IMPACT OF SMALL DECENTRALIZED PV GRID-CONNECTED PLANTS ON LOAD SHEDDING IN NEPAL
|
|
|
- Lesley Cole
- 9 years ago
- Views:
Transcription
1 IMPACT OF SMALL DECENTRALIZED PV GRID-CONNECTED PLANTS ON LOAD SHEDDING IN NEPAL Domenico Chianese 1 *, Davide Rivola 1, Jagan Nath Shrestha 2, Alex Zahnd 3 1University of Applied Sciences and Arts of Southern Switzerland (SUPSI), 6952 Canobbio, Switzerland, [email protected] 2 Nepal Solar Energy Society, Kathmandu, Nepal, [email protected] 3 RIDS-Nepal, Kathmandu, Nepal, [email protected] ABSTRACT: The current unreliability of the electrical network in Nepal, and the growing needs of users, together with the high level of losses in the electricity distribution grid can be partially resolved by means of a decentralized and partly autonomous electricity supply. The Nepali grid is characterized by weak stability, frequent accidental powercuts and regular planned load shedding schemes (up to 20 hrs. a day in the dry season), causing particular suffering to SMEs (Small and Medium Enterprises). A feasibility study [1] has demonstrated the cost advantages of a small solar PV grid connected system in combination with a battery back-up, compared to traditional petrol gensets or battery chargers from the grid with stand-alone inverters. The pilot project foresaw the design, construction and monitoring of 5 grid-connected 1.11 kwp PV plants at three different strategic locations, P1, P2 and P3, in the urban and semi-urban environment of the Kathmandu valley. While four of the PV systems are standard grid connected systems, of which three are installed in No-Load Shedding Zone P2 and one in Load Shedding Zone P1, the fifth system P3, is installed in a Load-Shedding Zone, but is designed with a battery bank backup system, and can therefore function as a micro-grid. The setup parameter limit of the grid-connected inverter was adjusted in accordance with the effective situation of the distribution grid (voltage and frequency limits, duration of power cut, etc.). Performance monitoring of the plants started in late The first 9 months of analysis shows energy generation losses of about 47.6% (475kWh) at P1, due to the load shedding schedule at the time. The performance of the three PV plants at P2, where no load shedding occurs, was as expected, with all generated energy fed into the grid. The 1.11 kwp PV grid-connected plant with a battery backup at P3 in effect performs as a stand-alone system providing enough energy for one household and an NGO office. Keywords: Small Grid-connected PV System, System Performance, Grid Stability, Grid Integration, Developing Countries. 1 INTRODUCTION The Nepalese national grid is weak, unreliable, undersized and of poor quality. It cannot meet the electricity demand of Kathmandu, the capital of Nepal. In addition to the high electricity distribution losses, the grid cannot keep up with the annual growth demand, which has amounted to of 8-10% annually over the last decade. The government was therefore forced to introduce load shedding in 2001, resulting today in up to 20 hours per day during the dry season with no access to electricity. So it is not surprising that local users and small/medium sized enterprises (SMEs) have been demanding a more reliable, more adequate power supply, in order both to reduce interruptions to family life, and to support their businesses. A feasibility study [1], carried out in , showed that the present situation could be partially solved through decentralized solar PV roof-top systems. The study showed a cost advantage of a solar PV roof-top grid connected system in combination with a battery back-up, compared to a traditional petrol genset, or a battery charging system, charged from the grid, when available, with a stand-alone inverter. 1.1 Grid reliability in Nepal The current unreliability of the electricity network in Nepal, and the growing needs of users (SMEs as well as the population), together with the high level of losses in the electricity distribution grid can be partially resolved by means of a decentralized and partly autonomous electricity supply. In terms of stability, the Nepali grid is weak, unable to meet the load demand and experiences frequent accidental power cuts in addition to the regular, planned seasonal load shedding schemes. The power supply system of Nepal is suffering from lack of production, forcing the distributor to practice regular load shedding, which can reach up to 20 hrs./day in the dry season, causing particular suffering to SMEs. The problem of load shedding has become drastically more serious since The electricity distribution grid presents a very high level of loss (about 26%, of which ~19% in the distribution system, ~ 5% in the transmission system and about 1% in the generation system [2]). The growth in demand cannot be covered by the production capacity because this capacity has not been developed sufficiently, there are significant losses in the system and insufficient hydro reservoir capacity. Moreover, the current use of a battery-inverter back-up system increases consumption because of system losses (up to 50% of losses), worsening the situation of electricity supply. In comparison, the use of gridconnected PV systems would provide additional energy to the grid and consumers and therefore limit the necessity for load shedding, which causes severe socioeconomic damage to Nepal. 1.2 Main obstacles to decentralized small PV systems In order to deploy small, decentralized PV systems throughout the country it is necessary to address the main obstacles that hinder the wider dissemination of solar PV grid connected systems in Nepal. The main impediments are: no legal framework (policies, subsidies or feed-intariffs in place), the technical features of the grid (voltage
2 and frequency fluctuation out the limits, frequent interruptions, flickers, etc), economic viability, lack of public awareness and trained professionals. Technical obstacles refer to the grid instability and poor grid quality characteristics, where the standard limits are often exceeded. In addition to the diffused load shedding schemes (up to 20 [hrs/day] of electricity cuts), frequent short blackouts can create problems in the operation of electronic equipment (PV inverters and chargers). The inability to purchase appropriate inverters locally (PV grid-connected and bidirectional battery inverters for mini-grid purpose) can slow down the deployment of this technology. Economically, the high initial investment costs represent a considerable obstacle, together with the need to develop specific markets (appropriate inverters and PV modules) and import channels. Despite recent decreases in the price of PV systems, PVGC systems remain affordable only for the middle upper class. Institutionally, the current legal context does not yet allow the grid connection of PV systems and would need to be adapted, as would existing standards and norms, and finally the policy and decision makers are not yet aware of the potential and advantages, for Nepal, of gridconnected PV technology; they need clear evidence of its appropriateness in order to support its development. Solar Home Systems (SHS) are very common in rural and urban Nepal. Many companies are installing stand-alone systems all over the country, particularly in rural areas. The Alternative Energy Promotion Centre (AEPC) organizes training courses on stand-alone systems, but solar PV companies do not have the knowledge or skilled professionals required in order to design, install and maintain grid-connected solar PV systems or mini-grid systems. Therefore, in addition to the five pilot PV grid-connected plants installed and monitored, the project also includes training activities. Furthermore, an important part of the project is the specially designed web site, which aims to demonstrate and disseminate the technologies used ( and the performances of the five plants by means of a live performance data site ( 1.3 Project Partners In order to include all the stakeholders and line agencies in the solar PV sector in Nepal, the project set out with partnerships with the Government, academia, the solar PV business community. The project therefore includes the participation of Nepal Electricity Authority (NEA) and Alternative Energy Promotion Centre (AEPC) from the Government side, with the main project implementing partners, the University of Applied Sciences and Arts of Southern Switzerland (SUPSI), Rural Integrated Development Services (RIDS-Nepal) as the local NGO, the Centre of Energy Studies (CES) of Tribhuvan University (TU), the Nepal Solar Energy Society (NSES) and Gham Power, a local, Kathmandu based solar PV company. 2 METHODOLOGY AND APPROACH 2.1 PV systems layout and Real Time Monitoring Five 1.11 kwp solar PV grid-connected systems were installed between October and December 2102 in the Kathmandu Valley in three different, urban, locations. At the CES (Centre of Energy Study) Pulchowk Engineering Campus of Tribhuvan University, Nepal s first Government University, a standard grid-connected 1.11 kwp PV plant, P1, was installed. This location is subjected to the regular planned load shedding schedule, reaching up to 20 hours per day with no grid power supply during the dry season. Figure 1: standard grid-connected 1.1 kwp PV plant at the CES (Centre of Energy Study) Pulchowk Engineering Campus of Tribhuvan University, Nepal s first Government University (P1). At the NEA (Nepal Energy Authority) Min Bhawan office three equal, standard grid-connected 1.11 kwp PV systems (together called Plant P2) were installed and connected to the grid. This location experiences no load shedding and thus is considered as the reference location for the project. In particular, this setup allows the measurement of the energy output, under the climatic conditions of Kathmandu, without the hassles of electrical network found elsewhere. Three different grid connected inverters were installed to compare their performances. Figure 2: three 1.1 kwp PV systems were installed and connected to the grid at the NEA (Nepal Energy Authority) Min Bhawan office (P2). In the third location, P3, in Imadol, Lalitpur district, in the outskirts of the main urbanized, densely populated city area, a 1.11 kwp solar PV grid-connected system, with a battery bank as back-up system, was installed, since this building also experiences the enforced daily load shedding. It is positioned on the roof of the NGO RIDS-Nepal office, providing electricity to the NGO and to a private household when load shedding take place. The building itself is connected to the grid at a
3 considerable distance away from a transformer. 3.1 Load shedding conditions and grid system losses The country is currently passing through a severe energy crisis. Each year, load shedding is increasing [2]. NEA had predicted resorting to a maximum of 18 hours of load shedding per day per consumer during the driest months of January to April However, they succeeded in restricting the load shedding hours to an avg. 12 hrs/day per consumer, with peaks of up to 20hrs/day. A new Nepal Load shedding schedule is announced every week for the 7 regions. There are two load shedding events per day. Figure 3: 1.1 kwp PV system with a back-up battery at the main head office of RIDS-Nepal in Imadol, Lalitpur district (P3). The setup parameters of all the 5 inverters in the three locations were chosen so that the energy fed into the grid is maximized, limiting the interruptions due to poor grid quality, but without compromising the security of the grid system at any given time. The load profiles in P1 and P2 are defined only by internal power supply for internet communications, monitoring system and its back-up system. All five grid connected solar PV system parameters are monitored in great detail (in 10 minute values), with their hourly average performance values updated live on our specifically designed SEPV Nepal website ( available for registered users. 3 RESULTS At the CES (P1) solar PV system location, 46% of the time during sunshine hours, when energy could have been generated, the grid was not available in January and February Thus, potential energy generation corresponding to 54% of the total potential solar energy converted electricity was lost due to load shedding. In the third location in Lalitpur district, the 1.11 kwp solar PV grid-connected plant with battery backup is still performing as a stand-alone RAPS (Remote Area Power Supply) system, since NEA permission to connect it to the grid was not granted until the end of February However, as it has been designed as a RAPS system with battery bank back-up, it provides the NGO RIDS-Nepal and one household with their daily electricity requirements during the daily enforced load shedding periods. All five grid connected solar PV system parameters are monitored in great detail, with their hourly value life updated on our specifically designed SEPV Nepal website ( available for registered users. The paper will discuss the detailed operation of each of the three site specific solar PV grid connected systems over their first 6 months of energy generation. It will highlight the individual performances of the systems in terms of energy conversion, efficiencies, induced losses, as well as the performances and energy conversion efficiencies of the three different grid connected inverters, by means of diagrams, pictures and live data. Table 1: Load shedding and blackout events in P1 & P2. Between February 2013 and September blackout events were recorded in P1 (Table 1). Two planned outages typically occur every day and we can estimate 524 planned load shedding events. There were also 71 other short events. In P2 only 40 events occurred during the whole period of observation, corresponding to 1.1 % of the time. Therefore P2 can be considered the reference location for evaluating Energy production. According to the NEA 2012 Annual Report [2], System losses are as high as 26.4% of the total consumption. This figure includes technical and nontechnical losses, where the proportion of non-technical losses is quite high. Strict measures for electricity theft control are also taken, such as confiscation of electrical equipment and legal action against culprits. In the last fiscal year the NEA was able to reduce system losses by around 2%. 3.2 Grid measurements The Nepali grid is characterized by weak stability, frequent accidental power cuts and regular planned load shedding schemes (up to 20 hrs. in the dry season), and SMEs in particular suffer from this situation. Distribution lines are also often overloaded. An analysis of changes in the voltage and frequency of the power grid has made it possible to define the inverter setting parameters. Table 2 shows the values for average frequency and mean and maximum voltage; periods without outage (P1 and P2) or when P3 was connected as a mini-grid, were the only periods considered. Table 2: frequency and voltage limits in the three locations (P1, P2, P3).
4 Mean frequency values are critical for normal inverter reconnection parameters (P1 and P2). The frequency at P3 is defined by the mini-grid inverter, and is thus precisely 50.0 Hz. Figure 6: Relative frequency distribution of voltage at the P3 power plant operating in grid connected mode (red) and with Mini-grid mode (Blue). Figure 4: Grid voltage distribution in the three locations (P1, P2, P3) Figure 4 shows the relative cumulative voltage distribution. In P2, the reference location in the NEA Min Bhawan Office, the voltage remains very stable with an average of 217.3V (standard voltage: 220V). The installation is located near three HV-MV and MV-LV transformers, so the line losses and voltage drops are very limited. P1 is located in the Pulchowk University Campus in the middle of the city of Kathmandu, where an MV-LV transformer provides energy to the buildings and laboratories. The distribution voltage in P1 is therefore similar to that recorded in the P2 location, but shifted to an higher level (avg V). The situation of distribution voltages in P3 is quite problematic. It was not possible to fully connect the minigrid system (with backup) to the grid because of lack of NEA permission. It was only possible to connect the system for 37 days, for research purposes. P3 is located in the outskirts of the main, densely populated, urbanized city area, far away from the MV-LV transformer. This results in significant voltage losses at peak user times, when the voltage can drop to 170 Volt AC. The injection of only 1kW peak power has no relevant impact on improving the poor conditions of the line voltage grid. Figure 5: Grid voltage variation during the selected period of analysis of the P1 PV system, at POI. Figure 5 shows the voltage variability at point of injection (POI) in the P1 location, and the setting limits defined in the inverter parameters (170V to 252V). The frequent voltage reductions caused by the planned and unplanned blackouts can be seen clearly. The distribution of AC voltage at the P3 power plant during the period of analysis ( ), illustrated in Figure 6 in red, is fixed at 220V for most of the time, because of the inverter output voltage regulation during Mini-grid mode. In Grid-connected mode (Figure 6 in blue), the voltage is very irregular and varies typically from 170 to 225V. Figure 7: Grid frequency at reference location P2. The Frequency ranges from 48.5 Hz to 52.1 Hz (Figure 7). The frequency in the systems under consideration remained within the limits of the standard range. However, the frequency can remain at low or high levels for weeks, preventing inverters with normal settings from connecting to the grid, so the upper reconnection frequency limit has been set at 51.25Hz, and the lower reconnection limit at 47.25Hz. 3.3 Inverter setup for poor and fluctuating grid conditions With the national grid mean Frequency of Hz (with a Frequency range between 48.5 Hz to 52.1 Hz), and a voltage range between 170 V and 255 V, the set-up parameters of all five grid connected inverters had to be adjusted in order to accommodate these enormous fluctuations while still being able to feed into the national grid. New inverter new settings for Nepal grid conditions: Maximum voltage: 253 V Minimum voltage: 170 V Lower max threshold: Hz (51.25 Hz) Upper min threshold: Hz (47.75 Hz) Lower min threshold: Hz (47.50 Hz) Reconnection delay: 15 s The other inverter parameter settings must also be
5 considered. In particular, the P/f function (reduction in active power vs. frequency) should be disabled. 3.4 Energy production without load shedding (P2) After adjusting the input and output parameters of the three inverters in order to accommodate the weak grid quality, the three PV systems performed rather well, with average monthly performance ratios of between 80-90% (Table 3). The differences between the three PV systems are mainly due to the performances of the grid-inverters, and amount to only 2.3% Irradiation Hi [kwh/m2] PV1 (SMA) Energy ac [kwh] Yf day ac [kwh/kw/day] Monthly PR ac [ ] PV2 (Samil) Energy ac [kwh] Yf day ac [kwh/kw/day] Monthly PR ac [ ] PV3 (Fronius) Energy ac [kwh] Yf day ac [kwh/kw/day] Monthly PR ac [ ] February % % % March % % % April % % % May % % % June % % % July % % % August % % % September* % % % TOTAL 1' % % % Table 3: Monthly irradiation, energy production, final ac yield and PR from to * of the three systems in the NEA Min Bhawan Office. The irradiation during the period was 22% lower than the meteorological data analyzed in 2010 [1], and the Final Yields (Yf) are therefore 20% lower than expected. The PR is very high, however, thanks to the use of inverters with high performance at high irradiation. Table 4 summarizes the values for energy production during nine months of operation, the Final Yields and Performance Ratios of the five PV plants connected to the grid. The losses caused by the planned load sheddings amount to 47.6% of production at the P1, while in P2 the losses caused by unplanned outages correspond to only 1.5% of the 9 months energy production. 3.5 Energy production in a load shedding context (P1) The CES (P1) PVGC system has no storage system and can supply energy only during normal operation. From to , there were 596 power outage events (524 load shedding events and 71 other short blackout events). Figure 9: dc final yield, ac final yield, losses during load shedding events, energy used and energy injected into the grid in location P1, CES/IOE Tribhuvan University, Kathmandu, Nepal. These blackouts correspond to 38% of the time period, and generated 47.6% of losses (475kWh) in the injection into the NEA electrical grid (Figure 9). Storage systems are necessary if the supply conditions do not improve. Figure 8: Power and energy distribution at the P2 Nepal reference location in the NEA Min Bhawan Office, Kathmandu. The power distribution reflects the local climatic conditions (Figure 8); as expected, the irradiance level is very high in the Kathmandu area, despite the fact that the analysis period includes the monsoon months. The energy distribution is therefore high, amounting to between 0.6 and 0.9 kw of the power level, corresponding to between 700 and 1000 W/m2 of the irradiance level. Table 4: summary of the Energy production, Final yields, load shedding losses and Performance Ratios of the five PVGC systems in Kathmandu. Figure 10: Energy production (Yf_ac final yield) and calculated losses during load shedding events; location P1. Figure 10 shows the substantial energy losses resulting from the load shedding events. In particular, during the months of February, March, June and September 2013, the calculated production losses exceeded the effective real production (> 50%) Energy production with load shedding and battery back-up (P3) Table 5 shows the irradiation values (Hi) used in simulations, and the simulated results (PR_sim) compared to actual production levels and PRs.
6 Irradiation Hi Energy dc 2013 Hi sim PR sim [kwh/m2] [kwh] Energy ac [kwh] Yf day ac Monthly [kwh/kw] PR ac [ ] January % February % % March % % April % % May % % June % % July % % August % % September % % October % November % till December % TOTAL 1' ' % Table 5: Irradiation Hi, energy production (dc and ac), daily final yield and PR(ac) from to (location P3), compared to previous simulated values Hi (sim) and PR (sim). Although the system in Imadol, Lalitpur district (P3) was connected in mini-grid mode for most of the observation period, the installation performed very well. The PR ranges between 63.2% and 76.6%. 3.7 Cost of a small PV grid-connected system in Nepal In a previous Feasibility Study [1] conducted in 2009, the cost of a PV system (17.5 NPR/kWh) was higher than the actual cost. Figure 11: Cost per Wp of a PVGC system in Kathmandu, Nepal. The total cost of a 1.1kWp PVGC system was 11, and today it would cost 324 NPR/Wp (2.4 /Wp). With a reliable power grid (without load shedding), the annual energy production would reach 1725kWh, and the cost of the energy produced would therefore correspond to 12.5 NPR/kWh (9.25c /kwh); calculation conditions: no loan, investment paid in cash, VAT included, 25 years of operation, 2%/year O&M (Operation and Maintenance). It should be noted that the cost of the final energy always depends on the O&M activities (2%/year in 25 years correspond to 1/3 of the energy cost). There is still no market for grid inverters at present, so their cost is high. Costs are expected to decrease substantially in the future. In the past the common understanding that PV systems are expensive was due to the high initial investment cost. However, in terms of energy costs, PV systems are very economical when compared to other alternatives, because of the long lifespan of the technology (>25 years). Compared to the current tariff rate for the middleupper class population, where energy consumption exceeds 250kWh, the cost of PV solar energy is near the level of grid-parity, 12.5 NPR/kWh, compared to 11.0 NPR/kWh. However, after NEA Fiscal Year 2011/2012, the energy tariff increased 20% on average [2]. 3.7 Legal framework and policies for solar PVGC power injection As yet there is no legal framework or government approved policy for solar PVGC power injection, in either the low voltage or high voltage transmission lines owned by NEA. However, existing regulations allow entrepreneurs to inject micro-hydro based power into the 11 kv NEA transmission line, provided the injection power is no lower than 100 kw. Most micro-hydro power stations are installed in remote areas of Nepal, generally with installed capacities of lower than 100 kw. A recent exception to this general rule, and the first of its kind in Nepal, is a 680 kwp PV power station, installed in Kathmandu by means of a Japanese Government funded project, and connected to the NEA 11 kv transmission line. NEA has a plan to connect a 100 kwp PV power station, to be installed at its training center in Kharipati near Kathmandu, to the NEA grid, with the assistance of Asian Development Bank. There could be significant power injection from 1 to 10 kwp PV roof top systems in urban areas such as Kathmandu. For this to happen, a legal framework must be formulated as soon as possible. The findings of the ongoing research at the three locations (P1, P2 and P3) will definitely help stakeholders in formulating the required policy. The following factors should be considered while formulating this policy: - the power of PVGC systems installed at roof top level in urban areas should not be less than 1 kwp; - power injection accounting will be based on annual net metering basis only; - roof top systems, including all accessories, should be installed as per the guidelines of the Government of Nepal Alternative Energy Promotion Center, and - incentives of some form (such as tax rebates) should be offered to owners of PVGC roof top systems. The fact that solar PV grid-connected systems are still generally unknown to most of the institutions and politicians in Nepal makes it difficult for policy and decision makers to have confidence in the capacity of this technology to potentially help improve the availability of electricity. This project aims to highlight the appropriateness of photovoltaic technology in the Nepalese context. 3.8 Training and dissemination Solar Home System (SHS) are very common in Nepalese rural and urban contexts. Many companies are installing stand-alone systems throughout the country. The Alternative Energy Promotion Centre (AEPC) organizes training courses on stand-alone systems, but professional companies do not know about gridconnected systems. So in November 2012 a seminar on PV Grid-connected systems, with 60 participants, was conducted at Tribhuvan University in Kathmandu (Figure 12). It was attended by many students and engineers from solar companies wishing to enter the future gridconnected solar market.
7 permitted. As yet there is no legal framework or government approved policy for solar PVGC power injection. There could be significant power injection from 1 to 10 kwp PV roof top systems in urban areas such as in Kathmandu. In 2012 a seminar on PV Grid-connected systems, with 60 participants, was conducted at Tribhuvan University. It was attended by many engineers from solar companies wishing to enter the future PVGC solar market. Figure 12: Training course on PV Grid Connected Systems, November 2012, Tribhuvan University, Kathmandu, Nepal. Increasing the local knowhow through specific training programs and using the pilot plants as a demonstration field, helped the main local stakeholders to gain confidence in grid-connected PV technology. In the early stages of the project it was crucial to involve all the main local stakeholders: universities and schools, government, power utilities and interested local businesses. 4 CONCLUSIONS Five 1.1kWp PV grid-connected systems were installed in the Kathmandu urban area. They have been operating safely for 1 year. The voltage and frequency of the Nepali grid vary considerably, so the inverter settings were adjusted accordingly. New inverter settings: V limits = Vac; frequency reconnection limits: Hz; delay = 15s. The CES (P1) PVGC system has no storage system and can supply energy only during normal operation. From to there were 596 power outage events (524 load shedding events and 71 other short blackout events). These blackouts correspond to 38% of the time period, and generated 47.6% of losses (475kWh) in the injection into the NEA electrical grid. Storage systems are necessary if the supply conditions do not improve. The energy production was as high as expected, comparable to the irradiation level. During these 7 months of first analysis, the irradiation level was 22% lower than NASA meteorological data. PRs were slightly higher than expected in the three reference PV systems at the NEA Office (P2). Short blackout events had little impact on energy production (-1.5%). The performance Ratio of P1 was only 51.3% due to the critical load shedding situation. P3 is not yet connected to the grid (no NEA permission) but the storage system makes it possible to increase overall performance by up to 61.6%. A small distributed grid-connected system of up to 50MW can be installed in a very short period in the Kathmandu Valley context and would help to improve the energy availability in the country. The short-term potential of small rooftop systems across Nepal is greater than 100MW, and a program of 100,000 small solar roofs could be launched. In order to do this, solar energy feed-in must be 5 REFERENCES [1] D. Chianese, D. Pittet, J.N. Shrestha, D. Sharma, A. Zahnd, M.R. Upadhyaya, S. Thapa, N. Sanjel, M. Shah, REPIC Final report: Development of PV gridconnected plants in Nepal - A feasibility study and training programme (2010), and [2] Nepal Electricity Authority (NEA), Annual Report, Fiscal year 2011/2012 (2012) 6 ACKNOWLEDGEMENTS The authors thank REPIC Plattform - c/o NET - St. Ursen (CH), the Swiss interdepartmental platform for the promotion of renewable energy and energy efficiency in international cooperation, and the Fondation Assistance Internationale (FAI) - Lugano (CH) for the financial support provided.
Techno-Economic Analysis of Solar PV Based FM Radio Broadcasting Stations
pp. 150 154 Techno-Economic Analysis of Solar PV Based FM Radio Broadcasting Stations Prakash Khadka 1 *, Jagan Nath Shrestha 2 1 Department of Mechanical Engineering, Institute of Engineering, Pulchowk
Performance Assessment of 100 kw Solar Power Plant Installed at Mar Baselios College of Engineering and Technology
Performance Assessment of 100 kw Solar Power Plant Installed at Mar Baselios College of Engineering and Technology Prakash Thomas Francis, Aida Anna Oommen, Abhijith A.A, Ruby Rajan and Varun S. Muraleedharan
Financial Analysis of Solar Photovoltaic Power plant in India
Financial Analysis of Solar Photovoltaic Power plant in India M. Ganga Prasanna, S. Mahammed Sameer, G. Hemavathi Department of Management Studies MadanapalleInstitute of Technology& Science Post Box No:
TECHNOLOGICAL AND ECONOMIC ASSESSMENT OF PV-DIESEL HYBRID SOLUTIONS VERSUS OTHER TECHNOLOGIES
TECHNOLOGICAL AND ECONOMIC ASSESSMENT OF PV-DIESEL HYBRID SOLUTIONS VERSUS OTHER TECHNOLOGIES Alexander Schies Fraunhofer Institute for Solar Energy Systems ISE PEP Information Workshop: PV- Hybrid Systems
Commercial Outlook for Solar Power Generation
Commercial Outlook for Solar Power Generation International Conference on Alternative Energy 2010 March 27, 2010 Karachi Expo Center Nadeem Haque Nadeem Haque Energy Potential Inc. Topics 1. Market Scenario
Coordinated and Optimized Control of Distributed Generation Integration
Coordinated and Optimized Control of Distributed Generation Integration Hui Yu & Wenpeng Luan China Electric Power Research Institute July, 2015 1 Background and introduction 2 Coordinated control of distributed
The business model of MICRO POWER ECONOMY DIRECTORY. INENSUS GmbH 2011. The business model
INENSUS GmbH TITEL 2011 DIRECTORY 01 The business model of 01 The business model of Micro Power Economy is a strategic tool to establish a market for economically and ecologically viable electrification
Energy Systems Integration
Energy Systems Integration Dr. Martha Symko-Davies Director of Partnerships, ESI March 2015 NREL is a national laboratory of the U.S. Department of Energy, Office of Energy Efficiency and Renewable Energy,
SMA Fuel Save Solution
SMA Fuel Save Solution SMA solutions for industrial photovoltaic diesel hybrid systems Electricity costs ($/kwh) Profit Diesel Genset Photovoltaic Today TIME PV electricity generation costs today are already
Energy Efficiency in the Greek Hotel Sector November 17th, 2009, Berlin, Germany Current Situation of PV systems deployment in Greece
Energy Efficiency in the Greek Hotel Sector November 17th, 2009, Berlin, Germany Current Situation of PV systems deployment in Greece Dr. Stathis TSELEPIS, CRES, [email protected] Overview Presentation of
AC COUPLED HYBRID SYSTEMS AND MINI GRIDS
, Michael; Hermes, Matthias SMA Technologie AG Hannoversche Str. 1-5 34266 Niestetal GERMANY E-mail: [email protected] E-mail: [email protected] 1. INTRODUCTION Distributed supply based on renewable
Modeling of PV Based Distributed Generator Systems with Diverse Load Patterns
Modeling of PV Based Distributed Generator Systems with Diverse Load Patterns Mehmet H. Cintuglu, [email protected], Armando Altamirano, [email protected] Osama A. Mohammed, [email protected] Energy Systems
Feasibility of Large Scale Solar PV in Nepal
Feasibility of Large Scale Solar PV in Nepal Solar Power to Fight Nepal s Energy Crisis - Presentation to IOE Centre for Energy Studies- Sandeep Giri President, Gham Power Nepal Private Limited Kathmandu,
Totally Integrated Power SIESTORAGE. The modular energy storage system for a reliable power supply. www.siemens.com/siestorage
Totally Integrated Power SIESTORAGE The modular energy storage system for a reliable power supply www.siemens.com/siestorage Totally Integrated Power (TIP) We bring power to the point. Our products, systems,
Thoughts on Inclusive Innovation: The Kenya Rural Electrification Initiative
Thoughts on Inclusive Innovation: The Kenya Rural Electrification Initiative Prof. Gerry George Imperial College London Themes from break-out sessions Radical changes occurring (e.g., climate change, urbanisation,
SA Power Networks Planning for Solar PV? Customer information guide to network connected solar PV inverter systems
SA Power Networks Planning for Solar PV? Customer information guide to network connected solar PV inverter systems Contents Introduction 3 How solar PV power systems work 4 Solar modules 5 Is solar power
Yield Reduction due to Shading:
1x4 1x16 10 x CBC Energy A/S x Danfoss Solar Inverters CBC-40W Poly 40 W TLX 1,5k 5 ; 1x11 3x4 0 1,5kW 1536 x CBC Energy A/S 1 x Power-One CBC-40W Poly 40 W TRIO-7,6-TL-OUTD 30 ; 4x14 0 7,6kW Location:
OFF-GRID ELECTRICITY GENERATION WITH HYBRID RENEWABLE ENERGY TECHNOLOGIES IN IRAQ: AN APPLICATION OF HOMER
Diyala Journal of Engineering Sciences ISSN 1999-8716 Printed in Iraq Second Engineering Scientific Conference College of Engineering University of Diyala 16-17 December. 2015, pp. 277-286 OFF-GRID ELECTRICITY
Micro-hydro applications in rural areas
OASYS South Asia: Dundee Workshop 20 Micro-hydro applications in rural areas Dr Arthur Williams Dept. of Electrical & Electronic Engineering University of Nottingham, UK Types of hydropower Conventional
PV And Storage: Solutions with Potential
EN PV And Storage: Solutions with Potential Energy on demand with the Sunny Central Storage Large-scale storages... support the growth of renewable energies complete diesel and solar diesel hybrid systems
Gross/Active PV Surface Area: 13.094,40 / 13.086,29 m². Energy Produced by PV Array (AC):
1x17 1x17 1x 8 x Trina Solar Trina TSM-PC5A 6 6 W 5 ; x Danfoss Solar Inverters TLX 1,5k 1,5kW Location: Arrondissement d'issoire Climate Data Record: Arrondissement d'issoire PV Output:.8, kwp Gross/Active
Storage Battery System Using Lithium ion Batteries
Offices and schools Utilities / Renewable energy Storage Battery System Using Lithium ion Batteries Worldwide Expansion of Storage Battery System s Commercial Buildings Residential The Smart Energy System
POWER PURCHASE AGREEMENT FOR ROOFTOP SOLAR PV PLANTS WITH NET METERING ARRANGEMENT
POWER PURCHASE AGREEMENT FOR ROOFTOP SOLAR PV PLANTS WITH NET METERING ARRANGEMENT This Power Purchase agreement is entered into at (place).. on this. day of between Electricity Supply Company Limited
AC Coupling of Inverters for Grid Tied PV Systems
AC Coupling of Inverters for Grid Tied PV Systems AC Coupling with Conext s, Xantrex GT Inverters, and Conext TX Inverters Application Note 976-0240-01-01 Rev B DANGER RISK OF FIRE, ELECTRIC SHOCK, EXPLOSION,
Professional Simulation Programmes. Design and Optimization
Professional Simulation Programmes for the Design and Optimization of Solar Thermal and Photovoltaic Systems Gerhard Valentin 1 Agenda Introduction Our Mission PV*SOL Simulation of Photovoltaic Systems
Perspectives for ESS in Germany and Europe legal situation and applications StoREgio energy storage system association
Perspectives for ESS in Germany and Europe legal situation and applications StoREgio energy storage system association Dr. Peter Eckerle Managing Director [email protected] Topics Who is StoREgio?
Policy and regulatory barriers to renewable energy deployment in South East Europe
Policy and regulatory barriers to renewable energy deployment in South East Europe Andreas Tuerk Dorian Frieden, Mislav Kirac, Mak Dukan, Leo Jerkic 3. March 2016 www.joanneum.at/life Method applied Interviews
Potential of Solarhomesystems, Biogas-plants and Micro-hydro in Nepal and Opportunities for MFI
Potential of Solarhomesystems, Biogas-plants and Micro-hydro in Nepal and Opportunities for MFI A Paper prepared for the MicroFinanceSummit 2010 in Kathmandu, Nepal. Prepared by Michael Wegstein, Financial
SOLARCARE SERIES PRODUCT AND APPLICATION GUIDE
SOLARCARE SERIES PRODUCT AND APPLICATION GUIDE for solar energy management LEATEC Delivering Solutions for Energy Management SOLAR ENERGY DATA CENTER BUILDING 4 to8 String Monitoring with 0.% Accuracy
2008-09 2009-10 2010-11 2011-12 2012- Total 5,926 24,514 66,355 97,042 68,624 262,461 0.6 4.7 22.9 94.3 101.6 224.1
Jan-10 Mar-10 May-10 Jul-10 Sep-10 Nov-10 Jan-11 Mar-11 May-11 Jul-11 Sep-11 Nov-11 Jan-12 Mar-12 May-12 Jul-12 Sep-12 Nov-12 Jan-13 MW kw Australians have installed more than a million rooftop photovoltaic
PERFORMANCE OF MPPT CHARGE CONTROLLERS A STATE OF THE ART ANALYSIS
PERFORMANCE OF MPPT CHARGE CONTROLLERS A STATE OF THE ART ANALYSIS Michael Müller 1, Roland Bründlinger 2, Ortwin Arz 1, Werner Miller 1, Joachim Schulz 2, Georg Lauss 2 1. STECA ELEKTRONIK GMBH, Mammostr.
ABB central inverters PVS800 100 to 1000 kw
Solar inverters ABB central inverters PVS800 100 to 1000 kw ABB central inverters raise reliability, efficiency and ease of installation to new levels. The inverters are aimed at system integrators and
Photovoltaic Systems II EE 446/646
Photovoltaic Systems II EE 446/646 Components of a grid-connected residential PV system (net meter) The inverter contains: Ground Fault Circuit Interrupter (GFCI) MPPT and Circuitry to disconnect the PV
The Status of the Wind Power Market in Egypt. Dr. Walid El-Khattam Ain Shams University (Cairo, Egypt) The Egyptian Electricity Regulator (EgyptERA)
The Status of the Wind Power Market in Egypt Dr. Walid El-Khattam Ain Shams University (Cairo, Egypt) The Egyptian Electricity Regulator (EgyptERA) Berlin, June 11 th, 2013 1 Contents Key Challenges for
The Renewable Energy Sector in Cyprus
Energie The Renewable Energy Sector in Cyprus Dr. Isabelle Riesenkampff, German Energy Agency (dena) Cologne, 29 November 2010 Conference Solar Industry in the Republic of Cyprus Outline: The Renewable
OFF-GRID SOLAR CASE STUDY AND OPPORTUNITIES IN KENYA J.M.P. MBITHI Deputy Director, Renewable Energy MINISTRY OF ENERGY AND PETROLEUM
OFF-GRID SOLAR CASE STUDY AND OPPORTUNITIES IN KENYA J.M.P. MBITHI Deputy Director, Renewable Energy MINISTRY OF ENERGY AND PETROLEUM PRESENTATION SUMMARY Introduction-Power situation in Kenya Off-grid
EssPro Energy Storage Grid Substation The power to control energy
EssPro Energy Storage Grid Substation The power to control energy EssPro Grid gives you the power to control energy helping to keep smart grids in balance Maximizing the value and performance of energy
Application of photovoltaic s in the building and construction industry as a power generating facility
Application of photovoltaic s in the building and construction industry as a power generating facility Matthew P. Peloso Science and Technology Business Services LLP 10 Gopeng Street, ICON #34-22 Singapore,
Reliability and security of electricity supply: the Italian blackout
Reliability and security of electricity supply: the Italian blackout Alessandro Ortis President AEEG The Regulatory Authority for Electricity and Gas of Italy 5th NARUC/CEER Energy Regulators Roundtable
Tina Völker, Renewables Academy AG (RENAC) TREE-Project: Transfer Renewable Energy & Efficiency International Capacity Building
Tina Völker, Renewables Academy AG (RENAC) TREE-Project: Transfer Renewable Energy & Efficiency International Capacity Building RENAC Renewables Academy Trainings Academic courses Services Client specific
SOFTWARE FOR THE OPTIMAL ALLOCATION OF EV CHARGERS INTO THE POWER DISTRIBUTION GRID
SOFTWARE FOR THE OPTIMAL ALLOCATION OF EV CHARGERS INTO THE POWER DISTRIBUTION GRID Amparo MOCHOLÍ MUNERA, Carlos BLASCO LLOPIS, Irene AGUADO CORTEZÓN, Vicente FUSTER ROIG Instituto Tecnológico de la Energía
Photovoltaic in Mexico Recent Developments and Future
Photovoltaic in Mexico Recent Developments and Future Rodolfo Martínez Strevel Berlin, Germany May 23th, 2013 Bufete de Tecnología Solar, S.A. (BUTECSA) Production of Primary Energy in Mexico, 2011 % 7,0
CHANGING THE WORLD WITH COMPELLING IDEAS. German Indian Renewable Energy Dialogue 1st of October 2008
Titel: IBC SOLAR mit starken Ideen die Welt verändern Autor: Ort, 00. Monat 2008 CHANGING THE WORLD WITH COMPELLING IDEAS German Indian Renewable Energy Dialogue 1st of October 2008 2008 IBC SOLAR Agenda
International Solar Energy Arena January 23rd, 2009, Istanbul STEAM (Strategic Technical Economic Research Center)
International Solar Energy Arena January 23rd, 2009, Istanbul STEAM (Strategic Technical Economic Research Center) Good morning. Sayin Bakanım. Members of Parliament. Ladies and Gentlemen. Slide 1: Opening
Self-consumption. that you need to purchase from your power company. Bosch Solar Energy recommends photovoltaic systems with self-consumption.
Self-consumption of Solar Energy Bosch Solar Energy Self-consumption The self-consumption of solar energy refers to the proportion of energy which is used directly in the building where a PV system is
Photovoltaic Roofing in Mediterranean Climate Countries
1 Photovoltaic Roofing in Mediterranean Climate Countries Pere Alavedra¹, Amado Guzmán ², Mauricio Torres ³, Samantha Gallowayº, Daniel Alavedra" Department of Construction Engineering, Catalonia Polytechnic
The Energy Transition in Germany Past, Present and Future
The Energy Transition in Germany Past, Present and Future smart energy Paraná, Conferência International 2014 9 May 2014 Dr. Carsten Tschamber A Brief History of the Energiewende 1973 - oil crisis, Federal
Solar Variability and Forecasting
Solar Variability and Forecasting Jan Kleissl, Chi Chow, Matt Lave, Patrick Mathiesen, Anders Nottrott, Bryan Urquhart Mechanical & Environmental Engineering, UC San Diego http://solar.ucsd.edu Variability
Performance ratio. Contents. Quality factor for the PV plant
Performance ratio Quality factor for the PV plant Contents The performance ratio is one of the most important variables for evaluating the efficiency of a PV plant. Specifically, the performance ratio
Using the sun to generate electricity
Using the sun to generate electricity Image source: http://www.globalsolarcenter.com/files/2009/04/commercial-solar.jpg Solar panels information sheet What are the benefits? How does it work? What is the
Advanced Electricity Storage Technologies Program. Smart Energy Storage (Trading as Ecoult) Final Public Report
Advanced Electricity Storage Technologies Program Smart Energy Storage (Trading as Ecoult) Final Public Report Introduction Ecoult, working with CSIRO as its principal subcontractor, was provided $1,825,440
About Southern California Edison
About Southern California Edison One of the nations largest investorowned utilities with 125 years of service. Service Area 50,000 square miles Over 430 cities and communities Population Served Nearly
OFF GRID HYBRID POWER PLANT Discover how to maximize the usage of the renewable energy.
OFF GRID HYBRID POWER PLANT Discover how to maximize the usage of the renewable energy. Introduction by Michele GRECA ( VP for Business Development) [email protected] Presentation by Gaetano
Photovoltaics in Germany Market Development and Perspectives
Photovoltaics in Germany Market Development and Perspectives Matthias Reitzenstein German Solar Industry Association (BSW-Solar) German Solar Industry Association 2 TASK To represent the German solar industry
Green Education through Green Power: Photovoltaics as a Conduit to Interdisciplinary Learning
Green Education through Green Power: Photovoltaics as a Conduit to Interdisciplinary Learning The proposed project will enable ABC University to: 1) develop an interdisciplinary educational program to
Concept for a DC low voltage house
Concept for a DC low voltage house Maaike M. Friedeman 1 Elisa C. Boelman Dr. Eng., MBA 1 Arjan van Timmeren, Ir. 1 Joop Schoonman, Prof. Dr. 2 1 TU Delft, Faculty of Architecture, dept. of building technology,
Balancing and Reserve Power by PV Plants. Ken Christensen MSEE, BSEE Global Product Manager, SMA Utility-Scale and Hybrid Solutions
Balancing and Reserve Power by PV Plants Ken Christensen MSEE, BSEE Global Product Manager, SMA Utility-Scale and Hybrid Solutions IEEE PES 2014 2 Disclaimer IMPORTANT LEGAL NOTICE This presentation does
A-B-C model for Off-grid Energy Solutions
A-B-C model for Off-grid Energy Solutions Monali Ranade World Bank Institute Climate Change Practice, as part of Incubating Innovation for Rural Electrification: The Telecom-Energy Initiative September
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI Draft Maharashtra Electricity Regulatory Commission (Net Metering for Rooftop Solar Systems) Regulations, 2015 Electricity Act, 2003 No. MERC / Legal
FIXED CHARGE: This is a cost that goes towards making the service available, including
ELECTRICITY BILL COMPONENTS FIXED CHARGE: This is a cost that goes towards making the service available, including installation and maintenance of poles, power lines and equipment, and 24-hour customer
First results of PV net metering implementation in Cyprus PV-NET. Ioannis Koumparou
PV-NET Promotion of PV energy through net metering optimization First results of PV net metering implementation in Cyprus Ioannis Koumparou PV Technology Laboratory FOSS Research Centre for Sustainable
A Stable DC Power Supply for Photovoltaic Systems
Int. J. of Thermal & Environmental Engineering Volume 12, No. 1 (216) 67-71 A Stable DC Power Supply for Photovoltaic Systems Hussain A. Attia*, Beza Negash Getu, and Nasser A. Hamad Department of Electrical,
Energy Storage Systems. New solutions for a new energy environment
Energy Storage Systems New solutions for a new energy environment Facilitating the integration of renewable energy The increase in the quantity of electricity produced by renewable sources is creating
Electricity from PV systems how does it work?
Electricity from photovoltaic systems Bosch Solar Energy 2 Electricity from PV systems Electricity from PV systems how does it work? Photovoltaics: This is the name given to direct conversion of radiant
Grid Connected Storage Various Applications Realised with Proven Technologies. Wilhelm van Butselaar Clean Energy Week 2013, Brisbane July 2013
Grid Connected Storage Various Applications Realised with Proven Technologies Wilhelm van Butselaar Clean Energy Week 2013, Brisbane July 2013 Disclaimer IMPORTANT LEGAL NOTICE This presentation does not
Spurring Growth of Renewable Energies in MENA through Private Sector Investment
MENA-OECD Business Council: Task Force on Energy and Infrastructure WORKING PAPER PRESENTING THE PRIVATE SECTOR S VIEW Spurring Growth of Renewable Energies in MENA through Private Sector Investment Agenda
Uttar Pradesh Rooftop Solar Photovoltaic Power Plant Policy, 2014
Uttar Pradesh Rooftop Solar Photovoltaic Power Plant Policy, 2014 Table of Contents 1- PREAMBLE - 1 2- OBJECTIVES - 1 3- OPERATIVE PERIOD - 1 4- IMPLEMENTATION PLAN - 2 5- ELIGIBLE ENTITIES - 2 6- TARGETS
Short-term solar energy forecasting for network stability
Short-term solar energy forecasting for network stability Dependable Systems and Software Saarland University Germany What is this talk about? Photovoltaic energy production is an important part of the
Minihydro to boost local economic growth The case of Nepal
Minihydro to boost local economic growth The case of Nepal Clara Kayser-Bril for T.A.C.E.C. Workshop Milano July 9 th 2014 Nepal s hydropower potential Potential 40 GW Installed 1 GW 2 Photo : Clara KB
APPLICATION NOTE TESTING PV MICRO INVERTERS USING A FOUR QUADRANT CAPABLE PROGRAMMABLE AC POWER SOURCE FOR GRID SIMULATION. Abstract.
TESTING PV MICRO INVERTERS USING A FOUR QUADRANT CAPABLE PROGRAMMABLE AC POWER SOURCE FOR GRID SIMULATION Abstract This application note describes the four quadrant mode of operation of a linear AC Power
Brochure Introducing HVDC
Brochure Introducing HVDC ABB and HVDC The world s first commercial high-voltage direct current (HVDC) link, situated between the Swedish mainland and the island Gotland, was delivered by ABB already in
Photo Kirklees IS SOLAR ENERGY FOR ME? A guide to going solar
Photo Kirklees IS SOLAR ENERGY FOR ME? A guide to going solar WHY SOLAR? Economics Solar energy can reduce bills, earn you money and protect you from rising energy prices. Solar is a free source of energy
STEADYSUN THEnergy white paper. Energy Generation Forecasting in Solar-Diesel-Hybrid Applications
STEADYSUN THEnergy white paper Energy Generation Forecasting in Solar-Diesel-Hybrid Applications April 2016 Content 1 Introduction... 3 2 Weather forecasting for solar-diesel hybrid systems... 4 2.1 The
COMMENTS OF THE SOLAR ALLIANCE NEW JERSEY INTERCONNECTION RULES APRIL 29 TH, 2011
COMMENTS OF THE SOLAR ALLIANCE NEW JERSEY INTERCONNECTION RULES APRIL 29 TH, 2011 I. Background The Solar Alliance is a group of approximately 30 of the largest photovoltaic (PV) solar development and
SOLAR PV-WIND HYBRID POWER GENERATION SYSTEM
SOLAR PV-WIND HYBRID POWER GENERATION SYSTEM J.Godson 1,M.Karthick 2,T.Muthukrishnan 3,M.S.Sivagamasundari 4 Final year UG students, Department of EEE,V V College of Engineering,Tisaiyanvilai, Tirunelveli,
Microgrid Building block for Smart Cities
Microgrid Building block for Smart Cities Shay Bahramirad, Ph.D. Manager of Smart Grid & Technology December 2014 COMED OVERVIEW 1 The service territory covers 11,400 mi 2 in Northern Illinois Serving
Future Grids: challenges and opportunities
Future Grids: challenges and opportunities Sistemi e strumenti per l'automazione, A. Flammini, AA2011-2012 Energy Distribution Today It is common believe that AC distribution is the most economic approach:
Distributed Power, Renewables, Stored Energy and the Grid Blinkless Synchronous Inverter System
Distributed Power, Renewables, Stored Energy and the Grid Blinkless Synchronous Inverter Go Electric Inc. www.goelectricinc.com 1 Distributed Power, Renewables, Stored Energy and the Grid Blinkless Synchronous
Simple project evaluation spreadsheet model
Simple project evaluation spreadsheet model Africa Electricity Institute Practitioner Workshop 15 November 2011 -- Dakar, Senegal Chris Greacen Two very different models Used by: Excel financial model
Photovoltaics and Solar Thermal Energy in Germany: Market Development, Applications, Industry and Technology
Photovoltaics and Solar Thermal Energy in Germany: Market Development, Applications, Industry and Technology Gerhard Stryi-Hipp Managing Director BSW - Bundesverband Solarwirtschaft e.v. German Solar Industry
The Solar Power Specialists. Elm Park House, Elm Park Court, Pinner, Middlesex, HA5 3NN Solutions House, Unit A19, 20 Heron Road, Belfast, BT3 9LE
The Solar Power Specialists GB: 0845 64 39 772 NI: 0845 50 40 444 Email: [email protected] Visit: www.metartecsolar.com Elm Park House, Elm Park Court, Pinner, Middlesex, HA5 3NN Solutions House,
Micro Hydro Interconnected Mini Grids in Nepal: Potential and Pitfalls (Experience from a pilot Interconnected Mini Grid projects in rural Nepal)
Micro Hydro Interconnected Mini Grids in Nepal: Potential and Pitfalls (Experience from a pilot Interconnected Mini Grid projects in rural Nepal) Bhupendra Shakya 1, Anna Bruce 1, Iain MacGill 2 1 School
Western Australian Feed-In Tariff Discussion Paper
Western Australian Feed-In Tariff Discussion Paper OVERVIEW In September 2008, the incoming State Government announced its intention to introduce a feed-in tariff as part of the Liberal Plan for Environmental
Solar power plants for residential, commercial, utility and off-grid applications Part 2
Solar power plants for residential, commercial, utility and off-grid applications Part 2 Professor Chem Nayar INTERNATIONAL CONFERENCE 2014 POWER AND ENERGY SYSTEMS: TOWARDS SUSTAINABLE ENERGY, BANGALORE
Energy Depot GmbH PRODUCT AND APPLICATION GUIDE. Total Monitoring Solution for PV. Delivering Solutions for Energy Management
Energy Depot GmbH Delivering Solutions for Energy Management PRODUCT AND APPLICATION GUIDE Total Monitoring Solution for PV SOLAR LOGGER & ANALYSIS DC STRING MONITORING Residential Comprehensive Solar
Solar Panels and the Smart Grid
Solar Panels and the Smart Grid In the Pepco Region Steve Sunderhauf Jeff Roman Joshua Cadoret David Pirtle Outline Pepco Region Background Renewable Portfolio Standards (RPS) Pepco s Blueprint for the
Green Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process
Green Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process Presented by: Marianne Mannschreck Date: Welcome A Look at the Net Energy Metering
Leasing Residential PV Systems BY MICHAEL RUTBERG; ANTONIO BOUZA, ASSOCIATE MEMBER ASHRAE
This article was published in ASHRAE Journal, December 2013. Copyright 2013 ASHRAE. Posted at www.ashrae.org. This article may not be copied and/or distributed electronically or in paper form without permission
Solar technology. A guide to solar power at utility scale. in Africa
Solar technology A guide to solar power at utility scale in Africa About solar power Solar electricity is generated using a free and abundant energy source the sun. In a single hour, the sun transmits
Report on the Status of Net Energy Metering In the State of Maryland. Prepared by The Public Service Commission of Maryland
Report on the Status of Net Energy Metering In the State of Maryland Prepared by The Public Service Commission of Maryland Prepared for the General Assembly of Maryland Under Public Utilities Article 7-306(h)
Enhancing solar contribution in PV-Diesel Hybrid Power Plants with advanced Li-ion Energy Storage Systems Michael Lippert
Enhancing solar contribution in PV-Diesel Hybrid Power Plants with advanced Li-ion Energy Storage Systems Michael Lippert Intersolar Munich, 1 June 215 Increasing numbers of microgrids Factors New facility
Design of a Photovoltaic Data Monitoring System and Performance Analysis of the 56 kw the Murdoch University Library Photovoltaic System
School of Engineering and Information Technology ENG460 Engineering Thesis Design of a Photovoltaic Data Monitoring System and Performance Analysis of the 56 kw the Murdoch University Library Photovoltaic
