PETE Well Completion Design
|
|
- Clifton Watts
- 7 years ago
- Views:
Transcription
1 PETE 71 Well Completion Design Casing Design Casing Design Why Run Casing? Types of Casing Strings Classification of Casing Wellheads Burst, Collapse and Tension Example Effect of Axial Tension on Collapse Strength Example 1
2 Casing Design Why run casing? To prevent the hole from collapsing. Onshore - to prevent contamination of fresh water sands To prevent water migration to producing formation To confine production to the wellbore To control pressures during drilling To provide an acceptable environment for subsurface equipment in producing wells 3 Casing Design To confine production to the wellbore. To control pressures during drilling. To provide an acceptable environment for subsurface equipment in producing wells. You need 14 ppg to control a lower zone, but an upper zone will fracture at 1 ppg. What do you do? 4
3 Types of Casing Strings Depth BML (ft) Diameter Range Example Drive pipe or structural pile (Gulf coast and offshore only) " 60" 30" Conductor casing " 48" 0" Surface casing /8" 0" 13-3/8" Intermediate casing As needed 7-5/8" 13-3/8" 9-5/8" 5 Types of Strings of Casing Depth BML (ft) Diameter Range Example Production casing As needed 4-1/" 9-5/8" 7" Liner(s) As needed 4-1/" 9-5/8" Tubing string(s) As needed Up to 4" 6 3
4 Example Hole and Casing Sizes Hole Size 36" 6" 17-1/" 1-1/4" 8-3/4" Structural casing Conductor casing Surface casing Intermediate casing Production liner Pipe Size 30" 0" 13-3/8" 9-5/8" 7" 7 Example Hole and String Sizes (in) Structural casing Conductor casing 50' 1,000' 4,000' Surface casing Intermediate casing Production Liner 8 4
5 Classification of Casing Outside diameter of pipe (e.g. 9 5/8 ) Wall thickness (e.g. 1/ ) Grade of material (e.g. N-80) Type to threads and couplings (e.g. API LCSG) Length of each joint (RANGE) (e.g. Range 3) Nominal weight per foot (e.g. 47 lb/ft) 9 Casing Grades and Properties Most Common Grades H-40 J-55 Minimum Yield Strength (psi) 40,000 55,000 Ultimate Tensile Strength (psi) 60,000 75,000 σ σ u K-55 C-75 L-80 55,000 75,000 80,000 95,000 95,000 95,000 σ y N-80 C-90 80,000 90, , ,000 ε C-95 95, ,000 P ,000 15,000 V , ,
6 Length of Casing Joints RANGE ft RANGE 5-34 ft RANGE 3 34 ft. 11 Casing Threads and Couplings API round threads (short) API round threads (long) Buttress Extreme line CSG LCSG BCSG XCSG 1 6
7 Typical API Design Factors Required 10,000 psi 100,000 lbf 10,000 psi Collapse 1.15 Tension 1.8 Burst 1.1 Design 11,50 psi 180,000 lbf 11,000 psi 13 Pore Pressure Conductor Pipe Abnormal Surface Casing Production Casing Production Tubing Liner Normal Pore Pressure psi/ft Abnormal Pore Pressure > psi/ft 14 7
8 15 Design Louisiana from State bottom University Wellhead Assembly 16 8
9 Wellhead Assembly 17 Casing Design Tension Depth Tension Burst Collapse Collapse Burst: Collapse: Tension: 18 STRESS Assume full reservoir pressure all along the wellbore. Hydrostatic pressure increases with depth Tensile stress due to weight of string is highest at top 9
10 Casing Design Tension 19 Casing Design Collapse (from external pressure) Yield Strength Collapse Plastic Collapse Transition Collapse Elastic Collapse Collapse pressure is affected by axial stress 0 10
11 Casing Design Collapse 1 Casing Design Burst Internal yield pressure for pipe Internal yield pressure for couplings Internal pressure leak resistance P P 11
12 Casing Design Example Burst Design a 7 casing string to 10,000 ft. Pore pressure gradient = 0.5 psi/ft Design factor, N i =1.1 Design for burst only. 3 Burst Example Calculate probable reservoir pressure. psi p res = 0.5 = ft ( 10,000 ft ) 5,000 psi Calculate required pipe internal yield pressure rating ( 5,000)( 1.1) 5,500 psi pi = pres Ni = = 4 1
13 Example Select the appropriate casing grade and weight from tables: Burst pressure required = 5,500 psi 7", J-55, 6 lb/ft has BURST Rating of 4,980 psi 7", N-80, 3 lb/ft has BURST Rating of 6,340 psi 7", N-80, 6 lb/ft has BURST Rating of 7,40 psi Use N-80 casing, 3 lb/ft 5 Collapse Pressure The following factors are important: The collapse pressure resistance of a pipe depends on the axial stress There are different types of collapse failure Yield strength collapse Plastic collapse Transition collapse Elastic collapse 6 13
14 Casing Design Collapse pressure correction for axial stress (Neglects internal pressure) P C P CR σ A σ y σa P C = PCR σy σ σ A Y = Adjusted collapse rating = Collapse rating for zero axial stress = Axial stress in pipe (psi) = Pipe material minimum yield strength (psi) 7 Casing Design Collapse Calculate D/t to determine the proper equation to use for calculating the collapse rating Yield strength collapse P yp ( D/t) 1 ( ) D/ t = σy Plastic collapse P p F1 = σy F F3 D/ t 8 14
15 Casing Design Collapse Transition collapse: P t F4 = σy F5 D/t Elastic Collapse: P e = D D 1 t t 9 Casing Design Collapse If axial tension is zero: Grade Yield Plastic Transition Elastic J N P D/ t 30 15
16 Example Determine the collapse rack rating of 5 1/" (J- 55, 14 lb/ft) casing under zero axial load. Calculate D/t: D t = ( ) = Example Check the mode of collapse Table 7.4 on p. 309 of Bourgoyne et al. shows that, for J-55 pipe with < D/t < 5.01, the mode of failure is plastic collapse. The plastic collapse is calculated from: A Pp = Yp B C D/ t = ( 55,000 ) 3, psi
17 Example 3 Determine the collapse rating for a 5 1/" (J-55, 14 lb/ft) casing under axial load of 100,000 lbf The axial tension will reduce the collapse pressure as follows: P CC = P CR σ σ z y 1 σ σ z y 33 σ Tension = Area π 4 100,000 = = z ( ) 480 psi Example 3 (cont.) The axial tension will reduce the yield stress to an apparent value: σ y,e 480 ( ) = = 38,16 psi Here the axial load decreased the J-55 rating to an apparent J-38. rating 34 17
18 Example 3 (cont.) P p = σ y,e F1 F D / t F.945 = ( 38,16) 4.557x10.54,550 psi compared to 3,117 psi with no axial stress! 18
Step Rate Testing: Determining Fracture Pressure for Injection Wells 2016 UNDERGROUND INJECTION CONTROL CONFERENCE DENVER, CO LEWIS WANDKE, PE
1 Step Rate Testing: Determining Fracture Pressure for Injection Wells 2016 UNDERGROUND INJECTION CONTROL CONFERENCE DENVER, CO LEWIS WANDKE, PE AND KEN COOPER, PE PETROTEK ENGINEERING CORPORATION Overview
More informationHydraulic Fracturing Operations Well Construction and Integrity Guidelines API GUIDANCE DOCUMENT HF1 FIRST EDITION, OCTOBER 2009
Hydraulic Fracturing Operations Well Construction and Integrity Guidelines API GUIDANCE DOCUMENT HF1 FIRST EDITION, OCTOBER 2009 Hydraulic Fracturing Operations Well Construction and Integrity Guidelines
More informationTZ WEDGE ANCHOR FOR CRACKED AND UNCRACKED CONCRETE
SECTION 2.2 PAGE 1 / 9 l DESCRIPTION UCAN TZ torque controlled mechanical expansion wedge anchors have a Category 1 classification. They are used to resist static, wind and seismic tension and shear loads
More informationCoiled Tubes. Calculation of Burst Yield and Collapse Yield for Round Tubing. (σ a = (B - 1)+ σ a = π. σ h = σ r = p i. σ a (1) (OD 2 -ID 2 )
Coiled Tubes Calculation of Burst Yield and Collapse Yield for Round Tubing Burst Yield We assume no external pressure for the calculation of burst yield. If we denote axial stress as s a, hoop stress
More informationSystem. Stability. Security. Integrity. 150 Helical Anchor
Model 150 HELICAL ANCHOR System PN #MBHAT Stability. Security. Integrity. 150 Helical Anchor System About Foundation Supportworks is a network of the most experienced and knowledgeable foundation repair
More informationTECHNICAL PUBLICATION
TECHNICAL PUBLICATION Title: Permanent Wellbore Monitoring Components of the Page 1/9 COPYRIGHT NOTATION: This paper is copyright material of PROMORE, A Core Laboratories Company. Publication rights are
More informationEcoflex Wall Penetration Systems: An efficient, sustainable solution for penetrating concrete or block walls
Pre- insulated pipe systems ecoflex Wall Penetration installation guide Ecoflex Wall Penetration Systems: An efficient, sustainable solution for penetrating concrete or block walls Pre-insulated Pipe Systems
More informationAmerican Petroleum Institute Purchasing Guidelines Purchase API Spec 5CT online at www.api.org/publications
API Specification 5CT ISO 11960:2011 Petroleum and natural gas industries Steel pipes for use as casing or tubing for wells 9th Edition, June 2011 Table of Contents 1.0 Product 1.1 Products 1.2 Casing
More informationCode of Practice for Coal Seam Gas
Code of Practice for Coal Seam Gas Well Integrity DEPARTMENT OF TRADE & INVESTMENT, REGIONAL INFRASTRUCTURE & SERVICES RESOURCES & ENERGY SEPTEMBER 2012, WWW.RESOURCES.NSW.GOV.AU Title: NSW Code of Practice
More informationActivity 2.3b Engineering Problem Solving Answer Key
Activity.3b Engineering roblem Solving Answer Key 1. A force of 00 lbs pushes against a rectangular plate that is 1 ft. by ft. Determine the lb lb pressure in and that the plate exerts on the ground due
More informationStability. Security. Integrity.
Stability. Security. Integrity. PN #MBHPT Foundation Supportworks provides quality helical pile systems for both new construction and retrofit applications. 288 Helical Pile System About Foundation Supportworks
More informationSPECIFICATIONS, LOADS, AND METHODS OF DESIGN
CHAPTER Structural Steel Design LRFD Method Third Edition SPECIFICATIONS, LOADS, AND METHODS OF DESIGN A. J. Clark School of Engineering Department of Civil and Environmental Engineering Part II Structural
More informationSECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS
SECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS PART 1 GENERAL 1.01 SECTION INCLUDES A. The requirements for pipe material and installation in sewer and drainage collection systems. All materials
More informationHigh Strain Dynamic Load Testing of Drilled Shafts
Supplemental Technical Specification for High Strain Dynamic Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 3, 2015 1.0 GENERAL This work shall consist of performing high-strain
More informationDEPARTMENT OF PETROLEUM ENGINEERING Graduate Program (Version 2002)
DEPARTMENT OF PETROLEUM ENGINEERING Graduate Program (Version 2002) COURSE DESCRIPTION PETE 512 Advanced Drilling Engineering I (3-0-3) This course provides the student with a thorough understanding of
More informationRigorous Qualification and Development Program
FMC Subsea High Capacity 20K Wellhead System Overview 03/20/2013 UWD HC-20 Subsea Wellhead System Rigorous Qualification and Development Program 2 1 Qualification program Qualification testing is performed
More informationMATERIALS AND MECHANICS OF BENDING
HAPTER Reinforced oncrete Design Fifth Edition MATERIALS AND MEHANIS OF BENDING A. J. lark School of Engineering Department of ivil and Environmental Engineering Part I oncrete Design and Analysis b FALL
More informationFlowtite Jacking Pipe
U.S. COMPOSITE PIPE SOUTH, LLC. MEMBER OF KTI PIPE GROUP OF COMPANIES Flowtite Jacking Pipe 18585 Samuels Rd. Zachary, La. 70791 PH. 225-658-6166 Fax 225-658-0947 www.flowtitepipe.com Flowtite GRP Pipe
More informationTable 1 Mechanical Properties of Pipe Table 2 Section Properties of Pipe and Reinforcing Dowel The Fitting with the Rib
Table 1 Mechanical Properties o Pipe Material Minimum Minimum Allowable Modulus Tensile Yield Yield o trength trength trength* Elasticity (psi) (psi) (psi) (ksi) Aluminum 6063-T6 Pipe ATM429 30,000 25,000
More informationLINKING SEABED TO SURFACE
LINKING SEABED TO SURFACE The use of HIGH PRESSURE JACKUP DRILLING RISERS for SUBSEA DEVELOPMENTS 2 High Pressure Jackup Drilling Riser Contents Typical Jackup Well Configuration Typical Subsea Well Configuration
More informationReport on. Wind Resistance of Signs supported by. Glass Fiber Reinforced Concrete (GFRC) Pillars
Report on Wind Resistance of Signs supported by Glass Fiber Reinforced Concrete (GFRC) Pillars Prepared for US Sign and Fabrication Corporation January, 2006 SUMMARY This study found the attachment of
More informationMIA Training Example (Swank 4H)
MIA Training Example (Swank 4H) The Swank 4H is a 3-string gas well equipped with surface, intermediate, and production strings. It is a cased hole completion and the cement top on the production string
More informationSubmittal Information
Wedge SPECIFIED FOR ANCHORAGE INTO CONCRETE Wedge anchs feature a stainless steel expansion clip, threaded stud body, nut and washer. Anch bodies are made of plated carbon steel, hot-dipped galvanized
More informationDIRECT PUSH DRILLING.
DIRECT PUSH DRILLING. CONCEPT. Direct Push Drilling is a method of drilling and sampling where the tools are pushed or driven into the ground. No rotation is involved so all the samples are uncontaminated
More informationMicropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 JRHill@HaywardBaker.com
More informationComposite Drill Pipe Perfect Fit for Short-Radius Drilling
American Oil & Gas Reporter Article Composite Drill Pipe Perfect Fit for Short-Radius Drilling With much of the nation's "easy-to-produce" oil and gas gone, many U.S. companies are looking for lower cost
More informationEnergize your mind. www.halliburton.com April 2007. Lightweight Cement Meets Challenges of Weak Formations and Depleted Zones
Energize your mind. www.halliburton.com April 2007 Lightweight Cement Meets Challenges of Weak Formations and Depleted Zones Today, operators are forced to drill in increasingly challenging environments
More informationIntroduction of Gravel Pack with Inflow Control Completion in Brazil
Introduction of Gravel Pack with Inflow Control Completion in Brazil 6 th European Sand Management Forum Abrahão Jardim / Alberto Costa / Tobias Rocha / Hang Nguyen / Peter Kidd Baker Hughes Daniela Leite
More informationFoundation Underpinning Process and Relationship with Groundwater in West- Central Florida
Foundation Underpinning Process and Relationship with Groundwater in West- Central Florida Ahmed Said, PhD, PE Principal Engineering Consultant, Sinkhole Geotech, Inc. e-mail: admin@sinkholegeotech.com
More informationDecisionSpace Well Engineering Software
DATA SHEET DecisionSpace Well Engineering Software DecisionSpace Drilling & Completions Key features Configure the right tools to drill any type of well Dramatically simple to use, complete complex fluids
More informationLEGACY REPORT ER-5110. www.icc-es.org. ICC Evaluation Service, Inc. Reissued November 1, 2003. Legacy report on the 1997 Uniform Building Code
LEGACY REPORT Reissued November 1, 2003 ICC Evaluation Service, Inc. www.icc-es.org Business/Regional Office # 5360 Workman Mill Road, Whittier, California 90601 # (562) 699-0543 Regional Office # 900
More informationDrilling Performance Benchmark Metrics Overview: Benchmark Metric Definitions Below the Mudline (BML) SPUD Date Kick Off Point (KOP) KOP Date
Page 1 of 7 Drilling Performance Benchmark Metrics Overview: The primary application of the Dodson Drilling Performance Benchmark Database System is to measure and rank drilling performance for wells drilled
More informationDrill String Design. The following topics will be discussed
Drill String Design The following topics will be discussed Kelly Drill pipe Drill collars Accessories; heavy wall drill pipe, jars, stabilizers, reamers, shock sub and bit sub Drill bits 1 Kelly Used to
More informationDrilling Problems. pull
Drilling Problems Pipe Sticking Lost Circulation Hole Deviation Pipe Failures Borehole Instability Mud Contamination Formation Damage Hole Cleaning H S General Equipment & Personnel Pipe Sticking Can not
More informationBS PROGRAM IN PETROLEUM ENGINEERING (VERSION 2010) Course Descriptions
BS PROGRAM IN PETROLEUM ENGINEERING (VERSION 2010) Course Descriptions PETE201 Introduction to Petroleum Engineering (Core) (1-0-1) The course's main goal is to provide the student with an overview of
More informationHow To Learn How To Build A Class Vi Well
Well Construction, Operation, Monitoring and Testing Delivery: Online Online Hours: 5 UW CEUs:.5 Presentation Mode: Asynchronous Completion Deadline: 3 months Course Number: WCTI 106 Course Fee: $1000
More informationReinforced Concrete Design
FALL 2013 C C Reinforced Concrete Design CIVL 4135 ii 1 Chapter 1. Introduction 1.1. Reading Assignment Chapter 1 Sections 1.1 through 1.8 of text. 1.2. Introduction In the design and analysis of reinforced
More informationGROUNDWATER FLOW NETS Graphical Solutions to the Flow Equations. One family of curves are flow lines Another family of curves are equipotential lines
GROUNDWTER FLOW NETS Graphical Solutions to the Flow Equations One family of curves are flow lines nother family of curves are equipotential lines B C D E Boundary Conditions B and DE - constant head BC
More informationIntroduction. The following is an outline of the contents of this paper: Definition of Artificial Lift Page 2. How an Oil Well is Produced Page 2
Introduction Canadian Oilwell Systems Company and it s subsidiaries are suppliers of oil well Electric Submersible Pumping systems (ESPs). Such pumps are used to lift oil from oil wells so that the oil
More informationEstimation of shear force for blind shear ram blowout preventers
Estimation of shear force for blind shear ram blowout preventers Abdulkadir Tekin *, Changhyok Choi, Taylan Altan, Hamit Adin Online Publication Date: 17 Feb 2015 URL: http://www.jresm.org/archive/resm2014.02st1225.html
More informationTubular Design and Downhole Equipment
Well Construction Basics How Wells are Designed & Constructed Minimum Expectations and Best Practices Assessing Completion Reliability and Risk Key Performance Indicators Tubular Design and Downhole Equipment
More informationHIPPS Application in the Gulf of Mexico. Christopher Lindsey-Curran BP Senior Subsea Engineer
HIPPS Application in the Gulf of Mexico Christopher Lindsey-Curran BP Senior Subsea Engineer Agenda Introduction and background HIPPS overview Codes and standards System design Regulatory issues Conclusions
More informationGreen Thread Product Data
Green Thread Product Data Applications Dilute Acids Caustics Produced Water Industrial Waste Hot Water Condensate Return Materials and Construction All pipe manufactured by filament winding process using
More informationC O M P L E T I O N S E R V I C E S
Well Screens Well Screens Contents ProWeld TM ProWeld TM TOP DynoFlo TM DB UniFlo HELICAL Inflow Control Screen UniFlo TM ROI Inflow Control Screen SlimFlo TM Pre-packed CoilFlo TM DB Screen Communication
More informationTUBULAR Holing and Slotting Of Casing
TUBULAR Holing and Slotting Of Casing Holing and Slotting of Casing Introduction.................. 243-244 Slotting machines Hydraulic Handling System Holing Machines Deburring Pipe coating Banding QA
More informationDOE Award Number: TITLE PAGE. Phase I Topical Report. Don L. Hanosh
TITLE PAGE Report Title: Using Cable Suspended Submersible Pumps to Reduce Production Costs to Increase Ultimate Recovery in the Red Mountain Field in San Juan Basin Region Type of Report: Phase I Topical
More informationTechnical Report Example (1) Chartered (CEng) Membership
Technical Report Example (1) Chartered (CEng) Membership A TECHNICAL REPORT IN SUPPORT OF APPLICATION FOR CHARTERED MEMBERSHIP OF IGEM DESIGN OF 600 (103 BAR) 820MM SELF SEALING REPAIR CLAMP AND VERIFICATION
More informationTorsion Tests. Subjects of interest
Chapter 10 Torsion Tests Subjects of interest Introduction/Objectives Mechanical properties in torsion Torsional stresses for large plastic strains Type of torsion failures Torsion test vs.tension test
More informationSelection and Determination of Tubing and Production Casing Sizes
CHAPTER 3 Selection and Determination of Tubing and Production Casing Sizes OUTLINE 3.1 Overview 3.2 Overview of Nodal Analysis 3.3 Selection and Determination of Tubing and Production Casing Sizes for
More informationASTM D 1599 Standard Test Method for Resistance to Short-Time Hydraulic Pressure of Plastic Pipe, Tubing, and Fittings
ASTM D 1599 Standard Test Method for Resistance to Short-Time Hydraulic Pressure of Plastic Pipe, Tubing, and Fittings This test method establishes the short-time hydraulic failure pressure of pipe and
More informationDIVISION: 31 00 00 EARTHWORK SECTION: 31 63 00 BORED PILES REPORT HOLDER: HUBBELL POWER SYSTEMS, INC.
0 ICC ES Report ICC ES (800) 4 6587 (56) 699 054 www.icc es.org 000 Most Widely Accepted and Trusted ESR 794 Reissued 05/05 This report is subject to renewal 05/06. DIVISION: 00 00 EARTHWORK SECTION: 6
More informationHUS-H Screw Anchor. Technical data. Seismic design data. HUS-H Carbon steel screw anchor. HUS-H diameter 8, 10, 14. Seismic design data
Technical data HUS-H Carbon steel screw anchor HUS-H diameter 8, 10, 14 10 / 011 Version 011-10 1 HUS-H screw anchor seismic design data Anchor version Carbon steel screw Benefits - Quick and easy setting
More informationTRB Webinar, Sponsored by AFS40 (Subsurface Soil-Structure Interaction), June 20 th 2008
TRB Webinar, Sponsored by AFS40 (Subsurface Soil-Structure Interaction), June 20 th 2008 Culvert Relining Installation, Design and Hydraulic Considerations Presented by: Tim Toliver, P.E. Advanced Pipe
More information4D reservoir simulation workflow for optimizing inflow control device design a case study from a carbonate reservoir in Saudi Arabia
4D reservoir simulation workflow for optimizing inflow control device design a case study from a carbonate reservoir in Saudi Arabia O. Ogunsanwo, 1* B. Lee, 2 H. Wahyu, 2 E. Leung, 1 V. Gottumukkala 1
More informationDesign of reinforced concrete columns. Type of columns. Failure of reinforced concrete columns. Short column. Long column
Design of reinforced concrete columns Type of columns Failure of reinforced concrete columns Short column Column fails in concrete crushed and bursting. Outward pressure break horizontal ties and bend
More informationPlug and Abandonment Producing Well. Slides for very basic education only!
Plug and Abandonment Producing Well. Slides for very basic education only! Different from drilling P&A operations. Specific regulations set by governing bodies. This presentation covers the intent of P&A:
More informationThe Impact Of Cementing On Proper Well Control
The Impact Of Cementing On Proper Well Control Lee Dillenbeck Senior Advisor, Cementing Chevron ETC Drilling and Completions 2010 Chevron Learning Objectives Explain the main reasons for cementing wells
More informationSPECIFICATIONS FOR STEEL PIPE
SPECIFICATIONS FOR STEEL PIPE Published pipe standards serve three functions. 1. They dictate manufacturing and testing requirements and prescribed methods of measuring the required mechanical and physical
More informationTremie Concrete CM 420 CM 420 CM 420 CM 420. Temporary Structures. Tremie Concrete
Tremie Concrete Underwater concrete plays an important role in the construction of offshore structures. It may be used to tie together various elements in composite action (i.e., to tie piling to the footing).
More information9. Direct screwing into plastics and metal
9. Direct screwing into plastics and metal 9.1 Direct screwing into plastics The use of plastics is gaining in importance through new application possibilities. Optimised thread pitch Advantages here are
More informationCertificate Programs in. Program Requirements
IHRDC Online Certificate Programs in OIL AND GAS MANAGEMENT Program Requirements IHRDC 535 Boylston Street Boston, MA 02116 Tel: 1-617-536-0202 Email: certificate@ihrdc.com Copyright International Human
More informationGEOSYNTHETICS ENGINEERING: IN THEORY AND PRACTICE
GEOSYNTHETICS ENGINEERING: IN THEORY AND PRACTICE Prof. J. N. Mandal Department of civil engineering, IIT Bombay, Powai, Mumbai 400076, India. Tel.022-25767328 email: cejnm@civil.iitb.ac.in Module - 4
More informationSubsea Drilling Systems
Subsea Drilling Systems 2 Reliable, cost-effective solutions for offshore drilling... FMC Technologies Subsea Drilling Systems lead the industry with reliable and cost-effective drilling solutions which
More informationHilti KWIK HUS-EZ I (KH-EZ I) Internally Threaded Carbon Steel Screw Anchor
Hilti KWIK HUS-EZ I (KH-EZ I) Internally Threaded Carbon Steel Screw Anchor Supplement to Hilti North American Product Technical Guide Volume 2: Anchor Fastening Technical Guide 2011 Edition 3.3. KWIK
More informationTex-421-A, Splitting Tensile Strength of Cylindrical Concrete Specimens
Contents: Section 1 Overview...2 Section 2 Apparatus...3 Section 3 Test Specimens...4 Section 4 Procedure...5 Texas Department of Transportation 1 08/99 06/08 Section 1 Overview Effective dates: August
More informationFatigue. 3. Final fracture (rough zone) 1. Fatigue origin. 2. Beach marks (velvety zone)
Fatigue Term fatigue introduced by Poncelet (France) 1839 progressive fracture is more descriptive 1. Minute crack at critical area of high local stress (geometric stress raiser, flaws, preexisting cracks)
More informationAn Overview of Drill Cuttings Re-Injection Lessons Learned and Recommendations ABSTRACT
11 th International Petroleum Environmental Conference Albuquerque, New Mexico, October 12-15, 24. An Overview of Drill Cuttings Re-Injection Lessons Learned and Recommendations M-I SWACO ABSTRACT Drill
More informationPlug and Abandonment Forum
Plug and Abandonment Forum Developments in Non-Traditional Plug and Abandonment Methods Thomas Ferg ConocoPhillips Norway June 13, 2013 Efficient P&A Thoughts - Do as Much as Possible Without a Rig Remove
More informationThe Stabilizer TM. Benefits. www.griptite.com. Supplemental support system for sagging beams and floor joists within a crawl space
The Stabilizer TM Supplemental support system for sagging beams and floor joists within a crawl space Pre-drilled holes in steel plate allow for connection to beam or floor joists. Benefits Levels and
More information1.3.2 Method of construction and restoration of existing water service connections. This shall include:
1.0 GENERAL 1.1 DESCRIPTION: This specification shall cover the rehabilitation of existing water lines using the GRUNDOCRACK PIPE BURSTING SYSTEM. Pipe bursting is a system by which the pneumatic bursting
More informationHow to Design Helical Piles per the 2009 International Building Code
ABSTRACT How to Design Helical Piles per the 2009 International Building Code by Darin Willis, P.E. 1 Helical piles and anchors have been used in construction applications for more than 150 years. The
More informationHydraulic Jack Units. Contact Us! 888-577-EECO (3326) Delivery & Lead Times
Hydraulic Jack Units Elevator Equipment Corporation (EECO) has been manufacturing hydraulic elevator equipment since 1946, and is one of the leading suppliers in the industry for hydraulic jack units and
More informationNORSOK Standard D-010 Rev. 4, August 2012
Below is a listing of the main changes 1. Definitions of suspension, temporary and permanent abandonment 2. Included more examples of well barrier schematics 3. Included illustrations for permanent abandonment
More information60.12. Depend-O-Lok FxE Expansion Coupling. System No. Submitted By Spec Sect Para Location Date Approved Date. DEPEND-O-LOK FxE EXPANSION COUPLING
60.1 D-O-L FxE expansion couplings are a bolted, split-sleeve design that provides for expansion and contraction at the coupled joint. These couplings are furnished with restraint rings that, when affixed
More informationTolerance +/- 0,5 mm, +/- 0,2 mm. Length 15-350 mm ( standard) SLOTS. 9 5/8 x 36 Ibs/ft. 4 1/2 x 9,5 Ibs/ft. Slotted casing
Slotted casing Tube API 5CT, grade J/K55, R1, R2, STC: 4 1/2 x 9,5 Ibs/ft number of slots / meter number of ranges on circumference number of ranges per linear meter 24 4 6 9 5/8 x 36 Ibs/ft 48 8 6 Slotted
More informationComprehensive Design Example 2: Foundations for Bulk Storage Facility
Comprehensive Design Example 2: Foundations for Bulk Storage Facility Problem The project consists of building several dry product storage silos near an existing rail siding in an open field presently
More informationIrresponsible of Statoil
Irresponsible of Statoil Having reviewed all the available information, Bellona feels it is irresponsible of Statoil to resume production at Gullfaks C. All production from the Gullfaks C platform was
More informationRISER SYSTEMS. Our world class innovation solving your riser challenges
RISER SYSTEMS Our world class innovation solving your riser challenges OUR WORLD CLASS INNOVATION SOLVING YOUR RISER contents Riser Analysis 3 Subsea Riser Systems 4 Connectors (Subsea and Surface) Surface
More informationStrengthening of Large Storage Tank Foundation Walls in an Aggressive Environment by External Post-tensioning. May 7th 2013: Dominique Deschamps
Strengthening of Large Storage Tank Foundation Walls in an Aggressive Environment by External Post-tensioning May 7th 2013: Dominique Deschamps Scope of the paper Presentation of the project Cause of cracks
More informationWireline Operations - Slickline Calculations
Calculations Stem Force To calculate the force to be overcome to enter the well use the following formula, remember this will give you the balance point, your weight needs to exceed this amount. Force
More informationAmerican Petroleum Institute Purchasing Guidelines Purchase API Spec 7K online at www.api.org/publications
Purchase API Spec online at www.api.org/publications 7.9.3 Forgings and Castings All repair welding shall be performed in accordance with the manufacturer s written welding specifications. WPSs shall be
More informationMANUFACTURER'S CERTIFICATION SCHEDULE 40 PVC PIPE And SCHEDULE 80 PVC PIPE
SCHEDULE 40 PVC PIPE And SCHEDULE 80 PVC PIPE PVC materials used in Schedule 40 and Schedule 80 pipe manufactured by Texas United Pipe, Inc., comply with the ASTM Standard D-1784 and are a Type I Grade
More informationENGINEERED FOUNDATIONS. Department of Public Works Jeff Hill, PE
ENGINEERED FOUNDATIONS Department of Public Works Jeff Hill, PE What is an engineered foundation. A Foundation Design Developed by a Trained Professional (Engineer) Types of Foundations (All of which can
More informationCellar Tech Containment Well Cellar Systems www.cellartech.com
Sealed Well Cellars are protected by US patent 7637692, 7987904, 8127837, and 8256505. Additional US patents pending. Basic Containment Well Cellar Sealed Well Cellars are protected by US patent 7637692,
More informationThe International Workshop on Micropiles, 2007
MICROPILE FOUNDATION REPAIR AND UNDERPINNING, ARTS AND SCIENCE MUSEUM, UNIVERSITY OF PUERTO RICO, MAYAGUEZ Presented at: International Society of Micropiles (ISM) The International Workshop on Micropiles,
More information53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines:
Division 53: Slip-Lining of Existing Sewer Line 53.01 GENERAL: This section includes all labor, materials, transportation, equipment necessary to rehabilitate by means of Instituform deteriorated sections
More informationPage 1 of 18 28.4.2008 Sven Alexander Last revised 1.3.2010. SB-Produksjon STATICAL CALCULATIONS FOR BCC 250
Page 1 of 18 CONTENT PART 1 BASIC ASSUMPTIONS PAGE 1.1 General 1. Standards 1.3 Loads 1. Qualities PART ANCHORAGE OF THE UNITS.1 Beam unit equilibrium 3. Beam unit anchorage in front..1 Check of capacity..
More informationGUARDRAIL POST STEEL
GUARDRAIL POST STEEL Guardrail posts meeting materials certification are evaluated and checked for: 1. Dimensional acceptance 2. Physical test results a. Chemical b. Physical 3. Galvanized or painted coating
More informationPerforating Basics. How the perforating processes work. George E. King Engineering GEKEngineering.com 3/14/2009 1
Perforating Basics How the perforating processes work 3/14/2009 1 Perforating Methods 1. The vast majority of all perforating work is performed with shaped charge or jet perforating charges. 2. Bullet
More informationSECTION 1 GENERAL REQUIREMENTS
Page 1 of 6 SECTION 1 GENERAL REQUIREMENTS 1. SCOPE OF WORK: The work to be performed under the provisions of these documents and the contract based thereon includes furnishing all labor, equipment, materials,
More informationCITY OF LOS ANGELES CALIFORNIA
BOARD OF BUILDING AND SAFETY COMMISSIONERS VAN AMBATIELOS PRESIDENT E. FELICIA BRANNON VICE PRESIDENT JOSELYN GEAGA-ROSENTHAL GEORGE HOVAGUIMIAN JAVIER NUNEZ CITY OF LOS ANGELES CALIFORNIA ERIC GARCETTI
More informationAn Introduction to Oil and Gas Well Servicing
An Introduction to Oil and Gas Well Servicing Educational Material from the IOM 3 Oil and Gas Division The global network for the materials cycle Introduction The Institute of Materials, Minerals & Mining
More informationSheet metal operations - Bending and related processes
Sheet metal operations - Bending and related processes R. Chandramouli Associate Dean-Research SASTRA University, Thanjavur-613 401 Table of Contents 1.Quiz-Key... Error! Bookmark not defined. 1.Bending
More informationources of Drinking Water
The drop on water Sources of Drinking Water Did you know that 40 per cent of Nova Scotians get their water privately from a drilled well, a dug well, or a surface water source? The other 60 per cent rely
More informationTubing Data. Contents. Tubing Selection. Tubing Handling. Tubing Material. Tubing Outside Diameter Hardness. Tubing Wall Thickness
www.swagelok.com Tubing Data Contents Tubing Selection... 1 Tubing Handling.... 1 Gas Service... 2 Tubing Installation.... 2 Suggested Allowable Working Pressure Tables Carbon Steel Tubing... 3 Stainless
More informationSewer Line Rehabilitation
1.0 GENERAL 1.1 DESCRIPTION: This specification shall cover the rehabilitation of existing sanitary sewers using the GRUNDOCRACK PIPE BURSTING SYSTEM. Pipe bursting is a system by which the pneumatic bursting
More informationUltraviolet (UV) Light Cured Fiberglass Reinforced Cured-In-Place Pipe (CIPP) It is not just for sanitary sewer rehabilitation
Ultraviolet (UV) Light Cured Fiberglass Reinforced Cured-In-Place Pipe (CIPP) It is not just for sanitary sewer rehabilitation Dan Broderick Director of Pipeline Rehabilitation ACHEN-GARDNER ENGINEERING,
More informationThe Suitability of CRA Lined Pipes for Flowlines Susceptible to Lateral Buckling SUT Global Pipeline Buckling Symposium, 23 24 February 2011
The Suitability of CRA Lined Pipes for Flowlines Susceptible to Lateral Buckling SUT Global Pipeline Buckling Symposium, 23 24 February 2011 Duncan Wilmot, Technical Manager, Cladtek International, Australia
More informationSeries 4000 Fiberglass Pipe and Fittings
Series 4000 Fiberglass Pipe and Fittings for corrosive industrial service Uses and applications Listings Performance Acid drains Chemical process piping Corrosive slurries Food processing Geothermal Nonoxidizing
More informationKentucky Lake Bridge Pile Load Testing Overview Ohio Transportation Engineering Conference Columbus, Ohio 10/28/2015
Kentucky Lake Bridge Pile Load Testing Overview Ohio Transportation Engineering Conference Columbus, Ohio 10/28/2015 Presented by: Jeff Dunlap, P.E. Terracon Consultants 1 Project Site Kentucky Official
More information