1 Eidelweiss Asset Management Project Plan Revision 0 - Draft Written by Larry Leonard Eidelweiss Commissioner / Team Chairperson 5/29/2014
2 Table of Contents Section Description 1 Overview 2 Development Strategy 3 Asset Management Project Team 4 Project Approach 5 Asset Management Implementation 6 Data Collection and Software 7 Implementation Challenges 8 Asset Management Benefits 9 NHDES Grant Programs 10 Work order system 11 Implementation Action Plan 12 Eidelweiss Water System overview 13 Research & Investigation 14 Cost 15 Schedule 16 References / Resources 17 Appendix 2
3 Eidelweiss Asset Management 1 - Overview: Asset management as defined by the Environmental Protection Agency (EPA) is maintaining a desired level of service for what you want your assets to provide at the lowest life cycle cost, which means the best appropriate cost for rehabilitating, repairing, or replacing an asset. The New Hampshire Dept of Environmental Services (NHDES), is encouraging all small water systems in the State to develop an asset management system. The Village District of Eidelweiss with just under 500 homes connected to our water system is such a small water system. In a discussion at the VDOE annual meeting, the residents expressed with an over-whelming acceptance that the village pursue Asset Management. Asset management planning will help us with decision making regarding the operation, maintenance, and financial planning of our water system and roads. The Environmental Protection Agency (EPA) is a huge proponent of the process and they have developed a comprehensive set of implementation guidelines, training materials, and software to aide communities in the implementation process. The New Hampshire Department of Environmental Services (NHDES) has created a new position in their organization called Asset Management Specialist. The role of this new staff expert is to promote and assist small community water systems in their asset management implementation. We are working closely with the NHDES and other agencies to bring asset management into focus within the VDOE. 2- Development Strategy: The Environmental Protection Agency (EPA) has set forth five key areas as a framework for effective asset management development:- 1- Current state of assets 2- Required sustainable level of service 3- Identifying critical assets for sustained performance 4- Determine minimum life-cycle costs 5- Develop a long tern funding strategy The Commissioners of Eidelweiss fully support the need for the Asset Management Plan as a tool to better manage our system and communicate with the community. The Eidelweiss Asset Management Team was formed by the commissioners in May The Asset Management Team is empowered to create the project plan, determine the actions, and outline tasks that will be needed during implementation. 3
4 As Eidelweiss moves forward with development of the Asset Management Plan we will shift from reactionary management to a culture of strategic planning, cost-effective decision making, information sharing, and community involvement. 3- Project Team: The team approach works because it brings together the right people to coordinate and drive the asset management activities and assist the Commissioners in the decision making process. The Asset Management Team will champion the process of developing the Plan and Philosophy. This does not mean the team will do all the work, but the team will identify the tasks, projects, partnerships, and contractors that will support the implementation. The team will promote and articulate the benefits of the plan while addressing the core questions of the asset management framework. Asset management is not a one time, 1 year, or 5 year project, it is a continual, fundamental change in the way infrastructure assets are managed. A high level commitment to the process is required and by forming the asset management team, a fundamental step in that commitment is made. Attributes of a Successful Asset management Team 1- Has the authority and resources to answer the core questions 2- Flexibility and encourage critical thinking 3- Create opportunities for open sharing of ideas and information 4- Work through problems, share the success, avoid blame 5- Foster an atmosphere that builds trust and partnerships 6- Understands the use of existing elements for the plan 7- Starts implementation during planning to achieve early results 4 - Project Approach: It is important to achieving the benefits, that all aspects of asset management be recognized and included in the implementation plan. This means that while searching and gathering historical data, collecting current asset information, and performing strategic planning that we also use the process to help with prioritizing current water system projects and maintenance issues. The decision making and 2014 water system projects that are implemented will benefit from the in-process Asset Management Process. While large water districts may implement a totally integrated asset management plan, smaller communities like Eidelweiss may select to start with planning, data collection or strategic planning. The Commissioners of the Eidelweiss Village District (VDOE) will oversee the implementation planning of the Asset Management Project; tasks will include: a- Formation of the Asset Management Team b- Review Project Plans c- Hiring of consultants 4
5 d- Approve funding e- Provide project management 5 - Asset Management Implementation: Although the completed Asset Management Plan will include both the water system and roads of Eidelweiss, the water system is more complicated, critical to our community and a high priority. Therefore, it has been determined we treat the asset management plan in two (2) parts. Part A - the water system Part B - the roads, driveways, culverts, drainage and facilities. Although the start of implementation will focus mainly on Part A, (the water system), much of the methodology will also apply to the part B, (the roads and other facilities within the village district). Key tasks to Implementation (part A): 1- Formation of the Asset Management Team 2- Create an inventory of water system physical assets a- Wells b- Tanks c- Pump houses d- Distribution and Supply lines e- Curb stops f- Chemical treatment g- Supplies and Repair Parts h- Unique features and other 3- Create an inventory of water system documentation a- Master Plan b- Engineering plans c- Proposed upgrade plans d- Existing system schematics / maps / GIS e- Curb stop documentation f- Repair and service records g- Other 4- Determine physical assets condition a- Make, model, age b- Flow rates (design and actual) c- Physical condition, operator input, service records d- Service life (Published data, industry standards, engineer/operator judgment) 5
6 5- Determine documentation condition a- Availability b- Completeness c- Accuracy d- Usefulness 6- Determine Asset Management Plan formats, filing structure, database and software requirements 7- Create a water system operations and maintenance manual 8- Determine required hardware (computer, metal detector, GPS, etc..) 9- Develop level of service document 10- Create a work statement (SOW) for Asset Management Plan sub-contract or consultant work as may be needed to assist in: a- Asset inventory, Condition statements, Probability of failure, Consequence of failure b- System mapping / GIS / GPS c- Life cycle costing d- Financial (Long term funding) e- Project Management / meetings / training 11- Create bid package / Determine bidders / RFP 12- Review bids & Proposals / Award contract 13- Project Management 14- Review and modification Key tasks to Implementation (part B): (Roads & Facilities) 1- Review of road conditions 2- Review of drainage and culvert issues / requirements 3- Inventory of equipment and buildings 4- Determine condition of assets 5- Mapping of roads and key features 6- Database of above items 7- Training of employees 8- Short and long term planning of projects 9- Implementation of plan 10- (More to follow) 6
7 6 Data Collection and Software Alternatives: An important aspect of Asset Management Planning is determining the data gathering and field records format. There are many database and software solutions that have been developed and can be employed. Having new software or computer systems should not interfere with the start of the implementation, this is because simple record keeping in a format that supports data entry into a software package at a later date is sufficient and should be utilized as an initial step. In the EPA Asset Management handbook, they provide many examples of the data capturing formats and the blank forms which can be used right away. They are in a Microsoft Excel spreadsheet format, so that program can be used to electronically store the data, this format can be imported directly into a database later. While many providers have designed custom databases for asset management and data collection, seeing the need to have a standardized platform with ease of use, the Environmental Protection Agency has developed the CUPSS database system specifically designed for use by small to medium water systems entering asset management, and it is free. It is supported by downloadable user manuals, training materials, webinars, and NHDES consultants. The Eidelweiss Asset Management Team will review the CUPSS software database as a possible tool for our database. We will use a spreadsheet database (see attached- Data Records) to catalog all existing water system data noting level of accuracy, location, file format, and storage location. This will include engineering information, master plan, maps, etc.. A goal would be to enable water operators to utilize handheld field devices to monitor the water system operation and provide key data via those devices during system repair and maintenance. 7 - Implementation Challenges: There are obstacles which may have to be overcome in the implementation of the Asset Management Plan. Including: - Determining data collecting methodology - Determining GPS and GIS system needs - Working with GIS software for mapping of data - Changing focus from operations to focus on assets - Determining the condition of existing assets - Gathering and integration of complete and accurate data - Availability of historical data - Availability of construction, maintenance and repair records - Determining life cycle costs 7
8 - Hardware and software requirements - Availability of resources - Team coordination - Long term planning vs. short term priorities 8 - Asset Management Plan Benefits: The benefits of the Asset Management Plan will be worth the efforts, challenges and financial commit of the Village District. There will be immediate and long term benefits as implementation tasks are in process. These benefits will include: - Immediate benefit in prioritizing current projects - Immediate benefit of following Asset Management protocol for current projects - Utilizing a work order tracking and approval system - Address aging water infrastructure before failure - Creation of a water systems operations manual - Improvements to the SCADA system - Creation of a preventative maintenance program - A well documented strategic management decision making process - Improved risk management - Treat decisions as investment decisions to maximize resources - More efficient and focused operations - Choosing capital projects that meet the systems true needs - Improve system security and safety - Reduce environmental impacts or violations due to poorly performing assets - The ability to convey plans clearly to the community - Improve information sharing and system awareness - Support to Financial Planning and Budgeting - Improve water system cost tracking and water rate calculation - Building partnerships with other water system operations - Full support of NHDES in our water system planning and management - Access to lower cost funding and grants 9- New Hampshire Dept. of Environmental Services Grant Programs: A- Asset Management Grant The New Hampshire Department of Environmental Services (DES) has an upcoming grant for Public Water System Asset Management Planning. This grant is intended to assist community water systems in developing an asset management plan. The program will provide a 50% matching grant up to $15,000 for water systems to conduct asset management initiatives. The goals of the Asset Management Planning Grant program are: 1- to initiate an asset management program at community water systems 2- to assist systems in developing an asset inventory with condition assessment 8
9 3-to review the current rates and determine if the existing structure supports future investment needs; 4- to communicate these planning efforts to customers and decision makers. The VDOE will be preparing to summit our application for Asset Management funding. B- Drawings and Maps Grant Record drawings are an important tool for efficient and reliable water system operations and maintenance. By maintaining current and accurate plans of the water system infrastructure, especially underground facilities, the system is best positioned to respond to system repairs in the most timely and cost-effective way. What to Include on record drawings: (Each should have two ties to fixed objects -All distribution mains, service lines & shutoffs -All blow-offs, hydrants & valves -Type, size & depth of pipe -Other utilities NHDES DWGB offers a Record Drawing matching grant up to $1,500 to develop or update community system drawings. A list of firms offering services for record drawings for small public water systems is available at Publications/Factsheets, DWGB fact sheets # 7-3 and 7-4. Record drawings are required by DES construction standards Env-Ws (small community systems), (non-community systems) and operational standards (all systems). C- Leak Detection The New Hampshire Department of Environmental Services ( DES ) is currently soliciting requests for leak detection surveys from community water systems in New Hampshire. Acoustic leak detection surveys locate leaks using mechanical and electronic listening equipment to detect leakage sounds. Proactive leak detection provides the opportunity to repair leaks early and minimize wasteful water withdrawals, capture lost revenue, and control disruption to the water system. Project requests will be prioritized on a competitive basis and leak detection surveys awarded to those that demonstrate the greatest potential for water savings and/or provide the most benefit to the water system. The surveys will be funded by DES and completed using a professional leak detection firm. Project requests must be received by DES no later than July 11, 2014 in order to be considered. 9
10 D- SRF Program The State of NH DWSRF program is a low-interest loan program that assists public water systems with the cost of improving drinking water infrastructure, including new and replacement well sources, treatment and pump house upgrades, storage tanks, water main replacements, new or replacement service water meters, interconnections between two or more existing public water systems, water conservation improvements, and energy efficiency improvements. Eligible public water systems include all community public water systems and non-transient non-profit public water systems. DWSRF projects are ranked based upon the relative impact of the project in achieving the objectives of the Safe Drinking Water Act, protection of public health, water and energy efficiency and affordability of water service. In the future, the State may forgive up to 30% of the loan to communities with Asset Management Planning in place as they currently do for wastewater asset management planning. The VDOE has sent a preliminary application in for this grant as of June 27, Work order system: The use of a work order system is a key element to project planning and updating records in an Asset Management System. The VDOE has implemented a work order management system as of 6/27/2014. (See the VDOE work order procedure and form) The VDOE Work Order is used to initiate, track and approve work being performed within the Village District. This will apply to work being performed on the water system, DPW/roads and facilities. Technical and cost information will be filed and used for asset management and budgeting purposes Implementation Action Plan: During planning and implementation the ability to track tasks and the status of projects will be paramount to good organization and visibility of actions. The asset management team will be utilizing the newly created project/actions/tasks spreadsheet which will be used to keep track of the items to be worked on, list ideas for implementation, assign tasks, and review status of asset management work. This list will be reviewed and updated on a regular basis as new tasks come up and others are completed. (see attached sample) 12- Eidelweiss Water System overview: The Eidelweiss water system is a complex mixture of wells, pump stations, storage tanks, chemical equipment, controls, Scada electronics, valves, pressure reducers, and piping. The system has seven major elements which we will call stations that consist of well heads, pumps and storage. They are identified as follows: 1- DPW Station: Here we have the primary well head with a 20hp pump producing approximately 175gpm, chemical treatment, and Scada controls main system. 10
11 2- Jungfrau Station: Located on Jungfrau Rd at an elevation of 708ft, there is a 5000gal tank, 20hp and 10hp pumps which move water that has come form the main well to the Reinach tanks and Oak Hill pump station. A significant amount of valves, piping, scada and controls reside within the building as well. 3- Muddy Beach Station: Located at Muddy Beach on Pea Porridge Pond are two (2) well heads identified as well#1 (10hp-88gpm) and well#2 (5hp-40gpm). A 5000gal tank, 2 10hp-110gpm pumps, piping, valves, and controls. These wells supply water to the Reinach tanks. 4- Reinach Station: Located at the top of Reinach Rd at 930ft elevation, with two (2) 30,000 gal tanks. 5- Oak Ridge Station: Located part way up Oak Ridge Rd at 777ft elevation, this station houses two (2) 5hp pumps each capable of 54gpm. This pumps water to Chocorua station. 6- Chocorua Station: Located further up Oak Ridge Rd, there is a 5000gal tank and two (2) 5hp-34gpm pumps. Water pumped from Chocorua goes to the summit tanks. 7- Summit Station: Located at the top of Oak Hill at 1242ft elevation. Contained in this large building are 30,000gal and 10,000gal atmospheric tanks and a 5000gal pressurized tank. There are two (2) 5hp-70gpm pumps. The VDOE water distribution system has nine (9) pressure zones that service homes, there may be homes serviced from piping outside the pressure zones, that is yet to be determined. The Pressure zones are identified as: Summit Gravity Chocorua Winnigon Summit Hydro Aspen Reinach Rigi Jungfrau Cumo The number of homes serviced by each zone is to be determined. Each of the 7 stations have manual as well as computer controls for operation and reporting of status, tank levels, and flow. The scada system is the computer control, which has PLCs at each location, unique station programming, and radios that send the data to a master PLC and PC located at the office. The supply and distribution system is made up of miles of pipe of various diameters, Junctions, shut-off valves, and curb stops at the service entrance to each home on the system. There are between 450 to 500 homes serviced. Asset Management planning will start to determine and document the details of this system. 11
12 13- Research & Investigation: Some of the asset management team tasks will include investigating the current water system data, files, history, drawings, maps and the like to catalog known data and seek inputs for the gaps in our information needs. Additional there is the research that will need to be done to obtain the missing or needed data, contact sources that can be of assistance to us, look at inventory data to complete the evaluation of condition and life-cycle. There may be the need to subcontract some of the requirements and engage consultants as required. Results of research and investigations will be documented, shared with others, and reviewed at asset management team meetings Cost: The cost of developing and maintaining the Asset Management System for Eidelweiss will be a year to year budget requirement. Initially, we have approved an article of $20,000 to get the project planned and into implementation. In addition, there are the already existing funds from the various line items in the main budget. Beyond this year, it will be an ongoing process of updating and improvement as data becomes available, changes are made, improvements are implemented and prioritized needs arise in the water system. There will be some combination of budget line items, warrant articles, rate fees, grants, loans, and reserve funds to support the financial requirements of the plan. 15- Schedule: Asset management as a way of operating, maintaining and managing the VDOE water system will be a ongoing process. It starts now in 2014 and will continue into the future, there is no end date, only intermediate milestone dates and schedule goals that will support the plan and provide Eidelweiss with the required structure to maintain the water system in the most efficient and coat effective manor. The Commissioners will employ Asset Management Methodologies immediately in our project planning for water system evaluation and improvements this summer. Some projects that come to mind are: A- Jungfrau pump station B- Reinach Storage system C- Muddy Beach well and pump station D- Oak Hill Pump Station E- Summit Storage Station F- Scada System Schedules are to be determined based on priority, critical needs and budget constraints. 16 References / Resources: a- VDOE Water System Master Plan Fluet Engineering b- NH Department of Environmental Services (NHDES) 12
13 c- US Environmental Protection Agency (EPA) d- Eidelweiss Scada System Specification & System Drawings e- Eidelweiss Curb Stop Data - Card file and Digital Files f- Water Industry Officials Report for Asset Management benefits (EPA) g- Guide to Supervisory Control and Data Acquisition (SCADA) (NIST) h- Check up software program for small systems (CUPSS software) (EPA) i- Water Resource Engineering (McGraw Hill) 17 - Appendix: The following is a preliminary list of references and documents to assist the team in Asset Management. These documents are available online. 1- Asset management handbook (EPA) 2- Asset management best practices (EPA) 3- Handbook for Owners of small water systems (NHDES) 4- Guide to asset management (National environmental services center) 5- Planning for sustainability handbook (EPA) 6- Asset management financial planning grant (NHDES) 7- Sustainability of small public water systems (NHDES) 8- Building an Asset Management Team (EPA) 9- Asset Management development flowchart 10- VDOE Water System Block Diagram (VDOE) 11- Preliminary List of VDOE Water System Maps at Lodge (VDOE) 12- UNH Asset Management Training Information (UNH) 13- Review of Municipal Work Order Systems 14- Review of Municipal Asset Management Systems 16- Asset Management- an ISO initiative (International Stds. Organization) 17- Water System Operator Roles and Responsibilities- Best Practices Guide (EPA) 18- Energy Efficiency Improvements (EPA) 19- Strategic Asset Management (HDR Waterscapes) 20- Ohio RCAPO Water System Asset Management Plan (Ohio State) 21- Capacity Planning using Asset Management (Mass DPW) 22- Check Up Program for Small Systems (CUPSS) - (EPA) 23- Asset Management for Local Officials- (EPA) 24- Water Industry Report of Benefits of Asset Management (USGAO) 25- Asset management Guide (New Mexico Environmental Finance Center) 26-Implementation Planning for AM- (State of Florida) 27- Record Keeping Rules for Public Water System (EPA) 28- Major Issues in Asset Management Implementation- (Water Research Foundation) 29-Worksheets to capture asset management data- (EPA) 30- Asset management best practices- (State of New Jersey) 31- Best practices for asset management- (US Army Corp of Engineers) 32- Water infrastructure asset management- (CH2MHIL, consulting) 13
Ohio RCAP Methodology for Asset Management / CMOM Demonstration Projects
Ohio RCAP Methodology for Asset Management / CMOM Demonstration Projects December 10, 2014 from 2:00-3:00 p.m. Presented by Wayne Cannon Ohio RCAP Rural Development Specialist, [email protected] Why Asset
Hillsborough County Water
0407 FWRJ 3/20/07 4:23 PM Page 54 Selecting & Implementing a Comprehensive Asset Management System Celine A. Hyer Hillsborough County Water Resource Services (WRS) provides water, wastewater, and reclaimed
INNOVATION AND COST EFFECTIVE APPROACH TO POTABLE WATER PIPE REPLACEMENT STRATEGICALLY FOCUSED ON DISTRIBUTION SYSTEM WATER QUALITY IMPROVEMENT By
INNOVATION AND COST EFFECTIVE APPROACH TO POTABLE WATER PIPE REPLACEMENT STRATEGICALLY FOCUSED ON DISTRIBUTION SYSTEM WATER QUALITY IMPROVEMENT By ABSTRACT Migdalia Hernandez, City of Sanford P.O. Box
CMOM How to Develop Your Collection System Maintenance Program NWOWEA Pre-Conference Utility Workshop June 22, 2015 Kalahari Conference Center
CMOM How to Develop Your Collection System Maintenance Program NWOWEA Pre-Conference Utility Workshop June 22, 2015 Kalahari Conference Center Thomas A. Fishbaugh Ohio RCAP What is CMOM? CMOM: Capacity,
Affordable Asset Management Workshop Making Use of the Data You Have An Owners Perspective
Affordable Asset Management Workshop Making Use of the Data You Have An Owners Perspective Building the Foundation for an Effective Asset Management Program Scott D. Kelly, P.E. Assistant City Administrator
Terms of Reference. Aqaba Water and Wastewater Utility Asset Valuation
Technical Support for Procurement and Project Management and Private Sector Participation to the Ministry of Water and Irrigation, Water Authority of Jordan and the Jordan Valley Authority Support for
Clean Water State Revolving Fund (CWSRF) Requirements and Guidance for a Fiscal Sustainability Plan (FSP)
Clean Water State Revolving Fund (CWSRF) Requirements and Guidance for a Fiscal Sustainability Plan (FSP) Maine CWSRF Fiscal Sustainability Plan Requirements Starting October 1, 2014, a Fiscal Sustainability
Asset Management Overview. Water & Wastewater Utility Operation and Management for Tribes
Asset Management Overview Water & Wastewater Utility Operation and Management for Tribes Asset Management Overview What is an Asset? What is Asset Management? What are the Benefits of Implementing Asset
Meet the requirements of the New Hampshire Safe Drinking Water Act, RSA 485 (state SDWA);
#10 FP 2016-41 Fixed Text 06-09-16 1 Readopt with amendment Env-Dw 600, 3-23-08 (doc. # 9107), to read as follows: CHAPTER Env-Dw 600 CAPACITY ASSURANCE Statutory Authority: RSA 485:2, V PART Env-Dw 601
Affordable Asset Management Making Use of the Data You Have: An Owner s Perspective
Affordable Asset Management Making Use of the Data You Have: An Owner s Perspective An Owner Operator s Approach for Asset Management on a Budget Lane Longley, City of St. Petersburg Presented by the April
Pennie huck Corporation and Subsidiaries Capital Expenditure Budget - 2008 ($000) Project
Pennie huck Corporation and Subsidiaries Capital Expenditure Budget 008 00B Dept 007 Carryover Proiects Description 007 Carryover s New Services Renewed Services 4 Hydrants 4 Valves/0 Bleeders 0 New Meters
WATER LEAKAGE AND DETECTION IN MUNICIPAL WATER DISTRIBUTION NETWORKS. N. Merzi (1) and T. Özkan (2)
Water Supply and Drainage for Buildings, 29th Int. Symposium, Turkey WATER LEAKAGE AND DETECTION IN MUNICIPAL WATER DISTRIBUTION NETWORKS N. Merzi (1) and T. Özkan (2) (1)[email protected] (2)[email protected]
TOWN OF SURFSIDE UTILITY UPGRADE PROJECT Project Completion
TOWN OF SURFSIDE UTILITY UPGRADE PROJECT Project Completion Project Overview Sanitary Sewer System 2 Town of Surfside Project Overview Potable Water System 3 Town of Surfside Project Overview Storm Water
Water Loss Auditing and Water Leak Detection: How Much is Being Lost and Where Does it Go? PNWS-AWWA Annual Conference Michael W. Grimm, P.E.
Water Loss Auditing and Water Leak Detection: How Much is Being Lost and Where Does it Go? PNWS-AWWA Annual Conference Michael W. Grimm, P.E. April 29, 2015 1 2 What Will Be Covered Determining the magnitude
Historic Flood Impact on the Nashville Drinking Water System. Scott Potter, Director Metro Water Services, Nashville, TN
Historic Flood Impact on the Nashville Drinking Water System Scott Potter, Director Metro Water Services, Nashville, TN Historic Event = 13.53 /48 Hours May 1 6.32 of Rain = 3rd greatest one-day rainfall
Suggested Procedures for School Boards
Suggested Procedures for School Boards The Chronology of a Project: Some of the steps described may not apply to certain types of projects, or might occur concurrently with others. As you confer with the
Asset Management Overview. Wastewater Utility Operation and Management for Small Communities
Asset Management Overview Wastewater Utility Operation and Management for Small Communities Asset Management Overview What is an Asset? What is Asset Management? What are the Benefits of Implementing Asset
a GAO-04-461 GAO WATER INFRASTRUCTURE Comprehensive Asset Management Has Potential to Help Utilities Better Identify Needs and Plan Future Investments
GAO United States General Accounting Office Report to the Ranking Minority Member, Committee on Environment and Public Works, U.S. Senate March 2004 WATER INFRASTRUCTURE Comprehensive Asset Management
UTILITIES OPERATIONS AND MAINTENANCE MANAGER
CITY OF HAYWARD UTILITIES OPERATIONS AND MAINTENANCE MANAGER DEFINITION Under general direction, to manage, plan, schedule, and review activities related to the operations, maintenance, installation and
Asset management it s a simple concept. Know your system s
Asset Management for Small Communities The Village of Weedsport Story by Timothy Taber and James Saroodis Asset management it s a simple concept. Know your system s assets equipment, pipes, machinery and
Sustainable Infrastructure Initiative to Advance Asset Management Practices. In Local, State, Tribal, and Federal Governments.
Sustainable Infrastructure Initiative to Advance Asset Management Practices In Local, State, Tribal, and Federal Governments David Reazin U.S. Environmental Protection Agency Region 6 Dallas, TX Challenges
Asset Management Guidance and Best Practices
The standards and best practices contained in this document are required elements for new projects seeking State funding under the New Jersey Environmental Infrastructure Finance Program (NJEIFP). Further
Asset Management Guidance for Wastewater and Stormwater Systems
Asset Management Guidance for Wastewater and Stormwater Systems What is Asset Management? Wastewater and stormwater systems are made up of assets; some are buried assets and invisible, while the rest are
of The New England Water Works Association
Journal Our 132nd Year of The New England Water Works Association Volume 127 No. 2 June 2013 PUTNAM WATER TREATMENT PLANT AQUARION WATER COMPANY OF CONNECTICUT GREENWICH, CONNECTICUT New England Water
California Department of Public Health Drinking Water Program. TMF Assessment Form. ASSESSMENT TYPE: Funding Project New System Change of Ownership
California Department of Public Health Drinking Water Program TMF Assessment Form ASSESSMENT TYPE: Funding Project New System Change of Ownership WATER SYSTEM CLASSIFICATION: Community Water System Nontransient
CRS Report for Congress
Order Code RS22285 Updated March 22, 2006 CRS Report for Congress Received through the CRS Web Hurricane-Damaged Drinking Water and Wastewater Facilities: Impacts, Needs, and Response Summary Claudia Copeland
WATER SUPPLY CONTINGENCY PLAN CITY OF LAKE WOBEGON, MINNESOTA
WATER SUPPLY CONTINGENCY PLAN CITY OF LAKE WOBEGON, MINNESOTA INDEX A. PURPOSE B. PUBLIC WATER SUPPLY CHARACTERISTICS 1. Current Supply Source 2. Treatment 3. Storage and Distribution 4. Maps and Plans
CAPITAL IMPROVEMENT PROGRAM (CIP) MANAGEMENT & TRACKING PROCESS, SYSTEMS, & PEOPLE APPROACH
CAPITAL IMPROVEMENT PROGRAM (CIP) MANAGEMENT & TRACKING PROCESS, SYSTEMS, & PEOPLE APPROACH ABSTRACT Aditya Ramamurthy, PMP, ARCADIS US, Inc. Like most water and sanitary sewer utilities around the nation,
BEFORE THE PHILADELPHIA WATER, SEWER AND STORMWATER RATE BOARD DIRECT TESTIMONY OF STEPHEN J. FURTEK
BEFORE THE PHILADELPHIA WATER, SEWER AND STORMWATER RATE BOARD Re Application of the Philadelphia Water Department for Increased Rates and Related Charges Fiscal Years 2017-2018 DIRECT TESTIMONY OF STEPHEN
The Piping System Model a New Life Cycle Document. Elements of the Piping System Model
Piping System Model as a Life Cycle Document White Paper Introduction When designing piping systems, a variety of documents are created providing the details necessary to design, purchase, build, and test
White Paper. www.geodecisions.com
White Paper www.geodecisions.com A Geo Spatial Total Asset Management System (TAMS) To Improve Asset Management Decision Making Fall 2013 Abstract This paper describes a Geospatial Total Asset Management
Many water and wastewater utilities
Designing an Asset Management System Michael P. Smith, Michael W. Lovett, and John T. Caldwell Many water and wastewater utilities in Florida are beginning to understand the need to develop a good asset
RULE 8-8 - ORGANIC COMPOUNDS - WASTEWATER COLLECTION AND SEPARATION SYSTEMS
BAY AREA AIR QUALITY MANAGEMENT DISTRICT RULE 8-8 - ORGANIC COMPOUNDS - WASTEWATER COLLECTION AND SEPARATION SYSTEMS (ADOPTED: January 17, 1979) (AMENDED: November 1, 1989; October 6, 1993; June 15, 1994;
Reduce Leaks Using water audits and leak detection surveys
February 2008 DOH 331-388 Reduce Leaks Using water audits and leak detection surveys In 2000, public water suppliers in Washington produced a total of 1,020 million gallons of drinking water per day to
Bridges & Culverts Condition by Quantity
3.4.3 What condition is it in? Approximately 93% of the municipality s bridge structures are in good to excellent condition, with the remaining 7% in fair condition. As a result, the municipality received
COMPREHENSIVE DRINKING WATER SOURCE-TO-TAP ASSESSMENT GUIDELINE
COMPREHENSIVE DRINKING WATER SOURCE-TO-TAP ASSESSMENT GUIDELINE MODULE 4 EVALUATE WATER SYSTEM MANAGEMENT, OPERATION AND MAINTENANCE PRACTICES Source Protection Emergency Response Training Treatment Multiple
SERVING WITH SUCCESS WILLOWS WATER. Willows Water District 6930 South Holly Circle Centennial, Colorado 80112 303-770-8625 www.willowswater.
Willows Water District 6930 South Holly Circle Centennial, Colorado 80112 303-770-8625 www.willowswater.org WILLOWS WATER. SERVING WITH SUCCESS Willows office building is located at 6930 S. Holly Circle.
Director of Utilities. Manager. Regulatory Compliance Supervisor. Distribution Supervisor. Utilities Analyst. Account Clerk. Water
DEPARTMENT ORGANIZATIONAL CHART WATER RESOURCES Director of Utilities Secretary Resources Manager Business Services Manager Utilities Engineer Resources Supervisor Distribution Supervisor Utilities Project
MAP KEYS GLOSSARY FOR THE DRAINAGE AND WATER REPORT
Record MAP KEYS GLOSSARY FOR THE DRAINAGE AND WATER REPORT Abandoned Gravity Private Combined Gravity Private Foul Gravity Private Surface Water Gravity Public Combined Gravity Public Foul Gravity Public
Force Main Condition Assessment: New Technologies & Case Studies
Force Main Condition Assessment: New Technologies & Case Studies Andy Dettmer, Ph.D., P.E. CMOM Workshop August 19, 2014 2 1 Three takeaways 1. Most of your force mains are good 2. We can pinpoint the
RE: 2014 Asset Management Plan. OBJECTIVE: To present Council with an Asset Management Plan and recommended implementation strategy moving forward.
HALDIMAND COUNTY Report PW-GM-01-2014 of the General Manager of Public Works For Consideration by RE: 2014 Asset Management Plan OBJECTIVE: To present Council with an Asset Management Plan and recommended
Recommended Practice for Software Acquisition
Recommended Practice for Software Acquisition PSIG 003/2000 Objective: To develop a set of practices that may be used in the acquisition of pipeline simulation software. Pipeline Simulation Interest Goup,
Douglas County, Nevada Request for Qualifications Douglas County Public Works Asset Management Plan
Douglas County, Nevada Request for Qualifications Douglas County Public Works Asset Management Plan Douglas County, Nevada ( County ) is soliciting Statement of Qualifications (SOQ) from qualified firms
The city of Odessa, Texas,
http://dx.doi.org/10.5991/opf.2012.38.0027 John D Antoni is a principal with Alan Plummer Associates (www.apaienv.com), Houston. Roy Staggs, assistant director of utilities, and Ajay Shakyaver, city engineer,
Ann Arbor Wastewater Treatment Plant Facilities Renovations Project September 2015
Ann Arbor Wastewater Treatment Plant Facilities Renovations Project September 2015 The Facilities Master Plan was completed in 2004 and identified the need for improvements to the City of Ann Arbor s Wastewater
ZIONSVILLE WASTEWATER DEPARTMENT 10-YEAR SEWER REHABILITATION REPORT 2013-2022
ZIONSVILLE WASTEWATER DEPARTMENT 10-YEAR SEWER REHABILITATION REPORT 2013-2022 Town of Zionsville, Indiana December 19, 2012 PREPARED BY BEAM, LONGEST & NEFF, LLC. 8126 Castleton Road Indianapolis, Indiana
Water Treatment Plant
Water Treatment Plant What is Asset Management? EPA defines it as A process for maintaining a desired level of customer service at the best appropriate cost. Source EPA Power Point Presentation. CUPSS
6500m HOV Project Stage 1: A-4500 HOV
6500m HOV Project Stage 1: A-4500 HOV Systems Engineering, Integration & Testing Plan Document Control No.: 0000000 01-November-2009 WOODS HOLE OCEANOGRAPHIC INSTITUTION WOODS HOLE, MA 02543 Document Control
PIPE INSPECTION AND REPAIR. Larry Ritchie
PIPE INSPECTION AND REPAIR Larry Ritchie February 23, 2010 PIPE INSPECTION AND REPAIR The Florida Department of Transportation builds and maintains hundreds of miles of underground infrastructure as part
Leakage Management & Control
Leakage Management & Control (An overview) Saroj Sharma April 2008 Delft, The Netherlands Contents Introduction Causes of leaks and benefits of leakage control Leakage management strategy Economic level
TOWNSHIP OF BRIGHTON REQUEST FOR PROPOSALS SANITARY SEWER REPAIRS AND/OR GRINDER PUMP INSTALLATION
TOWNSHIP OF BRIGHTON REQUEST FOR PROPOSALS SANITARY SEWER REPAIRS AND/OR GRINDER PUMP INSTALLATION April 25, 2014 DUE DATE/LOCATION: Friday, May 9, 2014 Bid forms and references are due by 9:30 A.M. at:
CRS Report for Congress
Order Code RS22285 Updated October 19, 2005 CRS Report for Congress Received through the CRS Web Hurricane-Damaged Drinking Water and Wastewater Facilities: Impacts, Needs, and Response Summary Claudia
CNAM May 2012 (Montreal) Asset Management Roadmap
CNAM May 2012 (Montreal) Asset Management Roadmap Presentation Outline Halifax Water background Asset management program Project goals and objectives Engaging and mobilizing stakeholders Findings Next
This presentation premiered at WaterSmart Innovations. watersmartinnovations.com
This presentation premiered at WaterSmart Innovations watersmartinnovations.com Cutting Our Losses: The Los Angeles Water Loss Audit Experience WaterSmart Conference October 2, 2013 Penny Falcon, P.E.
American Society of Civil Engineers
American Society of Civil Engineers America s drinking water systems face an annual shortfall of at least $11 billion to replace aging facilities that are near the end of their useful lives and to comply
Implementing a Work Order and. Asset Management System? Learning Objectives. What We Have. The City of Colleyville
A Small City s Story of Implementing a Work Order and Asset Management System American Public Works Association 2013 Congress August 28, 2013 Introductions Public Works Department City of Colleyville,
LIFECYCLE MANAGEMENT OF UTILITY ASSETS A PRACTICAL APPROACH
LIFECYCLE MANAGEMENT OF UTILITY ASSETS A PRACTICAL APPROACH Dr. Petros Kolovopoulos (Hydro-Comp Enterprises Ltd, Cyprus), Dr Dinos Constantinides (Hydro-Comp Enterprises Ltd, Cyprus) Key words: Asset Management,
The City of Atlanta: Investing in a Useable Water Utility GIS
The City of Atlanta: Investing in a Useable Water Utility GIS Esri UC 2013 Session Title: GIS Implementation July 10, 2013 Rasheed Ahmed, PH.D, P.E. Senior Watershed Manager, Atlanta DWM Dax Flinn, GISP,
Asset Management B.C.
Asset Management BC Roadmap Project Guide for using the Asset Management BC Roadmap Asset Management B.C. ROADMAP MAY 2011 Asset Management BC ROADMAP PROJECT Guide for using the Asset Management BC Roadmap
Using GIS to Track and Prioritize Your Assets
Using GIS to Track and Prioritize Your Assets What is GIS?? Geographic Information System Geographic Location of an asset Information Characteristics of an asset System Software that allows connection
ATTACHMENT 1 DRINKING WATER STATE REVOLVING LOAN FUND INTENDED USE PLAN (IUP) RANKING FRAMEWORK. for PENNVEST DRINKING WATER PROJECTS
ATTACHMENT 1 DRINKING WATER STATE REVOLVING LOAN FUND INTENDED USE PLAN (IUP) RANKING FRAMEWORK for PENNVEST DRINKING WATER PROJECTS April, 2014 Prepared by Bureau of Point and Non-Point Source Management
Asset Management Guidance for Water Systems
Asset Management Guidance for Water Systems What is Asset Management? Water systems are made up of assets; some are buried assets and invisible, while the rest are visible. These are the physical components
DEPARTMENT OF ENVIRONMENTAL QUALITY
PROJECT IDENTIFICATION DEPARTMENT OF ENVIRONMENTAL QUALITY City of Burton Sanitary Sewer Collection System Improvements State Revolving Fund (SRF) Environmental Assessment April 2015 Applicant: Authorized
Water Quality and Drinking Water Revolving Loan Fund Programs
Water Quality and Drinking Water Revolving Loan Fund Programs TABLE OF CONTENTS I. Purpose II. III. IV. Overview SRF Loan Interest Rates, Terms and Fees Loan Process V. General SRF Program Information
Utilizing Trenchless Technology to Achieve Watermain Asset Management Objectives
North American Society for Trenchless Technology (NASTT) NASTT s 2015 No-Dig Show Denver, Colorado March 15-19, 2015 MM-T6-05 Utilizing Trenchless Technology to Achieve Watermain Asset Management Objectives
USE OF GIS AS A REAL TIME DECISION SUPPORT SYSTEM FOR IRRIGATION DISTRICTS. Gabriele Bonaiti, Ph.D. 1 Guy Fipps, Ph.D., P.E.
USE OF GIS AS A REAL TIME DECISION SUPPORT SYSTEM FOR IRRIGATION DISTRICTS Gabriele Bonaiti, Ph.D. 1 Guy Fipps, Ph.D., P.E. 2 ABSTRACT GIS technology has been utilized in the past years by drainage and
Advanced_O&M_Task_List_Example_Tool_06_02_16: O&M Example
Name Type of O&M Activity O&M Activity Frequency O&M Tracking Location Runa Valves Exercise mainline valves. Semi Inspect pumps, motors, and controls Once per week / Onsite Kreger 6 inch PVC Lakeview Heights
How To Develop a Multi-Year Capital Plan Planning Saves Time and Money
How To Develop a Multi-Year Capital Plan Planning Saves Time and Money Defining a shared community vision or setting community goals are two ways that communities can begin the [] process. by Mike Hattery
Our Challenging Future
Protecting Our Future by Making Advanced Asset Management Decisions < All stories in this section Gregory M. Baird Dec 23, 2011 America s economic dominance as a world power over the past several decades
Innovative Solutions in the Water Industry: Leak Detection
Maureen Duffy 856-309-4546 [email protected] Innovative Solutions in the Water Industry: Leak Detection Introduction Meeting current water demand and supplying water for future generations is a
ATTACHMENT 7. CWSRF Project Descriptions and Examples for Green Project Reserve
Attachments 7 and 8 are from the American Recovery and Reinvestment Act Guidance, produced March 2, 2009 by the U.S. EPA Office of Water. Attachments 7 and 8 specifically address the 20% Green Project
WATER METER CALIBRATION, REPAIR, AND REPLACEMENT PROGRAM
WATER METER CALIBRATION, REPAIR, AND REPLACEMENT PROGRAM EPD Guidance Document AUGUST 2007 TABLE OF CONTENTS Part 1: OVERVIEW OF WATER METERING 3 SUMMARY 3 NECESSITY OF METERS 3 TYPES OF WATER METERS 4
Intelligent systems for locating leaks and monitoring water pipe networks
Intelligent systems for locating leaks and monitoring water pipe networks Product overview Zone measuring / monitoring Data loggers for pressure, flow and noise level Ultrasonic and electromagnetic flow
PUBLIC WORKS DEPARTMENT STRATEGIC PLAN 2015 2020
PUBLIC WORKS DEPARTMENT STRATEGIC PLAN 2015 2020 1 Purpose of Strategic Plan This document serves as the road map for the Public Works Department. It identifies where we are going and how we are going
Components of a Basement Flooding Protection Plan: Sewer System Improvements. November 2000
Components of a Basement Flooding Protection Plan: Sewer System Improvements November 2000 Components of a Basement Flooding Protection Plan: Sewer System Improvements November 2000 SEMCOG 2000 Prepared
CHELTENHAM TOWNSHIP. SANITARY SEWER UPDATE Public Works Committee Meeting September 7, 2010 Curtis Hall
CHELTENHAM TOWNSHIP SANITARY SEWER UPDATE Public Works Committee Meeting September 7, 2010 Curtis Hall 1 SANITARY SEWER UPDATE 1. Overview a. The Problem b. Pennsylvania Department of Environmental Protection
The Corporation of the Municipality of Callander. Asset Management Plan
The Corporation of the Municipality of Callander Asset Management Plan April 2014 1 Index A) Executive Summary P. 3 B) Introduction P. 4 C) State of Local Infrastructure P. 7 D) Expected Levels of Service