Investment and Performance Board (IPB)
|
|
|
- Gilbert Gallagher
- 9 years ago
- Views:
Transcription
1 Investment and Performance Board (IPB) Date of meeting: 19 January 2016 Title of paper: To be presented by: Cleared by: Classification: Funding for Boiler Scrappage Scheme Jamie Ratcliff, Assistant Director, Programme, Policy and Services David Lunts, Executive Director, Housing and Land Richard Blakeway, Deputy Mayor, Housing, Land and Property Public 1 Executive summary 1.1 This paper sets out proposals for a GLA pan-london boiler scrappage scheme this winter, as part of the Mayor s RE:NEW domestic retrofit programme. Its purpose is to rapidly boost domestic retrofit activity and the level of carbon savings in the capital, to help progress against Mayoral carbon reduction targets for homes. The scheme would, in addition, cut household fuel bills, have air quality benefits and would in many cases address fuel poverty and reduce coldrelated ill health, as well as excess winter deaths. 1.2 It is proposed that 2.6m of capital funding is used to provide 6,500 owner occupiers and private landlords each with 400 cash back on replacement of a working G-rated/low efficient or equivalent boiler with a new A-rated boiler or renewable heating generation. Vouchers would be issued when applicants apply and would be redeemed once the new gas boiler is installed by a certified and accredited engineer/installer. 1.3 The scheme could be mobilised quickly for commencement on 1 February 2016 and would close before the end of the pre-election period. 1.4 The scheme would result in estimated annual savings of 9,750 tonnes of carbon dioxide (tco 2 ), increasing RE:NEW s emissions reduction to date by nearly a third, and a reduction in annual energy bills of around 340 per household (over 2.2m per year off Londoners fuel bills in total). 1.5 Robust mechanisms would be in place to minimise fraud and assure quality. First, the installation of gas heating systems is highly regulated through Gas Safe (formerly CORGI). Second, a Fraud Reduction Framework would be put in place, which would include pre- and post-installation visits to a sample of those applicants and checks against the Gas Safe register. 1.6 The scheme would be administered by an external contractor. 1.7 Similar successful schemes have been run by both the UK and Scottish governments. These have resulted in substantial carbon savings that exceeded initial estimates, high levels of customer satisfaction and minimal levels of apparent misuse of funds.
2 2 Recommendation 2.1 That the Board agrees in principle to seek the Mayor s approval to implement a GLA boiler scrappage scheme at the start of February, with capital funding of 2.6m and revenue funding of up to 200,000. This is existing funding within the Housing and Land Directorate that will be redirected for this purpose. An external contractor would be procured to administer the scheme. 3 Introduction and background 3.1 The Mayor s Climate Change Mitigation and Energy Strategy (CCMES) sets out a plan to reduce London s emissions by 60 per cent by 2025 compared to 1990 levels. Emissions from homes account for 36 per cent and the CCMES enshrines ambitious reduction targets from the domestic sector. 3.2 Delivering energy efficiency measures in London has historically been difficult due to multiple challenges. These include the age and fabric of the housing stock, conservation areas, and the high proportion of privately rented homes (26 per cent 10 per cent of which have the lowest energy efficiency rating), where there are split incentives. 3.3 In addition, a raft of Government policy changes and proposals within a relatively short period of time have led to challenges to the delivery of domestic retrofit in London at scale, including through the RE:NEW programme, in the short to medium term. In respect of energy policy, these are changes to the Energy Company Obligation, the scrapping of Green Deal and Zero Carbon Homes Standard (and Allowable Solutions), and Government s recent decision to cut the domestic Solar Feed-In-Tariff by 64 per cent. Recent and proposed housing policy changes may also mean that energy efficiency will be less of a focus within the social housing sector. 3.4 It is therefore necessary to explore programmes and initiatives that can rapidly boost domestic retrofit delivery in the capital, in order to realise additional carbon savings to help achieve the Mayor s targets. 3.5 In addition, last winter there were over 4,000 excess winter deaths, compared to 1,700 in 2013/14 levels. While the reasons for the increase are not entirely clear, poorly heated homes are likely to have contributed (due to fuel poverty caused by inefficient heating systems). 4 The case for a GLA boiler scrappage scheme 4.1 Old inefficient boilers, which are still working after many years, are not necessarily a priority to replace for homeowners. This has two costs associated with it. Firstly, the homeowner will be paying higher bills to operate the boilers compared to new efficient ones. Secondly, in environmental terms older boilers generate far higher emissions (both CO 2 and NOx). 4.2 Installing an efficient boiler can be a cost-effective way to cut household energy bills, CO 2 and NOx emissions. Domestic heating accounts for around three quarters of household energy consumption and boilers, in particular, for around 55 per cent of household energy spend each year. Gas boilers also account for approximately 12 per cent of London s NOx emissions. Replacing a G-rated boiler (which is below 70 per cent efficient) with an A-rated
3 boiler (which is above 90 per cent efficient) can save over 1.5tCO 2 per year, 1.2kg NOx per year, and around 340 a year off a household s fuel bills. 4.3 Gas boilers, of all energy efficiency measures, have delivered the biggest savings in London s homes since 2005 (over 0.6MtCO2), and the scope to do more is considerable. Replacing 6,500 G-rated boilers with highly efficient A-rated ones could save in the order of 9,750 tco 2 per year and over 8000kg NOx per year. Since legislation was introduced in 2005 mandating the installation of condensing gas boilers in all but special applications, installation rates have increased to over 200,000 in London every year. However, it is estimated that up to 212,000 homes could have G-rated boilers across the capital, the overwhelming majority of which are in the private sector so there is clearly scope to achieve far more. 4.4 A strong precedent already exists boiler scrappage schemes in particular have been some of most successful Government energy efficiency interventions and have secured excellent consumer satisfaction ratings (~96 per cent), assuring rapid carbon reduction and energy savings. DECC s 2010 Boiler Scrappage Scheme in England (launched by the Prime Minister), which was set up at one week s notice, offered a voucher contributing 400 towards replacing old inefficient boilers with new efficient models. The scheme opened on 5 January 2010, and the demand was such that, the majority of vouchers were allocated for the scheme within weeks of opening resulting in the scheme having fully allocated all available vouchers by 18 March The assumed CO 2 savings for the Government scheme also exceeded the estimates stated at the beginning of the scheme by 71 per cent. However, at this point the Government has no plans for a further scheme. (Further background on Government s 2010 scheme is set out at Appendix 2). 4.5 There is sufficient demand for boiler scrappage schemes in London, as proven by DECC s previous scrappage scheme. In 2010 over 9,700 households in over 20 London boroughs received vouchers equating to 3.88m (significantly more than would be delivered through the proposed GLA boiler scrappage scheme). 5 Scheme design: eligibility and requirements 5.1 The eligibility criteria and requirements for the scheme would be as follows: 1. properties must be homes in London 2. applicants must be homeowners or private landlords 3. boilers being replaced must be G-rated gas, oil, LPG or solid fuel (typically 15+ years old), in working order and the main boiler used to heat the home 4. replacement boilers must be A-rated energy efficient boiler or a renewable heating technology (further details of proposed eligible technologies are at Appendix 3) 5. installations must be undertaken by a Gas Safe (formally CORGI) registered installer (in line with the legislative requirement to do so) or, for renewable heat technologies (e.g. heat pumps or solar thermal), a
4 Microgeneration Certification Scheme (MSC) certified installer (see section 8 below on fraud and quality assurance) to avoid issues of additionality, the boiler scrappage voucher must not be used in conjunction with any other central government scheme. 5.2 It is central to our climate and energy strategy to make this scheme applicable to renewables. However, due to higher installation costs, we do not expect many renewable heat technologies to be installed under the scheme. For example, Government s 2010 scrappage scheme only resulted in 75 renewable heat installations out of a total of 118,600 installations. 6 Scheme design: level of cashback 6.1 Similar to previous successful schemes, a GLA Scrappage Scheme would provide 400 scrappage vouchers to around 6,500 households across the capital this winter. The GLA would stipulate that the scheme closes once the money is spent and successful applicants have up to 12 weeks after receiving their voucher to have the work done and claim the money off the cost of installation. We would plan to issue vouchers equal to the overall capital budget ( 2.6m) plus ~5 per cent, recognising that there will be at least 8-10 per cent drop out. Previous schemes have resulted in around 10 per cent drop out (either as a result of failing to meet eligibility criteria or applications either being withdrawn or reaching expiry) is considered the right level of grant to provide to consumers and there is a clear precedent. Both UK and Scottish governments have provided 400 vouchers through previous scrappage schemes, which have received 100 per cent take-up. This amount of grant would also represent approximately 20 per cent of the overall installation cost (assuming an average boiler replacement is around 2,000). According to DECC this level was also based on a consumer perception of what value of voucher was worth the aggravation of applying. Offering less than 400 may also discourage householders on lower disposable incomes (e.g. those who are fuel poor). 6.3 The cost of a new energy-efficient gas boiler varies greatly, from 1,500 to around 3,000, and is estimated by the Energy Savings Trust at an average of around 2,300 including installation. It is proposed that vouchers are provided at the same rate to all homes regardless of total outlay. 7 Scheme design: application and claim process 7.1 The application and claim process includes eight key steps: 7.2 Step 1: the homeowner checks whether their existing boiler is G-rated (through an already established open-source website) and, if it is, secures a quote from a certified installer before making an application for a voucher. The GLA would encourage through marketing prospective applicants to seek up to three quotes to ensure they are getting the best deal. 7.3 Step 2: the homeowner applies for their Boiler Scrappage Scheme voucher either on-line or by phone (on website/call centre administered by 1 For the remainder of this paper, Gas Safe and Microgeneration Certification Scheme (MSC) installers will be referred to as certified installers
5 RE:NEW Support Team) prior to carrying out any work, uploading personal information and their boiler replacement quotation. 7.4 Step 3: subject to rigorous checks (by GLA) that the application meets eligibility criteria and required information have been provided (including the quotation), a letter and rebate voucher is issued by . Terms and conditions on the voucher state that it is a condition of the rebate being paid that: work on the installation has not commenced before the date on which the rebate voucher is issued the applicant is replacing a working G-rated (or equivalent) or worse rated boiler the applicant is having an A-rated (or equivalent) boiler installed or a renewable heat microgeneration technology the installer is a certified installer. 7.5 Step 4: on receipt of the voucher the applicant is then be free to proceed with their boiler replacement. Each applicant has 12 weeks (from the voucher being issued) to have their old boiler replaced with a new one and return a completed voucher and required documentation. NB: each voucher would have an expiry date pertaining to the offer. 7.6 Step 5: on completion of the installation, the applicant can then apply for their cash back by completing their voucher. Each applicant will have to check the following which will be stated on the claim form: 1. installation address 2. old boiler manufacturer 3. old boiler make/model 4. rebate value 5. voucher expiry date. 7.7 Step 6: subject to 1 to 5 being correct, the applicant can proceed with arranging for the voucher to be countersigned by a certified installer. 7.8 Step 7: the applicant submits the voucher to the RE:NEW Support Team electronically along with a copy of their installer s invoice. 7.9 Step 8: if the claim meets all criteria and requirements, and all required documents are submitted, then 400 rebate is paid Similar to previous government schemes, to minimise administration and delays to customers, there would be no facility to submit paper applications for the scheme. (A flowchart showing the process in more detail can be found at Appendix 4). 8 Fraud prevention and quality assurance 8.1 Robust mechanisms would be in place to minimise fraud and assure quality. First, the installation of gas heating systems is highly regulated. Second, a Fraud Reduction Framework would be put in place, which would include pre-
6 and post-installation visits to a sample of those applicants and checks against the Gas Safe register. Regulation 8.2 The installation of gas heating systems is highly regulated through Gas Safe, which is primarily a health and safety regulatory regime where installers have to be accredited. Installers risk losing their jobs and can be subject to criminal proceedings if they do not carry out their duties in accordance to the law. The Gas Safe Register contains details of all certified gas installers in the UK. In addition, the Microgeneration Certification Scheme for renewable heating systems is a nationally recognised quality assurance scheme, supported by the Department of Energy and Climate Change. In practice however, as stated above, we do not expect many renewable heat technologies to be installed under such a scheme. Fraud detection 8.3 In order to provide assurance that funds under the boiler scrappage scheme would not be acquired or used fraudulently, a programme of eligibility checks, and pre-installation and post-installation audits would be carried out. A percentage of installations would therefore be verified through regular data checks and some physical visits at four different stages of the installation process. To that end, we would agree a Fraud Reduction Framework with the external contractor, comprising: 1. visits to up to two per cent of a random sample of those who have applied for a voucher to verify if their boiler is indeed a G-rated boiler eligible for replacement under this scheme (the Government s BSS in 2010 did this and found that 93 per cent of applications were valid) 2. visits to up to two per cent of a random sample of householders who have completed installation to check that an eligible replacement heating system has been installed (the Government s BSS also did this with a 99.7 per cent pass rate) 3. checks of all claims against work notified to Gas Safe. If claimed jobs are not notified to Gas Safe, which is currently a requirement, this would be investigated further 4. daily checks (using an integrated database) to ensure that no more than one voucher per property is given. This would be done by monitoring postcode data. If multiple applications are detected we would investigate further. 9 Targeting specific groups 9.1 In terms of demography, the scheme would be designed to attract all social groups. However, by encouraging lower installation costs (e.g. by encouraging consumers to shop around and obtain up to three Gas Safe quotes) could help broaden the social reach of the scheme by making boiler replacement even more affordable. We would expect a boiler scrappage scheme to trigger some energy companies and installers to complement, and in some cases match, the GLA offer, offering even better value for the consumer. 9.2 We plan to work through boroughs to ensure that existing referral mechanisms (i.e. fuel poverty and seasonal health networks) are used to communicate the
7 scrappage scheme. We would intend the Mayor to write to boroughs when the scheme is launched inviting their engagement and highlighting the need to ensure households that are fuel poor are assisted, where possible. 9.3 We are also mindful that this scheme would come ahead of the new private rented sector (PRS) regulations which will come into force in April 2016, empowering private domestic tenants to request consent for energy efficiency measures that may not unreasonably be refused by their landlord. As stated above, an overwhelming majority of inefficient homes and indeed boilers are in the private sector, so we would want to ensure as many PRS homes as possible are treated through this scheme. This would be achieved by marketing the scheme through a wide range of sources, including boroughs. Marketing material will be specifically targeted at London Rental Standard (LRS) accredited landlords through the LRS accrediting organisations, all of which will be asked to disseminate information about the scheme direct to their members. We would also strongly encourage those landlords applying for vouchers to join the LRS. 9.4 Marketing material will also be targeted at other groups in the private sector, such as first time buyers. 10 Alternative options 10.1 Consideration was given to using the same level of capital funding for other retrofit measures, such as solid wall insulation or solar PV. However, there is currently a far stronger cost benefit for gas boiler replacement compared to other measures, in terms of levels of carbon savings and consequent fuel bill savings, reductions in fuel poverty and health benefits to households. The table below shows CO 2 and bill savings for A-rated condensing gas boilers compared with solar PV and solid wall insulation. Technology Condensing Gas Boilers Up-front cost (average range) Energy bill savings ( /year) 1,500 3, ,500 Solar PV 5,000 8, (incl. export tariff) Solid Wall Insulation Carbon dioxide savings (kgco2/year) 1,870 8,000 22, , The implementation of other measures would also be far more complex, present numerous physical challenges and take far longer (and be more costly) to implement: solar PV: while average carbon savings are slightly higher than a typical gas boiler installation, the average domestic solar PV system costs between 5,000-8,000 (including VAT at five per cent) nearly three times the cost of a boiler, on average. Solar PV will also not deliver air quality benefits in London (given it is replacing electricity from the grid which is predominantly generated outside of London), or help alleviate fuel poverty
8 solid wall insulation: given up-front costs range between 8,000 22,000, the GLA would be required to spend considerably more money to entice householders to install solid wall insulation. Grants would therefore have to be far larger than 400 and therefore fewer homes would be supported. Planning permission may also be required in Conservation Areas (if external wall insulation is installed) The reason for focusing the scheme on the private rather than social housing sector is that, first, due to Decent Homes and other asset maintenance programmes implemented by social landlords, there is a very low incidence of energy inefficient boilers in that sector. 85 per cent of social housing stock is between EPC C and D compared to the owner occupied and private rented sector where over 30 per cent are between EPC E and G. Second, the RE:NEW Support Team are already working closely with the social housing sector to support them to retrofit their stock, with support plans in place with 58 organisations. Third, there are lower rates of fuel poverty in social housing It would be possible to have a more targeted approach, focusing specifically on fuel poor households or those at risk of or experiencing cold-related illness. However, in the absence of available data to enable very specific groups of households to be targeted, a more blanket approach tackling the most inefficient boilers/heating systems is one way to deal with the least efficient homes (where fuel poverty may be acute). Moreover, the less targeted a scheme is, the higher the take up and therefore the CO 2 savings will be Consideration was given to whether the GLA should make individual grants direct to householders, who would then arrange for their own installations, or whether grants and potentially installations should be administered through London boroughs. The former option is considered preferable due to economies of scale, the need to efficiently accommodate private landlords operating across more than one borough, and the need to implement the scheme quickly. 11 Communications and marketing 11.1 It is envisaged that the offer, combined with a Mayoral launch and tactical communications campaign, will be quickly picked up by the media and awareness will spread. Previous Government schemes have involved very little marketing, and following high profile launches - awareness has spread effectively and widely through word of mouth A tactical marketing campaign would include: Mayoral launch on 1 February 2016 (potentially to coincide with the annual Cold Homes Week which is scheduled for 1 5 February 2015, which receives significant press coverage) webpages on London.gov.uk promoting and explaining the scheme with links to the contractor s site which will hold the transaction pages letter from Mayor to boroughs inviting their engagement marketing to industry bodies (e.g. Heating and Hot Water Industry Council), and associated London Rental Standard accreditation organisations
9 encouraging the Government to communicate the scheme on gov.uk appropriate social media at launch and to communicate progress. 12 Proposed next steps 12.1 Subject to approval by IPB and subsequently the Mayor, we plan to appoint a contractor who would deliver the boiler scrappage scheme, including, project management and scheme administration, fraud prevention (including physical pre and post installation audits), communications and marketing, and monitoring and evaluation In advance of the scrappage scheme commencing, the GLA would convene trade bodies, manufacturers (who directly communicate with suppliers/installers) and NGOs, to brief them on the scrappage scheme. As stated above, we would expect a boiler scrappage scheme to trigger some energy companies and installers to complement, and in some cases match, the GLA offer. This would enable more households to benefit, so generating greater CO 2 savings. To that end, we would engage with the market during January to help extend the scheme to many more householders across London this winter However, the GLA would not give preference to a given manufacturer, supplier or installer. To avoid any distortion of the relevant market the GLA will interact with eligible homeowners throughout the scrappage scheme to whom the benefit of the 400 cash back will accrue, albeit for efficiency of delivery and management of the scheme will be administered by an external delivery agent Around the time of launch, we would contact boroughs inviting their support and assistance, to ensure the scheme is directed at appropriate demographic groups. 13 Objectives and expected outcomes 13.1 The proposals outlined above will drive significant savings in carbon, energy and financial savings across London, contributing to the achievement of the Mayor s target to reduce carbon emissions by 60 per cent by 2025 and both RE:NEW programme KPIs and ELENA targets The GLA Scrappage Scheme will: a. save carbon. Replacing 6,500 G-rated boilers should save in the region of 9,750tCO 2 per year, increasing our total domestic CO 2 reduction from 32,000 tco 2 to around 42,000tCO 2 (an increase of nearly a third); b. save over 2.2m per year off Londoners fuel bills. An individual household's energy bill will be cut by around 340 a year, (depending on the size of the property); c. improve air quality, reducing NOx emissions by 8000kg per year; d. help tackle fuel poverty and prevent excess winter deaths;
10 e. act as a catalyst to spur on additional energy efficiency improvements to the home (e.g. heating controls and insulation); and f. investment of 15m or more in new boilers/renewable heating systems helping to sustain work for the low carbon and heating sectors across the capital. 14 Equality comments 14.1 The GLA will take appropriate steps to ensure that there are no potential negative impacts expected on those with protected characteristics. Those with protected characteristics will gain from the positive benefits of this scheme in equal measure should their properties be selected, and there will be equality of access to participate in the delivery and benefit from the scheme, without discrimination. 15 Key risks and issues 15.1 The key risks and issues for delivery of these projects are set out in the table below: Risk Lack of takeup results in lower than expected savings Overprovision of the vouchers leads to overspend Likelihood (out of 5) Impact (out of 5) Rating Mitigation Avoid. GLA will ensure a comprehensive marketing and communications campaign for the boiler scrappage scheme. In addition, the GLA will convene the market and trade bodies ahead of the launch so they can also advertise the scheme Avoid. Though vouchers will be issued commensurate with the total budget (plus ~5 per cent), there is expected to be at least 10 per cent drop out (as is consistent with other similar grant programmes). Most applications for similar schemes which are recorded as rejected were done so at application stage and were duplicate applications for a particular installation address. This was particularly common at the beginning of a scheme where consumers are very keen to secure funding and therefore applied several times through different channels. Over commitment of vouchers will therefore be mitigated, and the overall programme funds will be brought back within budget.
11 Drop out due to not meeting eligibility criteria leads to underspend (and reduced number of installations and benefits) Voucher system is misused and fraudulent claims are made Reduce. GLA will issue vouchers equal to the overall budget plus ~5 per cent (recognising that there will be some drop out) Avoid. GLA will expressly state that all boiler replacements made as part of the scheme need to be undertaken by a certified Gas safe engineer in accordance with the law. In addition, a programme of pre-installation and post-installation audits will be carried out (as set out above). 16 Project costs 16.1 There are no alternative sources of funding available to fund the scheme. Therefore, without the Mayor s investment in the scheme, there is a serious risk that London will not achieve the required levels of carbon savings and other associated benefits that will arise from the scheme Given the priority to address carbon savings in the domestic sector, and shortterm challenges with the RE:NEW strategy of targeting social landlords, it is proposed to move 2.6m from the Housing Zones budget to a boilerscrappage scheme for winter 2015/16. This will still leave an overall increased budget of 410m to support the original 20 Housing Zones (plus the additional 200m proposed elsewhere on this agenda) Revenue funding of up to 200,000 will be come from the RE:FIT and the RE:NEW 2015/16 budgets. The RE:FIT funding was earmarked as contingency for the procurement of the new RE:FIT framework, but will not now be required for that purpose, and the RE:NEW funding is for programme activity (so will be used for its intended purpose). 17 Financial comments of the Executive Director Resources 17.1 The report proposes for GLA to fund and implement a pan-london boiler scrappage scheme for winter 2015/16 to help progress Mayoral carbon reduction targets for homes The anticipated capital expenditure for the scheme is expected to be 2.6m, which is based on 6,500 successful applicants at a rebate of 400 per applicant. It is proposed that this will be funded from existing GLA capital budget.
12 17.3 It is estimated that revenue expenditure will not exceed 200,000 and it is proposed that the costs will be covered by RE:FIT contingency ( 90,000) and RE:NEW ( 110,000) budgets. All of the funding is expected to be spent in 2015/16 financial year. The proposed spend will be contained within the agreed budget terms and any overspend must be accompanied by a separate decision However, the total budget of 2.8m which is being proposed for this scheme can also be considered to fund other projects within the GLA. 18 Legal comments 18.1 The foregoing sections of this report indicate that the decisions requested of IPB fall within the GLA s statutory powers to do such things considered to promote or which may be considered facilitative of or conducive to the promotion of the economic development and wealth creation in Greater London Should IPB be minded to accept that the Mayor s approval of the proposals set out in this report be sought and such approval is obtained officers must ensure that they: do not proceed further until obtaining Mayoral approval: pay due regard to the principle that there should be equality of opportunity for all people; consider how the proposals will promote the improvement of health of persons, health inequalities between persons and to contribute towards the achievement of sustainable development in the United Kingdom; consult with appropriate bodies; the award grant funding to third parties is distributed fairly, transparently, in accordance with the GLA s equalities and in manner which affords value for money in accordance with the GLA s Contracts and Funding Code and appropriate funding conditions are put in place between the GLA and eligible recipients before any commitment is made to provide such funding; and any supplies, services or works required for the delivery of the programme are procured in a manner which corresponds with the principles of the GLA s Contracts and Funding Code and all applicable procurement law and that appropriate contract documentation is put in place with and executed by proposed provider(s) before the commencement of the required supplies, services or works Given that the proposed programme and expenditure period extend beyond the current mayoral term officers must also observe the principle that an incumbent administration should not unreasonably fetter the discretion of any future administration, ensuring that its and all relevant documentation are structured so as to enable the GLA to terminate funding and supporting contractual arrangements at any point for convenience and milestones and payments should be structured so as to minimise the impact of the exercise of such termination rights.
13 19 Next steps 19.1 The next steps following consideration/in-principle approval by IPB on 10 December are summarised below: Activity Timeline Investment and Performance Board approval 19 January 2016 Mayoral approval 25 January 2016 Develop website and marketing materials Develop T&Cs, vouchers and on-line administration system and back-end system to link with electronic payment of vouchers w/c 25 January 2016 w/c 25 January 2016 Agree contract 29 January 2016 Agree works scope and delivery timetable and mobilise core project team 29 January 2016 Convene and prepare market and trade bodies 1 February 2016 Annoucement and lauch of boiler scrappage scheme 1 5 Febaruary 2016 Scheme close 18 April 2016 (NB: indicative date) Appendices: Appendix 1 Appendix 1 GLA Economics Appendix 2 DECC s boiler scrappage scheme Appendix 3 Proposed eligible technologies Appendix 4 Application and claim process flow chart Appendix 5 Stage 1 and 2
Domestic energy consumption in Barnet has reduced but remains higher than the British average:
HOME ENERGY EFFICIENCY ACT (HECA) RETURN LB BARNET 31ST MARCH 2013 The following report sets out the energy conservation actions being or proposed to be taken by London Borough of Barnet that it considers
Warmer Healthier Homes: A Consultation Paper on a new Fuel Poverty Strategy for Northern Ireland
Warmer Healthier Homes: A Consultation Paper on a new Fuel Poverty Strategy for Northern Ireland A Response by the Chartered Institute of Housing in Northern Ireland September 2010 The Chartered Institute
THE POWER TO BUILD YOUR BUSINESS
THE POWER TO BUILD YOUR BUSINESS FIND out how our products and services can power your business to success the power behind your business who we are NICEIC and ELECSA are leading voluntary regulatory bodies
GREEN DEAL Saving money by understanding the Energy Agenda. Dave Princep BSc LLB MCIEH
GREEN DEAL Saving money by understanding the Energy Agenda Dave Princep BSc LLB MCIEH Energy Efficiency Energy Efficiency What a difference a years makes! Energy Efficiency 2010 Energy Efficiency 2011
Energy Efficient Homes Package
Energy Efficient Homes Package Solar Hot Water Rebate Applicant Information Booklet The Australian Government's $3.9 billion Energy Efficient Homes Package aims to improve the energy rating of Australian
SAP 2012 IN A NUTSHELL
SAP 2012 IN A NUTSHELL The consultation version of the SAP 2012 methodology was published by the Department of Energy and Climate Change (DECC) on January 4th 2012. This article from Dyfrig Hughes of National
Feed in Tariffs for Microgeneration. Jos Mister Energy Saving Trust
Feed in Tariffs for Microgeneration Jos Mister Energy Saving Trust Funding and Finance Feed in Tariffs Clean Energy Cashback April 2010 Renewable Heat Incentive April 2011 Business support Enhanced Capital
APPENDIX B - PL1 Homes that meet people s needs and aspirations
APPENDIX B - PL1 Homes that meet people s needs and aspirations Decent and accessible homes are vital to all. Our focus on providing affordable homes is being progressed primarily through the Affordable
A Strategic Approach to Housing Asset Management
Housing A Strategic Approach to Housing Asset Management www.milton-keynes.gov.uk/housing-mkc 0 A Strategic Approach to Housing Asset Management Contents Page 1. Introduction 1 2. Developing a New Set
Energy Performance Certificate
Energy Performance Certificate 0 Raleigh Drive CULLOMPTON EX15 1FZ Dwelling type: Date of assessment: Date of certificate: Reference number: Type of assessment: Total floor area: Semi detached house 09
LHT S ASSET MANAGEMENT STRATEGY 2015-20. It s My Home
LHT S ASSET MANAGEMENT STRATEGY 2015-20 It s My Home 0 ASSET MANAGEMENT STRATEGY 2015-20 It s My Home Contents Page No 1. WHAT DOES OUR ASSET MANAGEMENT STRATEGY AIM TO DO? 2 2. WHY IS ASSET MANAGEMENT
GENERATING YOUR OWN ENERGY. A planning guide for householders, communities and businesses
GENERATING YOUR OWN ENERGY 1 1 A planning guide for householders, communities and businesses Climate change is happening now We know that innovations such as the internet and mobile phones have transformed
Private Sector Landlords. Making your properties more energy efficient
Making your properties more energy efficient 2 3 Improving the energy performance of your properties in Scotland As a landlord you will be aware that the energy performance of housing has become increasingly
Gravesham Borough Council. Leader of the Executive
Classification: Key Decision: Part 1 Public Yes Gravesham Borough Council Report to: Leader of the Executive Date: 18 January 2013 Reporting officer: Subject: Kevin Burbidge, Director (Housing and Regeneration)
Domestic Green Deal and Energy Company Obligation in Great Britain, Monthly report
Domestic Green Deal and Energy Company Obligation in Great Britain, Monthly report Statistical release: Experimental statistics 19 December 2013 Crown copyright 2013 You may re-use this information (not
Waltham Forest 2009-2011. Private Sector Housing. Renewal Assistance. Policy. Author: [email protected]
Waltham Forest Private Sector Housing Renewal Assistance Policy 2009-2011 Author: [email protected] 1 Contents Page 1. Introduction and background 3 1.1 Tenure Mix in The Borough 3 1.2
A housing stock fit for the future: Making home energy efficiency a national infrastructure priority
A housing stock fit for the future: Making home energy efficiency a national infrastructure priority The benefits of home energy efficiency Reduce carbon emissions Energy efficiency can reduce carbon emissions
Cabinet Sub Group - Performance Board
Cabinet Sub Group - Performance Board Part 1 1 November 2012 Item No 4 Subject Purpose Author Ward Summary Fuel Poverty To provide Performance Board with an outline of what constitutes Fuel Poverty and
KIRKLEES. Visions and Strategies related to Energy and Climate Issues
KIRKLEES Visions and Strategies related to Energy and Climate Issues In recognition of the urgency of climate, the UK Government has committed to take action now and has introduced the Climate Change Act
QUALITY OF SERVICE DISCRETIONARY REWARD SCHEME GAS DISTRIBUTION NETWORK OPERATORS ENTRY FORM
QUALITY OF SERVICE DISCRETIONARY REWARD SCHEME GAS DISTRIBUTION NETWORK OPERATORS ENTRY FORM Please note that the deadline for receipt of applications is 5pm, 15 May 2009. GDN DETAILS: (please complete)
Introduction to the London Energy Efficiency Fund (LEEF)
Executive Summary Introduction to the London Energy Efficiency Fund (LEEF) 1. The London Green Fund (LGF) is a 100m Fund comprising of 50m from the London 2007-13 European Regional Development Fund (ERDF)
tap into opportunities to develop your business
Find out more about the Green Deal, ECO and renewable energy markets and how your business can benefit tap into opportunities to develop your business Background and overview Over recent years, the UK
(92 plus) (81-91) (69-80) (55-68) (39-54) (21-38) (1-20)
Energy Performance Certificate Georgia House Stud Bradley Road Burrough Green NEWMARKET CB8 9NH Dwelling type: Detached house Date of assessment: 17 August 2011 Date of certificate: 17 August 2011 Reference
Domestic energy bills and costs of implementing environmental measures
Domestic energy bills and costs of implementing environmental measures The Sustainable Development Commission has analysed household electricity and gas bills to show the contribution of the additional
Department of Energy South Africa
Department of Energy South Africa Policy to support the Energy Efficiency and Demand Side Management Program for the Electricity Sector through the Standard Offer Incentive Scheme 20 May 2010 1 TABLE OF
The Real Estate Loan and Equity Release Schemes
Housing Assistance Policy (Loans) 1 1.0 Introduction...3 2.0 Background...3 3.0. Research into the potential demand for equity release / loan schemes...4 4.0. The loan scheme...5 5.0 Eligibility for grant
Carbon Management Plan
E-2015-02-02 Addendum Carbon Management Plan Date: 14 May 2014 Owners: Approval: K.W.Bullimore & M.Sackett A.Burrell Executive Summary This document sets out the Carbon Management Plan (CMP) for The Open
Solar Power Frequently Asked Questions
General information about solar power 1. How do I get solar power? Solar Power Frequently Asked Questions Many companies install solar power systems including some electricity retailers. It is worth comparing
PRIVATE SECTOR HOUSING RENEWAL POLICY
Background and Local Context PRIVATE SECTOR HOUSING RENEWAL POLICY This Policy is published in response to the New Regulatory Reform Order 2002. The overall picture presented by Woking Borough Council
Your guide to the Energy Company Obligation (ECO) How we can make it work for you. A5_ECOguide_AW.indd 2 24/10/2012 16:04
Your guide to the Energy Company Obligation (ECO) How we can make it work for you A5_ECOguide_AW.indd 2 24/10/2012 16:04 Energy Company Obligation guide 2 Your ECO Partner The current Carbon Emissions
Saving energy, growing jobs
Saving energy, growing jobs Victoria s energy efficiency and productivity statement June 2015 Contents Minister s foreword 1 Why energy efficiency matters for Victorians 2 Our plan for energy efficiency
UK-London: IT services: consulting, software development, Internet and support 2011/S 165-273114 CONTRACT NOTICE. Services
1/6 This notice in TED website: http://ted.europa.eu/udl?uri=ted:notice:273114-2011:text:en:html UK-London: IT services: consulting, software development, Internet and support 2011/S 165-273114 CONTRACT
The Energy Saving Trust s community solar programme How your community can benefit from discounted solar panels and Feed-in Tariffs
The Energy Saving Trust s community solar programme How your community can benefit from discounted solar panels and Feed-in Tariffs 1 Introduction Feed-in Tariffs have arrived, which means there has never
An offer to extend Right to Buy discounts to housing association tenants
An offer to extend Right to Buy discounts to housing association tenants This document sets out the terms of an offer the National Housing Federation has made to the Government for a potential agreement
6 YEAR * PAYBACK A GUIDE TO DOMESTIC RENEWABLE HEAT INCENTIVE (RHI) SOLAR THERMAL SOLUTIONS
6 YEAR * PAYBACK A GUIDE TO DOMESTIC RENEWABLE HEAT INCENTIVE () SOLAR THERMAL SOLUTIONS RENEWABLE HEAT INCENTIVE KINGSPAN SOLAR RENEWABLE HEAT INCENTIVE () EXPLAINED The Renewable Heat Incentive is intended
MAKING YOUR HOME WARMER
MAKING YOUR HOME WARMER INTRODUCTION This guide has been written to help householders take the first steps to improving the homes they rent or own, making them warmer and cosier to live in, and less expensive
Special Report on Fuel Poverty
UK GENERAL ELECTION 2015 Special Report on Fuel Poverty Supported by Introduction Energy Action Scotland is the national charity working for warm, dry homes and an end to fuel poverty in Scotland. With
Investment & Performance Board (IPB)
Investment & Performance Board (IPB) Date of meeting: 19 January 2016 Title of paper: Developing a New Junior Electricity Supply Licence - Progress Report To be presented by: Cleared by: Classification:
Danish-German Energy Efficiency Summit. Cost effective policy instruments Obligations on Energy Companies
Danish-German Energy Efficiency Summit Cost effective policy instruments Obligations on Energy Companies Eoin Lees Senior Advisor RAP Europe 8 th February 2012 The Regulatory Assistance Project 48 Rue
Energy efficiency and excess winter deaths: Comparing the UK and Sweden
Westgate House 2a Prebend Street London N1 8PT 020 7359 8000 [email protected] Energy efficiency and excess winter deaths: Comparing the UK and Sweden November 2013 1 Introduction David Cameron pledged in
First Fix Leak Repair Scheme
Irish Water First Fix Leak Repair Scheme For Domestic Water Customers CER Consultation Public Submissions: Irish Water Response Submission to the CER Reg_PP_IW_FFLRS_003 31/07/15 1 Introduction This document
H 7. Factoring Policy. If you require this policy in a different format please ask a member of staff. Date of Approval Oct 12 Review Due Dec 15
H 7 Factoring Policy If you require this policy in a different format please ask a member of staff Date of Approval Oct 12 Review Due Dec 15 1.0 The Association s Objective 1.1 Elderpark Housing Association
Energy usage in households with Solar PV installations
Energy usage in households with Solar PV installations Background The National Energy Efficiency Data-Framework (NEED) is produced and published by DECC to provide detailed information on annual electricity
A Landlord s Guide to Housing Benefit
A Landlord s Guide to Housing Benefit October 2009 A landlord s guide to Housing Benefit; Table of Contents Introduction...3 Standards Of Service...3 Processing Housing Benefit Claims...3 Changes in circumstances...3
A guide to energy performance certificates for the Construction, sale and let of non-dwellings
A guide to energy performance certificates for the Construction, sale and let of non-dwellings Preface This document is intended to give a simplified overview of Commercial Property Energy Certification.
Growing the Green Economy
Growing the Green Economy Labour Green Economy Paper.indd 1 05/02/2016 17:44 Our Plan Establish a green infrastructure fund worth 1bn. We recognise the need to fund immediate action on climate change.
CHESTERFIELD BOROUGH COUNCIL PRIVATE SECTOR HOUSING RENEWAL STRATEGY DRAFT FOR CONSULTATION
CHESTERFIELD BOROUGH COUNCIL PRIVATE SECTOR HOUSING RENEWAL STRATEGY 2012 2015 DRAFT FOR CONSULTATION October 2011 CONTENTS 1. Introduction 2. Links to other corporate strategies and policies 3. Policy
Electricity Settlements Company Ltd Framework Document
Electricity Settlements Company Ltd Framework Document This framework document has been drawn up by the Department of Energy and Climate Change in consultation with the Electricity Settlements Company.
The Green Deal & ECO 8 Months In
The Green Deal & ECO 8 Months In Presentation to Yorkshire Energy Services Event Richard Mellish, DECC 2 October 2013 Green Deal energy savings help pay for home improvements Green Deal helps people and
Energy Performance Certificate
Energy Performance Certificate Flat 307 Windsor House Cumberland Market LONDON NW1 4DE Dwelling type: Date of assessment: Date of certificate: Reference number: Total floor area: Mid-floor flat 8361-6824-6900-7049-8026
Generating your own ENERGY. A planning guide for householders, communities and businesses
Generating your own ENERGY 1 1 A planning guide for householders, communities and businesses Climate change is happening now Climate change is one of the biggest challenges facing the world and one that
Using Less Energy: Nova Scotia s Electricity Efficiency and Conservation Plan
Using Less Energy: Nova Scotia s Electricity Efficiency and Conservation Plan April 2014 Contents Summary...1 Introduction...2 Objectives of the Plan...3 Plan of Action...5 The Benefits of Energy Efficiency...
THE RECOVERY OF CAPITAL GRANT
THE RECOVERY OF CAPITAL GRANT A consultation on proposals for a revised determination 2015 January 2015 Contents CONTEXT... 3 KEY PROPOSALS FOR CHANGE... 5 THE DETAIL ON AREAS FOR CONSIDERATION... 6 TIMETABLE...
Information Guide Domestic Air Source Heat Pumps
Information Guide Domestic Air Source Heat Pumps Issue 41 Domestic Air Source Heat Pumps This is an independent guide produced by Mitsubishi Electric to enhance the knowledge of its customers and provide
GREEN EFFICIENT FRIENDLY SUSTAINABLE ENERGY: CERTIFICATED TRAINING
GREEN EFFICIENT FRIENDLY SUSTAINABLE ENERGY: CERTIFICATED TRAINING Petroc is putting its energy into renewables and sustainable technologies. Are you? Petroc has developed Environmental Technologies CoVE
Economic impacts of expanding the National Insurance Contributions holiday scheme Federation of Small Businesses policy paper
Economic impacts of expanding the National Insurance Contributions holiday scheme Federation of Small Businesses policy paper Overview This research paper sets out estimates for the economic and employment
Information Guide. The Application of Heat Pump Boilers. Issue Eighteen >
Information Guide The Application of Heat Pump Boilers Issue Eighteen > The Application of Heat Pump Boilers Information Guide This is an independent guide produced by Mitsubishi Electric to enhance the
Section 1 Summary and Recommendations
REPORT FOR: CABINET Date of Meeting: 10 December 2015 Subject: Key Decision: Responsible Officer: Portfolio Holder: Exempt: Decision subject to Call-in: Wards affected: Homes for Harrow: Building homes
Energy Performance Certificates (EPCs) and renting homes: A landlord s guide
Energy Performance Certificates (EPCs) and renting homes: A landlord s guide From 1 October 2008 landlords are required to provide an Energy Performance Certificate when they rent out a home. An Energy
Council Tax and Housing Benefit Overpayments Vale of Glamorgan Council
September 2010 Authors: Margaret Griffiths and Jayne Power Ref: 426A2010 Council Tax and Housing Benefit Overpayments Vale of Glamorgan Council Good arrangements helped the Vale of Glamorgan Council overpay
LANDLORDS FORUM MEETNG NOTES OF MEETING HELD ON 12 TH JUNE 2002
LANDLORDS FORUM MEETNG NOTES OF MEETING HELD ON 12 TH JUNE 2002 Introduction Marc Williams, Senior Environmental Health Officer, Wrexham County Borough Council opened the 3 rd Landlords Forum and gave
How To Manage Property In Tower Hamlets
2015 2020 Page 1 of 15 Contents 1 Introduction 2 What is Asset Management 3 Limitations 4 THCH Asset Profile 5 How the Asset Management Strategy Supports THCH s Strategic Priorities 6 How The Asset Management
Siemens and The Carbon Trust The Free Money Deal. Free Money. Money doesn t grow on trees. But it does now grow on roofs and in boiler houses.
Siemens and The Carbon Trust The Free Money Deal Free Money Money doesn t grow on trees. But it does now grow on roofs and in boiler houses. Under this delicious funding scheme sponsored by Siemens and
SP Energy Networks 2015 2023 Business Plan
SP Energy Networks 2015 2023 Business Plan Updated March 2014 Annex Heat pump and energy efficiency scenarios Frontier Economics 41 January 2014 1 Frontier Economics January 2014 Confidential Heat pump
Ecodan Air Source Heat Pump and Flow Temperature Controller 2
HOMEOWNER STANDALONE Homeowner Information SEPTEMBER 2011 Ecodan Air Source Heat Pump and Flow Temperature Controller 2 Ecodan Air Source Heat Pump Model Number PUHZ-W50VHA(2)-BS PUHZ-W85VHA(2)-BS PUHZ-HW140VHA(2)-BS
Help to Buy. House Builder and Developer Participation Guidance. July 2014. Page 1 of 15
Help to Buy House Builder and Developer Participation Guidance July 2014 Page 1 of 15 Contents Ministerial Foreword page 3 Introduction... page 4 Help to Buy overview... page 5 Help to Buy registration...
AGENDA ITEM: 8 SUMMARY
AGENDA ITEM: 8 SUMMARY Report for: Housing and Community Overview and Scrutiny Committee Date of meeting: 28th January 2015 PART: 1 If Part II, reason: Title of report: Contact: Purpose of report: Recommendations
EI Data Service useful information: DSI20 UK & EU energy initiatives & legislation factsheet
EI Data Service useful information: DSI20 UK & EU energy initiatives & legislation factsheet Updated September 2012 Consumer Initiatives I Business Initiatives I UK legislation I EU legislation & initiatives
Electricity Market Reform:
Electricity Market Reform: Consultation on Low Carbon Contracts Company s and Electricity Settlements Company s operational costs 2015/16 Government Response January 2015 Crown copyright 2015 URN 15D/001
