Installation Guide. Recommendations For Installation of AWWA C900 And AWWA C905
|
|
|
- Marjory Randall
- 9 years ago
- Views:
Transcription
1 Installation Guide Recommendations For Installation of AWWA C900 And AWWA C905
2 INDEX Index Diamond Plastic Pipe PVC Installation Guide Receiving Handling & Storage Inspection Unloading Cold Weather Handling Joint Weights (TABLE 1) Trench Preparation Stringing Pipe Width Dew atering Foundation Bedding Gasket Lubricant Assembly Curvilinear Alignment Thrust Restraint Thrust Forces Service Connections Casing Dimensions (C900) (C905) Haunching & Initial Backfill Acceptance Testing Final Backfill LOK Warranty
3 DIAMOND C900 & C905 PVC PIPE Diamond Plastics Corporation supplies PVC pipe of AWWA C-900 and AWWA C-905 dimensions w ith integral coupling w hich utilizes an elastomeric gasket for an assembled seal. In this guide w e w ill attempt to outline the basic handling, storage, assembly, and installation procedures for these products. -Installation Guide Disclaimer- TECHNICAL DATA CONTAINED IN THIS INSTALLATION GUIDE IS FURNISHED WITHOUT CHARGE AND IS ACCEPTED BY RECIPIENT AT RECIPIENT S SOLE RISK. EVERY EFFORT HAS BEEN MADE TO VERIFY THE INFORMATION CONTAINED IN THIS INSTALLATION GUIDE, HOWEVER, DIAMOND PLASTICS CORPORATION MAKES NO REPRESENTATION REGARDING ITS ACCURACY DIAMOND PLASTICS CORPORATION ASSUMES NO RESPONSIBILITY FOR, AND IS NOT LIABLE FOR, ANY USE OF THE INFORMATION CONTAINED IN THIS INSTALLATION GUIDE OR ANY USE MADE OF THIS INSTALLATION GUIDE FOR WHICH IT WAS NOT INTENDED. IN NO EVENT SHALL DIAMOND PLASTICS CORPORATION BE LIABLE FOR INCIDENTAL OR CONSEQUENTIAL DAMAGES CLAIMED ATTRIBUTABLE TO USE OF THIS INSTALLATION GUIDE. IF THIS INSTALLATION GUIDE IS UTILIZED AS A SUBMITTAL APPURTENANCE, THE USER ASSUMES ALL RESPONSIBILITY TO VERIFY THE ACCURACY OF INFORMATION CONTAINED IN THIS INSTALLATION GUIDE AND TO CONFIRM THAT THIS GUIDE IS OF CURRENT PUBLICATION. -Receiving and Handling- Inspection: Each pipe shipment should be inspected carefully upon arrival. The carrier is responsible for delivering the pipe. Make certain all material listed on the bill-of-lading has arrived. The receiver must make certain there has been no loss or damage. Should there be any errors or damage, make proper note on the delivery receipt. Make claim in accordance w ith the carrier s instruction. Do not dispose of any damaged material. Carrier w ill advise you of the procedure to follow for freight damage. Unloading Pipe should be low ered, not dropped, from trucks to the ground or into a trench. DO NOT ATTEMPT TO HANDLE PIPE BUNDLES BY PULLING ON STRAPPING OR PACKAGING MATERIAL. The forklift truck, boom and sling, or other material handling Photo #1 equipment should be equipped to avoid excessive sw inging. DO NOT USE CHAINS AS A SLING. Avoid all impact blow s, gouging, or abrasions caused by metal surfaces, rocks, material handling equipment, or any other source. Cold Weather Handling: Extra care should be used in handling during cold w eather
4 WARNING: Carelessly unloading pipe can be hazardous. Use appropriate equipment and stay clear when removing tie-downs, banding, and dunnage material. TABLE 1 Approximate Joint Weights (Lbs) Size DR 14 DR 18 DR 25 DR 32.5 DR 41 DR 51 4" " " " " " " " " " " " " " Trench Preparation- Proper installation procedures and trench preparation are essential to successful PVC pipe performance. Trench preparation procedures for PVC pipe do not vary substantially from procedures used w ith other piping products. There should be no more trench prepared than the footage of pipe w hich can be laid in a day. A typical trench cross section and terminology are given in figure 1. Figure 1-3 -
5 Stringing Pipe: Pipe should be placed near the trench on the opposite side of the excavated earth. The coupling should be pointed in the direction of w ork progress. Trench width: Working space is the primary consideration in determining the trench w idth to be used. Trench w idth at the ground surface may vary w ith and depend upon depth, type of soils, and position of surface structures. The minimum clear w idth of the trench, sheeted or unsheeted, measured at the springline of the pipe is generally specified at least one foot (300 mm) greater than the outside diameter of the pipe to enable Photo 2 backfill material to be installed in the haunching area. Refer to Figure 1 for the location of the haunch area. Where embedment compaction is required, the trench shall be w ide enough to accommodate the compaction equipment. If minimum trench w idth is exceeded, and embedment compaction is required, pipe zone haunching should be compacted at least one pipe diameter from the pipe on both sides of the pipe. Dewatering: Where conditions are such that running or standing w ater occurs in the trench bottom or the soil in the trench bottom displays a quick tendency, the w ater should be removed by pumps and suitable means such as w ell points or pervious underdrain bedding until the pipe has been installed and the backfill has been placed to a sufficient height to prevent pipe flotation. Photo 3 Foundation: An adequate or stable foundation should be present (or provided) to uniformly support the full length of the pipe. Bell holes should be provided at each joint to permit proper assembly and support of the pipe. Unstable trench bottoms shall be stabilized by methods and w ith materials required, by the specifying engineer, to provide adequate and permanent support for the conditions encountered
6 Bedding: When rock, hard pan, boulders, or other material (w hich might damage the pipe) are encountered in the trench, the trench bottom should be over excavated 1/4th of the pipe diameter, or a minimum of four inches to permit bedding. The bedding should consist of an evenly graded, free flow ing, granular material w hich is free of large stones or frozen material and w ith particle size of up to approximately 10% of the pipe size and no larger than 1 ½ in size. Bell holes should be utilized to reduce axial deflection and support the barrel of the pipe. Photo 4 -Lubricant- Clean any dirt or foreign matter from the gasket and spigot. An even, uniform application of gasket lubricant must be applied to the bevel and spigot to the first insert reference Photo 5 (in open Photo 6 (remove debris) Photo 7 (clean annular storage) space) mark as w ell as the contact surface of the gasket. Gasket lubricant may be applied w ith a sw ab, brush, or roller. Gasket lube is furnished w ith each truckload of pipe. Additional lubricant may be purchased from your distributor. Photo 8 (lubricate gasket) Photo 9 (lubricate spigot) - 5 -
7 -Assembly- Assembly is made by sliding the lubricated spigot end into the gasketed bell end. The gasket seals the joint against leaks, into or out of the pipeline. Insert the spigot end into the socket so that it is near contact w ith the gasket. Keep the pipe lengths in proper alignment. Brace the bell w hile the spigot end is pushed through the gasket so that previously completed joints in the line will not be stacked, over belled, or inserted past the second reference mark. (refer to Encasements.) Push the spigot end in until the lip of the bell is Photo 10 (Large Diameter Joint Assembly) inserted beyond the first insert reference mark, laying length w ill be lost. Loss of laying length can be significant on long footage projects. Also, joint flexibility is reduced w hen the spigot is inserted beyond the second insert reference mark. Some joints may require barring to seat the joint. If so, use a w ood block to protect the end of the pipe. A come-a-long may be preferred to the bar and block, but a sw inging stab is not recommended. Where the physical w eight or trench conditions make the recommended betw een the reference marks on the spigot end. If the spigot is methods unsafe, joints may be assembled using mechanical equipment provided that the pipe is properly lubed and aligned. The end must be protected from damage, and the joint must not be over belled or inserted beyond the second insert reference mark. If the second insertion mark is not visible after assembly, the pipe w as over-inserted. The joint needs to be disassembled and done correctly. Likew ise, if the first mark falls w ell short of the lip of the bell, the pipe needs to be pushed a little further until the lip is betw een the tw o reference marks. Here the cutaw ay show s that the joint has no flexibility, and cannot expand. An over-assembled joint can be under substantial stress. In pressure pipe these stresses are additive to hydrostatic stresses Photo # 12: Over Inserted Spigot Photo # 11: Properly Inserted Spigot and bells can fail directly due to overinsertion
8 Curvilinear Alignment (Without Bending the Pipe.) During construction, it may become necessary to make very slight changes of direction. When this situation is encountered, the clearance betw een the inside diameter of the socket and the outside diameter of the spigot may be utilized to accomplish curvilinear alignment w ithout bending the pipe. Neither the pipe nor the joint should be axially deflected in any manner to cause stress at the joint. Diamond C900 and C905 w ill accommodate a 1 change in direction for a four inch offset per joint. The minimum radius of curvature for 20 joints is 1,146 feet. This, minimum radius One Degree Offset of curvature, assumes the spigot is not inserted beyond the second insert reference mark. Inserting the spigot beyond the second insert reference mark reduces allow able joint offset. -Thrust Restraint- Diamond s gasketed C-900 and C-905 PVC pipe utilizes an integral bell socket w ith an elastomeric sealing gasket and is not self restraining. Therefore, thrust restraining is required at certain points in the piping system such as at valves, change in horizontal or vertical direction, fittings, etc. The follow ing diagram illustrates typical locations w here thrust restraint is required. While thrust blocking is depicted, thrust restraint devices meeting the requirements of ASTM F1674 may be utilized. Typical joint restraint devices are seen in photo
9 Thrust at 90 degree elbow based on 100 psi internal pressure. Pipe Size* Thrust 4 (100) C-900 2,560 6 (150) C-900 5,290 8 (200) C-900 9, (250) C , (300) C , (350) C , (400) C , (450) C , (500) C , (600) C , (750) C , (900) C , (1050) C , (1200) C ,000 As the chart above demonstrates, enormous thrust loads may be generated. Properly designed thrust restraint is a must. The specifying engineer should provide this information. -Service Connections- Service lines are connected to w ater mains by either: 1. Direct Tapping 2. Saddle Tapping 3. Tapping Sleeve & Valve Direct tapping is restricted to C900 pipe sizes 6 through 12 inch w ith pressure classes of DR 18 or DR 14. Saddle tapping is restricted to a maximum corporation stop of 2 inches. Tapping sleeves and valves are used w hen service connections larger than 2 inches are required. Direct tapping of Diamond C-905 pipe is not recommended. A w ide strap tapping saddle may be used for outlets less than tw o inches. For outlets larger than tw o inches, use a tapping sleeve and valve. Taps should follow the placement guidelines in the Uni-Bell Tapping Guide for PVC Pressure Pipe. It is recommended that prior to tapping, those responsible for completion of the tap w atch the video by Uni-Bell PVC Pipe Association entitled Direct Tapping PVC Pipe and familiarize themselves w ith the Uni-Bell Tapping Guide for PVC Pressure Pipe. You may obtain these from your Diamond Pipe Sales Representative or from the Uni-Bell PVC PIP Association ( ) w w w.uni-bell.org. Proper tapping procedures and tools are very important in maintaining safety
10 -Casings- Casings may be installed by boring w here open excavation is not desirable, for example, under highw ays, runw ays, or railw ays. To provide long term support to the pipe and to prevent damage to belled sockets during installation, skids or casing spacers must be attached to the pipe before the pipe is installed in casings. Casing spacers or skids should be fastened securely to the pipe w ith steel strapping, cables, or clamps. The installer must ensure the pipe is not over-belled or inserted beyond the second insert reference mark, the skids or casing spacers must be aligned w ith the reference marks on the spigot. Use of gasket lube betw een the skids and the casing can ease installation into the casing. (Caution: Prolonged exposure to petroleum products can damage some elastomeric gaskets.) Pipe dimensions may be found in the follow ing tables. The socket diameter is the critical dimension for casing installation
11 RIEBER SEAL AWWA C900 PIPE DIMENSIONS Nominal Pipe Approximate C900 Minimum Wall Size O.D. Socket O.D. DR-14 DR-18 DR-25 4 (100) (121.9) 6 ½.343 (8.71).267 (6.78).192 (4.88) 6 (150) (175.3) 9 ¼.493 (12.52).383 (9.73).276 (7.01) 8 (200) (229.9) 11 ¾.646 (16.41).503 (12.78).362 (9.19) 10 (250) (281.9) 14 ¼.793 (20.14).617 (15.67).444 (11.28) 12 (300) (335.3) 16 ¾.943 (23.95).733 (18.62).528 (13.41)
12 Nominal Pipe Approximate C905 Minimum Wall Size O.D. Socket O.D. DR-18 DR-21 DR-25 DR-32.5 DR-41 DR (350) (388.6) 19 ¼.850 (21.59).729 (18.51).612 (15.54).471 (11.96).373. (9.47) 16 (400) (442.0) 21 ¾.967 (24.56).829 (21.05).696 (17.68).535 (13.59).424 (10.77) 18 (450) (495.3) 24 ¼ (27.51).929 (23.60).780 (19.81).600 (15.24).476 (12.09).382 (9.70) 20 (500) (548.6) 26 ¾ (30.48) (26.14).864 (21.95).665 (16.89).527 (13.39).424 (10.77) 24 (600) (655.3) 31 ¾ (36.40) (31.22) (26.21).794 (20.17).629 (15.98).506 (12.85) 30 (750) (812.8) 38 ½ (38.71) (32.51).985 (25.02).780 (19.81).627 (15.93) 36 (900) (972.8) (38.91) (29.92).934 (23.72).751 (19.08) 42 (1050) (1130.3) (45.21) (34.77)1.085 (27.56).872 (22.15) 48 (1200) (1290.3) 58 ½ (39.70)1.239 (31.47).996 (25.30) 11
13 -Haunching & Initial Backfill- Initial backfill is completed in tw o stages and should be completed as soon as possible after the pipe has been laid. The first stage (haunching) should be placed in layers of no more than six inches (150mm) at a time up to the springline of the pipe. Compact as required by the designer of the pipe system. The second stage of initial backfill is again placed in no more than six inch (150mm) layers from the springline to a point 6 to 12 inches ( mm) above the top of the pipe. Both stages of initial backfill material shall be free of large stones (1-1/2 or larger) frozen material, or debris. Attention should be given to assure that no voids remain betw een the pipe, trench bottom, and sides of the trench. -Acceptance Testing- If portions of the pipeline are tested as they are completed, and if the joints are to be exposed during testing, center loading the pipe to resist movement of the pipe during testing is recommended. After testing, the pipe embedment requirements are to be follow ed in placing the initial backfill around the exposed joints prior to completing the final backfill. Fill the pipeline slow ly, limiting the flow to approximately one foot per second, making sure that there is no imposed surge or w ater hammer. Take steps to ensure that all entrapped air is released from the line w hile filling. Entrapped air can lead to very unsafe explosive failures. Fire hydrants are not an 12
14 adequate replacement for air / vacuum release valves. The pipeline should be filled but not pressurized until ready to conduct the pressure tests. Appropriate pressure relief, air release and vacuum release valves should be installed prior to testing. Duration of test pressures should be in accordance w ith the contract specifications as set forth by the designing engineer. Repair any leaks encountered prior to completing the backfill. After any necessary repairs are made subsequent to the initial test, a leakage test should be conducted to determine if the leakage is w ithin the contract allow ance. The allow able leakage (gallons per hour) from the table above w ere determined by the follow ing formula: The above equation calculates an allow able leakage of 10.5 gallons per inch of diameter, per mile, per day, at a pressure of 150 psi. The same precautions and procedures exercised during pressure tests should also be taken in preparing the pipeline for the leakage tests. Purge the pipeline of any entrapped air, and test in accordance w ith contract specifications. PVC pipe joints do not leak w hen properly constructed; an allow able leakage is provided to account for the losses w hich may occur w ith the addition of appurtenances and accessories along w ith expulsion of entrapped air. -Final Backfill- After placement and compaction of pipe embedment materials, the balance of backfill materials may be returned to the trench. The material should not contain large stones or rocks, frozen materials, or debris. Compaction procedures of the remainder of the backfill should be in accordance w ith the contract specification. -Diamond LOK 21 - Diamond Lok-21 is standard AWWA C900 pipe w ith a modification to the bell to accommodate a casing and gripper ring to provide a thrust restraint joint. As such it should be unloaded, handled and strung the same as for our standard AWWA C900 pipe. Those guidelines may be found in other parts of this document. A separate installation guide detailing the specific installation guidelines is provided w ith each load of Diamond Plastics Lok-21 pipe. Both guides should be read entirely before beginning the installation of the product. 13
15 Illustration of metallic restraint casing and gripper-ring. Points of Gripper-Ring toward back of bell Prior to joint assembly, any dust or foreign material must be removed from the relative joining areas of the socket and the spigot. Verify that the points of the gripper ring are pointed toward the back of the bell and away from the bell entrance. The points are sharp and care should be taken w hen verifying proper direction. When in proper position the gripper ring can be easily rotated (turned) by hand w ithin the casing cavity if the ring is not in proper position, it w on t easily rotate w ithin the casing cavity. It is extremely important that the casing and gripper ring assembly be clean. This along with straight alignment reduces the assembly force required. Lubricate the spigot end and the gasket and grip ring of the socket. Lube on the grip ring w ill ease assembly. Insure straight alignment and push the spigot into the socket until the entry lip of the socket is betw een the t w o assembly marks. Be careful not to over-assemble because the gripper ring w ill not allow the spigot to be pulled out to proper position. The assembled joint can not be pulled apart w ithout potential damage to the joint. The Diamond Lok-21 s restraint system provides uniform circumferential contact w ith a simple push together system that is suited for directional drilling operations, encasements, and other applications w hich require joint restraint. It can sustain the follow ing levels of pull force: Maximum Allow able Pull Force (straight alignment) Size Force (Pounds) 4 15, , , , ,000 14
16 The pull loads used in directional drilling and casing installations should be measured and set not to exceed the allow able pull forces that are listed above. In horizontal drilling applications the angular deflection and bending radius for the finished installation should comply w ith the guidelines contained in AWWA C605 (The minimum bending radius is the pipe diameter times 250), In these kinds of applications the entrance and exit may require a more severe bending radius. Caution is advised in that the strength of the bell could be exceeded resulting in broken pipe. 15
17 LIMITED WARRANTY AND LIABILITY Diamond Plastics Corporation, 1212 Johnstow n Road, P. O. Box 1608, Grand Island, NE 68802, does hereby w arrant subject to the limitations hereinafter stated, its PVC Pipe to be free from defects in material and w orkmanship under normal use and service for a period of tw elve (12) months from the date of invoice. This limited w arranty extends only to the original purchase for use, and w ill be void if the product is used under conditions other than those for w hich it w as designed or if it is not used in compliance w ith all instructions contained in any operating manual or specification sheets provided for such product. The sole obligation of Diamond Plastics Corporation, under this limited warranty, and the exclusive remedy of the purchaser under this limited warranty is the repair or replacement, without charge, F.O.B. shipping point, of such products or parts of products only, specifically excluding any labor or installation thereof, w hich Diamond Plastics Corporation, after inspection, determines to be defective. Purchase must notify Diamond Plastics Corporation, in w riting at its address show n above w ithin ten (10) days from the date of discovery of any claimed defect specifically stating the details of such defect, and, if requested by Diamond Plastics Corporation, return the defective product, freight prepaid, to Diamond Plastics Corporation, F.O.B. shipping point as show n on Diamond Plastics Corporation s order acknow ledgement. Diamond Plastics Corporation shall not be liable for any other damages, w hether direct or consequential. Specifically, but w ithout limitation, Diamond Plastics Corporation shall not be liable for any crop damage or any other incidental or consequential damages resulting from any breach of w arranty, express or implied, or from any defects in its products. No statement, remark, agreement, representation, promise or understanding, oral or w ritten, made by Diamond Plastics Corporation, or any agent, representative or employee thereof, w hich is not contained herein, w ill be recognized by, or be enforceable or binding upon Diamond Plastics Corporation. There are no understandings or undertakings of any kind w ith respect to the products or any part thereof w hich are not expressly set forth and contained herein, and all sales are made w ithout any representation or w arranty by Diamond Plastics Corporation that the goods are suitable for any particular purpose. In the event any provision of this LIMITED WARRANTY AND LIMITATION OF LIABILITY is held to be illegal or unenforceable by any court of competent jurisdiction, the remaining provisions shall remain in full force and effect. STATUTE OF LIMITATION: Any action for breach of this LIMITED WARRANTY AND LIMITATION OF LIABILITY must be commenced w ithin one (1) year after the cause of action has accrued. THERE ARE NO EXPRESS OR IMPLIED WARRANTIES BY DIAMOND PLASTICS CORPORATION, OTHER THAN THOSE SPECIFICALLY SET OUT ABOVE. THERE ARE NO IMPLIED WARRANTIES OF MERCHANTABILITY OR OF FITNESS FOR A PARTICULAR PURPOSE IN CONNECTION WITH ANY SALE EXECPT ASSET FORTH ABOVE. 16
18 17
19 Sales Office DIAMOND PLASTICS CORPORATION P.O. Box 1608 Grand Island, NE Manufacturing Plants: Grand Island, Nebraska Golconda, Nevada Lubbock, Texas Macon, Georgia Muncie, Indiana Plaquemine, Louisiana Casa Grande, Arizona 8/12 18
Installation Guide. Recommendations for Installation of IPS & PIP Pressure Pipe
Installation Guide Recommendations for Installation of IPS & PIP Pressure Pipe INDEX Index......... 1 Diamond Plastic Pipe....... 2 PVC Installation Guide...... 2 Handling & Storage....... 2 Receiving
Installation Guide For PVC Sewer Pipe
Installation Guide For PVC Sewer Pipe (ASTM D3034 & F679) TABLE OF CONTENTS: Introduction... 2 Receiving...3 Unloading and Handling... 4-5 Storage... 6 Trenching... 7 De-Watering... 8 Field Cutting...
The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.
Section 33 0200- Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.
SECTION 15125 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION
SECTION 15125 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION PART 1 GENERAL.01 SECTION INCLUDES Furnishing and installing 4 inch through 16 inch high density
Section 02702 SEWER PIPE INSTALLATION AND TESTING
PART 1 - GENERAL Section 02702 SEWER PIPE INSTALLATION AND TESTING 1-1. SCOPE. This section covers the installation and testing of all sewer pipe furnished under the following specification sections: Concrete
Diamond LOK-21 Assembly Information
Diamond LOK-21 Assembly Information Proper assembly of a Diamond LOK-21 is much like that of conventional bell-and-spigot PVC pressure pipe. Proper assembly of the joint requires: A clean bell and spigot,
SECTION 33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE
SECTION 33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE PART 1: GENERAL 1.01 SECTION INCLUDES PVC pressure pipe and fabricated fittings in nominal sizes 4-inches through 12-inches with cast iron pipe equivalent
CLEANING, INSPECTION, AND TESTING OF SEWERS
CLEANING, INSPECTION, AND TESTING OF SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Cleaning, Inspecting, and Testing Sanitary Sewers B. Cleaning, Inspecting, and Testing Storm Sewers C. Cleaning and
SECTION 33 11 00.13 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS
SECTION 33 11 00.13 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS PART 1: GENERAL 1.01 SECTION INCLUDES Furnishing and installing up to 16-inch high density polyethylene (HDPE) pipe and fittings for
SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE
6.01 SCOPE The work covered by this section of the specifications consists of the furnishing of all plant, labor, materials, equipment and supervision and performing all operations involved in the construction
TEXAS A&M CENTRAL ACADEMIC BUILDIING & PATRIOT S CASA SUBMITTAL. 23 21 13.19 Pre-Insulated Piping 4-8-13
TEXAS A&M CENTRAL ACADEMIC BUILDIING & PATRIOT S CASA SUBMITTAL 23 21 13.19 Pre-Insulated Piping 4-8-13 MATERIAL SUBMITTAL JOB NAME: TEXAS A&M SAN ANTONIO CENTRAL ACADEMIC BUILDING & PATRIOTS CASA CONTRACTOR:
SECTION 33 31 00.11 GRAVITY SANITARY SEWERS
SECTION 33 31 00.11 GRAVITY SANITARY SEWERS PART 1: GENERAL 1.01 SCOPE A. Gravity sanitary sewers and appurtenances. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 Submittals. B. Submit
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary
3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.
The following shall serve as the minimum requirements for contractors performing work in relation to the Authority s potable water and sanitary sewer system(s), appurtenances and service connections. General:
SECTION 15105 DUCTILE IRON PIPE AND FITTINGS
SECTION 15105 DUCTILE IRON PIPE AND FITTINGS PART 1 GENERAL.01 COORDINATION OF WORK Connection to existing pipelines may require shutdown of Owner facilities. Closely coordinate construction work and connections
SECTION 33 11 00.15 DUCTILE IRON PIPE AND FITTINGS
SECTION 33 11 00.15 DUCTILE IRON PIPE AND FITTINGS PART 1: GENERAL 1.01 COORDINATION OF WORK Connection to existing pipelines may require shutdown of AW facilities. Closely coordinate construction work
SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE
SECTION 15076 CEMENT-MORTAR LINED AND COATED (CML&C) STEEL PIPE PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for steel pipe fabrication, test in shop, installation of steel
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains
1.3.2 Method of construction and restoration of existing water service connections. This shall include:
1.0 GENERAL 1.1 DESCRIPTION: This specification shall cover the rehabilitation of existing water lines using the GRUNDOCRACK PIPE BURSTING SYSTEM. Pipe bursting is a system by which the pneumatic bursting
Model Specification 509 DRISCOPLEX 4200 and DRISCOPLEX 4300 Gravity Flow Sanitary Sewer
Model Specification 509 DRISCOPLEX 4200 and DRISCOPLEX 4300 Gravity Flow Sanitary Sewer The user may choose to adopt part or all of this Model Specification; however, the user should ensure that all parts
SECTION 02110 - ASBESTOS CEMENT PIPE REPAIRS, DEMOLITION, AND DISPOSAL
SECTION 02110 - ASBESTOS CEMENT PIPE REPAIRS, DEMOLITION, AND DISPOSAL PART 1 - GENERAL 1.1 WORK INCLUDED IN THIS SECTION A. The WORK of this Section includes the repair, demolition, and disposal of asbestos
32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.
SECTION 32: SANITARY SEWER INSTALLATION 32-01 SCOPE. The Work shall consist of furnishing and installing sewer mains, manholes, laterals, cleanout fittings and appurtenances; and testing, flushing and
53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines:
Division 53: Slip-Lining of Existing Sewer Line 53.01 GENERAL: This section includes all labor, materials, transportation, equipment necessary to rehabilitate by means of Instituform deteriorated sections
Gasketed Sewer Pipe and Fittings Installation Guide. Suitable for Gasketed Sewer Applications
Gasketed Sewer Pipe and Fittings Installation Guide Suitable for Gasketed Sewer Applications Royal Muincipal Solutions Gasketed Sewer Pipe and Fittings Installation Guide TABLE OF CONTENTS Introduction...2
SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.
SECTION LS 2530 SANITARY SEWERS PART 1 GENERAL 1.1 SUBMITTALS A. General: Submit the following in accordance with The General Conditions. 1. Product data for drainage piping specialties. 2. Shop drawings
Bethel Township Municipal Authority (BTMA) RESIDENTIAL SEWER CONNECTION MANUAL
155 E. Front Street (rear) Lititz, PA 17543 Phone (717) 625-1930 Fax (717) 625-1931 Bethel Township Municipal Authority (BTMA) RESIDENTIAL SEWER CONNECTION MANUAL CONSTRUCTION SPECIFICATIONS AND DETAILS
San Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS
ITEM NO. 1100 SLIP-LINING SANITARY SEWERS 1100.1 DESCRIPTION: This item shall consist of slip-lining sanitary sewer pipe, which is accomplished by pulling or pushing liner pipe into existing sewers by
Wastewater Capital Projects Management Standard Construction Specification
CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,
TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe
TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe TN 5.14 February 2010 Introduction It may be at times necessary, in an aging infrastructure, to rehabilitate drainage and sanitary lines
Section 2100-Trenching and Tunneling
SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial
A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.
PART 1 GENERAL 1.1 SCOPE A. This item shall include the work necessary for the installation of storm sewer line construction. B. Reference Section 3800 Trenching and Backfill and the General Conditions,
PROTECTO 401 Price List
Price List January 1, 2015 Protecto 401 Price List Certification and General Installation Certification All Ductile Iron Spooling manufactured by is made in accordance with current ANSI/AWWA- C115/A21.15
SANITARY SEWER SPECIFICATIONS
SANITARY SEWER SPECIFICATIONS OCTOBER 2003 HARVEST-MONROVIA WATER, SEWER, AND FIRE PROTECTION AUTHORITY SECTION 1.00 1.10 Purpose The purpose of this document is to assemble the sewer specifications, policies,
LS 2540 SEWER LATERALS AND INSPECTION TEES
LS 2540 SEWER LATERALS AND INSPECTION TEES A. Summary B. Submittals C. Site Information D. Sewer Pipe and Fittings E. Lateral Locations F. Lateral Installation G. Inspection Tee Installation H. Removal
Price List January 1, 2015
Price List January 1, 2015 Cement Lined Price List Certification and General Installation Certification All Ductile Iron Spooling manufactured by is made in accordance with current ANSI/AWWA- C115/A21.15
DIVISION 4300 STORM DRAINAGE
DIVISION 4300 STORM DRAINAGE SECTION 4305 STORM SEWER PART 1 - GENERAL 1.01 SCOPE This section covers the construction of storm sewers for the collection and transport of stormwater runoff. 1.02 REFERENCES
STANDARD SPECIFICATIONS SECTION 02701 INSTALLATION OF GRAVITY SEWER PIPELINES. 1. Trenching, Backfilling and Compacting: 02223
STANDARD SPECIFICATIONS SECTION 02701 INSTALLATION OF GRAVITY SEWER PIPELINES PART 1 - GENERAL A. Description This section describes the installation of gravity sewer pipelines fabricated of vitrified
Pressure Pipe and Fittings Installation Guide. Suitable for Pressure Applications Installation Guide
Pressure Pipe and Fittings Installation Guide Suitable for Pressure Applications Installation Guide Royal Muincipal Solutions Pressure Pipe & Fittings Installation Guide Table of Contents Introduction...1
CHAPTER 6 - SANITARY SEWER
CHAPTER 6 - SANITARY SEWER 6.1 GENERAL This section covers the requirements for PVC plastic sewer pipe materials and installation in sanitary sewer construction. 6.2 PIPE PVC gravity sewer pipe and fittings
STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY
STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY Approved and adopted as Official Document Number 800576 this 10th day of December, 1980 Donald R. Boyd, P.E., Director Water
SECTION 1 GENERAL REQUIREMENTS
Page 1 of 6 SECTION 1 GENERAL REQUIREMENTS 1. SCOPE OF WORK: The work to be performed under the provisions of these documents and the contract based thereon includes furnishing all labor, equipment, materials,
Section 02415. Installation of pipe and casing for sanitary sewer by methods of augering.
ITY OF PRLN UGRING PIP OR SING FOR SWRS Section 02415 UGRING PIP OR SING FOR SWRS 1.0 G N R L 1.01 STION INLUS Installation of pipe and casing for sanitary sewer by methods of augering. References to Technical
STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS
STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for cleaning and lining existing cast iron and ductile iron water mains
SECTION 02400 - STORM DRAIN SYSTEM
SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And
Beacon Hill Sewer District Standard Specifications
Beacon Hill Sewer District Standard Specifications Residential Gravity Side Sewer Including Design Criteria and Standard Construction Drawings Residential Gravity Side Sewer Design Criteria 1. Provisions
TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe
TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe TN 5.18 October 2015 In sanitary sewer, it is often necessary to use trenchless technology methods to install a casing pipe under high volume roads,
Sewer Water Pipeline Replacement with CERTA LOK RESTRAINED JOINT PVC PIPE
1.0 GENERAL 1.1 DESCRIPTION This section addresses the procedures to be employed for pipe bursting existing water/sewer pipelines, as identified on the drawings, and replacing with new Restrained Joint
Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS
Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS TABLE OF CONTENTS I. RULES AND REGULATIONS A. TABLE OF CONTENTS... 2 B. TERMS AND DEFINITIONS... 3 C. DEVELOPER S/CONTRACTOR S RESPONSIBILITIES...
AWWA Butterfly Valve Operation and Maintenance Manual Series 511A & 510A 20 and Smaller
January 2013 AWWA Butterfly Valve Operation and Maintenance Manual Series 511A & 510A 20 and Smaller Milliken Valve Company 190 Brodhead Avenue, Suite 100 Bethlehem, PA 18017 Phone: (610) 861-8803 Fax:
Engineering Specifications
PUREFLOW PEX PRODUCTS PART 1 GENERAL 1.1 SUMMARY 1.1.1 This specification covers Branch & Main, Parallel Water Distribution Systems (MANABLOC), Cross-linked Polyethylene tubing and fittings using PEX Press
CITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General
General All sanitary sewers, manholes and force mains shall be acceptance tested, as hereinafter specified in the presence of a City representative. Acceptance testing shall be performed after backfilling
SECTION 15056 DUCTILE-IRON PIPE AND FITTINGS
SECTION 15056 PART 1 GENERAL 1.01 DESCRIPTION This section includes materials and installation of ductile-iron pipe and fittings for potable and recycled water systems. A written request to use Ductile
SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION
SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION 1. SCOPE Pipe subsoil drains shall be constructed in accordance with this specification and in conformity with the lines, grades and cross-sections shown
SECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES
SECTION 33 05 16.13 PRECAST CONCRETE PART 1 - GENERAL 1.01 SECTION INCLUDES A. This item shall consist of the construction of both sanitary and storm sewer precast concrete manholes in accordance with
San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS
ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS 1103.1 DESCRIPTION: 1. Repair of sanitary sewer lines by replacing short lengths of failed pipe with new pipe. 2. Repair of service laterals located
DeZURIK 3-20" BAW AWWA BUTTERFLY VALVES WITH TRANSFER MOLDED SEAT
3-20" BAW AWWA BUTTERFLY VALVES WITH TRANSFER MOLDED SEAT Instruction D10386 August 2013 Instructions These instructions provide installation, operation and maintenance information for BAW Butterfly Valves.
DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL
DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL 1.01 DESCRIPTION A. Furnish and install all storm drains, including manholes, inlets, service lines and other appurtenant
SECTION 21 REHABILITATION OF SANITARY SEWER MAINS BY THE PIPE BURSTING AND TRENCHLESS PIPE REPLACEMENT METHOD
SECTION 21 REHABILITATION OF SANITARY SEWER MAINS BY THE PIPE BURSTING AND TRENCHLESS PIPE REPLACEMENT METHOD 21.01 SCOPE: It is the intent of the Specification to define the approved methods and materials
SECTION IV - TESTS AND INSPECTIONS PART 1 - GENERAL. 1.01 Testing - General
SECTION IV - TESTS AND INSPECTIONS PART 1 - GENERAL 1.01 Testing - General Testing shall be of the type and frequency described in each section and summarized in Item 1 of this section. In addition to
2.0 DESIGN CRITERIA FOR WATER DISTRIBUTION SYSTEMS
2.0 DESIGN CRITERIA FOR WATER DISTRIBUTION SYSTEMS Water system improvements proposed for inclusion into Western s service area shall be designed in accordance with all appropriate AWWA standards, include
WATER MAIN CONSTRUCTION TECHNIQUES DEPARTMENT OF PUBLIC WORKS WATER & WASTEWATER DIVISION
WATER MAIN CONSTRUCTION TECHNIQUES Overview Water Main - Materials Specifications Installation Future? Water Main Materials Material Types There are various material types used for water mains, these include:
SECTION 31 20 00 EARTH MOVING
SECTION 31 20 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for excavating, filling, and grading for earthwork at Parking Structure, new exit stair and as required to
SECTION 02401 - SANITARY SEWER PIPE
PART 1 - GENERAL 1.1 DESCRIPTION A. The WORK under this Section includes providing all labor, materials, tools and equipment necessary for furnishing and installing sanitary sewer pipe, in accordance with
San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS
San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS 854.1 DESCRIPTION: This item shall govern sanitary sewer laterals installed in accordance with these
60.12. Depend-O-Lok FxE Expansion Coupling. System No. Submitted By Spec Sect Para Location Date Approved Date. DEPEND-O-LOK FxE EXPANSION COUPLING
60.1 D-O-L FxE expansion couplings are a bolted, split-sleeve design that provides for expansion and contraction at the coupled joint. These couplings are furnished with restraint rings that, when affixed
ARTICLE II (2) ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH 020001 Purpose and Application.
ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH 020001 Purpose and Application. Article II provides rules governing the allowable connection to the City POTW and the construction and inspection of
DESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES 33 00 00 SITE UTILITIES
SECTION INCLUDES Domestic Water Fire Water Service Water Well Sanitary Sewer Storm Drains Foundation Drainage RELATED SECTIONS 03 30 00 Concrete 21 00 00 Fire Suppression - Sprinklers 22 00 00 Plumbing
SECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS
SECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS PART 1 GENERAL 1.01 SECTION INCLUDES A. The requirements for pipe material and installation in sewer and drainage collection systems. All materials
Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe
Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe 1. GENERAL The following supplemental sewer main specifications are intended to address the installation of high-density polyethylene
SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)
SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO) 1 Intent: The intent of trenchless sewer pipe Insertion is to rehabilitate the existing sewer
High Strain Dynamic Load Testing of Drilled Shafts
Supplemental Technical Specification for High Strain Dynamic Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 3, 2015 1.0 GENERAL This work shall consist of performing high-strain
The Manitoba Water Services Board SECTION 022180 Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11
Page 1 of 11 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the excavation of trenches (or excavation of tunnels); the supply and placing of bedding and backfill materials;
2013 Edition. Flanged fittings 30"-64" NSF. industrial Applications, water & Wastewater. Certified to ANSI/NSF 61
30"-64" Ductile Iron industrial Applications, water & Wastewater 2 Table of Contents Flanged Fittings for Water 3 Flange Details 5 Flanged Fittings 6 90º and 45º Bend 6 22-1/2º and 11-1/4º Bends 7 Tees
SECTION 02732 BUILDING SEWERS. B. Connection of building sanitary drainage system to municipal sewers.
SECTION 02732 BUILDING SEWERS PART 1 GENERAL 1.01 SECTION INCLUDES A. Lateral piping, fittings, and accessories. B. Connection of building sanitary drainage system to municipal sewers. 1.02 REGULATORY
MDWASD 8/1999 SECTION 02315 TRENCHING AND BACKFILLING FOR PIPING SYSTEMS
PART 1 - GENERAL 1.01 WORK INCLUDED SECTION 02315 TRENCHING AND BACKFILLING FOR PIPING SYSTEMS A. The work included under this Section consists of excavating, backfilling and compaction as required for
Installation Instructions
85-3976 rev. 05 08-13 Installation Instructions Thank you for purchasing this antisway bar kit. Please read through these instructions before installation. Rear Anti-Sway Bar Kit for Dodge Ram Pick-Up
Section C-1 Pipes and Fittings
Section C-1 Pipes and Fittings C1.00 Work Included The work under this Division of the Specifications shall include all labor, materials, and equipment necessary to furnish and install all piping, pipelines,
SECTION 16402 UNDERGROUND ELECTRIC SERVICE
SECTION 16402 UNDERGROUND ELECTRIC SERVICE PART 1 GENERAL 1.1 SUMMARY A. Description of System 1. Furnish all labor, materials, and equipment for below grade work external to buildings as required, and
Sewer Line Rehabilitation
1.0 GENERAL 1.1 DESCRIPTION: This specification shall cover the rehabilitation of existing sanitary sewers using the GRUNDOCRACK PIPE BURSTING SYSTEM. Pipe bursting is a system by which the pneumatic bursting
SECTION 33 11 00.19 ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section 01 33 00 - Submittals.
SECTION 33 11 00.19 ABANDONMENT OF WATER MAINS PART 1: GENERAL 1.01 SCOPE A. Abandonment in place, by cutting and capping, of existing water mains, hydrants, service lines, and valves. B. Abandonment in
SKT-SP Tangent Terminal
Assembly Instructions for SKT-SP Tangent Terminal & FLEAT-SP Flared Terminal SP Standard Post System Guardrail Terminals ROAD SYSTEMS, INC. P. O. Box 2163 Big Spring, Texas 79721 Phone: (432) 263-2435
AWWA Small Systems Pipe Repair Checklist, as published in July 2008 Opflow Question of the Month
, as published in July 2008 Opflow Question of the Month Thanks to: Mike Grahek, Los Angeles Department of Water, Los Angeles, California Ahmad Havivian, Black & Veatch, Gaithersburg, Maryland David Kroon,
AIR RELEASE, CLEANOUT, AND SEWER MANHOLES
AIR RELEASE, CLEANOUT, AND SEWER MANHOLES **From Hartford IM BLDG(10) DESCRIPTION. This work shall consist of the construction of air release, cleanout, and sanitary sewer manholes; and the furnishing
Installation Instructions
7.3L & 6.0L 5/8 FUEL TANK PICKUP KIT Fits 94-07 7.3L & 6.0L Powerstroke Diesel Trucks & Excursions Installation Instructions These instructions are intended simply to be a guide for the installation of
IMPORTANT DOCUMENTATION DO NOT DISCARD!
PART NO.: 6441-263C SERIES GRT 3 JAW PARALLEL GRIPPERS INFORMATION SHEET IMPORTANT DOCUMENTATION DO NOT DISCARD! Use this information sheet to assist with gripper installation and setup. File with maintenance
INSTALLATION RECOMMENDATIONS. Outdoor Rubber Tiles
INSTALLATION RECOMMENDATIONS Outdoor Rubber Tiles Prior to Installation: The Outdoor Rubber Tiles and accessory transition pieces intended for this installation have been shipped to you via a freight carrier
Retractable Screen. Replacement Screen Instructions
Retractable Screen Patent Pending Replacement Screen Instructions For RTS, RET, & RTM Products ATTENTION! Retractable screens are not intended to provide security or provide for the retention of objects,
SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.
SECTION 02763 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Repairs to existing sewer lines by replacing short lengths of failed pipe. 1.02 UNIT PRICES A. Measurement for point repairs is on a unit price
SECTION 33 41 03 POLYVINYL CHLORIDE (PVC) PIPE
SECTION 33 41 03 POLYVINYL CHLORIDE (PVC) PIPE PART 1 GENERAL 1.01 SECTION INCLUDES A. This section includes all labor, materials, equipment, and incidentals required and installation of Polyvinyl Chloride
PRE INSTALLATION MANUAL
REINFORCED CONCRETE PIPE PRE INSTALLATION INSPECTION & REPAIR MANUAL Kentucky Transportation Cabinet Kentucky Department of Highways Division of Materials 1227 Wilkinson Boulevard Frankfort, KY 40601 (502)
SE-100-1, SE-200-1, SE-500-1, and SE-1000-1 AIR CHAMP PRODUCTS. User Manual SE BRAKE MODELS: (i) MTY (81) 83 54 10 18 ventas@industrialmagza.
AIR CHAMP PRODUCTS User Manual SE BRAKE MODELS: SE-00-, SE-200-, SE-500-, and SE-000- (i) FORM NO. L-20084-E-040 In accordance with Nexen s established policy of constant product improvement, the specifications
General Guidelines for Repairing Buried PE Potable Water Pressure Pipes
515 General Guidelines for Repairing Buried PE Potable Water Pressure Pipes Introduction Traditional piping systems have gasket-sealed bell and spigot joints every 20 feet, which can be a potential maintenance
Quality Products, People & Locations
Quality Products, People & Locations Diamond Plastics Corporation is one of today s leading PVC pipe producers in North America and one of the largest producers in the world. The Corporation was established
SECTION 02401 SHEETING, SHORING AND BRACING
SECTION 02401 SHEETING, SHORING AND BRACING This section should be edited to reflect soil conditions specific to the project site and the recommendations of a Geotechnical Engineer licensed in the State
BUILDING MATERIALS, Wood, Laminated (Page 1 of 3) Viz.: Rafters; Arches; Beams; Joists; Timbers or Planks, structural or roof.
BUILDING MATERIALS, Wood, Laminated (Page 1 of 3) Viz.: Rafters; Arches; Beams; Joists; Timbers or Planks, structural or roof. 1155 & 4155 LCL: Applies to all freight in less than container load quantities.
EXHIBIT "A. Technical Specifications for Water and Sewer Service Lines
EXHIBIT "A Technical Specifications for Water and Sewer Service Lines Water and Sewer Line Bedding and Backfill: Drawings show cross-section of trench, pipe laid on top of 6" min. bedding material, bedding
*PATENT PENDING. NS1100 / NS2200 Installation Manual & Owner s Guide
*PATENT PENDING NS1100 / NS2200 Installation Manual & Owner s Guide Installation Tips Contents 1 Control Panel 1 Spool of Signal Wire 2 Mounting Screws & Drywall Inserts 2 Wire Clips 3 Wire Ties Tools
STANDARD SPECIFICATION SECTION 15292 POLYVINYL CHLORIDE (PVC) PRESSURE PIPE (AWWA C900)
STANDARD SPECIFICATION SECTION 15292 POLYVINYL CHLORIDE (PVC) PRESSURE PIPE (AWWA C900) PART 1 - GENERAL 1.01 DESCRIPTION This section includes materials, installation, and testing of PVC pressure pipe
Green Thread Product Data
Green Thread Product Data Applications Dilute Acids Caustics Produced Water Industrial Waste Hot Water Condensate Return Materials and Construction All pipe manufactured by filament winding process using