1 Fisheries and Oceans Canada Pêches et Océans Canada Fisheries and Oceans Canada-Saskatchewan District 2011 Post-Flood Shoreline Restoration and Stabilization Protocol 1.0 Introduction Valid until March 31, 2012 The Province of Saskatchewan has experienced widespread flooding in the spring of As a result, there has been a substantial amount of flood damage to residential and recreational properties at numerous lakes throughout the province. In response, Fisheries and Oceans Canada (DFO) Saskatchewan District has developed a protocol to help guide and assist property owners who want to undertake certain types of shoreline activities in response to this flooding event. The purpose of this protocol is to describe what types of projects apply, the conditions under which property owners may carry out their projects and the mitigation measures that need to be incorporated into these projects in order to avoid negative impacts to fish and fish habitat. Provided the conditions of this document can be met, further review by DFO is not required. However, DFO requests that proponents wishing to utilize this shoreline stabilization document notify the nearest District Office prior to starting the work (see attachment for contact information). It is important to note that this document is not intended to apply to all types of projects that may be undertaken in response to flood damage. In particular, it does not include: industrial or commercial development properties; the reconstruction or installation of vertical retaining wall structures (i.e., concrete, wood, gabion baskets, sheet pile, etc.), located at or below the ordinary high water mark (OHWM) 1. large vertical erosion /slumping shorelines which require some form of geotechnical/engineering input into the stabilization design; projects that require infilling into the water beyond where the shoreline existed prior to the 2011 flood event; and, the replacement/repair of other types of infrastructure such as boathouses, boatlifts and docks. 2.0 Shoreline cleanup The general cleanup of debris from the shoreline due to elevated water levels is considered low risk to fish and fish habitat. However, the following mitigations should be followed while undertaking this work: Care is to be taken to minimize any further damage to shoreline areas when removing or hauling materials, especially if heavy machinery is being used. 1 The OHWM refers to the usual or average level to which a body of water rises at its highest point and remains for sufficient time so as to change the characteristics of the land.
2 Overhanging rooted vegetation, exposed plant roots and rocks located along the shoreline and below the OHWM should not be removed as they provide habitat for fish and help to stabilize the bank. Dispose of all permanently removed materials in an appropriate area where they cannot re-enter the waterbody. You should consult with your local municipality or Ministry of Environment office regarding appropriate disposal sites for potentially hazardous materials (e.g., chemical containers, propane cylinders, treated timbers, etc.). Where sandbags have been used for flood protection they should be removed from the area after they are no longer needed. Check with your local authorities regarding disposal plans for sandbags. The sand from the sandbags should not be dumped into or around the waterbody. Depositing sand into the lake or on the shoreline can harmfully alter or destroy fish habitat. Depending on its source, sand can contain harmful substances, like road salt, that are prohibited from entering the lake. Sand may be deposited on your lot above the high water mark as long as the sand is effectively contained so that it cannot erode into the lake and its origin is known to prevent leaching of any contaminants into the water. 3.0 Shoreline stabilization Littoral areas located adjacent to lake shorelines are often highly productive components of aquatic ecosystems. As such, any disruption to the productive capacity of these areas, either through improper stabilization techniques, or by allowing excessive erosion to continue, can result in significant impacts to fish and fish habitat. An eroding or slumping shoreline may require stabilization to: protect property and infrastructure such as buildings, roads and natural features; maintain sufficient setbacks for residential development; and, prevent excessive erosion and sediment transport that is detrimental to fish and fish habitat. Where multiple properties have contiguous erosion problems along their shoreline, you should try to work with other property owners to stabilize multiple properties at once to prevent causing additional erosion problems on adjacent properties. Following is a discussion on acceptable shoreline stabilization techniques that can be undertaken as part of this protocol. 3.1 Vegetative plantings Planting vegetation (bioengineering) utilizes the roots of the plants to stabilize the erodible soil. On relatively flat slopes that are not subject to regular wave or ice impacts, re-seeding or re-planting deep rooted native vegetation is often sufficient to stabilize the shoreline. This may include the use of deep-rooted grasses or sedges, shrubs, and trees. The most effective plant-based shoreline stabilization is a multi-layered strip that includes trees, shrubs, and ground covers with limited or no mowing to help minimize
3 future loss of land. It is recommended that native vegetation species such as willow, redosier dogwood or poplar be used to re-vegetate the shoreline. The highest success rate occurs when transplanting is done in late fall through early spring. Ensuring the plants have plenty of water until they are well established is also important. Vegetation planting is a good long term stabilization strategy that works well in conjunction with other techniques such as rock rip rap to provide a more natural looking shoreline. 3.2 Rock rip rap The most common type of stabilization used on Saskatchewan shorelines is rock rip rap (Figure 1). Rock rip rap is typically a mixture of cobbles and boulders placed on top of a geotextile fabric and/or granular filter layer on a stable slope [i.e., 2:1 or 3:1 (horizontal:vertical)]. The geotextile fabric/granular layers help prevent erosion beneath the rocks and keep the slope intact. Fieldstone can be used and is usually the least expensive option; however, commercial rock may also be available for a more uniform look. Rock size should be appropriate to the amount of wind wave and ice action that may be expected at your location. For example, rock with an average diameter of 30 cm (1 ) with a range of both smaller and larger sizes to fill in gaps is often effective. This allows for hand placement which is beneficial where access is restricted or when trying to prevent machine damage to the shoreline. It is important to remember that rocks may not be taken from below the OHWM of any fish bearing water and must be clean before placing on the shoreline. The rock rip rap should follow the contour of the natural shoreline and be tapered into the shoreline of the adjoining properties to avoid future erosion around the ends. Figure 1: Schematic drawing of rock rip rap.
4 Figures 2 and 3: Rock rip rap immediately after installation (left) and after a few years of vegetation growth (right). The general procedure to install rock rip rap armouring is as follows: Locate the OHWM of the shoreline and install silt fencing or filter fabric around this area to isolate it from the lake. The silt fencing or filter fabric may need to be in the water depending on water levels at time of construction. If working inland on a vertical eroded bank, re-grade the slope so that it is no steeper than 2:1 (horizontal:vertical). Dig a shallow trench at the base of where the rip rap armouring will be located. This is where the largest rocks will be placed to provide a strong support for the remaining rock above it. Install a layer of granular material (20 cm thick) or geotextile/landscaping fabric on the exposed slope. Silt fencing should not be used for this purpose as it is not porous enough. The fabric must extend from the footing/trench up and over the top of the re-graded slope. Make sure to overlap separate sections of the fabric by at least 20 cm. The top of the fabric should also be buried into the top of the slope so it can t slip down as rocks are placed on it. Place the rocks on the slope starting from the bottom. Once in place, add smaller materials to fill the voids and help lock the rocks together. It is recommended that the upper layer of the rip rap be backfilled with topsoil and planted with deep rooted native plants to increase both the strength of the structure and the aesthetic appeal of the armouring. 3.3 Vegetation and rip rap combination To create a more natural looking and stronger shoreline, it is highly recommended that native vegetation be incorporated into the riprap and above slope areas. This may be achieved by planting nursery raised shrubs, transplanting suitable species from stable areas on your property or by driving live stakes into the voids in the rip rap. The live stakes should be placed randomly in the rip rap, spaced about every 25 cm on center and cut off so only about 10 cm (4 ) is sticking out of the ground. As mentioned, willow, red osier dogwood and poplar are native species that work well for this purpose.
5 3.4 Retaining walls above the ordinary high water mark The use of vertical retaining walls for shoreline stabilization is not encouraged and generally not approved where they are located at or below the OHWM. However, if the slope to be stabilized is well above the OHWM, vertical retaining walls may be used but care should be taken to ensure the walls are appropriately constructed and designed to prevent deflection or failure. For excessively steep slopes or high banks DFO strongly recommends retaining the services of an experienced professional in designing retaining walls. In certain circumstances where, for example, building foundations have been built too close to the water and are threatened by shoreline erosion, the use of vertical walls may be necessary but you should contact the nearest DFO office prior to undertaking your project. 4.0 Measures to protect fish and fish habitat when stabilizing your shoreline The following mitigation measures listed below must be incorporated into your shoreline stabilization project. These mitigation measures are to be considered throughout the entire construction process to minimize impacts to the aquatic environment before, during and after your project is complete: No in-water work is to be undertaken during the Saskatchewan In-Water Closed Construction Timing Windows for your waterbody (see attached). If in-water work must occur during the closed timing window to protect property or infrastructure from imminent damage you must contact your nearest DFO office for direction prior to proceeding with your works. If work does need to be undertaken in the water, the work area must be effectively isolated from the rest of the waterbody prior to starting the project. Common techniques for isolation include installing sediment fencing or draping a sediment curtain/filter fabric over a support fence to contain any suspended sediment to the work area. If sediment fencing is used, the bottom of the fence should be weighted down so it remains in contact with the lakebed. If a sediment curtain/filter fabric is used, it should be suitable weighted down or anchored so it remains in contact with the lakebed at all times. Whatever isolation technique is selected, it must be regularly inspected and maintained as required to ensure effectiveness throughout the project. The shoreline stabilization works should attempt to follow the natural shape and contour of the shoreline to the greatest extent possible. Natural vegetation growing along the shoreline should be retained as much as possible to prevent additional erosion and strengthen the shoreline. No aquatic vegetation will be impacted during the project. Every reasonable effort must be made to minimize the duration of works taking place in the waterbody. Where possible, in-water work will be scheduled when conditions are calm and the potential for precipitation is low to minimize the potential for sediment to migrate from the site during in-water work activities and until exposed soils are stabilized.
6 All materials (e.g., gravel, cobble and rocks) used for shoreline stabilization are to be clean and free of fine sediments and contaminants. All material used for stabilizing the disturbed areas must not introduce additional sediment into fish habitat. All sand, gravel, rock/cobble used during the project will be obtained from an appropriate location that will not result in erosion of disturbed sediments into any water body. No materials are to be taken from below the OHWM of any waterbody. During construction and until a stable shoreline is re-established, effective sediment and erosion control measures must be used on disturbed areas to prevent sediment laden runoff from entering fish habitat. All debris from construction will be removed from the site upon completion of the project. Any garbage encountered on the shoreline during construction (e.g., tires, other debris, etc.) should be removed and disposed of in a landfill or other appropriate disposal site. Areas used for stockpiling construction materials or other equipment storage will be back from the edge of the waterbody and if possible, in areas which have already been disturbed or are devoid of vegetation. Where appropriate, DFO recommends the planting of deep rooted native vegetation species (e.g., willows, red osier dogwood, poplar, etc.) along the shoreline to provide greater stability to the bank and provide a more natural looking shoreline. Appropriate precautions should be taken to ensure that deleterious substances do not enter any waterbody: o Equipment operating near any fish bearing waters should be properly maintained, in sound mechanical condition and free of any fuel, oil, hydraulic fluid or coolant leaks. Cleaning, fueling and servicing of equipment should be conducted in an area from which spills or wash water will not enter fish habitat. o Any spilled materials should be cleaned up as soon as possible and disposed of in an environmentally safe manner. Spilled material should not be left where it may enter any fish habitat. Photographs should be taken of the project at various stages of completion so they are available upon request by DFO staff. If you feel that that you cannot meet the terms and conditions of document, then you are advised to contact your nearest DFO office prior to undertaking your project. This document does not authorize you to harmfully alter, disrupt or destroy fish habitat which is a violation of Section 35(1) of the federal Fisheries Act. Please note that this shoreline restoration and stabilization protocol document does not release you from the responsibility for obtaining any other approvals that may be required under federal, provincial or municipal legislation.
7 TIMING WINDOWS SASKATCHEWAN IN-WATER CLOSED CONSTRUCTION TIMING WINDOWS Restricted activity timing windows have been identified for Saskatchewan lakes, rivers and streams to protect fish during spawning and incubation periods when spawning fish, eggs and fry are vulnerable to disturbance or sediment. During these periods, no in-water or shoreline work is allowed except under site- or project-specific review and with the implementation of protective measures. Restricted activity periods are determined on a case by case basis according to the species of fish in the water body, whether those fish spawn in the spring or fall/winter, and whether the water body is located in Northern, Central, or Southern Saskatchewan. Fisheries and Oceans Canada Saskatchewan Operational Statement Version 3.0 Timing windows are just one of many measures used to protect fish and fish habitat when carrying out a work or undertaking in or around water. Be sure to follow all of the measures outlined in the Operational Statements to avoid negative impacts to fish habitat. Figure 1: Northern, Central, and Southern Saskatchewan boundaries for in-water closed construction timing windows. (Note: Central Region includes the Churchill River). How To Determine Timing Windows 1. Determine the fish species living in the water body where you wish to do work. Consult Saskatchewan Environment or your local Fisheries and Oceans Canada (DFO) office. 2. Determine if the fish living in the water body spawn in the spring or fall/winter according to Table 1. There may be one or both spawning types in any given water body. In Saskatchewan, essentially all lakes and streams contain one or more of the spring spawning fish listed, however far fewer contain fall/winter spawning fish. 3. Determine if the water body is located in Northern, Central, or Southern Saskatchewan according to Figure Use Table 2 to determine the in-water work timing restrictions according to the location of a water body (Northern, Central or Southern) and the type of fish found within (spring or fall spawners). During these periods, no in-water work (below the ordinary high water mark) is to occur without site- or projectspecific review by DFO.
8 Table 1: Common spring and fall/winter spawning fish. Spring Spawning Fish Fall/Winter Spawning Fish Arctic Grayling Rainbow Trout Brook Trout Bullhead Sauger Brown Trout Goldeye Smallmouth Bass Burbot (winter) Lake Sturgeon Suckers Cisco (Tullibee) Mooneye Walleye Lake Trout Northern Pike Yellow Perch Whitefish Table 2: Timing windows when no in-water work is to occur in order to protect spawning fish and developing eggs and fry. Location Spring Spawning Fish Fall/Winter and Spring Spawning Fish No Lake Sturgeon Lake Sturgeon present No Lake Trout Lake Trout present Northern Saskatchewan Central Saskatchewan Southern Saskatchewan May 1 July 15 May 1 July 31 October 1 July 15 Sept. 1 July 15 April 16 June 30 April 16 July 15 October 1 June 30 Sept. 15 June 30 April 1 May 31 April 1 July 15 October 1 May 31 Not Applicable FISHERIES AND OCEANS CANADA OFFICES IN SASKATCHEWAN Prince Albert Office Regina Office Fisheries and Oceans Canada Fisheries and Oceans Canada nd Street West 1804 Victoria Avenue East Prince Albert, SK S6V 8E2 Regina, SK S4N 7K3 Tel.: (306) Tel.: (306) Fax: (306) Fax: (306) Aussi disponible en français modernizing-moderniser/epmp-pmpe/index_f.asp DFO/ Her Majesty the Queen in Right of Canada 2007 This Operational Statement (Version 3.0) may be updated as required by Fisheries and Oceans Canada. It is your responsibility to use the most recent version. Please refer to the Operational Statements web site at to ensure that a more recent version has not been released.
Various options are discussed below.these low cost, low impact interventions can also be applied as general erosion control methods.
Week 10 River Hydraulics Rehabilitating Urban Waterways (From http://hubpages.com/hub/river-bank-erosion-control-methods) See also the resources placed on Moodle. Water channels should be viewed as a resource
How To Plan A Buffer Zone
Backyard Buffers Protecting Habitat and Water Quality What is a buffer? A buffer (also called a riparian buffer area or zone) is the strip of natural vegetation along the bank of a stream, lake or other
RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies.
RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies.htm#storm Definition: A permanent, erosion-resistant ground cover
Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile
Chapter 3 CULVERTS Description A culvert is a closed conduit used to convey water from one area to another, usually from one side of a road to the other side. Importance to Maintenance & Water Quality
Nipigon Bay. Area of Concern Status of Beneficial Use Impairments September 2010
Nipigon Bay Area of Concern Status of Beneficial Use Impairments September 2010 Nipigon Bay is in the most northerly area of Lake Superior. The Area of Concern takes in a large portion of Nipigon Bay and
CHAPTER 3A Environmental Guidelines for STREAM CROSSING BY ALL-TERRAIN VEHICLES
GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR CHAPTER 3A Environmental Guidelines for STREAM CROSSING BY ALL-TERRAIN VEHICLES WATER RESOURCES MANAGEMENT DIVISION Water Investigations
Storm Drain Inlet Protection
Objectives EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective
How To Write A Watercourse Crossing
Code of Practice for Watercourse Crossings Made under the Water Act and the Water (Ministerial) Regulation Consolidated to include amendments in force as of June 24, 2013 Office Consolidation Published
City of Shelbyville Site Inspection Checklist
City of Shelbyville Site Inspection Checklist General Information Project Name: KYR10 Permit Number: Date: Project Location: Contractor: Conractor Representative: Inspector's Name: Title: Signature : Weather
Outlet stabilization structure
Overview of Sedimentation and Erosion Control Practices Practice no. 6.41 Outlet stabilization structure Erosion at the outlet of channels, culverts, and other structures is common, and can cause structural
Emergency Spillways (Sediment basins)
Emergency Spillways (Sediment basins) DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short-Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1]
What Is Rehabilitation?
Location of Aggregate Operations Ready Mix Plant Locations Aggregate Locations Cement Terminal Locations What Is Rehabilitation? Rehabilitation is the treatment of land from which aggregate has been excavated
MEMORANDUM. Further discussion regarding the Community s solid waste facility is described further in this memorandum.
MEMORANDUM File: Sanikiluaq Improvement of the Existing Wastewater Treatment Facility To: Government of Nunavut Department of Community and Government Services Attention: Mr. Grigor Hope,, Project Officer
SECTION 5. Sediment Control Measures
SECTION 5 Sediment Control Measures 60. STORM DRAIN INLET PROTECTION When Runoff from earth change activities will discharge to a catch basin or storm drain inlet. A newly constructed catch basin or storm
DEPARTMENT OF THE ARMY SECTION 404 REGIONAL GENERAL PERMIT CHANNEL AND BANK PROTECTION STRUCTURES ON THE SOUTH PLATTE RIVER
DEPARTMENT OF THE ARMY SECTION 404 REGIONAL GENERAL PERMIT CHANNEL AND BANK PROTECTION STRUCTURES ON THE SOUTH PLATTE RIVER Permit Expires: December 31, 2017 Regional General Permit No. 87-01 Issuing Office:
Ruby River Grayling - Gravel Spawning Beds Monitoring Report January 2008
Ruby River Grayling - Gravel Spawning Beds Monitoring Report January 2008 In partnership with Montana Department of Fish, Wildlife, and Parks (FWP), American Wildlands, and Wildlife Forever, the Madison
Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1
6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT
Background Information: The Mamquam River Floodplain Restoration Project
Background Information: The Mamquam River Floodplain Restoration Project The Mamquam River Floodplain Restoration project is being undertaken in partnership with the Squamish River Watershed Society, Fisheries
Prattsville Berm Removal Project. 1.0 Project Location
Prattsville Berm Removal Project 1.0 Project Location The project site is located between the New York State Route 23 Bridge over the Schoharie Creek and the Schoharie Reservoir. The restoration plan encompassed
SE-10 STORM DRAIN INLET PROTECTION. Objectives
STORM DRAIN INLET PROTECTION SE-10 Objectives Erosion Control - EC Sediment Control - SE Tracking Control - TC Wind Erosion Control - WE Non-Storm Water Management - NS Waste and Materials Management -
SECTION 02100 SITE PREPARATION
SECTION 02100 SITE PREPARATION PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and General Provisions of Contract, including General Conditions and Supplementary Conditions and Division 1 through Division
RESTORING streams to reduce flood loss
RESTORING streams to reduce flood loss Flood Loss Reduction the Natural Way Flood disasters have become a regular Floods can devastate local occurrence. One in your community may have communities. threatened
Environmental Construction Operations Plan (ECO Plan) Framework
ALBERTA INFRASTRUCTURE AND TRANSPORTATION Environmental Construction Operations Plan (ECO Plan) Framework COPYRIGHT, MAY 2005 THE CROWN IN RIGHT OF THE PROVINCE OF ALBERTA, AS REPRESENTED BY THE MINISTER
Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department
Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth
Thunder Bay. Area of Concern Status of Beneficial Use Impairments September 2010
Thunder Bay Area of Concern Status of Beneficial Use Impairments September 2010 The Thunder Bay Area of Concern extends approximately 28 km along the shoreline of Lake Superior from north of Bare Point
Post-Wildfire Clean-Up and Response in Houston Toad Habitat Best Management Practices
Post-Wildfire Clean-Up and Response in Houston Toad Habitat Best Management Practices Purpose The purpose of this document is to provide guidance and recommendations for minimizing potential impacts to
Coldwater Heritage Partnership Implementation Grant Final Report Morrison Run Watershed Restoration Project Western Pennsylvania Conservancy Project Summary The goal of the Morrison Run Watershed Restoration
1.7.0 Floodplain Modification Criteria
1.7.0 Floodplain Modification Criteria 1.7.1 Introduction These guidelines set out standards for evaluating and processing proposed modifications of the 100- year floodplain with the following objectives:
Storm Drain Inlet Protection
Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Category
Interim Technical Guidelines for the Development of Environmental Management Plans for Underground Infrastructure Revised - July 2013.
Interim Technical Guidelines for the Development of Environmental Management Plans for Underground Infrastructure Revised - July 2013 Rationale Underground infrastructure may be at risk from valley, streambank
Angora Fire Restoration Activities June 24, 2007. Presented by: Judy Clot Forest Health Enhancement Program
Angora Fire Restoration Activities June 24, 2007 Presented by: Judy Clot Forest Health Enhancement Program California Tahoe Conservancy Independent California State Agency within the Resources Agency Governed
Neversink River East Branch
Neversink River East Branch Management Unit 10 Summary of Post-Flood Recommendations Intervention Level Full restoration of the stream reach including the eroding bank site between Station 38380 and Station
BMP-7. A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet.
BMP-7 BMP: STORM DRAIN INLET PROTECTION Definition A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet. To prevent sediment from entering storm drainage systems
COASTAL DAMAGE INSPECTION SOUTHWEST VITI LEVU, FIJI AFTER CYCLONE SINA
COASTAL DAMAGE INSPECTION SOUTHWEST VITI LEVU, FIJI AFTER CYCLONE SINA Brendan J. Holden SOPAC Technical Secretariat July 1992 SOPAC Technical Report 148 Prepared for: South Pacific Applied Geoscience
GLOSSARY OF TERMS CHAPTER 11 WORD DEFINITION SOURCE. Leopold
CHAPTER 11 GLOSSARY OF TERMS Active Channel The channel that contains the discharge Leopold where channel maintenance is most effective, sediment are actively transported and deposited, and that are capable
Minimizes sediment and debris from entering storm drains that lead to waterways and watercourses.
4.5-p DRAIN INLET PROTECTION Alternative Names: DI protection, Drop Inlet Protection DESCRIPTION Storm drain inlet (DI) protection slows and ponds stormwater, and filters sediment and debris before it
Request for Quotation. Bridge Construction
Request for Quotation Bridge Construction The Comox Valley Regional District (CVRD) is seeking quotations from contractors for the construction of two footbridges and some chainlink fencing at Masters
Table 4.9 Storm Drain Inlet Protetion Applicable for
BMP C220: Storm Drain Inlet Protection Purpose To prevent coarse sediment from entering drainage systems prior to permanent stabilization of the disturbed area. Conditions of Use Type of Inlet Protection
Sand and Silt Removal from Salmonid Streams
Sand and Silt Removal from Salmonid Streams Stream bank erosion Poor land use practices Sources of Sand and Silt Impacts of Sand and Silt Interstitial spaces infilled Little or no flow through the streambed
Stream Rehabilitation Concepts, Guidelines and Examples. Objectives. Pierre Y. Julien. Three Laws of Stream Restoration
Stream Rehabilitation Concepts, Guidelines and Examples Pierre Y. Julien Wuhan 2005 Objectives Part I - Stream restoration and rehabilitation: 1. Present and discuss important concepts, laws, criteria
BRIDGES ARE relatively expensive but often are
Chapter 10 Bridges Chapter 10 Bridges Bridg Bridges -- usually the best, but most expensive drainage crossing structure. Protect bridges against scour. BRIDGES ARE relatively expensive but often are the
Preventing Storm Water Pollution: What We Can Do
Preventing Storm Water Pollution: What We Can Do ~Employee Training Series~ Streets and Drainage Maintenance PREPARED IN COOPERATION WITH THE Texas Commission on Environmental Quality AND U.S. ENVIRONMENTAL
Mine Plan of Operations Reclamation Bond Checklist
Mine Plan of Operations Reclamation Bond Checklist NOTE: This checklist is provided to assist the operator in calculating the engineering and environmental costs required to properly stabilize, reclaim,
Carlton Fields Memorandum
Carlton Fields Memorandum TO: FROM: RE: DAN WEEDE FRED RUSHING RIPARIAN BUFFER DATE: JULY 26, 2013 BACKGROUND Both the state of Georgia and the city of Atlanta 1 have certain guidelines that must be followed
Operations and Maintenance Plan The Residences at Johnson Farm 189 Landham Road Sudbury, Massachusetts. Submitted to: Town of Sudbury
Operations and Maintenance Plan The Residences at Johnson Farm 189 Landham Road Sudbury, Massachusetts Submitted to: Town of Sudbury December 2011 Table of Contents 1.0 Introduction... 1 1.1 Responsibility...
Chapter 3 SENSITIVE AREAS AND VEGETATED CORRIDORS
Chapter 3 3.01 General Provisions 3.01.1 Introduction 3.01.2 Application and Interpretation of Chapter 3.01.3 Unbuildable Lots 3.01.4 Other Permits 3.01.5 Prohibited Activities 3.02 Service Provider Letter
COLORADO DEPARTMENT OF TRANSPORTATION STORMWATER FIELD INSPECTION REPORT - ACTIVE CONSTRUCTION
COLORADO DEPARTMENT OF TRANSPORTATION STORMWATER FIELD INSPECTION REPORT - ACTIVE CONSTRUCTION (1) Project Name: (2) Project Contractor: (3) Erosion Control Supervisor/SWMP Administrator: (4) CDOT Project
Q 4/17/13: Thank you for your quick response to our email dated April 10, 2013. In looking over your comments, we have a few clarifying remarks.
Q & A Q 4/10/13: In anticipation of the DEM action plan implementation in the next few days, Citizens Advocating for a Safe Environment (CASE) would like to bring a few concerns to your attention. Some
SAMPLE FRACTION MITIGATION CONTINGENCY PLAN FOR DIRECTIONAL DRILLING
SAMPLE FRACTION MITIGATION CONTINGENCY PLAN FOR DIRECTIONAL DRILLING 1 TABLE OF CONTENTS 1.0 Introduction and Purpose 3 2.0 Description of Work 3 3.0 Site Supervisor/Foremen Responsibilities 4 4.0 Equipment
Floodplain Connectivity in Restoration Design
Floodplain Connectivity in Restoration Design 2015 Symposium on Restoration in a Contaminated Environment: Lessons Learned and Challenges in Moving Forward Part II April 2015 Karin Boyd Applied Geomorphology,
City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements
City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements Overview of the City s Construction Storm Water Program The City of Paso Robles is committed to protecting
Appendix C. Municipal Planning and Site Restoration Considerations
Appendix C Municipal Planning and Site Restoration Considerations 67 68 Appendix C - Municipal Planning and Site Restoration Considerations This appendix contains best practice standards for site planning
Soakage Trenches. A better way to manage stormwater. Thinking Globally and Acting Locally
Soakage Trenches A better way to manage stormwater Thinking Globally and Acting Locally A partnership of the Scranton Sewer Authority, The Lackawanna River Corridor Association and the citizens of Scranton
Standard Operating Procedures for Flood Preparation and Response
Standard Operating Procedures for Flood Preparation and Response General Discussion Hurricanes, tropical storms and intense thunderstorms support a conclusion that more severe flooding conditions than
Communities, Biomes, and Ecosystems
Communities, Biomes, and Ecosystems Before You Read Before you read the chapter, respond to these statements. 1. Write an A if you agree with the statement. 2. Write a D if you disagree with the statement.
ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS
ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS PREPARED BY: DEPARTMENT OF ENVIRONMENT AND LANDS INDUSTRIAL ENVIRONMENTAL ENGINEERING DIVISION APRIL 16, 1992 - TABLE OF
SECTION 104 PREVENTION, CONTROL, AND ABATEMENT OF EROSION AND WATER POLLUTION
SECTION 104 PREVENTION, CONTROL, AND ABATEMENT OF EROSION AND WATER POLLUTION 104-1 Description. Provide erosion control measures on the project and in areas outside the right-of-way where work is accomplished
Construction Site Inspection Checklist for OHC000004 By making use of some simple Best Management Practices (BMPs) a construction site operator can
Construction Site Inspection Checklist for OHC000004 By making use of some simple Best Management Practices (BMPs) a construction site operator can do his or her share to protect Ohio's water resources
Waterway Technote Planning
Waterway Technote Planning Contents Benefits to planning your waterway management 1 Prioritising waterway management where to start? 1 What are your priorities? 1 Start with the best areas or those at
IAC 7/2/08 Utilities[199] Ch 9, p.1 CHAPTER 9 RESTORATION OF AGRICULTURAL LANDS DURING AND AFTER PIPELINE CONSTRUCTION
IAC 7/2/08 Utilities[199] Ch 9, p.1 CHAPTER 9 RESTORATION OF AGRICULTURAL LANDS DURING AND AFTER PIPELINE CONSTRUCTION 199 9.1(479,479B) General information. 9.1(1) Authority. The standards contained herein
WETLAND RESTORATION PROGRAM WATER ACT APPROVAL ADMINISTRATIVE GUIDE
WETLAND RESTORATION PROGRAM WATER ACT APPROVAL ADMINISTRATIVE GUIDE May 24, 2005 Table of Contents Introduction...3 Definitions...3 Types of Wetland Restorations...4 Re-Contouring...4 Engineered...4 Water
The Teton Creek Restoration Project Summary:
The Teton Creek Restoration Project Summary: The Teton Creek Restoration Project area extends for approximately one mile upstream from the Cemetery Road Bridge and includes the Aspen Pointe, The Aspens
Waterway Technote Drains
Waterway Technote Drains Contents Benefits of good drain practice 1 Are your drains healthy? 2 The Sustainable Dairying Water Accord 3 Planning drain maintenance 3 Fencing and clearing 3 Bank shaping (battering)
CITY UTILITIES DESIGN STANDARDS MANUAL
CITY UTILITIES DESIGN STANDARDS MANUAL Book 2 (SW) SW9 June 2015 SW9.01 Purpose This Chapter provides information for the design of open channels for the conveyance of stormwater in the City of Fort Wayne.
NATURAL RESOURCE RESTORATION LESSON PLAN Fix It!
NATURAL RESOURCE RESTORATION LESSON PLAN Fix It! Theme Repairing Damaged Resources Links to Overview Essays and Resources Needed for Student Research http://oceanservice.noaa.gov/education/corals http://oceanservice.noaa.gov/topics/coasts/restoration/
3. Given the geographic extent of the area, amendments have been made to the following regional planning documents
AMENDMENTS TO THE REGIONAL PLANS RELATING TO LAND REPAIR ON EARTHQUAKE DAMAGED RESIDENTIAL LAND UNDER s27 OF THE CANTERBURY EARTHQUAKE RECOVERY ACT 2011 1. This memorandum outlines the specific changes
Basic Soil Erosion and Types
Basic Soil Erosion and Types 2015 Wisconsin Lakes Convention Stacy Dehne DATCP Engineer Types of Soil Erosion Rain drop or splash erosion: Erosion preceded by the destruction of the crumb structure due
INFORMATION SHEET ORDER NO. R5-2011-XXXX TRIANGLE ROCK PRODUCTS, INC. FLORIN ROAD AGGREGATE PLANT SACRAMENTO COUNTY
ORDER NO. R5-2011-XXXX INFORMATION SHEET Background Triangle Rock, Inc. (Discharger) submitted a Report of Waste Discharge (RWD) on 23 August 2010. The Discharger is expanding the mining operations at
Helen Mercury Mine EE/CA OPINION OF PROBABLE COST
G Cost Estimates Helen Mercury Mine EE/CA Alternative 2: Limited Action 3 Minor Road Improvements 4 Clear & Grub diversion channel areas 5 Surveying 6 Cleanup & Demobilization 7 Pull back of material 8
Activity Yes No N/A Notes
CE 2020 (Rev. 12/11) Page 1 of 5 PROJECT NAME AND SITE ADDRESS: CONTRACT NUMBER: ORACLE NUMBER: WDID NUMBER: CONTRACTOR NAME AND ADDRESS: PROJECT SITE RISK LEVEL: Risk Level 1 Risk Level 2 Risk Level 3
Storm Drain Inlet Protection - IP
Storm Drain Inlet Protection - IP DEFINITION A temporary protective device formed around a storm drain drop inlet to trap sediment. PURPOSE To prevent sediment from entering storm drainage systems, prior
CW 3110 SUB-GRADE, SUB-BASE AND BASE COURSE CONSTRUCTION TABLE OF CONTENTS
December 2014 CW 3110 SUB-GRADE, SUB-BASE AND BASE COURSE CONSTRUCTION TABLE OF CONTENTS 1. DESCRIPTION... 1 1.1 General... 1 1.2 Definitions... 1 1.3 Referenced Standard Construction Specifications...
REFERENCE. All National Grid personnel who plan and perform work involving protected water resources are responsible for:
EG-30NY ENVIRONMENTAL GUIDANCE PAGE 1 of 9 DATE 10/1/10 EP 3 Natural Resource Protection 1.0 SCOPE AND RESPONSIBILITIES National Grid s New York service territory encompasses thousands of wetlands, lakes,
RESTORATION & REVITALIZATION
RESTORATION & REVITALIZATION Legal preservation has not proved to be sufficient to preserve natural communities. Restoration activities are diverse and includes revitalization of natural communities which
Pioneer Park Stormwater Management Rehabilitation Project Town of Richmond Hill Engineering and Public Works Department Design, Construction and
Pioneer Park Stormwater Management Rehabilitation Project Town of Richmond Hill Engineering and Public Works Department Design, Construction and Water Resources Division Presentation Outline Background
A Developer s Guide: Watershed-Wise Development
A Developer s Guide: Watershed-Wise Development Environmental Protection What is a watershed? It does not matter how far away you build from a creek, lake, or the ocean, you are in a watershed. Another
BUCK LAKE WALLEYE MANAGEMENT. Fisheries Management Update - Prairies Area July 2011
BUCK LAKE WALLEYE MANAGEMENT Fisheries Management Update - Prairies Area July 2011 Background Buck Lake has native fish populations of Walleye, Lake Whitefish, Northern Pike, Yellow Perch, Burbot, White
Living on the Fox River
This information could save you money! Living on the Fox River A Riverfront Property Owners Guide This brochure was developed by Fox River Ecosystem Partnership in cooperation with the Kane-DuPage Soil
ENVIRONMENTAL BEST PRACTICES FOR HIGHWAY MAINTENANCE ACTIVITIES OCTOBER 2010
ENVIRONMENTAL BEST PRACTICES FOR HIGHWAY MAINTENANCE ACTIVITIES OCTOBER 2010 Library and Archives Canada Cataloguing in Publication Environmental best practices for highway maintenance activities. [2nd
Watershed Works Manual
National Rural Employment Guarantee Act Watershed Works Manual DRAINAGE LINE TREATMENT: GABION STRUCTURE Baba Amte Centre for People s Empowerment Samaj Pragati Sahayog September 2006 Drainage Line Treatment:
Appendix H Dredging and Stream Channel Restoration
Appendix H Dredging and Stream Channel Restoration Mankind s intrusion into the natural environment in West Virginia began in earnest following the Civil War when extractive industries and settlement all
Construction Site Inspection. Inspecting to Keep You in Compliance
Construction Site Inspection Inspecting to Keep You in Compliance Inspection/Monitoring/Reporting Know if your plan is working Document corrective actions Ketchikan A Contractor that destroys their site
Position Statement regarding Offshore Wind Proposals on Lake Huron. Lake Huron Centre for Coastal Conservation
Position Statement regarding Offshore Wind Proposals on Lake Huron Lake Huron Centre for Coastal Conservation June 2010 Lake Huron Centre for Coastal Conservation (LHCCC) Corporate Position related to:
DESIGN GUIDELINES FOR EARTH RETENTION
DESIGN GUIDELINES FOR EARTH RETENTION Strata Systems, Inc. 380 Dahlonega Rd., Suite 200 Cumming, GA 30040 USA www.geogrid.com TABLE OF CONTENTS MECHANICS OF RETAINING WALLS... 3 THE STRATAWEB SOLUTION...4
Detention Ponds. Detention Ponds. Detention Ponds. Detention Ponds. Detention Ponds. Detention Ponds. CIVL 1112 Detention Ponds - Part 1 1/12
CIVL 1112 - Part 1 1/12 The water cycle, also known as the hydrologic cycle, describes the continuous movement of water on, above and below the surface of the Earth. The water cycle, also known as the
The purpose of this meeting is to inform the public of the updates to the project, and to get input before the finalization of the project.
The purpose of this meeting is inform the public of the updates the project, and get input before the finalization of the project. The following panels describe the purpose and hisry of the project, along
GREEN INFRASTRUCTURE DESIGNS BIOSWALE/HYBRID DITCH
GREEN INFRASTRUCTURE DESIGNS BIOSWALE/HYBRID DITCH JULY 2015 BIOSWALE/HYBRID DITCH SCALABLE TOOL AND DESIGN TEMPLATE This tool and associated design files are one section of a larger toolkit: Green Infrastructure
Final Report. Dixie Creek Restoration Project. Funded by Plumas Watershed Forum
Final Report Dixie Creek Restoration Project Funded by Plumas Watershed Forum Plumas Corporation January 2009 1 Background FR-CRM staff presented this project to the Dixie Valley Landowners Association
Illinois Coastal Management Program 2011
4 Coastal Erosion Assessment and Planning The Lake Michigan coast is a dynamic setting influenced by waves, ice, and changing lake levels. The potential for coastal erosion exists along nearly the entire
The Manitoba Water Services Board SECTION 022180 Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11
Page 1 of 11 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the excavation of trenches (or excavation of tunnels); the supply and placing of bedding and backfill materials;
BEST MANAGEMENT PRACTICES (BMPs)... What are They? GOOD HOUSEKEEPING PRACTICES Your Business Should Employ
BEST MANAGEMENT PRACTICES (BMPs)... What are They? CLEAN STREETS MEAN CLEAN STREAMS Inexpensive to implement and easy to use, BMPs help you to do your share to protect the environment. The term Best Management
STANDARD INSPECTION FORM GENERAL PERMIT FOR STORMWATER ASSOCIATED WITH CONSTRUCTION ACTIVITY
STANDARD INSPECTION FORM GENERAL PERMIT FOR STORMWATER ASSOCIATED WITH CONSTRUCTION ACTIVITY Project Name Permittee NOI # Start Time Inspector s Name(s) Green Card Certification # Inspector s Contact Information
4. Environmental Impacts Assessment and Remediation Targets
4. Environmental Impacts Assessment and Remediation Targets 4.1 Environmental Impacts Significant additional development in the Alder Creek watershed is not anticipated at this time; however, there are
piles of debris that accumulate after a rain such as leaves, trash, twigs, etc., water stains on fences and buildings, or salts extruded on bricks,
Extension Education Center 423 Griffing Avenue, Suite 100 Riverhead, New York 11901-3071 t. 631.727.7850 f. 631.727.7130 ASSESSING DRAINAGE PROBLEMS How can you tell the difference between a drainage problem