Chicago Crane Operators Examination Study Guide
|
|
|
- Jasper Crawford
- 9 years ago
- Views:
Transcription
1 Chicago Crane Operators Examination Study Guide Cranes and hoisting equipment with a rated capacity of 2,000 pounds or more require a licensed operator for use in the City of Chicago. This study guide includes general information about testing procedures (page 1), types of equipment requiring a Chicago license (page 2), content outlines (pages 3-4), study materials and a description of the practical exams (page 5), and sample questions (pages 6-12) to help candidates prepare for the written examinations. General Information PURPOSE OF THE EXAMINATIONS These examinations for Chicago Crane Operators assess the knowledge and skills of candidates who intend to operate cranes or hoisting equipment with a rated capacity of 2,000 pounds or more in Chicago. A candidate who passes the Class I written test is eligible to take any Class I or Class II practical exam for a specific license type listed on page 2 of this Study Guide. A candidate who passes the Class II written test is eligible to take any Class II practical exam for a specific license type. Chicago Building inspectors may stop work at locations that are using cranes or hoisting equipment without a properly licensed operator. TEST VALIDITY & TEST LENGTH Each written test is three hours in length. All test questions have been validated to meet strict psychometric controls and have been approved by the Chicago Crane Operators Examining Board. STUDY MATERIALS MISSING AN EXAMINATION WHAT TO BRING TO THE EXAM Study materials for these examinations are described in this Study Guide. OSHA requirements for crane operators are available free on the U.S. Department of Labor website. There are no "make-up" dates for written tests. You may re-register for the next examination date. THERE ARE NO REFUNDS. Each candidate should bring two (2) sharpened Number 2 black lead pencils and a non-programmable, non-printing, solar- or battery-powered portable or pocket calculator. No power source will be available for calculators at the test site. Candidates will not be permitted to use any books, notes or other reference materials during these examinations. Cell phones are prohibited during an examination. LICENSURE FAILURE Candidates who score 70 or higher will receive a PASS notice and instructions to schedule the appropriate practical examination(s). Candidates who score below 70 will receive a FAILURE notice and an application for re-examination. Candidates are encouraged to retake the examination; many candidates who initially fail such an exam pass on subsequent attempts. July 2015, Employment Research & Development Institute Continental Testing Services, Inc.
2 Page 2 Classifications of Equipment Requiring a Chicago Crane License All cranes and hoisting equipment with a rated capacity of 2,000 pounds or more require a licensed operator for use in the City of Chicago. The following classifications apply. Additional information about Practical Exams appears page 5 of this study guide. Written Practical License Class I Equipment Exam Exam Type Tower Crane Hammerhead Tower Crane Luffing Boom Tower Crane Self-Erecting Class I Class I Class I Yes Yes Yes A-1 A-2 A-3 Friction Crawler Crane or Friction Truck Crane Class I Yes B-1 to 4 a Hydraulic Crawler Crane or Hydraulic Truck Crane with Lattice Boom Class I Yes C-1 to 4 a Hydraulic Mobile Crane: rough terrain or all-terrain Class I Yes D-1 to 4 a Mobile Crane: boom truck Class I Yes E-1 to 4 a Industrial Crane or Carry Deck Crane Class I Yes F Spider Crane Class I Yes G Chicago Boom, Drumhoist or Derrick Class I Yes H Rack and Pinion Skips Class I Yes I Other Class I Cranes or hoisting equipment Class I Yes J a Four Boom Length classifications apply for License Types B, C, D and E: 1=Up to 100 feet 2=Up to 150 feet 3=Up to 189 feet 4=190 feet or greater Class II Equipment Written Exam b Practical Exam License Type Articulating Crane, Knuckleboom Crane or Mobile Crane: Knuckleboom Truck Class II Yes AA Multi-Purpose Machine with Hoisting Device Class II Yes BB All-Terrain Forklift with Hook or Winch Class II Yes CC Power-Operated Floor or Deck-Type Crane Class II Yes DD Overhead Crane Class II Yes EE Gantry Crane or Crane on a Monorail Class II No FF Boom attached to Mast-Climbing Work Platform Class II No GG Power Window Washing Unit when used to erect Class II No HH Track Backhoe used for erecting Class II Yes II Service/Mechanic Truck with Hoisting Device Class II Yes JJ Other Class I Cranes or hoisting equipment Class II Case by case KK b Candidates who pass Class I or Class II written tests may take any Class II practical exam. Any crane set on a flotation device, locomotive rail device, wheel mounted device, pedestal device or portal device shall have the appropriate classification, license and testing requirements for the underlying crane type identified above.
3 Page 3 Class I Crane Operators Written Test (65 questions) 1. Types of Equipment 10 questions A. Tower & mobile cranes B. Drum hoists, derricks, etc. C. Spider cranes, carry decks, etc. D. Forklifts, floor cranes, etc. 2. Operating Practices 8 questions A. Set-up B. Power lines C. Ground conditions 3. Rigging & Signals 15 questions A. Wire rope B. Drums C. Slings D. Rigging hardware E. Fiber rope F. Signaling 4. Inspections & Maintenance 4 questions A. Hoisting equipment B. Rope & rigging hardware 5. Safe Working Loads 14 questions A. Wire rope slings B. Chain slings C. Estimating load weights D. Safe load rules E. Capacity limits & deductions 6. OSHA Regulations & Workplace Safety 10 questions A. Crane types/safety B. Rigging equipment C. Power lines D. Equipment safety E. Demolition 7. Hoisting Personnel Safely 4 questions A. Manbasket design requirements B. Operating manbaskets safely
4 Page 4 Class II Crane Operators Written Test (65 questions) 1. Types of Equipment 8 questions A. Articulating crane, knuckleboom crane or mobile crane: knuckleboom truck B. Overhead gantry cranes C. Forklifts, floor cranes, etc. 2. Operating Practices 9 questions A. Set-up B. Power lines C. Ground conditions 3. Rigging & Signals 17 questions A. Wire rope B. Drums C. Slings D. Rigging hardware E. Fiber rope F. Signaling 4. Inspections & Maintenance 6 questions A. Hoisting equipment B. Rope & rigging hardware 5. Safe Working Loads 14 questions A. Wire rope slings B. Chain slings C. Estimating load weights D. Safe load rules E. Capacity limits & deductions 6. OSHA Regulations & Workplace Safety 11 questions A. Crane types/safety B. Rigging equipment C. Power lines D. Equipment safety
5 Page 5 Recommended Study Materials for the Chicago Crane Operators Written Examinations All candidates must respond to test questions that are based on information provided in the following sources. The Code of Federal Regulations (29 CFR 1910 and 1926) is available through the Occupational Safety and Health Administration (OSHA) website on at 1. Garby, Ronald G. IPT s Crane and Rigging Training Manual, 2005 Publisher: IPT Publishing and Training, Ltd. Phone: (403) Box 9590, Edmonton, Alberta, Canada T6E 5X2 2. Code of Federal Regulations, Title 29, (OSHA) Part 1910, Subpart N Materials Handling & Storage, Sections Part 1926, Subpart H Rigging Equipment, Section 251 Part 1926, Subpart N Cranes, Derricks, Hoists, Elevators & Conveyors Sections Part 1926, Subpart O Material Handling Equipment, Sections 600 & 602 Part 1926, Subpart T Demolition, Sections 858 & 859 Part 1926, Subpart CC Cranes & Derricks in Construction, Sections Publisher: U.S. Government Printing Office Available at Operating manuals for hoisting equipment and cranes also may help a candidate prepare for this examination. Chicago Crane Operators Practical Examinations A practical examination is required for each license type as identified on page 2 of this Study Guide. These practical exams require safety review, set-up, communications and signaling, and demonstration of safe operation while performing tasks suitable for that type of crane or hoisting equipment. All practical exams will be scored by two experienced crane operators in a facility designed to conduct such examinations safely. Candidates will be scheduled for up to two attempts to pass the practical exam on a specific type of crane or hoisting equipment within the scheduled exam period. Additional information will be available after a candidate passes the Class I or Class II written examination. Each candidate must pass the Class I or Class II written test before any practical exam can be scheduled. A candidate who passes the Class I written test is eligible to take any Class I or Class II practical exam for a specific license type as listed on page 2 of this Study Guide. A candidate who passes the Class II written test is eligible to take any Class II practical exam for a specific license type. Separate fees are due for each license type practical exam taken.
6 Page 6 Class I Crane Operator Sample Questions All questions on these examinations are multiple choice with one correct answer and three incorrect choices. For these sample tests only, answers and references are provided at the end of each sample test to help you prepare for these examinations. 1. Which of the following best describes the minimum requirement for wire anchorage on a hoist drum? A. At least three wraps when the load block is at its lowest position B. At least four wraps when the load block is at its highest position C. At least five wraps when the load block is at its lowest position D. At least six wraps when the load block is at its highest position 2. Crane operators must assure that no part of the equipment, load line or load including rigging and lifting accessories is closer than how many feet to a power line when voltage in the line is unknown? A. 5 B. 10 C. 15 D The lowest amount of ground pressure for a crane is exerted when the total weight of the machine is distributed A. over the entire area. B. over one corner. C. over the front. D. over the side. 4. Which of these requires immediate replacement of rotation-resistant wire rope under OSHA standards? A. Any sign of corrosion B. Insufficient lubrication C. Any reduction in diameter D. Two broken wires in six rope diameters
7 Page 7 5. Who should be watching the load when a crane is working in the blind? A. The rigger B. The operator C. One signalman D. Two signalmen 6. When the engine of a crane is running, maintenance personnel must never A. reset the controls. B. be under the machine. C. operate the machine. D. reposition the crane. 7. Which of the following most accurately describes wire rope faults? A. A protruding core indicates that the rope should be tightly wrapped before reuse. B. Bird caging may be caused by sudden release of tension on an overloaded rope. C. Fatigue fractures are always visible on the exterior of the wire rope. D. Strand nicking typically is caused by scrubbing or localized wear. 8. Cranes using a manbasket or personnel hoisting equipment must have what type of blocking equipment? A. Timber blocking B. A two-block device C. An anti-two-block device D. Two-block damage prevention 9. When do OSHA regulations authorize the use of a manbasket or suspended personnel platform to hoist personnel? A. When personnel prefer a manbasket over ladders or scaffolding B. When safer methods expose personnel to harsh weather conditions C. When conventional methods of transporting personnel are more expensive D. When no safer method exists due to structural design or worksite conditions
8 Page 8 Question 10 refers to the following information for a mobile crane. Boom Operating Boom Boom Capacity: Capacity: Length Radius Angle Point: Crawlers Crawlers in Feet in Feet Degrees Elev. Retracted Extended , , ,200 86, ,500 74, ,100 64, ,300 56, ,700 50, ,900 45, ,900 40, ,400 36, ,400 33, ,700 30, ,400 27, ,300 25,100 Feet ,400 23, ,700 21, ,200 19, ,800 17, ,500 16, ,300 15, ,200 13, ,200 12, ,200 11, ,300 10, ,400 9, ,600 9,900 Load weights: Jib 3,500 lbs. Headache ball & hook 750 lbs. Load block 4,550 lbs. Slings 660 lbs. Main load line below boom jib 1,125 lbs. Load line below the jib tip 50 lbs. Weight of load 44,750 lbs. 10. Which statement most accurately describes this load? A. The total lifted load cannot be hoisted safely with this crane. B. The maximum operating radius with crawlers extended is 55 feet. C. The boom and jib with lifting components should not be lowered below D. The maximum operating radius with no load and crawlers extended is 140 feet.
9 Page Which of these is required for moving parts of base-mounted drum hoists that could be a hazard? A. They must be guarded. B. They may not be used. C. They must have warning signs. D. They must have automatic disconnection devices. 12. In rigging, estimates of load weights typically are measured in which of these? A. Kilograms B. Pounds per cubic foot C. Grams per cubic meter D. Pounds per cubic inch Class I Crane Sample Question Answer Key Correct Question Answer Reference(s) 1 A IPT Manual 2005, pages D OSHA (a)(2) 3 A IPT Manual 2005, pages D OSHA (a)(2) 5 C IPT Manual 2005, page B IPT Manual 2005, page B IPT Manual 2005, pages C IPT Manual 2005, pages 92-3; OSHA (d)(5)(v) 9 D OSHA (a) 10 C IPT Manual 2005, pages * 11 A OSHA (a)(1) 12 B IPT Manual 2005, pages * Load chart calculations for Question 10 result in a total lifted load of 55,385 lbs., which limits the maximum operating radius with crawlers extended to 60 feet. The weight of all components is 10,635 lbs., which limits the boom angle to 52.5 and the maximum operating radius with no load and crawlers extended to 150 feet.
10 Page 10 Class II Crane Operator Sample Questions All questions on these examinations are multiple choice with one correct answer and three incorrect choices. For these sample tests only, answers and references are provided at the end of each sample test to help you prepare for these examinations. 1. Why are articulating or knuckleboom trucks favored in many applications? A. They have higher rated capacity than front or rear mounted turrets. B. They allow safe operation without setting outriggers for most loads. C. They are better suited for working in tight spaces. D. They do not require a rated capacity load limiter. 2. Crane operators must assure that no part of the equipment, load line or load including rigging and lifting accessories is closer than how many feet to a power line when voltage in the line is unknown? A. 5 B. 10 C. 15 D The lowest amount of ground pressure for a crane is exerted when the total weight of the machine is distributed A. over the entire area. B. over one corner. C. over the front. D. over the side. 4. Which of these requires immediate replacement of rotation-resistant wire rope under OSHA standards? A. Any sign of corrosion B. Insufficient lubrication C. Any reduction in diameter D. Two broken wires in six rope diameters
11 Page Who should be watching the load when a crane is working in the blind? A. The rigger B. The operator C. One signalman D. Two signalmen 6. When the engine of a crane is running, maintenance personnel must never A. reset the controls. B. be under the machine. C. operate the machine. D. reposition the crane. 7. Which of the following most accurately describes wire rope faults? A. A protruding core indicates that the rope should be tightly wrapped before reuse. B. Bird caging may be caused by sudden release of tension on an overloaded rope. C. Fatigue fractures are always visible on the exterior of the wire rope. D. Strand nicking typically is caused by scrubbing or localized wear. 8. What does OSHA specify for attachments to devices defined as cranes and related hoisting equipment? A. The category excludes concrete pumps. B. The category includes equipment used to move a suspended load. C. The category excludes equipment that is rarely used to hoist materials. D. The category includes all equipment that could be used to move materials onto a construction site. 9. Limit switches are prohibited for which of the following? A. To check capacity B. To scale weight C. As a fail-safe device D. As a stopping device
12 Page Material handlers or fork trucks may use which of these? A. A fifth wheel B. Double hooks C. Front stabilizers D. An overload alarm 11. Which statement accurately describes loads on cranes and hoisting equipment? A. Gross load is the net load plus the weight of all rigging components. B. Gross capacity indicates the maximum size of a safe load for a crane. C. Net capacity is the most important number in crane safe loading charts. D. Net load indicates the total weight of the lift and crane attachments. 12. In rigging, estimates of load weights typically are measured in which of these? A. Kilograms B. Pounds per cubic foot C. Grams per cubic meter D. Pounds per cubic inch Class II Crane Sample Question Answer Key Correct Question Answer Reference(s) 1 C IPT Manual 2005, pages D OSHA (a)(2) 3 A IPT Manual 2005, pages D OSHA (a)(2) 5 C IPT Manual 2005, page B IPT Manual 2005, pages B IPT Manual 2005, pages A OSHA (b) 9 D IPT Manual 2005, page C IPT Manual 2005, page A IPT Manual 2005, page B IPT Manual 2005, pages 27-28
How To Ensure Safety Of Lifting Equipment
1 of 12 2 of 12 CONTENTS 1.0 OBJECTIVES... 3 2.0 SCOPE... 3 3.0 DEFINITION OF TERMS... 3 3.2.1 Loose Lifting Tackle... 3 3.2.2 Examination... 4 3.2.3 Inspection... 4 4.0 RESPONSIBILITIES & AUTHORITIES...
SAFE HANDLING OF PRECAST CONCRETE PRODUCTS
SAFE HANDLING OF PRECAST CONCRETE PRODUCTS Safety Handling of Precast Concrete Products The lifting of any precast product requires the use of special equipment and substantial planning and knowledge.
Boom and fly capacities for this machine are listed by the following sections:
Lifting Capacities Telescopic Hydraulic Truck Crane HTC 8650 50 ton (45.36 metric ton) and fly capacities for this machine are listed by the following sections: Fully Extended Outriggers Working Range
Mobile Equipment Safety
Mobile Equipment Safety PLANNING THE JOB Hazard Assessment DO YOU HAVE THE RIGHT EQUIPMENT? ARE THERE HAZARDS TO BE AVOIDED? IS THE GROUND AREA STRONG ENOUGH TO SUPPORT THE EQUIPMENT? ARE THERE ANY UNUSUAL
Safety Manual For Overhead Crane Operators
Safety Manual For Overhead Crane Operators Contents Forward ---------------------------------------------------------------1 Qualifications---------------------------------------------------------1 Certification
MATERIAL HANDLING PROGRAM (Section 10)
MATERIAL HANDLING PROGRAM (Section 10) OVERVIEW (WMI Facility) (1) Only certified personnel will operate powered industrial lifts. (2) Training will be provided to those who require to be certified or
SAFETY AND HEALTH PPG INDUSTRIES, INC. -- LAKE CHARLES UNIT NAME RIGGING AND LIFTING SAFETY FOR PPG LAKE CHARLES
#: 4301-06-492 PAGE: 1 OF 17 1 Purpose The crane and rigging safety procedures shall be followed by PPG employees, contractors, and all persons working on PPG property, with the only exception for deviation
Guidebook for Lifting Supervisors
Guidebook for Lifting Supervisors Contents 1. Introduction and Background 2 2. Common Systematic Lapses Involving Lifting Activities 3 3. Roles and Responsibilities of Lifting Supervisors 4 4. Common Hazards
BB -508L/509L INSTALLATION MANUAL LATTICE BOOM CRANES. Greer Company Crane Systems. Greer Company
BB -508L/509L ANTI TWO-BLOCK ALARM SYSTEM LATTICE BOOM CRANES INSTALLATION MANUAL BB TM -508/509 Anti Two-Block System Lattice 1 of 14 PN W250015 01/21/01 BB -508L/509L ANTI TWO-BLOCK ALARM SYSTEM INSTALLATION
OSHA Crane Operator Regulations and Recordkeeping
OSHA Crane Operator Regulations and Recordkeeping Matthew Eckstine, Manager of Business Development National Commission for the Certification of Crane Operators Ray Feidt, Inspection/ Training Manager
Operator Training Questionnaire
Participants Name: Company Name: Score: Test Date: Location: Crane Operator's Permit Issued on Date: Instructor: 1. A Top Running Overhead Crane is any crane that runs on two parallel runway beams over
FALL PROTECTION PROGRAM
FALL PROTECTION PROGRAM Page 2 of 15 Table of Contents Applicability... 3 Overview... 3 Definitions... 3 Responsibilities... 5 Risk Assessment... 6 Risk Management... 7 Roof Access Procedure 10 Rescue
PROGRAM OUTLINE. Tower Crane Operator Program Outline
PROGRAM OUTLINE Tower Crane Operator Program Outline The latest version of this document is available in PDF format on the ITA website www.itabc.ca To order printed copies of Program Outlines or learning
Apprenticeship Curriculum Standard
Apprenticeship Curriculum Standard Mobile Crane Operator 1 and 2 and Tower Crane Operator Level 1 Common Core Trade Codes: 339A, 339B, 339C Date: 2006 Please Note: Apprenticeship Training and Curriculum
RT100 ROUGH TERRAIN CRANE DATASHEET - IMPERIAL. Features:
ROUGH TERRAIN CRANE DATASHEET - IMPERIAL Features: Rated capacity: 100 ton @ 10 ft working radius Maximum boom length: 174 ft Maximum tip height: 183 ft Maximum hook height: 174.5 ft CONTENTS Key............................................................................................
STANDARD PRACTICE INSTRUCTION
STANDARD PRACTICE INSTRUCTION DATE: SUBJECT: Crane Safety Program REGULATORY STANDARD: OSHA 29 CFR 1910.179 Overhead and Gantry Cranes OSHA 29 CFR 1926.550 Cranes and Derricks OSHA 29 CFR 1903.1 (The General
Advanced Rigging Annotated Instructor s Guide
Advanced Rigging Annotated Instructor s Guide Module 38301-11 Module Overview This module covers specialized rigging techniques and equipment. Load dynamics are explained. The use of specialized equipment
GUIDE TO TOWER CRANES 1
1 This Guide provides information on siting, erecting and using tower cranes and selferecting tower cranes in the workplace and supports the General guide for cranes. This Guide forms part of a series
Mobile (Truck) Cranes
Mobile (Truck) Cranes Definition: A truck or mobile crane consists of an upper carriage with front end attachment such as a box or lattice type boom and optional jib (boom extension). The upper carriage
CONSTRUCTION SAFETY. NOTE: Barriers, guards, and warning signs are required to ensure safety against existing hazards.
CONSTRUCTION SAFETY Introduction The following sections provide general guidelines and procedures for construction safety. This chapter covers the following topics: TOPIC PAGE General Construction Guidelines
4. How often should vehicles being used at worksites be inspected?
Notes for Scoring: The correct answer is highlighted in yellow. The source for the answer is listed in red. 1. Ground Fault Circuit Interrupters (GFCI) are required by the National Electrical Code: a.
UNIT 7 Crane safety. Engineering CASE STUDY. Cambridge English for. Professional English. Part 1. Part 2
Professional English Cambridge English for Engineering CASE STUDY Part 1 Read the extract from a handbook about crane safety. Then discuss the questions about the underlined keywords with a partner. When
LOAD TEST PROCEDURE. Bridge, Gantry and Jib Cranes & Monorail Systems B001-R05/07
LOAD TEST PROCEDURE Bridge, Gantry and Jib Cranes & Monorail Systems B001-R05/07 Introduction: Load testing and inspection of overhead cranes is required by many safety regulations, national consensus
`Fall Protection Guidelines in Construction
`Fall Protection Guidelines in Construction A Publication Provided by: 1681 Campus Delivery Fort Collins, Colorado 80523 (970) 491-6151 email: [email protected] web: http://www.bernardino.colostate.edu/public/
POTENTIAL HEALTH & SAFETY HAZARDS
Number: OH&S 18.27.1 Revision Date: 2014.01.28 Crane Safety Procedures 1. PURPOSE 1.1. These procedures provide the University requirements for the operation and management of overhead travelling cranes
Training Needs Assessments Chart. Index of Training Requirements Job Description: or Employee:
1910.1200 Hazard Communication HAZCOM 1910.147 The Control of Hazardous Energy, Lock-out/Tag-Out 1910.212 Machines, General Requirements 1910.305 Electrical, Wiring Methods, Components & Equip. 1910.132
Chapter 3: Fall Protection/ Scaffolding Safety
Chapter 3: Fall Protection/ Scaffolding Safety Learning Objectives In this chapter you will learn to: recognize the hazards commonly associated with work on or around scaffolds; be aware of common scaffold-related
EQUIPMENT SAFETY EARTHMOVING MATERIAL HANDLING NAVFAC MIDLANT
EQUIPMENT SAFETY EARTHMOVING MATERIAL HANDLING COMMON EARTHMOVING EQUIPMENT SKID LOADERS BACKHOE FRONT END LOADER GRADERS SCRAPERS BULL DOZERS Lots of stuff Here! COMMON MATERIAL HAULING TRUCKS ALL TYPES
HOW HYDRAULIC TRUCK CRANES WORK
HOW HYDRAULIC TRUCK CRANES WORK Heavy rains spawned by Hurricane Danny flooded many parts of Charlotte, NC. Flood waters rose so quickly in Little Sugar Creek that the underpinnings of a train trestle
EMPLOYEE FALL PROTECTION
EMPLOYEE FALL PROTECTION You can fall from any height and be seriously injured or killed. In the construction industry, as well as any other industry, when falls from heights happen, they are usually very
Mobile Crane Operator Certification Program
Mobile Crane Operator Certification Program Candidate Handbook N AT I O N A L C E N T E R F O R C O N S T R U C T I O N E D U C AT I O N A N D R E S E A R C H Contents Purposes of the Program........................................
CONSTRUCTION SAFETY SERIES: Crane Safety
ERI Safety Videos Videos for Safety Meetings C002 CONSTRUCTION SAFETY SERIES: Crane Safety Leader s Guide Marcom Group Ltd. Structure and Organization INTRODUCTION TO THE PROGRAM Information in this program
Contents. 1. Foreword 1. 2. Common accidents in lifting operations 2. 3. Legislative requirements and code of practice of lifting operations 2
Contents 1. Foreword 1 2. Common accidents in lifting operations 2 3. Legislative requirements and code of practice of lifting operations 2 4. People 3 5. Machinery 5 5.1 Cranes 6 5.1.1 Mobile crane 7
Cranes and Lifting Equipment
Standard Operating Procedures Cranes and Lifting Equipment Last Modified: JAN 2013 1 of 10 Cranes and Lifting Equipment I Purpose To establish standards for the safe operation of cranes or any other lifting
RT 780. RT 780 80 USt Lifting Capacity Rough Terrain Cranes Datasheet Imperial. Features
USt Lifting Capacity Rough Terrain Cranes Datasheet Imperial Features Rated capacity: US t @ ft working radius Maximum boom length: 126 ft Maximum tip height: 1 ft CONTENTS Page: Key...3 Dimensions Crane
This material was produced under grant number SH-17792-08-60-F-48 Occupational Safety and Health Administration, U.S. Department of Labor.
Big Four Construction Hazards: Fall Hazards This material was produced under grant number SH-17792-08-60-F-48 Occupational Safety and Health Administration, U.S. Department of Labor. It does not necessarily
ELEVATED WORK POLICY
ELEVATED WORK POLICY 1.0 BACKGROUND The purpose of this program is to prevent accidents and injuries to workers from falls and to provide employees with the information for the safe use of fall protection
Fall Protection Program
Fall Protection Program Policy: It is the policy of our company to provide fall protection for employees exposed to fall hazards greater than 7 ½ feet. Fall hazards include but, are not limited to; work
What is Fall protection?
What is Fall protection? The Occupational Safety and Health Administration s (OSHA s) fall protection standard deals with both human and equipment-related issues. The standard identifies areas or activities
2. Crane standing on firm, horizontal ground.
The operating weight includes the basic machine with HD undercarriage, 2 main winches 300 kn with speed change gear and 11 m boom, consisting of A frame, boom foot (4 m), boom head section (6.4 m), boom
Elkhorn Construction, Inc. Safety Manual Title: Fall Protection Policy Effective Date: 03-01-2000
1. General Requirements (OSHA References: OSHA 29 CFR 1926.503) 1.1 Elkhorn Construction, Inc. employee-owners and subcontractors are required to use fall protection equipment or systems when an assessment
SAFE USE OF LIFTING EQUIPMENT
Golden Rule 6 Mechanical Lifting SAFE USE OF LIFTING EQUIPMENT Do not operate any lifting equipment unless It has been approved for use The lift has been assessed by a competent person The load has been
Fall Protection Equipment
Fall Protection Equipment Quick Tips #130 Introduction Before you can begin a fall protection program, you must identify the potential fall hazards in your workplace. Any time a worker is at a height of
Appendix 6145-T1 Forklift Use Practices
Appendix 6145-T1 Operators must perform a preoperational inspection of the forklifts and attachments in accordance with the equipment operating manual. They will immediately report any equipment deficiencies
CHAPTER 9 MOBILE CRANES
CHAPTER 9 MOBILE CRANES This chapter specifies operation, inspection, maintenance, and testing requirements for the use of mobile cranes and implements the requirements of ASME B30.5 ( Mobile and Locomotive
OSHA Scaffold Standard for Construction. 29 CFR 1926 Subpart L
OSHA Scaffold Standard for Construction 29 CFR 1926 Subpart L EH&S Jim Walker What is the revised OSHA scaffold standard for construction? Issued on August 30, 1996 and became effective on November 29,
Owner s Manual Gantry Cranes
Owner s Manual Gantry Cranes Fixed Height Gantry Crane MODEL NUMBER: SERIAL NUMBER: CAPACITY IN TONS: Telescoping Gantry Crane Bushman AvonTec 262-790-4200, 800338-7810, Fax 262-790-4200 www.bushmanavontec.com
Tower Crane. Operator Certification Exam. Getting Ready Guide
Tower Crane Operator Certification Exam Getting Ready Guide BC Association for Crane Safety www.bcacs.ca November 2011 2 Table of Contents Introduction...4 Who Should Use This Guide... 4 How to Use This
Table of Contents Introduction How to Use This Manual How to Do a Facility Audit
Table of Contents Introduction How to Use This Manual How to Do a Facility Audit OSHA Plant Safety Audit Checklist: Self-Inspection Types of Hazards Addressing the Hazards in Your Work Area Safety and
Crane Best Practices in Tree Removal Hoisting a Qualified Arborist. By Mark Adams
Crane Best Practices in Tree Removal Hoisting a Qualified Arborist By Mark Adams Many tree companies today either own or rent cranes for use in removing trees. As cranes become more and more common in
A Guide to Cranes and Derricks
Industry Guide 20 A Guide to Cranes and Derricks N.C. Department of Labor N.C. Department of Labor Occupational Safety and Health Division 1101 Mail Service Center Raleigh, NC 27699-1101 Cherie Berry Commissioner
Aerial/Scissor Lift Program. Environmental Health & Safety Office
Aerial/Scissor Lift Program Environmental Health & Safety Office August 2013 Revised 08/2013 - Rev 4.0 Table of Contents INTRODUCTION... 1 PURPOSE... 1 SCOPE... 1 RESPONSIBILITIES... 1 DEFINITIONS:...
Series 90 Portable Capstan Hoist. Owners Manual ! CAUTION
Series 90 Portable Capstan Hoist Owners Manual! CAUTION The equipment covered in this document should be installed, used, and serviced only by competent personnel familiar with and following good work
June 22, 2013. Steve Johnson Operation Manager Best Roofing, Inc. 7002 N. 288th St. Sioux City, IA 68064. Booker Elementary Safety Survey Omaha, NE
June 22, 2013 Steve Johnson Operation Manager Best Roofing, Inc. 7002 N. 288th St. Sioux City, IA 68064 Re: Booker Elementary Safety Survey Omaha, NE Steve Johnson, This report is in follow-up to the safety
OSHA GUIDANCE DOCUMENT FALL PROTECTION IN RESIDENTIAL CONSTRUCTION
OSHA GUIDANCE DOCUMENT FALL PROTECTION IN RESIDENTIAL CONSTRUCTION OSHA GUIDANCE DOCUMENT FALL PROTECTION IN RESIDENTIAL CONSTRUCTION Table of Contents Executive Summary... 1 Introduction... 1 Installing
METHOD STATEMENT CRANE HIRE PROVIDING A CONTRACT LIFT SERVICE IN COMPLIANCE WITH BS7121 PARTS 1 & 3 AND LOLER REGULATIONS
METHOD STATEMENT CRANE HIRE PROVIDING A CONTRACT LIFT SERVICE IN COMPLIANCE WITH BS7121 PARTS 1 & 3 AND LOLER REGULATIONS CLIENT: Elliott Group CONTACT: Maurice Kennett SITE: Lympstone Church Ring School,
What should you check for when inspecting a crane before maintenance?
Crane Maintenance What should you check for when inspecting a crane before maintenance? Lower hoist to unload rope sheaves. Unwind all wire rope from the hoist drum to expose all parts of a rope, making
Aviva Insurance Limited
One Park Place, Hatch Street, Dublin 2 Registration number: 9002 is accredited by the Irish National Board (INAB) to undertake inspection as detailed in the Schedule bearing the above registration number,
Walking and Working Surface Checklist:
Walking and Working Surfaces Purpose: This information is presented to improve the level of safety in our operations, and to inform you that we will comply with the OSHA Standard 29 CFR 1910.23. Responsibility:
CHAPTER 10. FALL PROTECTION PROGRAM
CHAPTER 10. FALL PROTECTION PROGRAM 1000 GENERAL. This chapter establishes policy for developing fall protection programs to protect all Federal Aviation Administration (FAA) personnel working at elevated
FALL PROTECTION- Part 2 SELF INSPECTION CHECKLIST
OPTIONAL INFORMATION Name of School: Date of Inspection: Vocational Program/Course/Room: Signature of Inspector: FALL PROTECTION- Part 2 Instructions: This checklist covers fall protection systems criteria
Savard Labor & Marine Staffing, Inc. Rigging Safety Rev3/14 Rigging Safety
Rigging Safety The ability to handle materials to move them from one location to another, whether during transit or at the worksite is vital to all segments of industry. Materials must be moved, for example,
CHAPTER 2 GENERAL SAFETY REQUIREMENTS
Bridge Inspection Handbook 2-1 2.1 INTRODUCTION CHAPTER 2 GENERAL SAFETY REQUIREMENTS Safety is everyone's business. As an employer, MassDOT is obligated to promote job safety and furnish safe tools, equipment,
Memberships. W.F. Welding & Overhead Cranes Ltd. Since 1986. W.F. Welding & Overhead Cranes. 1-200 Ton Overhead Cranes. Jib Cranes.
Memberships Canadian Standards Association (CSA) W.F. is approved by the Canadian Welding Bureau and certified to CSA standard W47.1-03-Division 1. Other memberships include: W.F. Welding & Overhead Cranes
Working Copy WP 05-WH1401. Revision 4. 6-Ton Electric Forklifts 74-H-010B. Technical Procedure EFFECTIVE DATE: 01/04/06. John Guy APPROVED FOR USE
WP 05-WH1401 Revision 4 6-Ton Electric Forklifts 74-H-010B Technical Procedure EFFECTIVE DATE: 01/04/06 John Guy APPROVED FOR USE WP 05-WH1401 Rev. 4 Page 2 of 10 TABLE OF CONTENTS INTRODUCTION... 3 REFERENCES...
Technical Advisory for Safe Operation of Lifting Equipment. Programme-Based Engagement
Technical Advisory for Safe Operation of Lifting Equipment Programme-Based Engagement Contents 1. Introduction and Background 03 2. Case Studies of Accidents Involving Lifting Equipment 05 3. Common Systemic
WORKING AT HEIGHTS. Introduction. Risk Assessment
WORKING AT HEIGHTS Introduction This guideline makes reference to the provisions regarding working at heights in the Regulation for Industrial Establishments (Reg. 851) and the Regulation for Construction
AERIAL FIBER OPTIC CABLE PLACEMENT
Installation Practice IP003 Aerial Fiber Optic Cable Placement Rev.-June 2000 Page 1 of 6 AERIAL FIBER OPTIC CABLE PLACEMENT CONTENTS PARAGRAPH SCOPE...1 GENERAL PRECAUTIONS...2 GENERAL DESCRIPTION OF
Bechtel Rigging Handbook (Second Edition)
Constructing Our Future Bechtel Rigging Handbook (Second Edition) Bechtel Equipment Operations, Inc. BECHTEL RIGGING HANDBOOK 2nd Edition Copyright 1996, 2002 Bechtel Corporation Second Edition. All rights
National Occupational Health and Safety Commission
National Occupational Health and Safety Commission NATIONAL GUIDELINES FOR OCCUPATIONAL HEALTH AND SAFETY COMPETENCY STANDARDS FOR THE OPERATION OF LOADSHIFTING EQUIPMENT AND OTHER TYPES OF SPECIFIED EQUIPMENT
RESPONSIBILITIES IN MOBILE CRANE OPERATIONS CONSTRUCTION SAFETY ASSOCIATION OF ONTARIO
RESPONSIBILITIES IN MOBILE CRANE OPERATIONS CONSTRUCTION SAFETY ASSOCIATION OF ONTARIO MOBILE CRANE OPERATIONS WHO IS RESPONSIBLE? The question of who is responsible for the various aspects of a crane
Tower crane. Code of Practice 2006. Workplace Health and Safety Queensland Department of Justice and Attorney-General
Tower crane Code of Practice 2006 Workplace Health and Safety Queensland Department of Justice and Attorney-General This Queensland code of practice was preserved as a code of practice under section 284
HealthandSafetyOntario.ca. Hazards. Introduction. Legislation
Manual Materials handling Introduction Manual materials handling operations are carried out in most workplaces. Each handling task poses unique demands on the worker. However, workplaces can help workers
QUESTIONS AND ANSWERS ON NEW FALL PROTECTION LEGISLATION
QUESTIONS AND ANSWERS ON NEW FALL PROTECTION LEGISLATION 50.4(1) An owner of a place of employment, an employer and a contractor shall each ensure that each component of a fall-protection system is inspected
Record of Performance Inspection and Test Crawler, Locomotive, Truck, and Wheel Cranes
Appendix F Record of Performance Inspection and Test Crawler, Locomotive, Truck, and Wheel Cranes General All mobile cranes must be performance inspected and tested by the owner and/or contractor in accordance
Safety and Analysis in Material Handling of Construction Industry
Middle-East Journal of Scientific Research 23 (3): 523-528, 2015 ISSN 1990-9233 IDOSI Publications, 2015 DOI: 10.5829/idosi.mejsr.2015.23.03.22119 Safety and Analysis in Material Handling of Construction
Training Schedule 800.521.7669. Quality Service Superior Training Reliable Results. www.cranetech.com
2015 Training Schedule Scan with your mobile device to check programs and specials! Quality Service Superior Training Reliable Results Serving the Material Handling Industry Since 1977 800.521.7669 www.cranetech.com
tirfor lifting and pulling machines operating and maintenance instructions
tirfor lifting and pulling machines operating and maintenance instructions models equipment in accordance with CE directives Tirfor Limited Old Lane, Halfway, Sheffield S9 5GZ. Tel: (0) 28 2266 Fax: (0)
US&R Heavy Equipment & Rigging Specialist Training Module 3 Unit 3: Demolition Contractor Equip & Helicopter Ops
US&R Heavy Equipment & Rigging Specialist Training Module 3 Unit 3: Demolition Equip and Methods + Helicopter Ops 22Mar08 1 Unit Objective You will be able to explain how demolition contractors and their
One-third of all fatalities in the U.S. construction
Guardrail systems: Fall prevention for floor and wall openings and open-sided floors One-third of all fatalities in the U.S. construction industry result from falls from elevations. Falls from elevations
Operator s Manual EVENTER 20 / 25 Series Lifts
Operator s Manual EVENTER 20 / 25 Series Lifts May 2013! Before operating this lift, read and understand this Operator s Manual. Become familiar with the potential hazards of this unit. Call SUMNER should
Fall Protection Susan Harwood Grant Training Program 2013 Wood Frame Construction
WRONG BETTER Fall Protection Susan Harwood Grant Training Program 2013 Wood Frame Construction Learning Objectives Understand how OSHA defines residential construction Understand the proper use of guardrails
CONTRACTOR CRANE AWARENESS WEB BASED TRAINING STUDENT GUIDE NCC-CCA-01
CONTRACTOR CRANE AWARENESS WEB BASED TRAINING STUDENT GUIDE NCC-CCA-01 Naval Facilities Engineering Command Navy Crane Center Norfolk Naval Shipyard, Bldg. 491 Portsmouth, VA 23709-5000 Comm. Phone: 757.967.3803,
Slings, Rigging and Lifting Equipment
A printed or saved copy is an UNCONTROLLED copy. Check that it is the latest available version before use. Title: Number: SLINGS, RIGGING AND LIFTING EQUIPMENT GM-11-038-02 Version Number: 13.0 Date Revised:
Fall Protection Guidelines
OCT 2015 1 of 6 Fall Protection Guidelines 1.0 PURPOSE To establish the requirements and procedures to protect employees and other persons conducting work from hazards associated with falling from one
SCAFFOLD SAFETY IN THE CONSTRUCTION INDUSTRY
SCAFFOLD SAFETY IN THE CONSTRUCTION INDUSTRY AN OVERVIEW OF THE OCCUPATIONAL HEALTH AND SAFETY ADMINISTRATION (OSHA) STANDARD New England Laborers ' Health & Safety Fund 410 South Main Street Providence,
FALL PROTECTION WORK PLAN
FALL PROTECTION WORK PLAN INSTRUCTIONS A written fall protection work plan must be implemented by each employer on a job site where a fall hazard of 10 feet or greater exists, in accordance with OSHA Standards.
Topics of the Presentation
Drill Rig Safety Topics of the Presentation Personnel safety and monitoring PPE Health (Drugs and Alcohol) Drill Rig operation Safe set up procedures Safe operation of machine Safety related accidents
Does this topic relate to the work the crew is doing? If not, choose another topic.
TRAINING GUIDE HIGH VOLTAGE LINES 2001 Before you begin the meeting... Does this topic relate to the work the crew is doing? If not, choose another topic. Did you read this Training Guide and fill in the
Enhancing Safe Use of Cranes A Great Workforce A Great Workplace
Enhancing Safe Use of Cranes A Great Workforce A Great Workplace Ian Teh Yi Tian Engineering Safety Branch OSH Specialists Department Occupational Safety and Health Division, MOM Safe use of Cranes Scope
RESIDENTIAL ROOF TRUSS INSTALLATION PROCEDURES
RESIDENTIAL ROOF TRUSS INSTALLATION PROCEDURES Construction Safety Association of Ontario, October 2008 Prepared for the Low-Rise Residential Trade Labour-Management Health and Safety Committee CONTENTS