1 Vol. 21, No. 2, March April 2012, pp ISSN EISSN DOI /j x 2011 Production and Operations Management Society An Application of Master Schedule Smoothing and Planned Lead Time Control Chee-Chong Teo School of Civil & Environmental Engineering, Nanyang Technological University, Nanyang Avenue, Singapore , Rohit Bhatnagar Nanyang Business School, Nanyang Technological University, Nanyang Avenue, Singapore , Stephen C. Graves Sloan School of Management, Massachusetts Institute of Technology, Cambridge, Massachusetts , USA, M ake-to-order (MTO) manufacturers must ensure concurrent availability of all parts required for production, as any unavailability may cause a delay in completion time. A major challenge for MTO manufacturers operating under high demand variability is to produce customized parts in time to meet internal production schedules. We present a case study of a producer of MTO offshore oil rigs that highlights the key aspects of the problem. The producer was faced with an increase in both demand and demand variability. Consequently, it had to rely heavily on subcontracting to handle production requirements that were in excess of its capacity. We focused on the manufacture of customized steel panels, which represent the main sub-assemblies for building an oil rig. We considered two key tactical parameters: the planning window of the master production schedule and the planned lead time of each workstation. Under the constraint of a fixed internal delivery lead time, we determined the optimal planning parameters. This improvement effort reduced the subcontracting cost by implementing several actions: the creation of a master schedule for each sub-assembly family of the steel panels, the smoothing of the master schedule over its planning window, and the controlling of production at each workstation by its planned lead time. We report our experience in applying the analytical model, the managerial insights gained, and how the application benefits the oil-rig producer. Key words: make-to-order; production smoothing; master production schedule; planned lead times; oil-rig building History: Received: April 2009; Accepted: February 2011, after 2 revisions 1. Introduction An important competitive factor for a make-to-order (MTO) manufacturer is its ability to meet its promised delivery lead time. To achieve lead time reliability, a MTO manufacturer must have a reliable production plan for determining the procurement of raw materials, the production of parts, and the final assembly and testing of the end item. Typically, this production planning is based on material requirements planning (MRP) logic to coordinate the various decisions. For instance, the requirements schedule for the parts in the first tier of the bill of material is determined by offsetting the end-item assembly schedule by the planned lead time for assembly. The generation of part requirements continues for all subsequent levels of the bill of material in a similar fashion, including the procurement of raw materials. Thus, for manufactured parts, we can view their planned lead times as an internal delivery lead time (IDLT) to downstream internal customers. Violations of the IDLT for any part would result in a delay in the completion time of the end item. Increasing the IDLT can buffer against uncertainties in the parts s deliveries, but will result in a longer delivery lead time of the end item, which is detrimental to customer service. Ensuring availability of customized parts (for which the manufacturer cannot keep inventories) is a major challenge to most MTO manufacturers. The manufacturer must produce these customized parts within the IDLT to meet the production schedule. In the presence of a highly fluctuating demand, the MTO manufacturer must be able to flex its production capability in periods of high demand, e.g., by overtime or subcontracting, to meet the IDLT. This article reports an application that addresses the aforementioned problem, wherein we propose an improved production planning framework for a producer of MTO offshore oil rigs. At the time of the application, the company had experienced a sudden

2 212 Production and Operations Management 21(2), pp , 2011 Production and Operations Management Society surge in demand due to the global increase in demand for energy. However, given the cyclical nature of the industry, the firm was hesitant to invest heavily in expanding its capacity because this could result in over-capacity during the trough of the cycle. Historically, the firm s strategy had been to use subcontracting to handle upswings in its production requirements. This project was part of an initiative to improve the company s production planning to reduce its subcontracting cost. We focus herein on the production planning of customized steel panels, as these represent the key sub-assemblies of an oil rig and their production is on the critical path of oil-rig building. The panel production had experienced a highly variable loading on its capacity, resulting in high subcontracting costs that were incurred to expedite production to meet the IDLT for the steel panels. In this article, we report our effort to improve the production planning of panel production with the objective of minimizing subcontracting costs. We apply the model in Teo et al. (2011) in this case study. We focus on how best to smooth production in the multi-station steel panel production. We consider two key planning parameters, namely the planned lead time at each workstation and the planning window. The planned lead time at a workstation projects the planned amount of time each job spends at the station. A longer planned lead time implies more time at a station, resulting in more work-in-process (WIP) at the station, but allowing for smoothing of the workload. The planning window is the slack that reflects how much longer the IDLT is than the total planned lead time for a job. A longer planning window allows more smoothing of the master production schedule (MPS), which results in a less variable work release. In this project, we first recommended the tactics of MPS smoothing and the use of planned lead time control for the individual workstations. Subsequently, we determined the optimal planning windows and planned lead times that minimize the subcontracting cost. There is substantial literature on production smoothing in make-to-stock production, most of which focuses on the benefits of a stable capacity loading. However, there is not much work on production smoothing in the MTO context. Cruickshanks et al. (1984) consider production smoothing in a single-stage, MTO facility and introduce the concept of the planning window. Teo et al. (2011) also consider the planning window in smoothing the MPS, as well as planned lead time control in a multi-product, multi-station system. Furthermore, the article considers a production system that quotes a fixed delivery lead time, which is analogous to the fixed IDLT of the customized steel panels in this case study. Indeed, the model employed in this application comes from our work in Teo et al. The current article complements Teo et al. in that we show here with a real-life example that MPS smoothing and planned lead time control are effective tactics to improve production planning. Furthermore, we discuss the issues of implementing such tactics and develop managerial insights on the relationship between the key planning parameters. We believe this case study is representative of many MTO manufacturers and thus, we expect the insights derived to be useful for practitioners. This is especially true in the light of the current trend toward mass customization, as firms increasingly need to respond to customer pressure for greater product variety. This case study is also related to work on MTO production that quotes a fixed delivery lead time. So and Song (1998) and Rao et al. (2005) determine the fixed quoted delivery lead time to maximize profits for a single-stage system that produces an aggregate product. This article differs from both these works in that our paper is practice-based and our analysis encompasses decisions associated with the MPS and internal lead times in a multi-station, multi-product environment. This article is organized as follows. In the next section, we review the model in Teo et al. (2011) that was applied in this case study. In section 3, we describe the process flow and the problems of planning in the panel production. We then describe in section 4 the initial study and the plans for improvement. In section 5, we present the optimization model from Teo et al. and describe how we validate the underlying model assumptions and parameterize the model inputs. In section 6, we explain the recommendations and managerial insights based on the optimization solution. Subsequently, we validate the model output in section 7. We conclude in section 8 with a discussion on how the application had influenced the company. 2. Review of Model For completeness, we provide a high-level review of the model in Teo et al. (2011). Teo et al. consider a MTO, multi-station production system. The system produces multiple product families, each with a stochastic demand process and a fixed, guaranteed delivery lead time. The production schedule is controlled by the MRP-based logic, where the planned lead time at each workstation controls the production quantities. We will present the review in the context of this article, i.e., production planning to meet internal orders. The fixed guaranteed delivery lead times and product families in Teo et al. correspond to the IDLT and sub-assembly families, respectively. Note that we will present only the aspects of the model that are useful to the case discussion.

3 Production and Operations Management 21(2), pp , 2011 Production and Operations Management Society Product Planned Lead Time We begin by defining the product planned lead time PPLT k as the total planned duration that a job from sub-assembly family k takes to be completed by the shop after it is released into the shop. In addition, for each workstation, we define the station planned lead time SPLT i as the planned lead time at workstation i;it is the intended amount of time to complete processing of each job at the workstation, including both processing and waiting time. We assume each workstation has the same planned lead time for all sub-assembly families. We can express PPLT k by: PPLT k ¼ X i x ik SPLT i ; ð1þ where x ik is the number of times that each job from sub-assembly family k visits workstation i, assuming that each sub-assembly family has a pre-determined job routing MPS Smoothing The model assumes that orders arrive in each period according to a random process, with delivery dates specified by the IDLT. In addition, the MPS dictates how these orders are met. More specifically, we equate the MPS with the release schedule to meet the orders. Nominally, MRP logic would dictate that an order with due date t + IDLT k is released at time t + IDLT k PPLT k. We deviate from this logic to allow the smoothing of the MPS, and hence, less variable job releases into the shop. Smoothing of the MPS for each sub-assembly family k is possible only if its internal delivery lead time IDLT k is longer than its PPLT k. We define the resulting slack as the planning window W k : W k ¼ IDLT k PPLT k þ 1: ð2þ For orders received at time t, the planning window spans from t + PPLT k to t + IDLT k. The MPS over the planning window (i.e., the production quantities to be completed over t + PPLT k to t + IDLT k ) can be leveled, where the extent of leveling depends on W k ;a larger planning window allows for a more even spread of the MPS. We note that if IDLT k = PPLT k, then W k = 1; this corresponds to no smoothing of the MPS since the releases in each period t must correspond exactly to the quantities to be completed in t + PPLT k Workstation Control Besides the variable MPS, the effective workload at the workstations fluctuates over time due to varying job arrivals and production noise, e.g., setups, yields, and variable processing times. A longer SPLT i permits a smoother production at the workstation as it has greater flexibility to level out the variation in workload arrivals over the SPLT i. However, with a longer SPLT i, jobs stay longer at the workstation, which leads to a higher WIP inventory Optimization Model Given that the IDLT k is fixed, the decision variables are the SPLT i, which would determine the PPLT k and W k according to (1) and (2). Increasing the PPLT k, i.e., allowing for longer SPLT i at the workstations, leads to more smoothing for both job arrivals and production noise at the stations, but it would lead to a higher WIP inventory level. A longer PPLT k also implies a smaller W k, which causes a less stable job release and consequently more variable job arrival at the workstations. In addition, a longer SPLT i not only smoothes the workload at the workstation, but also smoothes the arrivals to downstream stations. We now consider how the aforementioned decision variables can affect the relevant production costs. We let P it be the random variable denoting the production requirements in workhours at workstation i in time period t. We interpret P it as the production quantities required at station i in period t that assure the work-in-queue meets the SPLT i. Furthermore, we define P it as the effective production output as we assume it includes both scheduled workload and (unscheduled) production noise. We let c i be the penalty cost per workhour of capacity shortfall, which may represent, e.g., subcontracting cost and overtime cost; m i denotes the nominal capacity for workstation i in workhours per period; h ik represents the unit WIP inventory holding cost (per workhour per period) at workstation i for product family k; Q ikt denotes the queue length in workhours at start of t for product family k at station i. We express the expected total cost across all workstations as: " # X i c i EP ½ it m i Š þ þ X k h ik EQ ½ ikt Š ð3þ where x + = max (x, 0). The term c i E[P it m i ] + is the expected penalty cost at workstation i resulting from capacity shortfall, i.e., if P it > m i. We assume that whenever P it > m i, the station is always able to complete P it but it incurs c i per hour for all production in excess of m i. A more variable P it leads to a higher expected penalty cost with its variability controlled by W k, PPLT k, and SPLT i. The term h i E[Q it ] signifies the expected WIP inventory holding cost at workstation i, where a larger SPLT i yields a higher WIP inventory level.

4 214 Production and Operations Management 21(2), pp , 2011 Production and Operations Management Society Equation (3) forms the objective function of the optimization program that determines the optimal SPLT i and W k. (To achieve a better flow of this article, we will defer the presentation of the optimization model to Section 5.) We compute R i c i EP ½ it m i Š þ by the linear loss integral, assuming that P it is normally distributed. In the rest of this section, we present the characterization of the first two moments of P it required for the computation Characterizing P it for a Single Sub-Assembly Family We first consider a single sub-assembly family and we drop the subscript k for notational convenience. We assume that the demand for each sub-assembly family is independent and identically distributed over time. For tractability, we introduce a dummy workstation to model the MPS smoothing and work release. We regard the unreleased orders as a demand queue at this dummy station, waiting to be released into the shop. The job arrival to the dummy station (station 0) in period t is the demand in t and the production output corresponds to the job release. We model the MPS smoothing by: P 0t ¼ Q 0t W ; ð4þ where P 0t is the production output (job release) in period t, Q 0t is the queue of work at the start of period t and W is the planning window (W 1). In (4), the shop releases 1/W of the on-hand orders in each period to approximate the requirement that every order does not wait more than W periods. Equation (4) models the smoothing of the release by spreading the on-hand orders evenly over the planning window. The model permits the linkage between discrete time planning and intra-period workflow. In particular, it models the MPS in discrete time buckets and the arrivals and production at the station are assumed to occur over smaller time grids to permit multiple arrivals and production within each time bucket. Specifically, each time period t at station i is sub-divided into p i equal sub-intervals, each with size D i = 1/p i. The main assumption here is that the workstation produces a fixed fraction D i /SPLT i of the work-inqueue at the start of each sub-period. The resulting production rule is similar to (4) albeit it is a function of the time grid. Effectively, the workstation i must not allow work to wait for more than SPLT i periods and thus it must process close to D i /SPLT i of the work-in-queue in each sub-period. In addition, to achieve tractability, the work arrival at the workstation in period t, which we denote as A it, is assumed to be uniform within each period t; that is, the arrival amount at the start of each sub-period is equal to A it /p. Teo et al. derive an expression for P it, which is given by: P it ¼ b i ð i ÞQ it þ c i ð i ÞA it ; ð5þ where the coefficients b(d i ) and c(d i ) are expressed as: b i ð i Þ¼1 ½1 ð i =SPLT i ÞŠ p i and c i ð i Þ ¼ 1 b i ð i Þ 1 ð i=splt i Þ : ð1=splt i Þ ð6þ Equation (5) expresses the production in each time period as a linear function of both the work queue at the start of the period and the arrivals during the period. The sub-interval D i reflects the size of underlying time interval for job movements at workstation i, where D i is set on the order of the average interarrival time. If the workflow is of a high enough frequency, the workflow can be approximated as a fluid-like workflow by considering the continuous time limits for b i (D i ) and c i (D i ) as D i goes to zero. The continuous time limits of b i (D i ) and c i (D i ) are given by: b i ð! 0Þ ¼ 1 e 1=SPLT i and c i ð! 0Þ ¼ 1 SPLT i b i : ð7þ Teo et al. show by a simulation study that accurate model output can be achieved if the appropriate coefficients are employed Workflow Model The workflow model links the MPS smoothing and the network of workstations so as to capture their interdependencies. We assume that each workhour of production at station j generates u ij workhours of input to station i on average. We model the work arrivals to station i by A it ¼ X j u ij P jt : ð8þ For the dummy station (station 0), we note that u i0 is the average amount of work that starts at workstation i for each new job. Furthermore, we express the balance equation at workstation i as: Q it ¼ Q i;t 1 P i;t 1 þ A i;t 1 þ f it ; ð9þ where f it denotes the random production noise at workstation i. By expressing (5), (8), and (9) in matrixvector form, Teo et al. then obtain the vector of expectation of P it and Q it, and covariance matrix of P it for all stations, namely E[P], E[Q], and Var(P), respectively.

5 Production and Operations Management 21(2), pp , 2011 Production and Operations Management Society 215 To extend the single-family model to accommodate multiple sub-assembly families, we model each subassembly family the same way as in the single-family model, i.e., each product family k has an MPS and each family has its own demand process, routings, and production noise. The single-family model characterizes the production requirements and WIP inventory for sub-assembly family k, i.e., E[P k ], Var (P k ), and E[Q k ]. We can obtain the expectation of the total production requirements and WIP inventory by aggregating across all sub-assembly families: E½P total Š¼ P k E ½ P kš and E½Q total Š¼ P k E ½ Q kš. If demand is independent between the sub-assembly families, we can obtain the variance of the total production requirements: VarðP total Þ¼ X k VarðP k Þ: ð10þ We can relax the assumption of independent demand by incorporating demand correlations between the sub-assemblies into (10) (refer to Teo [2006] for details). 3. Panel Production: Process Flow and Challenges The company is a producer of customized jack-up oil rigs. Jack-up oil rigs are offshore rigs that are mobile in water, and can anchor themselves by deploying jack-like legs. The fundamental structure of the oil rig is the hull, which is the platform on which most facilities of the rig are built. A typical hull consists of steel blocks; each steel block is constructed by joining steel structures called panels. A block commonly consists of 10 to more than 60 panels. The steel panel represents the most elementary sub-assembly in the hull construction. A panel is built using one or more steel plates, with outfitting components welded onto it to strengthen the structure. There are three sub-assembly families in the panel production: Big Panels, Small Panels, and Outfits. Big Panels are panels built by joining two or more steel plates, while the Small Panels are built using a single steel plate. The size of the panels varies widely with the weight of a panel ranging from 0.5 to 10 tons. The Outfits are the outfitting components welded onto the panels. Figure 1 shows the process flow map for the panel production. At the Blast station, raw plates are blasted by ball grids to remove surface impurities, followed by the application of a corrosion preventive coating. The typical raw steel plate is 1.5 m wide, 8 m long, and has a thickness of ¼ ¾ inch. The blasted plates are sent to the NC Gas Cut or NC Plasma Cut stations to be cut to the required dimensions. The NC Gas Cut station is capable of cutting both thin and thick plates, while the NC Plasma Cut station can only cut thin plates. The Big Panels require thick plates and are therefore sent to the NC Gas Cut station. The Small Panels require thin steel plates but are processed at the NC Gas Cut station to balance the workload between the two stations. For the same reason, although the Outfits also require thin plates, a fraction of the Outfits are cut in the NC Gas Cut station while the rest are processed at the NC Plasma Cut station. After cutting, the parts remain joined to the steel plate by connectors called bridges, and these are manually cut at the Bridge Cut station. Subsequently, the plates for each sub-assembly family follow different process routes. The thick plates for the Big Panels are beveled at the Bevel station, and then go through a series of welding processes at the Tack and Join stations to join the plates to form the basic panel structure. The panels are then paint-marked at the Mark station to indicate Figure 1 Process Flow Map for Panel Production Raw steel plates Blast NC Gas Cut NC Plasma Cut Bridge Cut Outfits Profile Small Panels Bevel Tack Join Mark Outfitting (Small Panels) Outfitting (Big Panels) Blasting Shop NC Shop Panel Shop Big Panels: Blast NC Gas Bridge Cut Bevel Tack Join Mark Outfitting (Big Panels) Small Panels: Blast NC Gas Bridge Cut Mark Outfitting (Small Panels) Outfits: Blast NC Plasma or NC Gas Bridge Cut Profile Shop Outfits (both Big and Small Panels)

6 216 Production and Operations Management 21(2), pp , 2011 Production and Operations Management Society the positions of the Outfits to be fitted. Eventually, the Big Panels are moved to the Outfitting (Big Panels) station to weld the Outfits. Since the Small Panels are built using a single plate, no welding is needed and they are moved directly to the Mark station and subsequently to the Outfitting (Small Panels) station. The Outfits are sent to the Profile Shop from the Bridge Cut, where the cut steel parts undergo some simple metal forming operations to produce the outfitting components. Finally, the Outfits are transferred to either the Outfitting (Big Panels) or the Outfitting (Small Panels) to be fitted onto their corresponding panels. The completed panels are then ready for quality checks before moving downstream to construct the steel blocks. The panel production shown in Figure 1 occurs in three separate shops, namely the Blasting Shop, NC Shop, and Panel Shop, which are physically located next to each other. The Blasting Shop consists of the Blast station, the NC Shop has the two NC cutting stations, and the Panel Shop includes the rest of the processing stations. Production control for the panel production had been based on the planned lead times at the shop level. The planned lead times for the Blasting Shop, NC Shop, and Panel Shop were 5, 8, and 13 days, respectively, resulting in an IDLT of 26 days for the panel production; that is, the panel production facilities need to deliver each internal order of panels exactly 26 days after receipt of the order. Any delay in delivering the panels hinders the downstream assembly for the steel blocks, which might in turn affect the meeting of the promised oil rig delivery dates. The progress of jobs is monitored against the shops planned lead times to approximate whether or not jobs are able to meet the delivery schedule. In times of high capacity loading, jobs are subcontracted to vendors to keep them from falling behind their planned lead times. Most of these vendors are located close by or within the panel production facility itself. While the production schedule of the Panel Shop is monitored based on the shop s planned lead time, work can be outsourced at each of its individual workstations. Production planning relies on a single MPS for all sub-assembly families. In addition, there is no regulation of the MPS and the job release, whereby jobs are released once the orders are received from the downstream internal customers. With the surge in demand, most workstations in the production shop experience a heavier and more variable workload, which results in rising subcontracting costs. The company sought to increase its utilization of in-house capacity and to reduce subcontracting costs. The management identified that one cause of the variable workload was the highly fluctuating MPS. The MPS was highly variable for three reasons. First, the production schedules of panels for the different oil-rig projects were not well coordinated. As a result, the total internal demand for panels was quite variable and resulted in variable work release. Second, raw steel plates of required thickness and grades were frequently unavailable, and this delayed the release of some panels. Third, the raw steel plates were stacked to conserve space and therefore, finding the required plate often took substantial time; this added considerable variability to the picking time of the raw plates. In addition to the varying MPS, another cause for the large workload variability was the diverse processing requirements at the workstations, due to the different sizes of plates as well as the different number of plates and outfitting components required for each panel. The challenges in the panel production are illustrated in Figure 2. The management recognized that addressing these causes could lead to a reduction in production variability. However, they believed that this would require a long-term effort and would depend on factors external to the company. Coordination of the project schedules would involve coordination Figure 2 Highly fluctuating MPS translates into highly variable release Challenges in Panel Production High variability leads to high subcontracting costs Blasting Shop NC Shop Panel Shop Project schedules are not well coordinated Raw steel plates are often unavailable Much time needed in locating plates Diverse processing requirements Many different cut dimensions of plates, as well as variable number of plates and outfitting components for each panel

7 Production and Operations Management 21(2), pp , 2011 Production and Operations Management Society 217 between the company s various departments as well as with its customers on delivery schedules. Improving availability of raw steel plates would need better coordination with suppliers and more accurate forecast of global steel supply. Shorter picking times for steel plates would require considerable capital investment and time to devise new ways or equipment for material handling. Reducing the diverse processing requirements would need standardization of panel types, which would involve setting restrictions on oil-rig customization that might be detrimental to customer satisfaction. The management decided that to reduce subcontracting cost within the short term, they should focus on tactical improvements. The panel production highlights the problems faced by many MTO manufacturers in producing customized parts to meet a production schedule. The characteristics of the panel production encompass various operational aspects that can be found in many production systems: a highly variable MPS, multiple product families and process routes, dissimilar processing requirements, and expediting actions taken to meet delivery schedules. 4. Initial Study and Recommendations The company learned about the concepts of MPS smoothing and lead time control from our work in Teo et al. (2011) and wished to explore if the tactics would be of help to improve the company s performance. A team was formed, consisting of the authors and personnel from the production department. After a careful study of the model, the production personnel were particularly interested in two potential improvement areas as follows Smoothing of MPS The production personnel recognized that a smoother MPS results in a less variable release and consequently fewer occurrences of spikes in capacity loading. The company became interested in finding out how the MPS can be smoothed in the panel production. The team recognized that the MPS can be smoothed over the planning window for each subassembly family if its IDLT k to its internal customer is longer than its PPLT k. One seemingly obvious solution was to increase the IDLT k to allow a longer planning window and PPLT k. However, the management did not wish to change the current internal lead time for panel production of 26 days, as the panel production is on the critical path of oil-rig building and they did not want to affect the delivery schedule of the oil rigs. Therefore, the team had to find other ways to smooth production given the fixed IDLT k. Initial recommendation 1. Upon studying the process flow, the team identified that the Small Panels and Outfits require fewer processing steps than the Big Panels. Thus, if each sub-assembly family has its own MPS and is planned separately, each of the Small Panels and Outfits would have a much shorter PPLT k. Hence, given that the IDLT k is the same for each family, the planning window W k would be considerably large for both sub-assembly families to perform substantial MPS smoothing. Thus, it was recommended that an MPS is created for each sub-assembly family Smoothing at Stations The team recognized that the production control in the Panel Shop had been based on the shop s planned lead time, rather than for its individual workstations. As a result, subcontracting decisions were often guesswork of predicting if a job could be completed in time to meet its due date. Furthermore, the planned lead times for the three shops were set based upon the experience of the production planners without any analytical basis. Initial recommendation 2. The team recommended a station planned lead time SPLT i for each workstation in the Panel Shop, whereby the progress of jobs could be tracked more precisely. The team also identified an opportunity to achieve a smoother workflow by determining the optimal values of SPLT i Planning Decisions The team then looked into the planning parameters and trade-offs in the panel production. We found that we could omit the holding cost of the WIP inventories from our analysis. We note that the exclusion of WIP inventory holding cost differs from Teo et al. and other earlier work on setting planning lead times, which consider the trade-off between capacity requirements and WIP inventory. The primary reason for excluding the WIP inventory is that the total inventory held by the firm is insensitive to the planning decisions under consideration. The majority of raw steel plates required for the entire oil rig are purchased before the start of each project, so the material cost of the steel plates represents a sunk cost, i.e., it is incurred regardless of how we release work into the production shop. Furthermore, since the IDLT is fixed, the raw plates stay in the production system for approximately the same duration no matter how the plates are scheduled. In addition, the team found that the value added to the jobs through processing (and hence the incremental holding cost) is significantly less than the subcontracting cost. The team re-evaluated the key trade-offs and identified the following planning considerations for the panel production:

8 218 Production and Operations Management 21(2), pp , 2011 Production and Operations Management Society The team needed to set the planning window W k and the SPLT i of each workstation (which determines PPLT k ). The planning window smoothes the MPS (and release) and the PPLT k (i.e., the sum of SPLT i ) smoothes both the arrivals and the noise due to the variable processing times at the workstations. Without considering the WIP inventory, the decision is to allocate SPLT i among the workstations solely to minimize the total subcontracting cost. The subcontracting cost incurred at each workstation depends on its unit subcontracting cost, nominal capacity level, and variability in job arrival, and processing times. In this multi-station, multiple-family setting, the team needed to take into account the interdependence of workflow among the stations as well as among the sub-assembly families. The team recognized that the main features of the panel production could be modeled by Teo et al.: production control using planned lead times, influence of MPS smoothing on production workflow, variability at the workstations as well as subcontracting production to meet the capacity shortfall. However, before applying the analytical model, we also considered other simpler alternatives. For example, the team considered setting the SPLT i of all stations to be proportional to each station s utilization rate while satisfying the IDLT constraints. The rationale behind this method was that the more heavily utilized stations would need longer station planned lead times. However, this method would not be able to account for many important aspects of the scenario, e.g., the variability of demand and processing requirements, the difference in subcontracting cost between stations and the interdependencies of workflow between stations. The team also considered the alternative of using a discrete-event simulation. However, they found that simulation was not suitable for the extensive what-if analysis they would like to perform, as it would be slow to make the numerous simulation runs, especially the runs requiring optimization. Furthermore, the management preferred a method that did not require an extensive learning process for its personnel. As our model was formulated and solved in MATLAB, the management thought that the planners and engineers could readily learn how to use it. In addition, the model parameters, e.g., unit subcontracting cost, workflow, and capacity levels, could be easily altered according to actual changes. Moreover, MATLAB provided an optimization toolbox that could be used to find the optimal planning windows and station planned lead times. 5. Model Application 5.1. Optimization Model We present the optimization model from Teo et al. (2011) but our objective in this application differs in that we minimize just the expected total penalty cost in (3) (i.e., we exclude the WIP inventory holding cost). The decision variables are the SPLT i of each workstation and planning windows W k of each subassembly family k. The discrete time period t of the model is one day, which is the time bucket used in the existing planning system. s:t: X i Min X i c i E½P it m i Š þ SPLT i þ W k 1 ¼ IDLT k ; 8k W k a k ; 8k SPLT i b i ; 8i ð11þ ð12þ ð13þ To evaluate the objective function, we need to determine the variances of the random variables P it ; these depend on the workstation s SPLT i (5 and 6), the SPLT i of its upstream workstations and the planning windows W k. Constraint (11) combines (1) and (2), which defines the relationship between W k, SPLT i, and IDLT k, where IDLT k are fixed at 26 days for all sub-assembly families. We note that in (11), x ik = 1 for all i and k since every job visits each workstation once. Constraints (12) and (13) assure a lower bound of at least a k and b i on the W k and the SPLT i, respectively. Lower bounds of SPLT i and planning windows are needed to avoid excessively frequent monitoring to track the job progress and the MPS. We set both a k and b i to be 1 day, as the planning time bucket of 1 day was the minimum duration that the management perceived to be suitable for planning within this highly dynamic system. The decision variables were not restricted to be integers, as non-integer values were acceptable for production control. The team set the SPLT i s of the Profile Shop which produces the Outfits, to be fixed at 2 days, as the station s processing time is relatively stable and reasonably independent of the workload. As reported in Teo et al., we have not been able to determine whether or not the objective function is convex. Therefore, we cannot assert that the solutions are global optimal. In this exercise, we solved each test problem using many different starting points. We attained the same solution for each test problem, which increased our confidence that we had obtained a global optimum.

9 Production and Operations Management 21(2), pp , 2011 Production and Operations Management Society Validation of Model Assumptions The team validated the following assumptions in Teo et al. for the current study Capacity Assumptions. Equation (3) assumes that every workstation is always able to meet the production requirements, although it incurs additional cost per workhour of capacity shortfall. In the panel production, subcontracting is routinely used to expedite work to meet the production requirements. Since the subcontracting is performed in nearby shops and by on-site contract workers, relatively little time is wasted in transporting the jobs. Furthermore, from the management s experience, there are very few occurrences where the subcontractors failed to produce the outsourced demand within the SPLT i. The team also examined the assumptions for the nominal capacity m i. To apply (3), m i must be measurable and its value assumed to be constant. It is straightforward to measure m i for NC Gas Cut and NC Plasma Cut stations as both are machine constrained. We observed that the other stations operate with skilled workers, some of whom are cross trained to work at more than one station. Thus, there is some flexibility in allocating workers to the heavily loaded stations, which somehow disagrees with the assumption of constant nominal capacity. However, the team found that such redeployment of workers was infrequent after the company experienced the high capacity loading due to the demand increase. This is because the stations with cross-trained workers become heavily loaded at the same time, thus preventing labor re-allocation Workflow Assumption. In deriving (5), the arrival to the workstation is assumed to be uniform within each time period t. However, in the panel production, jobs start to move to the next station upon completion and therefore the arrival at the downstream station is not exactly uniform within each period. Teo et al. validate this assumption via a simulation model wherein jobs move to the next station immediately after completion. The study shows that the simulation results are close to the model output despite relaxing the uniform flow assumption; the errors are small provided that the appropriate production function (i.e., either the subinterval function (6) or the continuous-time function (7)) is chosen at each workstation according to the average flow rate. The average percentage difference between the simulation results and the model output is 2.3% for all test problems and the maximum error is 6.5%. The study also establishes the range of average flow rates that (6) or (7) should be selected. The team observed that the arrival rates are low at Join, Mark and both the Outfitting stations, as these stations assemble or process panels rather than plates and Outfits. As a result, the arrival rates at these stations fall within the range of flow rates found in the simulation study that necessitates the use of the sub-interval function (6). Thus, we employed the sub-interval function for these stations. The other stations have sufficiently high flow rate to justify the continuous-time assumption and hence the continuous-time function (6) was utilized Production Assumption. The development of (5) assumes that the workstation is regulated to produce a fixed fraction of the work-in-queue to satisfy its SPLT i, even if capacity is available to produce the entire work-in-queue. In the panel production, the job start times at NC Plasma, NC Gas, Tack, and Join stations are scheduled to coordinate with the receipts of engineering drawings for cutting and welding (which is similar to the synchronization of part requirements in MRP logic). Furthermore, due to the large physical size of the jobs and the space constraints in the facilities, the stations usually produce just to meet the SPLT i, so as to avoid taking up the downstream shop space unnecessarily. To compute the total penalty cost in (3) (that forms the objective function) using the normal linear loss integral, P it is assumed to be normally distributed. To validate this assumption, we constructed normal probability plots for the daily production output from a 2-month data and the plots showed that this assumption is reasonable Demand Assumption. In contrast to the assumption of stationary demand, the observed demand for each sub-assembly family is generally non-stationary. However, if the time horizon is considered as successive time segments, with each segment representing a constant number of oil rigs in production in their respective stable project phase, we observed that the demand is stationary within each time segment. Each time segment typically ranges from about 15 to 45 days. In addition, the daily demand data showed a fairly constant coefficient of variation (standard deviation mean) of demand within each segment. We show the demand data for the Big Panels over a 3-month period in Figure 3. To test the sensitivity of our solution to the nonstationary demand, the mean demand for each sub-assembly family was set to be either 100% or 125% of the original mean demand while keeping the demand coefficient of variation constant. The analysis showed that for all eight test scenarios, the subcontracting cost resulting from the original demand s

10 220 Production and Operations Management 21(2), pp , 2011 Production and Operations Management Society Figure 3 Demand for Big Panels over 3-Month Period optimal station planned lead times is no more than 4% higher than the test scenarios minimum subcontracting cost Data Collection We discuss the data required for the model inputs, and how we obtain and parameterize the relevant data Capacity. To measure the nominal capacity levels m i, we observed the throughput rate in periods of high demand, when most stations were operating at full capacity. We approximate m i by the mean throughput (in hours) per day observed in these periods Subcontracting Cost. The vendors quote the subcontracting costs in terms of cost per metric ton. Since workload in our model is measured in hours, we had to convert the subcontracting cost at each station into average subcontracting cost per workhour c i. We approximated the average subcontracting cost based on the average weight of the jobs at the station (in metric tons) and the mean processing time of the jobs (in hours) Demand. We obtained the mean and standard deviation of the internal demand for each subassembly family from an 8-month demand record. We found a low correlation coefficient of 0.13 between the demands of Big Panels and Small Panels. However, the correlations between Big Panels and Outfits as well as between Small Panels and Outfits, are high with correlation coefficients at more than We modeled correlated demands between product families for (10) by incorporating the demand correlations Effective Processing Times. We acquired the mean and variance of the effective processing times (in hours) at each station from data collected in a 2-month period. We needed the mean processing times to define the workflow matrix consisting of u ij, which defines the average amount of work that each unit of production at a station generated for each downstream station. The variance of the processing time at each station is required to calculate the zeromean noise term n it at each station. We computed the noise due to the variability of processing time by: Varðn it Þ¼Expected number of jobs at station i Variance of processing time 6. Results and Insights We report the optimization results as well as the corresponding expected subcontracting work and costs in Table 1. The subcontracting costs presented herein have been scaled to protect the company s confidential data, but the insights drawn are identical to the conclusions based on the actual data. With a separate MPS for each sub-assembly family, there is a greater flexibility to adjust the planning windows of each sub-assembly family for a smoother release. The solution suggests that there should be substantial smoothing for the release of

11 Production and Operations Management 21(2), pp , 2011 Production and Operations Management Society 221 Table 1 Optimization Results Station Original W k or SPLT i Optimal W k or SPLT i work (hours/day) Expected subcontracting Expected subcontracting cost ($/day) Planning window for Big Panels Planning window for Small Panels Planning window for Outfits Blast NC Gas Cut NC Plasma Cut Bridge m Bevel 1.0 <0.01 <1 Tack 1.0 <0.01 <1 Join Mark 1.0 <0.01 <1 Panel Shop 13:0 Outfitting (Big Panels) Outfitting (Small Panels) Small Panels and Outfits, with planning windows equal to 10.8 and 9.8 days, respectively. The planning window for Big Panel is 1 day, meaning no smoothing of its MPS. The solution suggests that the SPLT i of Blast should be reduced from 5.0 to 1.0 day, and NC Gas Cut and NC Plasma Cut from 8.0 to 4.4 days. A proportion of the original SPLT i at these stations acts as safety time to buffer against the uncertainties of unavailable steel plates and the long picking times. For the Small Panels and Outfits, most of the excess days from this reduction are reallocated to their planning windows. Here, the planning windows would not just smooth the MPS but also act as the safety times for acquiring steel plates. For the Big Panels, the SPLT i of the Blast station is mainly reallocated to the other workstations. The optimal SPLT i at the Join station is the largest among the workstations at 7.8 days. We observed that the utilization rate at the Join station is more than 90%; its processing time is also highly variable, with a coefficient of variation of The optimal SPLT i sof Outfitting (Big Panels) and Outfitting (Small Panels) are also high at 6.6 days, but still lower than Join, despite both stations having higher utilization rates and coefficient of variation for their processing time. The reason is that the larger SPLT i at the Join station would smooth the production output, which in turn would lead to smoother arrival at the downstream Outfitting (Big Panels) and Outfitting (Small Panels). The solution also suggests that Bevel, Tack, and Mark stations have the shortest station planned lead times of 1.0 day due to their comparatively lower utilization. Even with a station planned lead times of 1.0 day, the expected subcontracting costs are low at these stations. By exercising the model for different what-if scenarios, the team developed the following insights for setting the planning windows and station planned lead times: The team gained insights on the interaction between the planning windows and the station planned lead times. A longer planning window is preferred if a sub-assembly family faces a highly variable demand and relatively lower workload variability at the stations. On the other hand, if the variability of processing time at the stations is relatively larger, longer station planned lead times are preferred to smooth production at the workstations. A workstation would require a longer SPLT i if it faces greater variability in processing requirements, has higher utilization rate and/or unit subcontracting cost. The management had previously thought that the SPLT i should be based only on the utilization rate. Smoothing at an upstream station has the added advantage of smoothing the arrivals to downstream stations. The management learned that looking at each individual station in isolation is suboptimal. We note that in situations where the WIP holding cost is significant, one also has to consider that longer SPLT i s lead to higher WIP inventory levels. The above insights are useful for understanding the trade-offs among capacity, lead time, and production smoothness. 7. Validation The team attempted to validate the predictive capability of the model, i.e., the accuracy of the model in characterizing the panel production. The most useful validation would be to compare the actual amount of work subcontracted out with that predicted by the

12 222 Production and Operations Management 21(2), pp , 2011 Production and Operations Management Society model. However, the subcontracting decisions in the Panel Shop were based on the aggregate planned lead time of the shop. In our model, production control is set based on the SPLT i of individual stations. Thus, the above comparison could not be made for the Panel Shop and unfortunately, this is where most of the workstations are located. For the Blasting Shop and NC Shop, we found that the amount of subcontracted work predicted by the model is about 26% and 21%, respectively, lesser than the actual data for the two stations. The team viewed this as a reasonable validation given the presence of high variability in the system and the somewhat incomplete subcontracting data, since the company did not keep an organized record of subcontracting cost incurred at Before implementing the recommendations, the management needed to gain confidence in the results. Given the incomplete subcontracting data at the time, the team first attempted to determine rough-cut potential savings that would result from these changes. The team attempted to compare the actual subcontracting cost with that computed by the model. To accommodate the model s predictive error, we adjusted the computed subcontracting costs for the Blasting Shop and NC Shop. Specifically, we modified the computed subcontracting cost by the percentage error determined through our validation of the model s predictive capability (i.e., the aforementioned errors of 26% and 21%, respectively) by: 100% Adjusted subcontracting cost ¼ Computed subcontracting cost 100% þ Percentage error each workstation. After the recommendation to assign the SPLT i to individual stations was implemented, new and more comprehensive data on subcontracting costs became available. We re-validated the predictive capability of the model and found that the model output is about 9% lower than the actual costs; this error is significantly lower than the initial limited validation using data only from the Blasting Shop and NC Shop. The corresponding percentage difference at each workstation is shown in Table 2. In the same table, we also present the actual cost at each workstation as a percentage of the total actual cost to show the relative significance in cost at each workstation. Table 2 Percentage Differences Between Actual Cost and Computed Cost Per Day (After Adopting SPLT i at Individual Workstations) Cost of subcontracting as percentage of total subcontracting cost Actual cost 100% Total actual cost Percentage difference 100% Blast NC gas station NC plasma Bridge Bevel < Tack < Join Mark < Outfitting (Big Panels) Outfitting (Small Panels) Computed Actual cost Actual cost As stated earlier, we could not determine the computation error at the Panel Shop. We use the percentage errors at the Blasting Shop and NC Shop as a guide and set the Panel Shop s percentage errors to be in the range 18 30%. Comparing the resulting adjusted optimal total subcontracting costs with the actual average historical cost, we estimated that the recommendations would result in a 20 30% cost reduction, which is acceptable to the management. In another effort to estimate the potential cost savings, the team input the current SPLT i s into the model and compared the resulting total subcontracting cost with the optimal cost. However, the individual stations in the Panel Shop had not been assigned SPLT i. To overcome this, the current cost was estimated by setting the SPLT i of the stations in the Panel Shop proportional to the station s utilization rate while satisfying the Panel Shop s planned lead time of 13 days. The results from this comparison showed that the optimal solution would reduce the cost by about 21.8%. We also compared the optimal cost with that of another alternative in which the SPLT i sofall stations were set proportional to each station s utilization rate while satisfying the IDLT constraint. By inputting the SPLT i based on this alternative into the MATLAB program, we found that the total expected subcontracting cost for this alternative is 14.4% higher than that of the optimal expected cost. We regard the abovementioned comparisons as conservative estimates of the true savings. This is because the actual production control of the Panel Shop was based on the shop s planned lead time, rather than the more accurate control using the SPLT i s of individual stations as assumed in the comparison.

13 Production and Operations Management 21(2), pp , 2011 Production and Operations Management Society 223 The major limitation of our model is that it does not account for rush orders of urgent panels. These panels are crucial components for the downstream steel blocks and their late completion would lead to serious delays in the steel block production. These orders are processed immediately upon arrival and are frequently subcontracted to expedite their completion. Typically, each order is subcontracted at some selected stations depending on the order s processing requirement; therefore the rush orders do not have distinct flow paths but have numerous processing routes. Hence, even though we had explored overcoming this limitation by defining the rush orders as separate product families, we faced difficulties in accurately capturing the rush orders with our existing shop data. Nevertheless, the management concluded that the collected data, model assumptions, and results were reasonable and that our model serves well for tactical planning since it is able to capture the core features of the problem. 8. Influences on Company The company adopted the recommendations of creating a MPS for each sub-assembly family and individual planned lead times for each station. In particular, each MPS is smoothed over the planning window with the job releases leveled, and the company uses the station planned lead time to monitor the progress of jobs at each workstation to determine whether or not a job should be subcontracted. More specifically, the shop managers monitor the job progress by approximating completion time of newly arrived jobs at each workstation based on estimation of total processing times of the jobs in queue. Before implementing the recommendations for the values of the planning windows and SPLT i s, the company decided to add production capacity as it observed a continuous growth in oil-rig demand and projected that the growth was sustainable. However, the company did not acquire excessive amount of capacity to buffer against demand variability but chose to maintain the strategy of subcontracting. Therefore, instead of implementing the precise recommendations for the values of planning windows and SPLT i s as a static solution, the company utilized the model to support the monthly updating of the values in response to the continual changes in production capacity. Furthermore, since the model requires large amounts of data as inputs, the use of the model is helped by the company s new initiative to regularly update shop data. The company also employs the model for what-if analysis to support planning; for instance, the model is used by the company to determine how capacity addition affects subcontracting cost. In addition, the model is also used as a guide for focusing improvement efforts. The model helped to identify steel availability and production scheduling as two potential areas in which subcontracting cost could be reduced; consequently, there were projects carried out to address these issues (see Huang [2006] and Tan [2006] for details of these projects). Another significant result is that the project has led to greater awareness of the importance of considering the interrelationship among lead time, capacity, and production smoothness. Furthermore, there is now a greater emphasis on reducing variability of production. However, we were not able to quantify the resulting savings in subcontracting cost because of the ongoing changes in the production shop and oil-rig demand, as well as fluctuations in global steel supply, and subcontracting charges. Acknowledgments This research has been supported by the Singapore-MIT Alliance (SMA) program. The authors thank the Departmental Editor, Senior Editor, and two anonymous referees for their valuable comments, which greatly improved the article. Note 1 Note that we use the term internal delivery lead time (IDLT) to represent the total planned lead time of producing a part or sub-assembly needed for downstream processes. References Cruickshanks, A. B., R. D. Drescher, S. C. Graves A study of production smoothing in a job shop environment. Manage. Sci. 30(3): Huang, F Production Scheduling in a Make-To-Order Job Shop under Job Arrival Uncertainty. Unpublished Master s Dissertation, Department of Mechanical Engineering, MIT, Cambridge, MA. Rao, U. S., J. M. Swaminathan, J. Zhang Demand and production with uniform guaranteed lead time. Prod. Oper. Manag. 14(4): So, K. C., J.-S. Song Price, delivery time guarantees and capacity selection. Eur. J. Oper. Res. 111(1): Tan, C. Y Inventory Management of Steel Plates at an Oil Rig Construction Company. Unpublished Master s Dissertation, Department of Mechanical Engineering, MIT, Cambridge, MA. Teo, C. C A Tactical Planning Model for Make-To-Order Environment under Demand Uncertainty. Unpublished Doctoral Dissertation, Singapore-MIT Alliance, Nanyang Technological University, Singapore. Teo, C. C., R. Bhatnagar, S. C. Graves Setting planned lead times for a make-to-order production system with master schedule smoothing. IIE Trans. 4(6):

Chapter 7. Production, Capacity and Material Planning

Chapter 7. Production, Capacity and Material Planning Chapter 7 Production, Capacity and Material Planning Production, Capacity and Material Planning Production plan quantities of final product, subassemblies, parts needed at distinct points in time To generate

More information

Universidad del Turabo MANA 705 DL Workshop Eight W8_8_3 Aggregate Planning, Material Requirement Planning, and Capacity Planning

Universidad del Turabo MANA 705 DL Workshop Eight W8_8_3 Aggregate Planning, Material Requirement Planning, and Capacity Planning Aggregate, Material Requirement, and Capacity Topic: Aggregate, Material Requirement, and Capacity Slide 1 Welcome to Workshop Eight presentation: Aggregate planning, material requirement planning, and

More information

Manufacturing Efficiency Guide

Manufacturing Efficiency Guide Note: To change the product logo for your ow n print manual or PDF, click "Tools > Manual Designer" and modify the print manual template. Contents 3 Table of Contents 1 Introduction 5 2 What Is Manufacturing

More information

CHAPTER 6 AGGREGATE PLANNING AND INVENTORY MANAGEMENT 명지대학교 산업시스템공학부

CHAPTER 6 AGGREGATE PLANNING AND INVENTORY MANAGEMENT 명지대학교 산업시스템공학부 CHAPTER 6 AGGREGATE PLANNING AND INVENTORY MANAGEMENT 명지대학교 산업시스템공학부 Learning Objectives You should be able to: Describe the hierarchical operations planning process in terms of materials planning & capacity

More information

PARADIGMS THAT DRIVE COSTS IN MANUFACTURING. The whole purpose of a business enterprise is pretty simple to make a profit by selling

PARADIGMS THAT DRIVE COSTS IN MANUFACTURING. The whole purpose of a business enterprise is pretty simple to make a profit by selling PARADIGMS THAT DRIVE COSTS IN MANUFACTURING The whole purpose of a business enterprise is pretty simple to make a profit by selling products or services to persons who desire those particular goods or

More information

TU-E2020. Capacity Planning and Management, and Production Activity Control

TU-E2020. Capacity Planning and Management, and Production Activity Control TU-E2020 Capacity Planning and Management, and Production Activity Control Copyright Jari Laine 11/23/2015 Copyright Jari Laine 11/23/2015 Different capacity planning options 1 4 7 10 13 16 19 22 25 28

More information

Operations Management

Operations Management Operations Management Short-Term Scheduling Chapter 15 15-1 Outline GLOAL COMPANY PROFILE: DELTA AIRLINES THE STRATEGIC IMPORTANCE OF SHORT- TERM SCHEDULING SCHEDULING ISSUES Forward and ackward Scheduling

More information

MASTER PRODUCTION SCHEDULE

MASTER PRODUCTION SCHEDULE 6 MASTER PRODUCTION SCHEDULE MGT2405, University of Toronto, Denny Hong-Mo Yeh So far, in discussing material requirement planning (MRP), we have assumed that master production schedule (MPS) is ready

More information

1 Material Requirements Planning (MRP)

1 Material Requirements Planning (MRP) IEOR 4000: Production Management page 1 Professor Guillermo Gallego 1 Material Requirements Planning (MRP) Material Requirements Planning (MRP) is a computer-based production planning and inventory control

More information

SUPPLY CHAIN MODELING USING SIMULATION

SUPPLY CHAIN MODELING USING SIMULATION SUPPLY CHAIN MODELING USING SIMULATION 1 YOON CHANG AND 2 HARRIS MAKATSORIS 1 Institute for Manufacturing, University of Cambridge, Cambridge, CB2 1RX, UK 1 To whom correspondence should be addressed.

More information

BEST PRACTICES IN DEMAND AND INVENTORY PLANNING

BEST PRACTICES IN DEMAND AND INVENTORY PLANNING WHITEPAPER BEST PRACTICES IN DEMAND AND INVENTORY PLANNING for Food & Beverage Companies WHITEPAPER BEST PRACTICES IN DEMAND AND INVENTORY PLANNING 2 ABOUT In support of its present and future customers,

More information

STRATEGIC CAPACITY PLANNING USING STOCK CONTROL MODEL

STRATEGIC CAPACITY PLANNING USING STOCK CONTROL MODEL Session 6. Applications of Mathematical Methods to Logistics and Business Proceedings of the 9th International Conference Reliability and Statistics in Transportation and Communication (RelStat 09), 21

More information

Production Planning Solution Techniques Part 1 MRP, MRP-II

Production Planning Solution Techniques Part 1 MRP, MRP-II Production Planning Solution Techniques Part 1 MRP, MRP-II Mads Kehlet Jepsen Production Planning Solution Techniques Part 1 MRP, MRP-II p.1/31 Overview Production Planning Solution Techniques Part 1 MRP,

More information

Inventory: Independent Demand Systems

Inventory: Independent Demand Systems Inventory: Independent Demand Systems Inventory is used in most manufacturing, service, wholesale, and retail activities and because it can enhance profitability and competitiveness. It is widely discussed

More information

Justifying Simulation. Why use simulation? Accurate Depiction of Reality. Insightful system evaluations

Justifying Simulation. Why use simulation? Accurate Depiction of Reality. Insightful system evaluations Why use simulation? Accurate Depiction of Reality Anyone can perform a simple analysis manually. However, as the complexity of the analysis increases, so does the need to employ computer-based tools. While

More information

2 Organizations and Organizational Structures 2.1 Functional and Project Organizations, Typical Goals and Performance Measures

2 Organizations and Organizational Structures 2.1 Functional and Project Organizations, Typical Goals and Performance Measures 2 Organizations and Organizational Structures 2.1 Functional and Project Organizations, Typical Goals and Performance Measures The history of organizations is probably as long as the history of mankind.

More information

Choosing Planning & Scheduling solutions for Metals

Choosing Planning & Scheduling solutions for Metals Choosing Planning & Scheduling solutions for Metals White Paper The planning and scheduling of metals production presents special problems because of the complexity of the manufacturing process and the

More information

Material Requirements Planning (MRP)

Material Requirements Planning (MRP) Material Requirements Planning (MRP) Unlike many other approaches and techniques, material requirements planning works which is its best recommendation. Joseph Orlicky, 1974 1 History Begun around 1960

More information

Marketing Mix Modelling and Big Data P. M Cain

Marketing Mix Modelling and Big Data P. M Cain 1) Introduction Marketing Mix Modelling and Big Data P. M Cain Big data is generally defined in terms of the volume and variety of structured and unstructured information. Whereas structured data is stored

More information

Demand forecasting & Aggregate planning in a Supply chain. Session Speaker Prof.P.S.Satish

Demand forecasting & Aggregate planning in a Supply chain. Session Speaker Prof.P.S.Satish Demand forecasting & Aggregate planning in a Supply chain Session Speaker Prof.P.S.Satish 1 Introduction PEMP-EMM2506 Forecasting provides an estimate of future demand Factors that influence demand and

More information

Using Queueing Network Models to Set Lot-sizing Policies. for Printed Circuit Board Assembly Operations. Maged M. Dessouky

Using Queueing Network Models to Set Lot-sizing Policies. for Printed Circuit Board Assembly Operations. Maged M. Dessouky Using Queueing Network Models to Set Lot-sizing Policies for Printed Circuit Board Assembly Operations Maged M. Dessouky Department of Industrial and Systems Engineering, University of Southern California,

More information

Small Lot Production. Chapter 5

Small Lot Production. Chapter 5 Small Lot Production Chapter 5 1 Lot Size Basics Intuition leads many to believe we should manufacture products in large lots. - Save on setup time - Save on production costs Costs associated with Lots

More information

Linear Programming Supplement E

Linear Programming Supplement E Linear Programming Supplement E Linear Programming Linear programming: A technique that is useful for allocating scarce resources among competing demands. Objective function: An expression in linear programming

More information

ECON20310 LECTURE SYNOPSIS REAL BUSINESS CYCLE

ECON20310 LECTURE SYNOPSIS REAL BUSINESS CYCLE ECON20310 LECTURE SYNOPSIS REAL BUSINESS CYCLE YUAN TIAN This synopsis is designed merely for keep a record of the materials covered in lectures. Please refer to your own lecture notes for all proofs.

More information

Case study of a batch-production/inventory system E.M.M. Winands 1, A.G. de Kok 2 and C. Timpe 3

Case study of a batch-production/inventory system E.M.M. Winands 1, A.G. de Kok 2 and C. Timpe 3 Case study of a batch-production/inventory system E.M.M. Winands 1, A.G. de Kok 2 and C. Timpe 3 The plant of BASF under consideration consists of multiple parallel production lines, which produce multiple

More information

Resource grouping selection to minimize the maximum over capacity planning

Resource grouping selection to minimize the maximum over capacity planning 2012 International Conference on Industrial and Intelligent Information (ICIII 2012) IPCSIT vol.31 (2012) (2012) IACSIT Press, Singapore Resource grouping selection to minimize the maximum over capacity

More information

TEACHING AGGREGATE PLANNING IN AN OPERATIONS MANAGEMENT COURSE

TEACHING AGGREGATE PLANNING IN AN OPERATIONS MANAGEMENT COURSE TEACHING AGGREGATE PLANNING IN AN OPERATIONS MANAGEMENT COURSE Johnny C. Ho, Turner College of Business, Columbus State University, Columbus, GA 31907 David Ang, School of Business, Auburn University Montgomery,

More information

Simulation-based Optimization Approach to Clinical Trial Supply Chain Management

Simulation-based Optimization Approach to Clinical Trial Supply Chain Management 20 th European Symposium on Computer Aided Process Engineering ESCAPE20 S. Pierucci and G. Buzzi Ferraris (Editors) 2010 Elsevier B.V. All rights reserved. Simulation-based Optimization Approach to Clinical

More information

BILL OF RESOURCES AND PRIORITY-CAPACITY BALANCING

BILL OF RESOURCES AND PRIORITY-CAPACITY BALANCING Bill of Resources and PriorityCapacity Balancing 5 BILL OF RESOURCES AND PRIORITYCAPACITY BALANCING MGT2405, University of Toronto, Denny HongMo Yeh Load and capacity are terms that are often used interchangeably.

More information

Modeling Stochastic Inventory Policy with Simulation

Modeling Stochastic Inventory Policy with Simulation Modeling Stochastic Inventory Policy with Simulation 1 Modeling Stochastic Inventory Policy with Simulation János BENKŐ Department of Material Handling and Logistics, Institute of Engineering Management

More information

Manufacturing Planning and Control

Manufacturing Planning and Control 1 Chapter Manufacturing Planning and Control The manufacturing planning and control (MPC) system is concerned with planning and controlling all aspects of manufacturing, including managing materials, scheduling

More information

The life cycle of new products is becoming shorter and shorter in all markets. For electronic products, life

The life cycle of new products is becoming shorter and shorter in all markets. For electronic products, life MANUFACTURING & SERVICE OPERATIONS MANAGEMENT Vol. 10, No. 2, Spring 2008, pp. 278 287 issn 1523-4614 eissn 1526-5498 08 1002 0278 informs doi 10.1287/msom.1070.0175 2008 INFORMS Strategic Inventory Placement

More information

Manufacturing Flow Management

Manufacturing Flow Management Manufacturing Flow Management Distribution D Distribution Authorized to Department of Defense and U.S. DoD Contractors Only Aim High Fly - Fight - Win Supply Chain Management Processes Information Flow

More information

Material Requirements Planning. Lecturer: Stanley B. Gershwin

Material Requirements Planning. Lecturer: Stanley B. Gershwin Material Requirements Planning Lecturer: Stanley B. Gershwin MRP Overview Primary source: Factory Physics by Hopp and Spearman. Basic idea: Once the final due date for a product is known, and the time

More information

jobs that obey the norms must ensure the load balancing qualities. Load balancing should be interpreted as releasing a balanced mix of jobs to the

jobs that obey the norms must ensure the load balancing qualities. Load balancing should be interpreted as releasing a balanced mix of jobs to the Summary The term job shops is used to indicate companies that produce customer-specific components in small batches. Jobs (production orders) in a job shop are characterised by a large variety of routings

More information

On Correlating Performance Metrics

On Correlating Performance Metrics On Correlating Performance Metrics Yiping Ding and Chris Thornley BMC Software, Inc. Kenneth Newman BMC Software, Inc. University of Massachusetts, Boston Performance metrics and their measurements are

More information

Single item inventory control under periodic review and a minimum order quantity

Single item inventory control under periodic review and a minimum order quantity Single item inventory control under periodic review and a minimum order quantity G. P. Kiesmüller, A.G. de Kok, S. Dabia Faculty of Technology Management, Technische Universiteit Eindhoven, P.O. Box 513,

More information

Determining Inventory Levels in a CONWIP Controlled Job Shop

Determining Inventory Levels in a CONWIP Controlled Job Shop Determining Inventory Levels in a CONWIP Controlled Job Shop Sarah M. Ryan* Senior Member, IIE Department of Industrial and Management Systems Engineering University of Nebraska-Lincoln Lincoln, NE 68588-0518

More information

Optimizing Strategic Safety Stock Placement in Supply Chains. Stephen C. Graves Sean P. Willems

Optimizing Strategic Safety Stock Placement in Supply Chains. Stephen C. Graves Sean P. Willems Optimizing Strategic Safety Stock Placement in Supply Chains Stephen C. Graves Sean P. Willems Leaders for Manufacturing Program and A. P. Sloan School of Management Massachusetts Institute of Technology

More information

Product Mix Planning in Semiconductor Fourndry Manufacturing

Product Mix Planning in Semiconductor Fourndry Manufacturing Product Mix Planning in Semiconductor Fourndry Manufacturing Y-C Chou Industrial Engineering National Taiwan University Taipei, Taiwan, R.O.C. ychou@ccms. ntu. edu. tw Abstract Since a semiconductor foundry

More information

CISCM STUDY GUIDE. International Purchasing and Supply Chain Management Institute, 2006 1

CISCM STUDY GUIDE. International Purchasing and Supply Chain Management Institute, 2006 1 CISCM STUDY GUIDE International Purchasing and Supply Chain Management Institute, 2006 1 TABLE OF CONTENTS PART PAGE PART I Materials, Production, Inventory, Logistics, and Supply Chain Management 3 PART

More information

Expert s Guide to Successful MRP Projects. September 2012

Expert s Guide to Successful MRP Projects. September 2012 September 2012 Ziff Davis Research All Rights Reserved 2012 White Paper Executive Summary For most manufacturers, the planning department performs business critical functions. It is responsible for balancing

More information

INTEGRATED OPTIMIZATION OF SAFETY STOCK

INTEGRATED OPTIMIZATION OF SAFETY STOCK INTEGRATED OPTIMIZATION OF SAFETY STOCK AND TRANSPORTATION CAPACITY Horst Tempelmeier Department of Production Management University of Cologne Albertus-Magnus-Platz D-50932 Koeln, Germany http://www.spw.uni-koeln.de/

More information

ISE 421 QUANTATIVE PRODUCTION PLANNING

ISE 421 QUANTATIVE PRODUCTION PLANNING ISE 421 QUANTATIVE PRODUCTION PLANNING LECTURE III MRP, MRPII, ERP, APS Dr. Arslan ÖRNEK 2013 2014 Fall Term PRODUCTION PLANNING & SCHEDULING (PP&S) PP&S is one of the most critical activities in a manufacturing

More information

Motivated by a problem faced by a large manufacturer of a consumer product, we

Motivated by a problem faced by a large manufacturer of a consumer product, we A Coordinated Production Planning Model with Capacity Expansion and Inventory Management Sampath Rajagopalan Jayashankar M. Swaminathan Marshall School of Business, University of Southern California, Los

More information

Achieving World-class Fabless Planning

Achieving World-class Fabless Planning Whitepaper Series Achieving World-class Fabless Planning Reduce lengthy cycle times and respond to change quickly Introduction The Fabless Semiconductor industry achieves high growth rates and superior

More information

Chapter 5. Process design

Chapter 5. Process design Chapter 5 Process design Slack et al s model of operations management Direct Product and service design Design Operations Management Deliver Develop Process design Location, layout and flow Key operations

More information

Inventory Management - A Teaching Note

Inventory Management - A Teaching Note Inventory Management - A Teaching Note Sundaravalli Narayanaswami W.P. No.2014-09-01 September 2014 INDIAN INSTITUTE OF MANAGEMENT AHMEDABAD-380 015 INDIA Inventory Management - A Teaching Note Sundaravalli

More information

Chapter 11 Monte Carlo Simulation

Chapter 11 Monte Carlo Simulation Chapter 11 Monte Carlo Simulation 11.1 Introduction The basic idea of simulation is to build an experimental device, or simulator, that will act like (simulate) the system of interest in certain important

More information

Scheduling Policies, Batch Sizes, and Manufacturing Lead Times

Scheduling Policies, Batch Sizes, and Manufacturing Lead Times To appear in IIE Transactions Scheduling Policies, Batch Sizes, and Manufacturing Lead Times Saifallah Benjaafar and Mehdi Sheikhzadeh Department of Mechanical Engineering University of Minnesota Minneapolis,

More information

How To Balance In A Distributed System

How To Balance In A Distributed System 6 IEEE TRANSACTIONS ON PARALLEL AND DISTRIBUTED SYSTEMS, VOL. 11, NO. 1, JANUARY 2000 How Useful Is Old Information? Michael Mitzenmacher AbstractÐWe consider the problem of load balancing in dynamic distributed

More information

Inflation. Chapter 8. 8.1 Money Supply and Demand

Inflation. Chapter 8. 8.1 Money Supply and Demand Chapter 8 Inflation This chapter examines the causes and consequences of inflation. Sections 8.1 and 8.2 relate inflation to money supply and demand. Although the presentation differs somewhat from that

More information

Alessandro Anzalone, Ph.D. Hillsborough Community College, Brandon Campus

Alessandro Anzalone, Ph.D. Hillsborough Community College, Brandon Campus Alessandro Anzalone, Ph.D. Hillsborough Community College, Brandon Campus 1. Introduction 2. Background and Fundamental Concepts 3. Bills of Material 4. The MRP Explosion 5. Other MRP Issues 6. Potential

More information

Chapter 7 Production Planning

Chapter 7 Production Planning Production Planning and Control Chapter 7 Production Planning Professor JIANG Zhibin Dr GRANG Na Department of Industrial Engineering & Management Shanghai Jiao Tong University Contents Introduction Master

More information

Appendix: Simple Methods for Shift Scheduling in Multi-Skill Call Centers

Appendix: Simple Methods for Shift Scheduling in Multi-Skill Call Centers MSOM.1070.0172 Appendix: Simple Methods for Shift Scheduling in Multi-Skill Call Centers In Bhulai et al. (2006) we presented a method for computing optimal schedules, separately, after the optimal staffing

More information

IT-375 using the 6 th Edition PRODUCTION AND INVENTORY CONTROL CHAPTER 1: INTRODUCTION TO MATERIALS MANAGEMENT

IT-375 using the 6 th Edition PRODUCTION AND INVENTORY CONTROL CHAPTER 1: INTRODUCTION TO MATERIALS MANAGEMENT IT-375 using the 6 th Edition PRODUCTION AND INVENTORY CONTROL CHAPTER 1: INTRODUCTION TO MATERIALS MANAGEMENT What is wealth? GDP = production = profits What is the source of wealth? The conversion process

More information

TU-E2020 ADVANCED OPERATIONS MANAGEMENT. Demand management Sales & Operations Planning Master Production Scheduling

TU-E2020 ADVANCED OPERATIONS MANAGEMENT. Demand management Sales & Operations Planning Master Production Scheduling TU-E2020 ADVANCED OPERATIONS MANAGEMENT Demand management Sales & Operations Planning Master Production Scheduling 1982 1983 1984 1985 1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999

More information

Oracle Value Chain Planning Inventory Optimization

Oracle Value Chain Planning Inventory Optimization Oracle Value Chain Planning Inventory Optimization Do you know what the most profitable balance is among customer service levels, budgets, and inventory cost? Do you know how much inventory to hold where

More information

Sales and Operations Planning in Company Supply Chain Based on Heuristics and Data Warehousing Technology

Sales and Operations Planning in Company Supply Chain Based on Heuristics and Data Warehousing Technology Sales and Operations Planning in Company Supply Chain Based on Heuristics and Data Warehousing Technology Jun-Zhong Wang 1 and Ping-Yu Hsu 2 1 Department of Business Administration, National Central University,

More information

Tapping the benefits of business analytics and optimization

Tapping the benefits of business analytics and optimization IBM Sales and Distribution Chemicals and Petroleum White Paper Tapping the benefits of business analytics and optimization A rich source of intelligence for the chemicals and petroleum industries 2 Tapping

More information

Going Lean the ERP Way

Going Lean the ERP Way Going Lean the ERP Way Somnath Majumdar Abstract: Lean concepts and techniques are widely used all over the world today to eliminate waste in all processes. These are applicable for all organizations,

More information

A Log-Robust Optimization Approach to Portfolio Management

A Log-Robust Optimization Approach to Portfolio Management A Log-Robust Optimization Approach to Portfolio Management Dr. Aurélie Thiele Lehigh University Joint work with Ban Kawas Research partially supported by the National Science Foundation Grant CMMI-0757983

More information

NEW MODELS FOR PRODUCTION SIMULATION AND VALIDATION USING ARENA SOFTWARE

NEW MODELS FOR PRODUCTION SIMULATION AND VALIDATION USING ARENA SOFTWARE NEW MODELS FOR PRODUCTION SIMULATION AND VALIDATION USING ARENA SOFTWARE Marinela INŢĂ 1 and Achim MUNTEAN 1 ABSTRACT: Currently, Lean Manufacturing is a recognized topic in many research fields, which

More information

An integrated Single Vendor-Single Buyer Production Inventory System Incorporating Warehouse Sizing Decisions 창고 크기의사결정을 포함한 단일 공급자구매자 생산재고 통합관리 시스템

An integrated Single Vendor-Single Buyer Production Inventory System Incorporating Warehouse Sizing Decisions 창고 크기의사결정을 포함한 단일 공급자구매자 생산재고 통합관리 시스템 Journal of the Korean Institute of Industrial Engineers Vol. 40, No. 1, pp. 108-117, February 2014. ISSN 1225-0988 EISSN 2234-6457 http://dx.doi.org/10.7232/jkiie.2014.40.1.108 2014 KIIE

More information

A Genetic Algorithm Approach for Solving a Flexible Job Shop Scheduling Problem

A Genetic Algorithm Approach for Solving a Flexible Job Shop Scheduling Problem A Genetic Algorithm Approach for Solving a Flexible Job Shop Scheduling Problem Sayedmohammadreza Vaghefinezhad 1, Kuan Yew Wong 2 1 Department of Manufacturing & Industrial Engineering, Faculty of Mechanical

More information

Issues in Information Systems Volume 14, Issue 2, pp.353-358, 2013

Issues in Information Systems Volume 14, Issue 2, pp.353-358, 2013 A MODEL FOR SIMULTANEOUS DECISIONS ON MASTER PRODUCTION SCHEDULING, LOT SIZING, AND CAPACITY REQUIREMENTS PLANNING Harish C. Bahl, California State University-Chico, hbahl@csuchico.edu Neelam Bahl, California

More information

Automated Scheduling Methods. Advanced Planning and Scheduling Techniques

Automated Scheduling Methods. Advanced Planning and Scheduling Techniques Advanced Planning and Scheduling Techniques Table of Contents Introduction 3 The Basic Theories 3 Constrained and Unconstrained Planning 4 Forward, Backward, and other methods 5 Rules for Sequencing Tasks

More information

Analysis of Load Frequency Control Performance Assessment Criteria

Analysis of Load Frequency Control Performance Assessment Criteria 520 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 16, NO. 3, AUGUST 2001 Analysis of Load Frequency Control Performance Assessment Criteria George Gross, Fellow, IEEE and Jeong Woo Lee Abstract This paper presents

More information

White Paper February 2009. IBM Cognos Supply Chain Analytics

White Paper February 2009. IBM Cognos Supply Chain Analytics White Paper February 2009 IBM Cognos Supply Chain Analytics 2 Contents 5 Business problems Perform cross-functional analysis of key supply chain processes 5 Business drivers Supplier Relationship Management

More information

MATERIAL REQUIREMENTS PLANNING

MATERIAL REQUIREMENTS PLANNING MATERIAL REQUIREMENTS PLANNING A basic tool for performing the detailed material planning function in the manufacture of component parts and their assembly into finished items. MRP s Managerial objective

More information

Airline Schedule Development

Airline Schedule Development Airline Schedule Development 16.75J/1.234J Airline Management Dr. Peter Belobaba February 22, 2006 Airline Schedule Development 1. Schedule Development Process Airline supply terminology Sequential approach

More information

Broadband Networks. Prof. Dr. Abhay Karandikar. Electrical Engineering Department. Indian Institute of Technology, Bombay. Lecture - 29.

Broadband Networks. Prof. Dr. Abhay Karandikar. Electrical Engineering Department. Indian Institute of Technology, Bombay. Lecture - 29. Broadband Networks Prof. Dr. Abhay Karandikar Electrical Engineering Department Indian Institute of Technology, Bombay Lecture - 29 Voice over IP So, today we will discuss about voice over IP and internet

More information

Prescriptive Analytics. A business guide

Prescriptive Analytics. A business guide Prescriptive Analytics A business guide May 2014 Contents 3 The Business Value of Prescriptive Analytics 4 What is Prescriptive Analytics? 6 Prescriptive Analytics Methods 7 Integration 8 Business Applications

More information

The Trip Scheduling Problem

The Trip Scheduling Problem The Trip Scheduling Problem Claudia Archetti Department of Quantitative Methods, University of Brescia Contrada Santa Chiara 50, 25122 Brescia, Italy Martin Savelsbergh School of Industrial and Systems

More information

BSCM Sample TEST. CPIM(Certified In Production & Inventory Management) - 1 -

BSCM Sample TEST. CPIM(Certified In Production & Inventory Management) - 1 - BSCM Sample TEST. 1. Which of the following demand fulfillment approaches typically provides the longest delivery time? A) Engineer-to-order. B) Make-to-order. C) Assemble-to-order. D) Make-to-stock. 2.

More information

Material Requirements Planning (MRP)

Material Requirements Planning (MRP) The Priority Enterprise Management System Material Requirements Planning (MRP) Contents MRP - Introduction...2 Calculating Demand for Top-Level Parts...2 Calculating Demand for Sub-assemblies and Raw Materials...3

More information

Basic Queuing Relationships

Basic Queuing Relationships Queueing Theory Basic Queuing Relationships Resident items Waiting items Residence time Single server Utilisation System Utilisation Little s formulae are the most important equation in queuing theory

More information

11.3 BREAK-EVEN ANALYSIS. Fixed and Variable Costs

11.3 BREAK-EVEN ANALYSIS. Fixed and Variable Costs 385 356 PART FOUR Capital Budgeting a large number of NPV estimates that we summarize by calculating the average value and some measure of how spread out the different possibilities are. For example, it

More information

EVERYTHING YOU NEED TO KNOW ABOUT INVENTORY

EVERYTHING YOU NEED TO KNOW ABOUT INVENTORY EVERYTHING YOU NEED TO KNOW ABOUT INVENTORY Introduction Inventory is considered the necessary evil of the supply chain. In fact, there has been a whole movement; lean manufacturing that has tried to reduce

More information

Change Management in Enterprise IT Systems: Process Modeling and Capacity-optimal Scheduling

Change Management in Enterprise IT Systems: Process Modeling and Capacity-optimal Scheduling Change Management in Enterprise IT Systems: Process Modeling and Capacity-optimal Scheduling Praveen K. Muthusamy, Koushik Kar, Sambit Sahu, Prashant Pradhan and Saswati Sarkar Rensselaer Polytechnic Institute

More information

SPARE PARTS INVENTORY SYSTEMS UNDER AN INCREASING FAILURE RATE DEMAND INTERVAL DISTRIBUTION

SPARE PARTS INVENTORY SYSTEMS UNDER AN INCREASING FAILURE RATE DEMAND INTERVAL DISTRIBUTION SPARE PARS INVENORY SYSEMS UNDER AN INCREASING FAILURE RAE DEMAND INERVAL DISRIBUION Safa Saidane 1, M. Zied Babai 2, M. Salah Aguir 3, Ouajdi Korbaa 4 1 National School of Computer Sciences (unisia),

More information

SINGLE-STAGE MULTI-PRODUCT PRODUCTION AND INVENTORY SYSTEMS: AN ITERATIVE ALGORITHM BASED ON DYNAMIC SCHEDULING AND FIXED PITCH PRODUCTION

SINGLE-STAGE MULTI-PRODUCT PRODUCTION AND INVENTORY SYSTEMS: AN ITERATIVE ALGORITHM BASED ON DYNAMIC SCHEDULING AND FIXED PITCH PRODUCTION SIGLE-STAGE MULTI-PRODUCT PRODUCTIO AD IVETORY SYSTEMS: A ITERATIVE ALGORITHM BASED O DYAMIC SCHEDULIG AD FIXED PITCH PRODUCTIO Euclydes da Cunha eto ational Institute of Technology Rio de Janeiro, RJ

More information

APICS acknowledges the Basics of Supply Chain Management Committee for its contributions in the development of this resource.

APICS acknowledges the Basics of Supply Chain Management Committee for its contributions in the development of this resource. APICS acknowledges the Basics of Supply Chain Management Committee for its contributions in the development of this resource. Jim Caruso, CPIM, CSCP (chair) Carol Bulfer, CPIM James F. Cox, Ph.D., CFPIM,

More information

INVENTORY MANAGEMENT. 1. Raw Materials (including component parts) 2. Work-In-Process 3. Maintenance/Repair/Operating Supply (MRO) 4.

INVENTORY MANAGEMENT. 1. Raw Materials (including component parts) 2. Work-In-Process 3. Maintenance/Repair/Operating Supply (MRO) 4. INVENTORY MANAGEMENT Inventory is a stock of materials and products used to facilitate production or to satisfy customer demand. Types of inventory include: 1. Raw Materials (including component parts)

More information

A Profit-Maximizing Production Lot sizing Decision Model with Stochastic Demand

A Profit-Maximizing Production Lot sizing Decision Model with Stochastic Demand A Profit-Maximizing Production Lot sizing Decision Model with Stochastic Demand Kizito Paul Mubiru Department of Mechanical and Production Engineering Kyambogo University, Uganda Abstract - Demand uncertainty

More information

Process design. Process design. Process design. Operations strategy. Supply network design. Layout and flow Design. Operations management.

Process design. Process design. Process design. Operations strategy. Supply network design. Layout and flow Design. Operations management. Process design Source: Joe Schwarz, www.joyrides.com Process design Process design Supply network design Operations strategy Layout and flow Design Operations management Improvement Process technology

More information

Steel supply chain transformation challenges Key learnings

Steel supply chain transformation challenges Key learnings IBM Global Business Services White Paper Industrial Products Steel supply chain transformation challenges Key learnings 2 Steel supply chain transformation challenges Key learnings Introduction With rising

More information

The Lecture Contains: Application of stochastic processes in areas like manufacturing. Product(s)/Good(s) to be produced. Decision variables

The Lecture Contains: Application of stochastic processes in areas like manufacturing. Product(s)/Good(s) to be produced. Decision variables The Lecture Contains: Application of stochastic processes in areas like manufacturing Product(s)/Good(s) to be produced Decision variables Structure of decision problem Demand Ordering/Production Cost

More information

THE VALUE OF SIMULATION IN MODELING SUPPLY CHAINS. Ricki G. Ingalls

THE VALUE OF SIMULATION IN MODELING SUPPLY CHAINS. Ricki G. Ingalls Proceedings of the 1998 Winter Simulation Conference D.J. Medeiros, E.F. Watson, J.S. Carson and M.S. Manivannan, eds. THE VALUE OF SIMULATION IN MODELING SUPPLY CHAINS Ricki G. Ingalls Manufacturing Strategy

More information

Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras

Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras Lecture - 36 Location Problems In this lecture, we continue the discussion

More information

Using simulation to calculate the NPV of a project

Using simulation to calculate the NPV of a project Using simulation to calculate the NPV of a project Marius Holtan Onward Inc. 5/31/2002 Monte Carlo simulation is fast becoming the technology of choice for evaluating and analyzing assets, be it pure financial

More information

pg. pg. pg. pg. pg. pg. Rationalizing Supplier Increases What is Predictive Analytics? Reducing Business Risk

pg. pg. pg. pg. pg. pg. Rationalizing Supplier Increases What is Predictive Analytics? Reducing Business Risk What is Predictive Analytics? 3 Why is Predictive Analytics Important to Sourcing? 4 Rationalizing Supplier Increases 5 Better Control of Sourcing and Costs 6 Reducing Business Risk 7 How do you implement

More information

Rule-based Traffic Management for Inbound Call Centers

Rule-based Traffic Management for Inbound Call Centers Vrije Universiteit Amsterdam Research Paper Business Analytics Rule-based Traffic Management for Inbound Call Centers Auteur: Tim Steinkuhler Supervisor: Prof. Dr. Ger Koole October 7, 2014 Contents Preface

More information

Sensitivity Analysis 3.1 AN EXAMPLE FOR ANALYSIS

Sensitivity Analysis 3.1 AN EXAMPLE FOR ANALYSIS Sensitivity Analysis 3 We have already been introduced to sensitivity analysis in Chapter via the geometry of a simple example. We saw that the values of the decision variables and those of the slack and

More information

Manufacturing. Manufacturing challenges of today and how. Navision Axapta solves them- In the current explosive economy, many

Manufacturing. Manufacturing challenges of today and how. Navision Axapta solves them- In the current explosive economy, many Manufacturing challenges of today and how Navision Axapta solves them- the solution for change; controlled by you. Manufacturing In the current explosive economy, many manufacturers are struggling to keep

More information

Glossary of Inventory Management Terms

Glossary of Inventory Management Terms Glossary of Inventory Management Terms ABC analysis also called Pareto analysis or the rule of 80/20, is a way of categorizing inventory items into different types depending on value and use Aggregate

More information

Operational Business Intelligence in Manufacturing

Operational Business Intelligence in Manufacturing Operational Business Intelligence in Manufacturing Copyright 2007 KeyTone Technologies Inc. Page 1 SmartWIP - Intelligent Manufacturing with RFID Manufacturers are under competitive pressure to fulfill

More information

Logistics Management SC Performance, SC Drivers and Metrics. Özgür Kabak, Ph.D.

Logistics Management SC Performance, SC Drivers and Metrics. Özgür Kabak, Ph.D. Logistics Management SC Performance, SC Drivers and Metrics Özgür Kabak, Ph.D. Outline Supply Chain Performance: Achieving Strategic Fit and Scope Competitive and supply chain strategies Achieving strategic

More information

Section A. Index. Section A. Planning, Budgeting and Forecasting Section A.2 Forecasting techniques... 1. Page 1 of 11. EduPristine CMA - Part I

Section A. Index. Section A. Planning, Budgeting and Forecasting Section A.2 Forecasting techniques... 1. Page 1 of 11. EduPristine CMA - Part I Index Section A. Planning, Budgeting and Forecasting Section A.2 Forecasting techniques... 1 EduPristine CMA - Part I Page 1 of 11 Section A. Planning, Budgeting and Forecasting Section A.2 Forecasting

More information