1 Session 3.3 Sensitivity and Risk Analysis Introductory Course on Economic Analysis of Investment Projects 5-9 July 2010
2 Why Sensitivity and Risk Analysis Project returns are spread over time costs and benefits are subject to uncertainty and may vary from the base case Sensitivity and risk analysis is an analytical framework for dealing with uncertainty. The objective is to reduce the likelihood of undertaking bad projects while not failing to accept good projects References: Guidelines (1997), Handbook (2002), Technical Note 2 (2002)
3 Sensitivity Analysis is the first step to risk analysis. Basically, it is a "What if" analysis testing which variables are important to project outcomes (NPV, EIRR) applies to all projects with quantified benefits and costs involves recalculating project outcomes (NPV, EIRR) for different values of major variables and combinations of variables when benefits are not valued, may use sensitivity analysis to assess impact of changed assumptions on unit costs only
4 Sensitivity Analysis: Procedure Determine key variables and their possible changes Re-calculate EIRR and NPV Calculate Switching Value
5 Switching Value Switching value is the value of the variable at which the project investment decision is changed. Usually is defined as percentage change from the base case. Percentage change in a variable required to reduce the net present value (NPV) to zero at the chosen discount rate: Set NPV = 0 v* SV = 100% x (v* - v 0 )/v 0 OR Percentage change in a variable required to make the project EIRR equal a chosen discount rate (e.g., 12%): Set EIRR = r v* SV = 100% x (v* - v 0 )/v 0
6 Sensitivity Analysis: Presentation Which variables have low switching values? Have the calculations used realistic changes? Do likely changes exceed switching values? How likely are the combinations to occur?
7 Risk Analysis A method to estimate the probability distribution of project outcome: F(EIRR), F(NPV) Determine a probability distribution of values of key variables: F(v 1 ), F(v 2 ),, F(v n ) Sample these values to determine a probability distribution of outcome Process greatly simplified by use of PCs and standard software packages
8 Probability Distribution for Economic Rate of Return EIRR<= % Mean = EIRR<= % EIRR
9 Implications for ADB Operations risk analysis is used for consideration of projects one-byone (i.e., not investment portfolio analysis) helps to identify relative importance of different variables as determinants of project returns analytic focus is on determining the likelihood that project returns (economic and financial, to economy and to particular groups) are unacceptable (i.e., EIRR< EOCC, or NPV<0; and also PIR<XX%) ultimately, leads to project re-design/incorporation of mitigating measures (including the appropriate allocation of risks among various project participants)
10 ERD S Retro 2005 Findings Sensitivity and risk analyses were inadequate or poor in about half of the RRPs reviewed. Most projects applied sensitivity test but the analysis is generally limited to a mechanistic plus 10% (20%) project costs, minus 10% (20%) of project benefits, or 1-year delay in project implementation (same as in Retros 2002 and 2003). Note that the focus of sensitivity test is on specific variables to inform project design. Only a small number of projects conducted quantitative risk analysis.
11 Final Notes There may be other risks very important to assess but cannot quantify (e.g., political and institutional risks). They are really a part of sensitivity and risk analysis and generally treated under qualitative risk analysis (e.g., risk matrix of typically low, medium, high impact). When risk is high (e.g., very small switching value, high probability that EIRR<EOCC), need to work out mitigating measures or change project design.
12 Thank you
PROJECT RISK EVALUATION METHODS - SENSITIVITY ANALYSIS
Annals of the University of Petroşani, Economics, 9(2), 2009, 33-38 33 PROJECT RISK EVALUATION METHODS - SENSITIVITY ANALYSIS MIRELA ILOIU, DIANA CSIMINGA * ABSTRACT: The viability of investment projects
ABI Position paper. Supplement to ED/2009/12 Financial Instruments: Amortised Cost and Impairment
ABI Position paper Supplement to ED/2009/12 Financial Instruments: Amortised Cost and Impairment March 2011 Page 1 of 17 Dear Sir/Madam, The Italian Banking Association welcomes the publication of the
A Basic Introduction to the Methodology Used to Determine a Discount Rate
A Basic Introduction to the Methodology Used to Determine a Discount Rate By Dubravka Tosic, Ph.D. The term discount rate is one of the most fundamental, widely used terms in finance and economics. Whether
NPV Versus IRR. W.L. Silber -1000 0 0 +300 +600 +900. We know that if the cost of capital is 18 percent we reject the project because the NPV
NPV Versus IRR W.L. Silber I. Our favorite project A has the following cash flows: -1 + +6 +9 1 2 We know that if the cost of capital is 18 percent we reject the project because the net present value is
FRC Risk Reporting Requirements Working Party Case Study (Pharmaceutical Industry)
FRC Risk Reporting Requirements Working Party Case Study (Pharmaceutical Industry) 1 Contents Executive Summary... 3 Background and Scope... 3 Company Background and Highlights... 3 Sample Risk Register...
NPV with an Option to Delay and Uncertainty
NPV with an Option to Delay and Uncertainty In all the examples and the theory so far, we have assumed perfect foresight when making investment decisions and analyzing future variables. We have also ignored
Solvency II for Beginners 16.05.2013
Solvency II for Beginners 16.05.2013 Agenda Why has Solvency II been created? Structure of Solvency II The Solvency II Balance Sheet Pillar II & III Aspects Where are we now? Solvency II & Actuaries Why
PROJECT CRITERIA: ECONOMIC VIABILITY AND PROJECT ALTERNATIVES
SESSION 1.2 PROJECT CRITERIA: ECONOMIC VIABILITY AND PROJECT ALTERNATIVES Introductory Course on Economic Analysis of Investment Projects Economics and Research Department (ERD) Discounted Cash Flow: Measures
AfDB New Procurement Policy: Training Program for the Bank s Procurement Staff. Risk-based design of Procurement Arrangements - Introduction
11 AfDB New Procurement Policy: Training Program for the Bank s Procurement Staff Risk-based design of Procurement Arrangements - Introduction 2 Bank's new Approach to Procurement New Vision of the Procurement
1. What Is Risk? 3. Perspectives on Risk. Risk Management. 6. Characteristics of Risk Management 7. Advantages of Risk Management
Risk Management 1. What Is Risk? 2. Why Do We Accept or Assume Risks? 3. Perspectives on Risk 4. What is Risk Management? 5. The Risk Management Process 6. Characteristics of Risk Management 7. Advantages
LECTURES ON REAL OPTIONS: PART I BASIC CONCEPTS
LECTURES ON REAL OPTIONS: PART I BASIC CONCEPTS Robert S. Pindyck Massachusetts Institute of Technology Cambridge, MA 02142 Robert Pindyck (MIT) LECTURES ON REAL OPTIONS PART I August, 2008 1 / 44 Introduction
Project Risk Management
Project Risk Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Risk Management
Capital Planning Guidelines
Capital Planning Guidelines Contents Capital Planning Guidelines... 1 1. INTRODUCTION... 3 2. CAPITAL PROJECTS EVALUATION PROCESS... 3 3. APPRAISAL PROCESS UNDERTAKEN BY DEPARTMENTS... 4 3.1 Extension
STANDARD. Risk Assessment. Supply Chain Risk Management: A Compilation of Best Practices
A S I S I N T E R N A T I O N A L Supply Chain Risk Management: Risk Assessment A Compilation of Best Practices ANSI/ASIS/RIMS SCRM.1-2014 RA.1-2015 STANDARD The worldwide leader in security standards
Overview of Financial Management
Overview of Financial Management Uwadiae Oduware FCA Akintola Williams Deloitte 1-1 Definition Financial Management entails planning for the future for a person or a business enterprise to ensure a positive
<Business Case Name> <Responsible Entity> <Date>
(The entity Chief Information Officer, Chief Financial Officer and Business Area programme Lead must sign-off the completed business case) Signed: Date:
Discounted Cash Flow. Alessandro Macrì. Legal Counsel, GMAC Financial Services
Discounted Cash Flow Alessandro Macrì Legal Counsel, GMAC Financial Services History The idea that the value of an asset is the present value of the cash flows that you expect to generate by holding it
1.1 Introduction. Chapter 1: Feasibility Studies: An Overview
Chapter 1: Introduction 1.1 Introduction Every long term decision the firm makes is a capital budgeting decision whenever it changes the company s cash flows. Consider launching a new product. This involves
EVA Issues as a Valuation Framework: Issues Solved By AFG s Economic Margin
EVA Issues as a Valuation Framework: Issues Solved By AFG s Economic Margin 1 EVA as a valuation tool Firm Value = NOPAT + EVA Future * 1 * T c* c* ( 1 + c* ) Existing Assets Future Investments The basic
ENTREPRENEURIAL FINANCE: Strategy, Valuation, and Deal Structure
ENTREPRENEURIAL FINANCE: Strategy, Valuation, and Deal Structure Chapter 11. The Entrepreneur s Perspective on Value Questions and Problems 1. A venture that requires an investment of $5 million is expected
January 6, 2010. The financial regulators 1
ADVISORY ON INTEREST RATE RISK January 6, 2010 MANAGEMENT The financial regulators 1 are issuing this advisory to remind institutions of supervisory expectations regarding sound practices for managing
A Methodology for Calculating the Opportunity Cost of Layered Sovereign DRFI Strategies
IMPACT APPRAISAL FOR SOVEREIGN DISASTER RISK FINANCING AND INSURANCE PROJECT: PHASE 1 ACTUARIAL AND REINSURANCE, PAPER 1 A Methodology for Calculating the Opportunity Cost of Layered Sovereign DRFI Strategies
Net Present Value (NPV)
Investment Criteria 208 Net Present Value (NPV) What: NPV is a measure of how much value is created or added today by undertaking an investment (the difference between the investment s market value and
Risk Analysis and Quantification
Risk Analysis and Quantification 1 What is Risk Analysis? 2. Risk Analysis Methods 3. The Monte Carlo Method 4. Risk Model 5. What steps must be taken for the development of a Risk Model? 1.What is Risk
Why Use Net Present Value? The Payback Period Method The Discounted Payback Period Method The Average Accounting Return Method The Internal Rate of
1 Why Use Net Present Value? The Payback Period Method The Discounted Payback Period Method The Average Accounting Return Method The Internal Rate of Return Problems with the IRR Approach The Profitability
10 Essential Steps to Portfolio Management
10 Essential Steps to Portfolio Management Portfolio Planning for 2013 Revised November 2012 http://epmlive.com Contents Introduction...2 Portfolio Management Overview...3 Portfolio Management Process
Measuring and. Communicating. Security's Value. A Compendium of Metrics. for Enterprise Protection
Measuring and Communicating Security's Value A Compendium of Metrics for Enterprise Protection George Campbell AMSTERDAM BOSTON HEIDELBERG LONDON NEW YORK OXFORD PARIS SAN DIEGO SAN FRANCISCO SINGAPORE
IBM Business Analytics Requirements Analysis and Planning
IBM Business Analytics Requirements Analysis and Planning Service Definition IBM Business Analytics Requirements Analysis and Planning 1 1. Summary 1.1 Service Description As an integral part of IBM Business
Risk Management and Internal Audit Specialized Training Course Audit Risk Assessment Methodology
Risk Management and Internal Audit Specialized Training Course Audit Risk Assessment Methodology May 20, 2015 Internal FR 2 Risk and Risk Assessment Defined Risk Institute of Internal Auditors (IIA) The
Guidelines for the Preparation of Project Performance Evaluation Reports on Nonsovereign Operations
Guidelines November 2014 Guidelines for the Preparation of Project Performance Evaluation Reports on Nonsovereign Operations Independent Evaluation Department ABBREVIATIONS ADB Asian Development Bank ADD
Economic value of reducing the risk of a gas supply outage
Economic value of reducing the risk of a gas supply outage A threshold benefit-cost analysis Prepared for ActewAGL Centre for International Economics Canberra & Sydney December 24 2009 The Centre for International
FINANCIAL ANALYSIS. A. Introduction and Methodology
Coastal Towns Environmental Infrastructure Project (RRP BAN 44212) FINANCIAL ANALYSIS A. Introduction and Methodology 1. The Coastal Towns Environmental Infrastructure project finances basic urban service
How to achieve excellent enterprise risk management Why risk assessments fail
How to achieve excellent enterprise risk management Why risk assessments fail Overview Risk assessments are a common tool for understanding business issues and potential consequences from uncertainties.
2010 MTEF: Budgeting for infrastructure and capital expenditure guidelines
2010 MTEF: Budgeting for infrastructure and capital expenditure guidelines Introduction The guidelines below provide departments and entities with information to make budget submissions for capital projects
Davy Defensive High Yield Fund from New Ireland
Davy Asset Management For Financial Advisors Only Davy Defensive High Yield Fund from New Ireland Davy Asset Management is regulated by the Central Bank of Ireland. Exposure to: equity-market type returns
Investment Project Financing Economic Analysis Guidance Note
2013 Investment Project Financing Economic Analysis Guidance Note OPSPQ This guidance notes are intended for internal use by Bank staff. The notes will be updated and complemented from time to time. April
(Relevant to AAT Examination Paper 4 Business Economics and Financial Mathematics)
Capital Budgeting: Net Present Value vs Internal Rate of Return (Relevant to AAT Examination Paper 4 Business Economics and Financial Mathematics) Y O Lam Capital budgeting assists decision makers in a
FINANCIAL AND ECONOMIC ANALYSES
Tonga-Fiji Submarine Cable Project (RRP TON 44172) FINANCIAL AND ECONOMIC ANALYSES A. Introduction 1. The Tonga Fiji Submarine Cable Project will support the Government of Tonga to establish an 827 kilometer
Cost Contribution Arrangements in Transfer Pricing International Best Practices
Cost Contribution Arrangements in Transfer Pricing International Best Practices Dr. Shanto Ghosh December 2008 Contents Overview Cost Contribution and cost sharing Cost Contribution for services Qualified
Strategy and Analysis in Using NPV. How Positive NPV Arises
Strategy and Analysis in Using NPV (Text reference: Chapter 8) Topics how positive NPV arises decision trees sensitivity analysis scenario analysis break-even analysis investment options AFM 271 - Strategy
Real Options. The Big Picture: Part II - Valuation
Real Options The Big Picture: Part II - Valuation A. Valuation: Free Cash Flow and Risk April 1 April 3 Lecture: Valuation of Free Cash Flows Case: Ameritrade B. Valuation: WACC and APV April 8 April 10
A Primer on Valuing Common Stock per IRS 409A and the Impact of FAS 157
A Primer on Valuing Common Stock per IRS 409A and the Impact of FAS 157 By Stanley Jay Feldman, Ph.D. Chairman and Chief Valuation Officer Axiom Valuation Solutions 201 Edgewater Drive, Suite 255 Wakefield,
Incorporating Risk Assessment into Project Forecasting
Incorporating Risk Assessment into Project Forecasting Author: Dione Palomino Conde Laratta, PMP Company: ICF International - USA Phone: +1 (858) 444-3969 [email protected] Subject Category: Project
Hot Topic FS Regulatory Centre of Excellence, 2 December 2013. Hot Topic. Solvency II requirements published
Hot Topic Hot Topic Solvency II requirements published The publication of the Omnibus II text provides much needed clarity to the market on some key topics FS Regulatory Centre of Excellence 2 December
ECONOMIC JUSTIFICATION
ECONOMIC JUSTIFICATION A Manufacturing Engineer s Point of View M. Kevin Nelson, P.E. President Productioneering, Inc. www.roboautotech.com Contents: I. Justification methods a. Net Present Value (NPV)
Best Estimate of the Technical Provisions
Best Estimate of the Technical Provisions FSI Regional Seminar for Supervisors in Africa on Risk Based Supervision Mombasa, Kenya, 14-17 September 2010 Leigh McMahon BA FIAA GAICD Senior Manager, Diversified
Chapter 5. Planning the Audit Engagement
Chapter 5 Planning the Audit Engagement A. Purpose for Planning the Engagement Engagement planning is performed to provide a means for developing an understanding of the business objectives of the auditee,
Safety of Nuclear Power Plant : Human Reliability Analysis (HRA) Prof. Wolfgang Kröger
Safety of Nuclear Power Plant : Human Reliability Analysis (HRA) Prof. Wolfgang Kröger (http://www.riskcenter.ethz.ch, [email protected]) Human influence on operation and safety of a system such as anpp
Dataline A look at current financial reporting issue
Dataline A look at current financial reporting issue No. 2013-24 November 25, 2013 What s inside: Overview... 1 At a glance... 1 The main details... 1 Contents of the Guide... 2 Concepts and application
AP4 Education Session Impairment requirements in IFRS 9 Financial Instruments
February 2016 IFRS Standards AP4 Education Session Impairment requirements in IFRS 9 Financial Instruments CMAC meeting 25 February 2016 The views expressed in this presentation are those of the presenter,
CAPITAL PLANNING GUIDELINES
CAPITAL PLANNING GUIDELINES 1. INTRODUCTION... 2 2. EXTENSION OF EXISTING INFRASTRUCTURE PROJECTS... 2 3. NEW CAPITAL PROJECTS... 2 4. MINIMUM INFORMATION REQUIRED... 3 5. PREPARATORY WORK... 3 5.1 NEEDS
Public Sector Cost of Capital and Discount Rates
Public Sector Cost of Capital and Discount Rates Professor Kevin Davis Research Director, Australian Centre for Financial Studies Outline Role of Cost of Capital Some Recent Issues Approaches to the Social
Guidance for Industry: Quality Risk Management
Guidance for Industry: Quality Risk Management Version 1.0 Drug Office Department of Health Contents 1. Introduction... 3 2. Purpose of this document... 3 3. Scope... 3 4. What is risk?... 4 5. Integrating
1. Introduction... 3. 2. Process for determining the solvency need... 4. 3. Definitions of main risk types... 9
Contents Page 1. Introduction... 3 2. Process for determining the solvency need... 4 2.1 The basis for capital management...4 2.2 Risk identification...5 2.3 Danske Bank s internal assessment of its solvency
Chapter 9 Capital Budgeting Decision Models
Chapter 9 Capital Budgeting Decision Models LEARNING OBJECTIVES (Slide 9-2) 1. Explain capital budgeting and differentiate between short-term and long-term budgeting decisions. 2. Explain the payback model
Lecture 8 (Chapter 11): Project Analysis and Evaluation
Lecture 8 (Chapter 11): Project Analysis and Evaluation Discounted cash flow analysis is a very powerful tool, but it is not easy to use. We have already seen one difficulty: How do we identify the cash
THE INSURANCE BUSINESS (SOLVENCY) RULES 2015
THE INSURANCE BUSINESS (SOLVENCY) RULES 2015 Table of Contents Part 1 Introduction... 2 Part 2 Capital Adequacy... 4 Part 3 MCR... 7 Part 4 PCR... 10 Part 5 - Internal Model... 23 Part 6 Valuation... 34
Solvency Assessment and Management: Capital Requirements Discussion Document 58 (v 3) SCR Structure Credit and Counterparty Default Risk
Solvency Assessment and Management: Capital Requirements Discussion Document 58 (v 3) SCR Structure Credit and Counterparty Default Risk EXECUTIVE SUMMARY Solvency II allows for credit and counterparty
QUANTITATIVE MODEL FOR INFORMATION SECURITY RISK MANAGEMENT
QUANTITATIVE MODEL FOR INFORMATION SECURITY RISK MANAGEMENT Rok Bojanc ZZI d.o.o. [email protected] Abstract: The paper presents a mathematical model to improve our knowledge of information security and
INTERNATIONAL STANDARD ON REVIEW ENGAGEMENTS 2410 REVIEW OF INTERIM FINANCIAL INFORMATION PERFORMED BY THE INDEPENDENT AUDITOR OF THE ENTITY CONTENTS
INTERNATIONAL STANDARD ON ENGAGEMENTS 2410 OF INTERIM FINANCIAL INFORMATION PERFORMED BY THE INDEPENDENT AUDITOR OF THE ENTITY (Effective for reviews of interim financial information for periods beginning
Personal Development Planning
Personal Development Planning Scope All programmes leading to a City University London award. This policy will apply for partnership programmes unless equivalent arrangements have been specifically agreed
EIOPACP 13/09. Guidelines on Forward Looking assessment of own risks (based on the ORSA principles)
EIOPACP 13/09 Guidelines on Forward Looking assessment of own risks (based on the ORSA principles) EIOPA Westhafen Tower, Westhafenplatz 1 60327 Frankfurt Germany Tel. + 49 6995111920; Fax. + 49 6995111919;
CHAPTER 11. Proposed Project. Incremental Cash Flow for a Project. Treatment of Financing Costs. Estimating cash flows:
CHAPTER 11 Cash Flow Estimation and Risk Analysis Estimating cash flows: Relevant cash flows Working capital treatment Inflation Risk Analysis: Sensitivity Analysis, Scenario Analysis, and Simulation Analysis
IFRS Project Insights Insurance Contracts
IFRS Project Insights Insurance Contracts December 2015 The International Accounting Standards Board ( IASB / the Board ) is undertaking a comprehensive project on the accounting for insurance contracts,
Session 4. System Engineering Management. Session Speaker : Dr. Govind R. Kadambi. M S Ramaiah School of Advanced Studies 1
Session 4 System Engineering Management Session Speaker : Dr. Govind R. Kadambi M S Ramaiah School of Advanced Studies 1 Session Objectives To learn and understand the tasks involved in system engineering
Chapter 5 Initiating and Planning Systems Development Projects
Chapter 5 Initiating and Planning Systems Development Projects Multiple Choice Questions 1. As a rule of thumb estimate, what percentage of the entire development effort should be devoted to the project
Professional Level Skills Module, Paper P4
Answers Professional Level Skills Module, Paper P4 Advanced Financial Management December 2011 Answers 1 Up to 4 professional marks are available for the presentation of the answer, which should be in
The Total Economic Impact Of SAS Customer Intelligence Solutions Real-Time Decision Manager
A Forrester Total Economic Impact Study Commissioned By SAS Project Director: Dean Davison May 2014 The Total Economic Impact Of SAS Customer Intelligence Solutions Real-Time Decision Manager Table Of
Negative Risk. Risk Can Be Positive. The Importance of Project Risk Management
The Importance of Project Risk Management Project risk management is the art and science of identifying, analyzing, and responding to risk throughout the life of a project and in the best interests t of
Internal Quality Assurance Arrangements
National Commission for Academic Accreditation & Assessment Handbook for Quality Assurance and Accreditation in Saudi Arabia PART 2 Internal Quality Assurance Arrangements Version 2.0 Internal Quality
FINDING THE RISK IN RISK ASSESSMENTS NYSICA JULY 26, 2012. Presented by: Ken Shulman Internal Audit Director, New York State Insurance Fund
FINDING THE RISK IN RISK ASSESSMENTS NYSICA JULY 26, 2012 Presented by: Ken Shulman Internal Audit Director, New York State Insurance Fund There are different risk assessments prepared: Annual risk assessment
What It Takes to Really Run IT like a Business
What It Takes to Really Run IT like a Business Issue 2 1 Running IT Like A Business 2 From the Gartner Files: Run IT as a Business Using Six Pillars of Effective IT Financial Transparency 14 About VMware
Solvency II Own Risk and Solvency Assessment (ORSA)
Solvency II Own Risk and Solvency Assessment (ORSA) Guidance notes September 2011 Contents Introduction Purpose of this Document 3 Lloyd s ORSA framework 3 Guidance for Syndicate ORSAs Overview 7 December
PERSONAL DEVELOPMENT PLAN. Understanding the PDP
PERSONAL DEVELOPMENT PLAN Understanding the PDP The following section will give you guidance on the Personal Development Plan, what it is and how you can utilise it in support of your educational aspirations.
Basic Electronics Prof. Dr. Chitralekha Mahanta Department of Electronics and Communication Engineering Indian Institute of Technology, Guwahati
Basic Electronics Prof. Dr. Chitralekha Mahanta Department of Electronics and Communication Engineering Indian Institute of Technology, Guwahati Module: 2 Bipolar Junction Transistors Lecture-2 Transistor
Audit Sampling. AU Section 350 AU 350.05
Audit Sampling 2067 AU Section 350 Audit Sampling (Supersedes SAS No. 1, sections 320A and 320B.) Source: SAS No. 39; SAS No. 43; SAS No. 45; SAS No. 111. See section 9350 for interpretations of this section.
On the Applicability of WACC for Investment Decisions
On the Applicability of WACC for Investment Decisions Jaime Sabal Department of Financial Management and Control ESADE. Universitat Ramon Llull Received: December, 2004 Abstract Although WACC is appropriate
Cumulative Diagrams: An Example
Cumulative Diagrams: An Example Consider Figure 1 in which the functions (t) and (t) denote, respectively, the demand rate and the service rate (or capacity ) over time at the runway system of an airport
Understanding Options: Calls and Puts
2 Understanding Options: Calls and Puts Important: in their simplest forms, options trades sound like, and are, very high risk investments. If reading about options makes you think they are too risky for
Welcome to the topic on creating key performance indicators in SAP Business One, release 9.1 version for SAP HANA.
Welcome to the topic on creating key performance indicators in SAP Business One, release 9.1 version for SAP HANA. 1 In this topic, you will learn how to: Use Key Performance Indicators (also known as
INTERNAL CAPITAL ADEQUACY ASSESSMENT
INTERNAL CAPITAL ADEQUACY ASSESSMENT 30 june 2011 Contents Page 1. Introduction... 3 2. Process for determining the solvency need... 4 2.1. The basis for capital management... 4 2.2. Risk identification...
CHAPTER 8 CAPITAL BUDGETING DECISIONS
CHAPTER 8 CAPITAL BUDGETING DECISIONS Q1. What is capital budgeting? Why is it significant for a firm? A1 A capital budgeting decision may be defined as the firm s decision to invest its current funds
Guidance on the management of interest rate risk arising from nontrading
Guidance on the management of interest rate risk arising from nontrading activities Introduction 1. These Guidelines refer to the application of the Supervisory Review Process under Pillar 2 to a structured
The Datacenter must evolve to meet
The Datacenter must evolve to meet new business challenges February 2016 2016 Lenovo. All rights reserved. 1 Agenda 1. Who is Lenovo 2. Key Business challenges 3. Key infrastructure challenge for I.T.
Cost Benefit and Opportunity Cost Analysis Guidelines
The Commonwealth of Virginia Cost Benefit and Opportunity Cost Analysis Guidelines For the Public-Private Education Facilities and Infrastructure Act of 2002 December 2015 Document Version control Version
Project cash flows and NPVs may be estimated under different assumptions to improve the decision process.
FIN 301 Class Notes Chapter 9: Project Analysis WHAT-IF Analysis Project cash flows and NPVs may be estimated under different assumptions to improve the decision process. Sensitivity Analysis A. Changing
Safety Management Systems (SMS) guidance for organisations
Safety and Airspace Regulation Group Safety Management Systems (SMS) guidance for organisations CAP 795 Published by the Civil Aviation Authority, 2014 Civil Aviation Authority, CAA House, 45-59 Kingsway,