newark, CA. Sun Microsystems is one of the leading providers of industrial-strength hardware and services that power the network. The project is to build the office and laboratory center for the client, Sun Microsystems, Inc. Phase IIIA project includes fully completing the three office and laboratory buildings (Building #18, 19, and 20) and all site works. Construction of the three other buildings (Building #21, 22, and 23) will follow this Phase IIIA. This project is a lump-sum contract and partial Design-Build project in which a contractor, DPR, Inc., is in charge of designing MEP (Mechanical, Electrical, and Plumbing) portions while a separate designer for civil works, KMD, is hired by a client. It is a 18-month project (Nov May 2002). The value of change orders is much greater than the original base construction contract values 3. It is due to the fact that the design was not completed at the time of contract. Note that numbers on tables are modified because they are confidential. Results1. Problem Identification The characteristics of current practice in controlling overhead costs are described as follows: Costs are assigned directly to accounts which are resources (employees). Project overhead costs are not distributed or allocated to different cost objects such as specialty contractors or work divisions. Home office overhead costs are allocated to projects based on the amount of contract. (This information is acquired from the interview with a cost engineer at DPR head office) The following problems are identified through discussion with managements: Even though in altered environments overhead costs have become more important than before, the management of overhead costs, costs for nonproduction sector, has not been given enough attention. As a result, the function of supporting activities has also not been given enough attention. 3 The contract amount is not shown in the paper by request of DPR.
6 Yong-Woo Kim and Glenn Ballard 6 Since the current volume-based allocation of overhead costs does not provide accurate allocation to cost objects such as projects or work divisions, the company hardly gets accurate information on profit relationships with clients and specialty-contractors. The cost reports on overhead costs include information on costs for each resources, but lack information on relationship with other project participants such as clients or specialty-contractors. Results 2. Cost Objects Three different types of cost objects are set up for the case study: activities, management areas, and work divisions. First, the resources are assigned to activities. Then activities are allocated to two other cost objects. Activities: There are sixteen activities identified via interviews with key personnel. mpower is defined as the activity that generates the internal cost accounting system, called mpower. Postnslipsheetdrawing is defined as the activity that is to post and slip the sheets of drawing. Regularreport is defined as the activity that generates weekly and monthly reports to head office and client. RFI represents the activity related to receiving, processing, and generating RFI (Request For Information). The activity list shown in Table 1, however, includes the mix of generators of activities and activities themselves. For example, change order, safety, and schedules are the results of activities, which include multi activities such as calls and meeting. Table 1: Activity List Table 2: List No Activity 1 Calls 2 Changeorder 3 Correspondence 4 Deliveries 5 Drawingreview 6 Fieldsupervise 7 Meeting 8 mpower 9 Postslipsheetdrawing 10 Pricing 11 Punchlist 12 Regularreport 13 RFI 14 Safety 15 Schedule 16 Submittals No. AreaSequence 1 Coordination 2 Cost 3 Humanresource 4 Leadership 5 Procurement 6 Quality 7 Safety 8 Scope 9 Time 10 Training 11 Etc : First, we set up eight project management functions as indicated in PMBOK (1996). Then we expanded management functions (areas) to eleven (11) management areas or functions including one undefined category. AreaSequenceCoordination is defined as a management area relating to coordinating the sequence of operations and area interventions. It is closely related to Time management but the management area of Time management in this case study is confined to updating the master and 3-week look-ahead schedule. Note that Safety is contained in both activity list and management area list.
7 Case Study - overhead costs analysis 7 Work Division: Another cost object group, work division, indicates the scope of work of the project such as earthwork, electrical, or HVAC. Through discussions with key personnel, we created twenty-five (25) work divisions including one open division. Admin in Table 3 is defined as a group of activities relating to work division of an administration. With Whom: We are concerned about the party with whom DPR resources (overhead) are consumed. This cost object group is called With Whom and its costs are called dealing costs. The list in Table 4 shows the names of subcontractors, architects, and client. Table 3: Work Division List No Work Division No Work Division 1 Admin 14 HVAC 2 CeramicTile 15 Landscape 3 CIPconcrete 16 LandscapeGate 4 CoilingDoor 17 Metals 5 Concrete 18 Painting 6 Door 19 Plumb 7 Drywall 20 RoofInsulation 8 EarthGrade 21 Scaffold 9 Electrical 22 Sprinkler 10 Elevator 23 StrSteel 11 Excavation 24 Taping 12 General 25 Etc 13 Glazing Table 4: With Whom List No With Whom No With Whom 1 ACCO 15 Jacob 2 AFCO 16 KMD 3 AlamioSteel 17 Lescure 4 AlcalRoofing 18 Meddco 5 AnningJohn 19 Newcon 6 Bagatelos 20 OCJohnes 7 CooksonDoor 21 Otis 8 COPaint 22 Peputable 9 DHS 23 Rosendin 10 Doyle 24 ShooterButts 11 DPR 25 Sun 12 DPRdrytape 26 SuperSprinkler 13 General 27 Etc 14 GoldenBay Results 3. Data Analysis The following results come from using different queries.
8 Yong-Woo Kim and Glenn Ballard 8 Table 5: Activity Costs No Activity Activity Costs ($) Percentage 1 Calls $ 4, % 2 Changeorder $ 3, % 3 Correspondence $ 6, % 4 Deliveries $ % 5 Drawingreview $ % 6 Fieldsupervise $ 3, % 7 Meeting $ 6, % 8 mp ower $ 1, % 9 Postslipsheetdrawing $ % 10 Pricing $ % 11 P unchlist $ % 12 Regularreport $ % 13 RFI $ % 14 Safety $ % 15 Schedule $ % 16 Submittals $ 2, % Total $ 29, % Table 5 shows that meeting and correspondence are major activities, which consume most overhead resources. Table 6: Costs No. Costs ($) Percentage (%) 1 AreaSequence Coordination $ % 2 Cost $ 7, % 3 Humanresource $ % 4 Leadership $ % 5 P rocurement $ 2, % 6 Quality $ 3, % 7 Safety $ % 8 Scope $ 8, % 9 Time $ 1, % 10 Training $ 1, % 11 Etc $ 1, % Total $ 29, % It is unusual for the scope management to amount to 28 %, and it is due to the peculiarity of the project. Since the drawing is not fixed, DPR should reallocate every scope of work when new drawings come out even though there is a written contract.
9 Case Study - overhead costs analysis 9 Table 7: Work Division Costs Table 8: Dealing Costs Work Division Work Division Costs ($) Percentage Admin $ 15% CeramicTil $ 1% CIPconcrete 401 $ 58 1% CoilingDoor 28 $ 80 1% Concrete $ 1% Door $ 5% Drywall $ 2% EarthGrade 4$ 4 3% Electrical $ 12% Elevator $ 0% Excavation $ 0% General $ 35% Glazing $ 0% HVAC $ 7% Landscape $ 1% LandscapeGate $ 2% Metals $ 5% Painting $ 1% Plumb $ 0% RoofInsulation 94 $ 16 0% Scaffold 49 $ 03 0% Sprinkler $ 0% StrSteel $ 0% Taping $ 0% Etc 21 $ 09 7% Total $ 29, % With Whom Costs ($) Percentage ACCO $ 1, % AFCO $ % A lamiosteel $ % AlcalRoofing $ % AnningJohn $ % Bagatelos $ % CooksonDoor $ % COPaint $ % D HS $ % Doyle $ % DPR $ 6, % DPRdrytape $ % General $ 5, % G oldenbay $ % Jacob $ 2, % KMD $ 1, % Lescure $ % Meddco $ 1, % N ewcon $ % O CJohnes $ % Otis $ % Peputable $ % Rosendin $ 2, % ShooterButts $ % Sun $ 1, % SuperSprinkler $ % Etc $ 2, % Total $ 29, % Overhead costs for ACCO and Rosendin are analyzed in Tables 9 to 12 since they are the major subcontractors consuming most of overhead resources of DPR as shown in Table 8. Table 9: Activity Costs for ACCO Table 10: Costs for ACCO Activity Activity Costs Percentage Calls $ % Chageorder $ % Correspondence $ % Drawingreview $ % Fieldsupervise $ % Meeting $ % mpower $ % Etc $ - 0% Total $ 1, % Cost for ACCO ($) Percentage AreaSequenceCoordination $ % Cost $ % Quality $ % Scope $ % Time $ % Etc $ % Total $ 1, %
10 Yong-Woo Kim and Glenn Ballard 10 Table 11: Activity Costs for Resendin Table 12: Costs for Rosendin Activity Activity Costs for Rosendin ($) Percentage Calls $ % Changeorder $ % Correspondence $ % Drawingreview $ % Fieldsupervise $ 1, % Meeting $ % Punchlist $ % RFI $ % Schedule $ % Submittals $ % Costs for Rosendin Percentage AreaSequence Coordination $ % Cost $ % Procurement $ % Quality $ % Scope $ % Time $ % Etc $ - 0% Total $ 2, % Etc $ - 0% Total $ 2, % Results 4. Time Consumed for New Cost Analysis Tool Five participants answered the question on required time for this new tool. The average duration was 10.8 min. Discussion with participants revealed that the new tool (activity analysis) did not give additional burden on employees psychologically. Results 5. Positives of New Cost Analysis Tool For identifying the positives of this tool, a researcher explained the output data (Table 5 to Table 12). Then a meeting was held for discussing the advantages and limitations of this tool, the results of which are discussed in this and the following section. The positives are as follows: [1] Data will be used for evaluation of subcontractors who are providing similar services for a general contractor under similar project conditions. The data can be used for future subcontractor selection. Under similar project condition, the ratio of subcontract amount to the overhead costs can be an indicator. However, analysis of components consisting of overhead costs compared with others provides more meaningful indicators than the ratio comparison. Suppose that one electrical subcontractor working with DPR under similar project has PPA results as below.
11 Case Study - overhead costs analysis 11 Table 13: Average Costs for Contractor A Under Similar Condition Costs for Aother Electical Contractor ($) Percentage (%) AreaSequence Coordination $ % Cost $ % Procurement $ % Quality $ 1, % Scope $ % Time $ % Etc $ - 0% Total $ 3, % Comparing Table 13 with Table 12 would give an idea as to performance of Rosendin as follows: Suppose the monthly average subcontract amount (direct costs) of contractor A is $97,000 and that of Rosendin is $108,000. The ratios of direct costs to overhead costs (personnel costs only) are as follows: Table 14: Comparison of ratio of direct costs to overhead costs Contractors Monthly Direct Costs Monthly Overhead Ratio Rosendin $ 108, $ 2, % Contractor "A" $ 97, $ 3, % The contractor A requires more overhead resources than Rosendin under the assumption that project conditions are almost identical. [2] PPA results would give the management the insight into the performance of subcontractor if components were analyzed. The comparison of two PPA results (Table 12 and Table 13) would tell the management that contractor A requires more resources on procurement than Rosendin. It would trigger exploration into the reason. The investigation, for example, would reveal that contractor A submitted submittals, which do not include the details of suppliers, which make it necessary for DPR personnel to get additional information. Such change of manner in which procurement submittal is made would reduce DPR resource input for procurement. The PPA results, as seen in the scenario, would pinpoint the area to be investigated for improving the profitability relationship. [3] The detailed cost data resulting from this analysis will be used for fee negotiation for an additional work. With traditional overhead costs reporting overhead costs for additional work scope is usually determined by the ratio of direct costs to the overhead cost for the entire project. [4] The fact that employees are required to fill out activity forms forces them to work more efficiently.
12 Yong-Woo Kim and Glenn Ballard 12 [5] The data will be used to convince clients to select a specific subcontractor especially when clients have different preferences in selecting specialty contractors rather than a general contractor. [6] The data would be used for bidding the future project using specific subcontractors since they can have more specific cost data for each subcontractor. Results 6. Limitations or Area for Improvement The following problems were identified through discussions with participants. [1] Even though the performance of a specialty contractor does not change, overhead costs might differ depending on the personnel in charge. A project manager who interviewed the authors mentioned that if an experienced HVAC coordinator was replaced by a less experienced one, the overhead costs would increase. Therefore one strong assumption for PPA analysis is that salary or wage reflects the experience and ability of personnel. For example, $2,000 salary scheduler is twice as efficient as $1,000 salary scheduler. [2] One activity such as phone calling can be involved with several management areas. In our study, 10 min is assumed to be dedicated to quality and 10 min to procurement in case a 20 minutes phone call is made for quality and procurement. [3] Several costs objects overlap. The form itself is problematic. Some participants, for example, indicated that area sequence and scheduling are somewhat superimposed. [4] There are environmental factors that partially determine the level of efforts required in the work of construction management staff. Among these factors quality in documentation is very important. Other factors are not examined in this case study. CONCLUSION This paper described the new overhead cost analysis tool and the results of the case study under the situation where most works are subcontracted. Multi-cost objects is one of characteristics of the tool. A case study revealed that the new analysis is feasible on actual construction projects and has many positives with some limitations. It is noted that the proposed method can be applied in the same manner to analysis of home office overhead costs to be allocated to multi projects. Important is that the new tool can pinpoint the area to be investigated for improving the profitability relationship. It can be construed as a tool for nurturing relationship as opposed to having a quantitative target as a motivation. ACKNOWLEDGEMENTS The authors gratefully acknowledge the contribution of the DPR, Inc and its participants in the case study project for the invaluable input into this paper by courageously implementing the new method to a real project. REFERENCES Cokins, G. (1996). Activity-based cost management making it work: a manager's guide to implementing and sustaining an effective ABC system, Irwin Professional Publishing, Burr Ridge, IL. Holland, N. and Hobson, D. (1999). Indirect cost categorization and allocation by construction contractors. Journal of Architectural Engineering, ASCE, 5(2)
13 Case Study - overhead costs analysis 13 Horngren, C.Y., Foster, G. and Datar, S. M. (1999). Cost Accounting, 10 th edition, Prentice Hall, Upper Saddle River, NJ, 906pp. Johnson, T. and Kaplan, R. (1987). Rise and Fall of Management Accounting. Management Accounting, IMA, January, Kim, Y. and Ballard, G. (2001). Activity-Based Costing and its Application to Lean Construction, Proceedings of the 9th Annual Conference of the International Group for Lean Construction, Singapore. Miller, J. A. (1996). Implementing activity-based management in daily operations, John Wiley & Sons, New York, NY. Sommer, B. (2001). Personal Communication, DPR Construction, Inc., Redwood City, CA.
NOTICE TO CONTRACTORS
NOTICE TO CONTRACTORS Notice is hereby given that San Luis Obispo County Community College District, ( District ) is accepting sealed Informal Bidding Prequalification Applications and Formal Bidding Prequalification
ST. MONICA FOOD PANTRY HOUSTON, TEXAS
PROJECT MANUAL FOR ST. MONICA FOOD PANTRY HOUSTON, TEXAS OWNER: ST. MONICA CATHOLIC CHURCH 8421 W. MONTGOMERY ROAD HOUSTON, TEXAS 77088 ARCHITECT: C SIX ARCHITECTURE, LLC 4606 F.M. 1960 WEST, STE 400 HOUSTON,
Linbeck Construction used the Last Planner system of production control on a $22 million remodel of the Chemistry Building at Rice University.
Linbeck Construction used the Last Planner system of production control on a $22 million remodel of the Chemistry Building at Rice University. This was one of four innovative practices was described by
Dynamic Change Management for Fast-tracking Construction Projects
Dynamic Change Management for Fast-tracking Construction Projects by Moonseo Park 1 ABSTRACT: Uncertainties make construction dynamic and unstable, mostly by creating non value-adding change iterations
MANAGEMENT ACCOUNTING AND CONTROL
MANAGEMENT ACCOUNTING AND CONTROL TIMETABLE: Monday, 12:00-13:30 Wednesday, 8:30-10:00 Friday, 8:30-10:00 Aim of the Course The purpose of management control processes is to carry out the strategies arrived
Teaching Special Decisions In A Lean Accounting Environment Daniel Haskin, University of Central Oklahoma, USA
Teaching Special Decisions In A Lean Accounting Environment Daniel Haskin, University of Central Oklahoma, USA ABSTRACT Lean accounting has become increasingly important as more and more companies adopt
TRADITIONAL VERSUS ACTIVITY-BASED PRODUCT COSTING METHODS: A FIELD STUDY IN A DEFENSE ELECTRONICS MANUFACTURING COMPANY
TRADITIONAL VERSUS ACTIVITY-BASED PRODUCT COSTING METHODS: A FIELD STUDY IN A DEFENSE ELECTRONICS MANUFACTURING COMPANY Myers, Joan K. Le Moyne College [email protected] ABSTRACT Organizational environments,
School Construction Projects
The process of educating young people seems to be continually developing. New insights regarding how students most effectively receive retain and gain understanding of information and principles affect
INTERNAL CONTROL MATRIX FOR AUDIT OF ESTIMATING SYSTEM CONTROLS Version No. 3.2 June 2006. 31-d Page 1 of 7
INTERNAL CONTROL MATRIX FOR AUDIT OF ESTIMATING SYSTEM CONTROLS Version No. 3.2 June 2006 Control Objectives Example Control Activities Audit Procedures 1. INTERNAL AUDITS Management should periodically
AC 2012-3090: THE METHOD OF COVERING MEP SCOPE IN AN ESTI- MATING COURSE
AC 2012-3090: THE METHOD OF COVERING MEP SCOPE IN AN ESTI- MATING COURSE Dr. Suat Gunhan, University of Texas, San Antonio Suat Gunhan received both his bachelor s of architecture and master s of science
Marketing Coordinator Bootcamp Session 2: ABCs of AEC
Marketing Coordinator Bootcamp Session 2: ABCs of AEC Debbie Chen, LEED AP, APMP CF Proposal Development Director Louis Berger [email protected] Matthew Daw, PE, LEED AP Principal Keast & Hood [email protected]
REAL-TIME SUPPLY CHAIN MANAGEMENT USING VIRTUAL DESIGN AND CONSTRUCTION AND LEAN
212 REAL-TIME SUPPLY CHAIN MANAGEMENT USING VIRTUAL DESIGN AND CONSTRUCTION AND LEAN ABSTRACT Sangwoo Cho 1 and Martin Fischer 2 Supply chain management in construction has evolved in response to various
CSTM 102 Spring 2013. Construction Documents to Contract Documents
CSTM 102 Spring 2013 Construction Documents to Contract Documents The Construction Industry THE PROJECT TEAM A Project and a Client A Designer Constructors THE GAME PLAN Risk Management Scope of Work The
Bidding and the California Uniform Public Construction Cost Accounting Act (CUPCCAA ) Everything You Need to Know
Bidding and the California Uniform Public Construction Cost Accounting Act (CUPCCAA ) Everything You Need to Know June 24, 2014 Sacramento, CA June 27, 2014 Ontario, CA Guiselle Carreon Commissioner, California
REQUEST FOR PROPOSALS (RFP) - Construction Management Services. Germantown School District Office
REQUEST FOR PROPOSALS (RFP) - Construction Management Services From: Germantown School District Project: Germantown School District Addition & Renovations to Rockfield Elementary School N132 W18473 Rockfield
How To Understand Cost Volume Profit Analysis
Course Title: Cost Accounting for Decision Making Professional Development Programme on Enriching Knowledge of the Business, Accounting and Financial Studies (BAFS) Curriculum 1 Learning
FINANCIAL STATEMENTS AND RATIO ANALYSIS
In following we will be demonstrating the use of ratios to help examine the health of a firm. Ratios allow managers evaluate to a firm's financial statements in order to point out the strengths and weaknesses
Assistant Project Management - Training Program A 3-year Program Beginning strategy places the new employee into a three-year program that provides
Assistant Project Management - Training Program A 3-year Program Beginning strategy places the new employee into a three-year program that provides for experience in the Construction Company's three areas
WORKPLAN: DATABASE FOR WORK PACKAGE PRODUCTION SCHEDULING
WorkPlan: Database for Work Package Production Scheduling WORKPLAN: DATABASE FOR WORK PACKAGE PRODUCTION SCHEDULING Hyun Jeong Choo 1, Iris D. Tommelein 2, Glenn Ballard 3, and Todd R. Zabelle 4 ABSTRACT
SECTION 01 32 00 - PROJECT PLANNING AND SCHEDULING PART 1: GENERAL 1.1 DEFINITIONS
SECTION 01 32 00 - PROJECT PLANNING AND SCHEDULING PART 1: GENERAL 1.1 DEFINITIONS A. The term Baseline Schedule, as used throughout the contract documents, shall refer to a fixed projection of the project
CASH-FLOW SIMULATION GAME FOR TEACHING PROJECT CASH-FLOW FORECASTING
CASH-FLOW SIMULATION GAME FOR TEACHING PROJECT CASH-FLOW FORECASTING Euysup Shim, Illinois State University; Byung-Cheol Kim, Ohio University; Seongchan Kim, Western Illinois University Abstract Having
Facilities Central Operational Rates and Charging Methodology FY13 & Base for FY14 Planning
Facilities Central Operational Rates and Charging Methodology FY13 & Base for FY14 Planning Questions please contact John Kaufhold, Director of Finance & Administration Facilities Rates: Physical Plant
PMBOK 5. Chapters. 1. Introduction What is Project Management 2. Organizational Influences and Project Life Cycle 3. Project Management Processes
PMBOK 5 Chapters PMBOK 5 1. Introduction What is Project Management 2. Organizational Influences and Project Life Cycle 3. Project Management Processes Knowledge Areas 4. Project Integration Management
Project Delivery Methods & Contract Types CSTM 102 Spring 2013
Project Delivery Methods & Contract Types CSTM 102 Spring 2013 Schedule February 16- Building Information Modeling February 21- Midterm Review February 23- Midterm In the industry the term Pre-Construction
- 1 - Cost Drivers. Product Diversity - Difference in product size, product complexity, size of batches and set-up times cause product diversity.
- 1 - Traditional Cost Accounting It arbitrarily allocates overheads to the cost objects. Total Company s overhead is allocated based on volume based measure e.g. labour hours, machine hours. Here the
Chapter 6 Cost Allocation and Activity-Based Costing
Chapter 6 Cost Allocation and Activity-Based Costing QUESTIONS 1. Indirect costs are allocated to (1) provide information for decision making, (2) reduce frivolous use of common resources, (3) encourage
1.040 Project Management
MIT OpenCourseWare http://ocw.mit.edu 1.040 Project Management Spring 2009 For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms. Project Organization Project
PASADENA AREA COMMUNITY COLLEGE DISTRICT (PACCD) 2015 California Uniform Public Construction Cost Accounting Act (CUPCCAA) Informal Bid List
PASADENA AREA COMMUNITY COLLEGE DISTRICT (PACCD) 2015 California Uniform Public Construction Cost Accounting Act (CUPCCAA) Informal Bid List At their Board meeting of August 21, 2013, the Trustees of the
Heating Ventilation, Air Conditioning and Refrigeration Associate in Applied Science Field of Study Code: HVACR.AAS.CONTRA
Heating Ventilation, Air Conditioning and Refrigeration Associate in Applied Science Field of Study Code: HVACR.AAS.CONTRA Catalog Description: The Contractor degree provides the technical and business
Abstract: BIM: A Technological Advancement in the Field of Architecture. Introduction:
BIM: A Technological Advancement in the Field of Architecture Abstract: BIM (Building Information Modeling), an innovative parametric software has seen widespread use in architecture design firms worldwide.
Time Error in Project Management: A Case Study in Yanbu, Saudi Arabia
Business and Management Studies Vol. 2, No. 1; March 2016 ISSN 2374-5916 E-ISSN 2374-5924 Published by Redfame Publishing URL: http://bms.redfame.com Time Error in Project Management: A Case Study in Yanbu,
Measuring, Estimating and Tendering Processes in Construction and the Built Environment
Unit 9: Measuring, Estimating and Tendering Processes in Construction and the Built Environment NQF Level 3: Guided learning hours: 60 BTEC National Unit abstract Estimating is concerned with the processes
James E. Bartlett, II is Assistant Professor, Department of Business Education and Office Administration, Ball State University, Muncie, Indiana.
Organizational Research: Determining Appropriate Sample Size in Survey Research James E. Bartlett, II Joe W. Kotrlik Chadwick C. Higgins The determination of sample size is a common task for many organizational
Learning Objectives. PRODUCT COSTING SYSTEMS Traditional Product Costing Systems Activity-Based Costing Systems
PRODUCT COSTING SYSTEMS Traditional Product Costing Systems Activity-Based Costing Systems Learning Objectives Learn the mechanics of product costing systems Understand cost distortions in traditional
How To Understand And Understand Activity Based Management
Technical Briefing DEVELOPING AND PROMOTING STRATEGY APRIL 2001 Activity-based Management An Overview IN THIS BRIEFING Part 1 General FAQs Part 2 Practical guidance on implementing ABM Part 3 Checklist
Stanford University Guest Lecturer, Professor s Assistant, 1999-2004 Advanced Construction Issues and Claims, Civil Engineering Department
Current Position PKR CONSULTING, INC. Founder and Chief Executive Officer, 2004 Present Provides construction consulting, dispute resolution and expert witness services to owners, contractors, subcontractors,
DESIGN IS GOOD BUSINESS
COMPENSATING YOUR ARCHITECT The creature comforts are one thing, but for a house to become a home it s got to be elevated to the point that it s about raising one s spirits as well. SAMUEL MOCKBEE Building
ISBN Proceedings of 2010 International Conference on Business, Economics and Tourism Management (CBETM 2010)
ISBN 978-1-84626-026-1 Proceedings of 2010 International Conference on Business, Economics and Tourism Management (CBETM 2010) Singapore, 26-28 February, 2010 Factors Influencing Activity-Based Costing
Audit Guide for Consulting Services Cost Rates. March 11, 2015
Audit Guide for Consulting Services Cost Rates March 11, 2015 Columbus Regional Airport Authority Audit Guide for Consulting Services Cost Rates TABLE OF CONTENTS: History... 3 Page Purpose and Objectives...
U.S. universities, U.S. community colleges
Indirect Cost Policy for Project Grants and Contracts for Applicant Organizations Definition The Bill & Melinda Gates Foundation defines indirect costs as: Overhead expenses or ongoing operational costs
Adoption and Implementation of Activity-Based Costing: A Web-Based Survey
Adoption and Implementation of Activity-Based Costing: A Web-Based Survey Narcyz Roztocki Sally M. Schultz State University of New York at New Paltz School of Business 75 South Manheim Boulevard New Paltz,
7. Do you perform any out of state work?... If yes, in what states and provide details of work performed
Applicant s Name* (*If more than one entity, attach separate sheet with description of each entity s operations, relationship to each other and ownership.) Contractors Application Agent Applicant Mailing
Introduction to Construction Project/Jobsite Management
Introduction to Construction Project/Jobsite Management Hal Johnston April 23, 2014 Professor Emeritus Construction Management California Polytechnic State University San Luis Obispo, California, US Visiting
How to Estimate the Cost of Interior Building Finishes from Schematic Drawings. CPE Candidate No. 0714108. December 2014
How to Estimate the Cost of Interior Building Finishes from Schematic Drawings CPE Candidate No. 0714108 December 2014 1 How to Estimate the Cost of Interior Building Finishes from Schematic Drawings Table
City Of Portsmouth, New Hampshire REQUEST FOR QUALIFICATIONS # 30-10 For. Construction Management Services for the
City Of Portsmouth, New Hampshire REQUEST FOR QUALIFICATIONS # 30-10 For Construction Management Services for the Renovation and Expansion of Portsmouth Middle School INVITATION The City of Portsmouth,
KIEWIT CM/GC Enabling/Utilities
South Terminal Redevelopment Program KIEWIT CM/GC Enabling/Utilities Contract Value $50 million M/WBE Goal 20 percent Contact John Todd, LEED AP Project Manager 303.930.9046 [email protected] General
Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06
SECTION 01310 CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. Construction Progress Schedule: The CONTRACTOR shall submit a detailed work progress schedule showing all work in a graphic format suitable
Introduction PURPOSE OF THIS BOOK
1 C H A P T E R Introduction PURPOSE OF THIS BOOK The purpose of this book is to enable the reader to gain fundamental knowledge of estimating the cost of projects to be constructed. Experienced estimators
GLOBAL OUTSOURCING COST MODELS
GLOBAL OUTSOURCING COST MODELS Clients and Outsourcing companies may use several engagement models both for delivery of the outsourced work and thereby arrive at the costing for the model. Choosing of
THIS AGREEMENT is made effective as of this day of in the year of.
STANDARD FORM OF CONSTRUCTION MANAGEMENT AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER (Where the basis of payment is Cost of the Work with a guaranteed maximum price) THIS AGREEMENT is made effective
Brian Lines, Ph.D. Facility Management Professional (FMP) International Facility Management Association (IFMA) Credential Program 2013
Brian Lines, Ph.D. Assistant Professor Department of Civil, Environmental and Architectural Engineering University of Kansas 1530 W. 15 th Street, 2135B Learned Hall Office: (785) 864-6503, Email: [email protected]
Q. Please provide resumes for Gary L. Murray, Sean LaCour, Glenn Samms, Trina L. Troke, Trina Cormier.
Requests for Information CA-47.0 NP NP 2007 CBA 1 2 3 4 5 6 Q. Please provide resumes for Gary L. Murray, Sean LaCour, Glenn Samms, Trina L. Troke, Trina Cormier. A. The resumes of Mr. Gary L. Murray,
Planning, Organisation and Control of Resources in Construction and the Built Environment
Unit 7: Planning, Organisation and Control of Resources in Construction and the Built Environment NQF Level 3: Guided learning hours: 60 BTEC National Unit abstract A successful project requires careful
CAREER LYNX Constructing Careers in Architecture
Students will understand the job description, skills, and education of various Architecture and Planning related jobs. Students will use the newspaper to make inferences about the role of various professionals
PRINCIPLES OF CONSTRUCTION
1 PART PRINCIPLES OF CONSTRUCTION CHAPTER 1 CHAPTER 2 CHAPTER 3 CHAPTER 4 CHAPTER 5 CHAPTER 6 CHAPTER 7 CHAPTER 8 CHAPTER 9 CHAPTER 10 An Overview of the Building Delivery Process How Buildings Come into
CHAPTER 2 QUANTITY TAKE-OFF
CHAPTER 2 QUANTITY TAKEOFF The quantity takeoff is an important part of the cost estimate. It must be as accurate as possible and should be based on all available engineering and design data. Use of appropriate
How To Manage An End Of Life Aircraft
LIFE MONITORING PROGRAM: A PROPOSAL FOR PRODUCT END OF LIFE MANAGEMENT Felipe Rudiuk Miglorância (ITA) [email protected] This work develops an aircraft end of life management framework
REQUEST FOR QUALIFICATIONS (RFQ) FOR PROFESSIONAL ARCHITECTURAL/ENGINEERING AND CONSULTING SERVICES FOR Fiscal Years 2015 2018
REQUEST FOR QUALIFICATIONS (RFQ) FOR PROFESSIONAL ARCHITECTURAL/ENGINEERING AND CONSULTING SERVICES FOR Fiscal Years 2015 2018 Solicitation No.: BFZ1523 1. Mission Statement and General Information 1.1.
CONSTRUCTION SUPPLY CHAINS: TURKISH SUPPLY CHAIN CONFIGURATIONS FOR CUT AND BENT REBAR
CONSTRUCTION SUPPLY CHAINS: TURKISH SUPPLY CHAIN CONFIGURATIONS FOR CUT AND BENT REBAR Gul Polat 1 and Glenn Ballard 2 ABSTRACT This paper presents current supply chain configurations for concrete reinforcement
College of the Siskiyous Insurance Requirements
College of the Siskiyous Insurance Requirements Minimum Insurance Coverages for 2016 Pre-Qualification Contractor Insurance. The Contractor shall obtain and maintain the following insurance coverages with
THE OPEN UNIVERSITY OF TANZANIA FACULTY OF BUSINESS MANAGEMENT DEPARTMENT OF MARKETING AND ENTREPREURSHIP OME 321: SALES MANAGEMENT COURSE OUTLINE
THE OPEN UNIVERSITY OF TANZANIA FACULTY OF BUSINESS MANAGEMENT DEPARTMENT OF MARKETING AND ENTREPREURSHIP OME 321: SALES MANAGEMENT COURSE OUTLINE INTRODUCTION: Sales management is a course that focuses
CPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson E: Risk and Procurement Management Presented by Sam Lane [email protected] Ph: 703-883-7149 Presented at the IPM 2002 Fall Conference Prepared by the Washington,
APPROXIMATING THE PROCESS CYCLE EFFICIENCY OF NON-PHYSICAL PRODUCTION SYSTEMS
123 APPROXIMATING THE PROCESS CYCLE EFFICIENCY OF NON-PHYSICAL PRODUCTION SYSTEMS ABSTRACT Chang-Sun Chin 1 The Process Cycle Efficiency (PCE), an important Lean Production metric, is the ratio of value-added
CULVER CITY UNIFIED SCHOOL DISTRICT 4034 Irving Place Culver City, CA 90232 (310) 842-4220 REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES
CULVER CITY UNIFIED SCHOOL DISTRICT 4034 Irving Place Culver City, CA 90232 (310) 842-4220 REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES is requesting qualified persons, firms, partnerships, corporations,
Checklist 26: How Owners Can Avoid Litigation on Construction Projects
Checklist 26: How Owners Can Avoid Litigation on Construction Projects While it is impossible to completely avoid litigation on construction projects, certain steps can be taken to minimize the potential
building and sustaining productive working relationships p u b l i c r e l a t i o n s a n d p r o c u r e m e n t
building and sustaining productive working relationships p u b l i c r e l a t i o n s a n d p r o c u r e m e n t INTRODUCTION 1 1 THE GROWING INFLUENCE OF PROCUREMENT PROFESSIONALS 2 2 GUIDELINES FOR
A decision support tool for subcontractor multi-project resource allocation
icccbe 2010 Nottingham University Press Proceedings of the International Conference on Computing in Civil and Building Engineering W Tizani (Editor) A decision support tool for subcontractor multi-project
FOREMAN TRAINING. John Songer Alan Still Larry Lawrence
FOREMAN TRAINING John Songer Alan Still Larry Lawrence WANTED: FOREMAN Looking for highly motivated, well trained, responsible leaders who can look after a job as good or better than I will. Who treats
TO HIRE OR NOT TO HIRE A BILLING SERVICE
TO HIRE OR NOT TO HIRE A BILLING SERVICE How to Make the Right Choice for Your Practice a resource presented by The business of medicine is growing more complicated every day as insurance reimbursement
School Building Authority of West Virginia BUILDING INFORMATION MODELING (BIM) EXECUTION PLAN SBA FORM 191
School Building Authority of West Virginia BUILDING INFORMATION MODELING (BIM) EXECUTION PLAN SBA FORM 191 Section 1: General 1.0 Alignment with Organizational Vision In the space provided below, read
CHAPTER 11 THE GOVERNMENT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION GENERAL REVENUE ACCOUNT. Information Technology Services Department
CHAPTER 11 THE GOVERNMENT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION GENERAL REVENUE ACCOUNT GOVERNMENT DEPARTMENT Information Technology Services Department Management of information technology outsourcing
Introduction To Cost Accounting
Page 1 Introduction To Cost Accounting 15.501/516 Accounting Spring 2004 Professor S. Roychowdhury Sloan School of Management Massachusetts Institute of Technology April 28, 2004 6 Outline Overview of
Activity-Based Costing for E-Business
Narcyz Roztocki School of Business, State University of New York at New Paltz 75 South Manheim Boulevard, New Paltz, NY 12561 USA Abstract-This paper proposes the use of Activity-Based Costing to more
Gordon L. Mountjoy & Associates, Inc.
INSURANCE REQUIREMENTS CHECKLIST Submit an Acord 25 form and the endorsements as required below. Your insurance must be in compliance immediately after you sign your subcontract and before you start work.
Franklin L. Burns School of Real Estate & Construction Management
University of Denver 1 Franklin L. Burns School of Real Estate & Construction Management Office: Daniels College of Business, Room 380 Mail Code: 2101 S. University Blvd. Denver, CO 80208 Phone: 303-871-3432
Career Path Project Engineer to Project Manager 1
Career Path Project Engineer to Project Manager 1 The Career Path standards listed below are designed to help a Project Engineer at Samet Corporation understand what skills, knowledge and experience they
1.3 What is Project Management? 1.4 Relationship Among Project Management, E-mail:[email protected]
1 Project Management Professional (PMP) is a credential offered by the Project Management Institute (PMI).The PMP Certification Exam assesses the adeptness of a professional in applying the knowledge,
IMPLEMENTING ACTIVITY-BASED COSTING IN
IMPLEMENTING ACTIVITY-BASED COSTING IN AN ENTERPRISE RESOURCE PLANNING SYSTEM Tommi Lahikainen Jari Paranko Marko Seppänen Tampere University of Technology Tampere, Finland ii ABSTRACT The main objective
SECTION 00 0110 TABLE OF CONTENTS. H. 00 2115.01 - Proposed Material, Product or Equipment Substitution Request
SECTION 00 0110 PROCUREMENT AND CONTRACTING REQUIREMENTS 1.1 DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS A. 00 0101 - Project Title Page B. 00 0105 - Certifications Page C. 00 0110 - Table
Department of Management
Department of Management Course Student Learning Outcomes (ITM and MGMT) ITM 1270: Fundamentals of Information Systems and Applications Upon successful completion of the course, a student will be able
APPLYING A STOCHASTIC LINEAR SCHEDULING METHOD TO PIPELINE CONSTRUCTION
APPLYING A STOCHASTIC LINEAR SCHEDULING METHOD TO PIPELINE CONSTRUCTION Fitria H. Rachmat 1, Lingguang Song 2, and Sang-Hoon Lee 2 1 Project Control Engineer, Bechtel Corporation, Houston, Texas, USA 2