1 CSBI TIMELINE TOOL A TOOL FOR ALIGNING TIMELINES FOR PROJECT EXECUTION, BIODIVERSITY MANAGEMENT AND FINANCING CROSS- SECTOR BIODIVERSITY INITIATIVE DECEMBER
2 The Cross Sector Biodiversity Initiative (CSBI) is a partnership between the International Council on Mining and Metals (ICMM), IPIECA, the global oil and gas industry association for environmental and social issues, and the Equator Principles Association. The initiative aims to develop and share good practices for the effective application of the new International Finance Corporation (IFC) Performance Standard 6 on Biodiversity Conservation and the Sustainable Management of Living Natural Resources. The aim of the CSBI is to bring together industry in order to share experiences as part of a culture of learning and continuous improvement. Disclaimer This publication has been developed to support the implementation of CSBI s mission and vision. Whilst every effort has been made to ensure the accuracy of the information, it is intended to provide general guidance only. It is not designed to provide legal or other advice, nor should it be relied upon as a substitute for appropriate technical expertise or professional advice. All attempts have been made to ensure the information is correct at of the date of publication. This publication does not constitute a mandatory commitment which members of CSBI are obliged to adopt. The views and conclusions expressed herein do not necessarily reflect the views of all CSBI members or the individuals, companies and institutions that contributed to this publication. While reasonable precautions have been taken to ensure that the information contained in this publication is accurate and timely, this publication is distributed without warranty of any kind, express or implied. CSBI does not endorse or accept responsibility for the content or availability of any website referred to, or linked to, in this publication. The responsibility for the interpretation and use of this publication lies with the user and in no event will CSBI nor any of its members past present or future regardless of its or their negligence, assume liability for any foreseeable or unforeseeable use made thereof, which liability is hereby excluded. Consequently, such use is at the recipient s own risk on the basis that any use by the recipient constitutes agreement to the terms of this disclaimer. This disclaimer should be construed in accordance with the laws of England. 2
3 1. ABOUT THIS TOOL This indicative timeline tool has been designed to assist staff involved in extractive project planning to better align project development, biodiversity impact management, and financial timelines and milestones. Its purpose is to provide a roadmap that helps identify key milestones and interdependencies between project development and financing timelines and the actions required to apply the mitigation hierarchy. It is not intended to be prescriptive, but rather to raise awareness of the operational challenges associated with biodiversity impact mitigation. The timeline tool may also be used as an internal capacity building resource or communications tool as it aims to support the work of a variety of people involved in project planning and execution. The intended target audience is staff involved in project planning (project managers, HSE advisors, environmental consultants, financial advisors, lenders). The tool was developed as a product of the Cross Sector Biodiversity Initiative. Other products in development include a catalogue of biodiversity mitigation options and guidance for biodiversity baseline surveys. 2. BACKGROUND AND INTRODUCTION The practices for managing potential biodiversity impacts from project development have evolved over the years with ever increasing focus on achieving positive conservation outcomes. The updated IFC Performance Standard 6 (PS6, 2012) provides a new benchmark. In PS6 the Mitigation Hierarchy is a central concept. It explains that actions should be taken to anticipate and avoid, or where avoidance is not possible, minimize and restore, and, where residual impacts remain, offset for risks and impacts to biodiversity. PS6 differentiates between Modified versus Natural habitats and distinguishes areas with high biodiversity value as Critical Habitat. PS6 provides end-goals for projects in Natural Habitat (aim to achieve No Net Loss) and Critical Habitat (must achieve Net Positive Impact). Net Positive Impact can be defined as a target for project outcomes in which the potential impacts on biodiversity from the project are outweighed by the actions taken, in accordance with the mitigation hierarchy, to achieve net gains for biodiversity. Appendix 1 provides more background on the definition of Critical Habitat. An issue where guidance is lacking is when actions to manage potential biodiversity impacts should occur relative to the overall project schedule. A key challenge in managing these is the alignment between (internal) project development timelines, and with (external) financing timelines. The exact timing of impact management actions and alignment with project and financing timelines may vary from project to project and often do not align perfectly, but this timeline tool provides an illustration as to how the timelines could be aligned in order to effectively manage risk and uncertainty. It consists of a graphic with the three timelines and major activities and milestones, along with a table and glossary with more detail on some of these activities and terms. 3
4 3. VARIABILITY IN ALIGNMENT OF TIMELINES PROJECT & MITIGATION TIMELINES During the various stages of extractive project development, decisions are made about project site selection, design concepts, facility locations, technology choices and impact mitigation measures. These decisions aim to minimize project risks and uncertainties and require input from both the project design perspective as well as the environmental management (biodiversity) perspective. At the beginning of the project there will be uncertainty on both the project design and the environment (see Appendix 2). This uncertainty is reduced through efforts to increase knowledge of the environment which then informs project related location and design decisions. However, the elimination of all risk and uncertainty before construction begins is generally not possible. KEY MESSAGES This tool is not prescriptive but intended to illustrate the link between project development, biodiversity mitigation planning, and financing timelines The appropriate timing of risk management actions and alignment with project and financing timelines must be made on a case-by-case basis. Biodiversity mitigation efforts should be front-loaded based on risk and uncertainty. Risk and uncertainty should be reduced to the extent possible before construction occurs, as well as before financing is sought or secured. FINANCING & MITIGATION TIMELINES A similar alignment challenge exists between the financiers need for information and the project and biodiversity impact management timelines. Ideally, all risks should be identified and mitigated (or planned to be mitigated) before financing contracts are signed, but that is often not possible. Front-end loading can reduce risks earlier, but comes at a financial cost and cannot pre-empt certain project decisions. If there is high risk and/or uncertainty related to potential environmental impacts, additional mitigation actions may need to be front-end loaded prior to commencement of construction and financial close. Financial institutions engage with project sponsors at different times in the project development process and have different roles with different leverage (see Appendix 3 for financing process). The financial institutions with the greatest leverage are called Mandated Lead Arrangers (MLAs) and provide capital for the project in the form of debt. MLAs are typically not involved with a project until much later in the process after many crucial decisions are made about biodiversity mitigation, including confirmation of habitat type (modified/natural/critical), biodiversity baseline identification, and application of the mitigation hierarchy. Once MLAs are involved, they may identify potentially time-consuming gaps to be filled before financial close. At a minimum, they will expect project sponsors to demonstrate technical and political feasibility of biodiversity impact mitigation, particularly if offsets are required (see Appendix 2 for explanation of feasibility stages). As a result, it is key that project sponsors initiate work related to the management of biodiversity impacts as early as possible in the project development process. In that respect, the Financial Advisor can play an important role. Front-end loading detailed and time-intensive biodiversity studies and assessments can greatly help in reducing the risks of project delays at the MLA selection stage, or of having financial institutions declining to participate in a transaction because of biodiversity-related concerns. 4
5 4. ILLUSTRATIVE ALIGNMENT OF TIMELINES 5
6 Year PROJECT TIMELINE BIODIVERSITY MITIGATION TIMELINE FINANCING TIMELINE 0-4 Opportunity Identification / Exploration This phase can take long and includes Exploration, which may include separate biodiversity mitigation and permitting. In many cases Exploration may not lead to full project development. Acquire claims/leases/ exploration concession (right to explore and/or develop) Demonstrate that the opportunity realistically has potential to realize commercial value. Assess realistic range of development concepts and demonstrate feasibility. Establish key risk factors. Prepare pre-feasibility and/or company specific deliverables. Screen environmental risks Identify environmentally sensitive areas and potential project cost implications Conduct screening to inform avoidance and minimization actions and identify baseline assessment needs. Develop environmental profile (e.g. critical habitat, protected areas, current threats, legislation, environmental constraints, etc.). Assess habitat type: Modified/ Natural/Critical (e.g. screen using IBAT) Engage financial advisor Determine whether external financing will be utilized, this could include project financing or corporate loans for a project. AVOID / MINIMISE 0-2 Select Complete advanced exploration. Evaluate options/choose preferred development concept, including site selection. Complete scoping, pre-feasibility and feasibility studies. Start baseline studies Confirm habitat type: Modified/ Natural/Critical. Prepare ESHIA scope and tender process (include lender requirements for No Net Loss (NNL)/Net Positive Impact (NPI)). Conduct risk assessment to determine if biodiversity impacts can be mitigated towards NNL/NPI of biodiversity values. Initiate impact assessment at the end of this phase. Identify financing strategy Mandate financial advisor. Develop environmental/financing timeline (including targets for closure on deliverables). Prepare information memorandum. 6
7 Year PROJECT TIMELINE BIODIVERSITY MITIGATION TIMELINE FINANCING TIMELINE AVOID / MINIMISE 1-3 Define Provide project specification, design base and execution plan to deliver sufficient value versus risk for investment decision. Include output from EHSIA process, e.g. mitigation options Front-end load Engineering and Design. Start ESHIA process Finalize detailed baseline studies. Assess potential impacts and design mitigation options as per mitigation hierarchy (avoid/minimize/restore/ offset) Quantify potential residual impacts to determine the need for offsets. Identify and assess potential offset options. Develop ESHMP and BAP, including mitigation actions, offset and compensation design, agreed with project team and stakeholders. Mandate lead arrangers and define deliverables Finalization of legal loan documentation between lenders and project, including establishment of Force Majeure clauses and penalty clauses. ESHMP included in Project Design and Execution Plan. Complete ESHIA, including ESHMP and BAP Develop offset governance and management mechanisms, including funding. Offsets should be at least technically feasible and covenanted including fallback options. Obtain societal acceptance/ license to operate. Environmental and Social Due Diligence/ Equator Principles Review Determine technical and political feasibility of offset. Develop formal offset agreements and fallback position. Obtain permits. Obtain permits Finalize terms & conditions within loan documentation Financial close AVOID / MINIMISE Final investment Decision 7
8 Year PROJECT TIMELINE BIODIVERSITY MITIGATION TIMELINE FINANCING TIMELINE 2-5 Execute / Construction Complete detailed design and construction. Deliver a safe and operable facility that is both within budget and the agreed timeline. Implement ESHMP and BAP Begin monitoring of environmental impacts Start offset implementation First Disbursement Initiate in parallel with offset milestones. Check Environmental and Social Condition Precedents to First Disbursement. Commissioning Hand-over from construction to operations. Commencement of operations/ ramp-up to full production. Ongoing impacts monitoring and offset implementation Compliance monitoring AVOID / MINIMISE / RESTORE / OFFSET 5-40 Operate Monitor progress towards NNL/NPI Compliance monitoring Safe and proficient production. Start of progressive closure in some cases Consider additional mitigation actions if mitigation goals are not being met Until end of lender involvement. AVOID / MINIMISE / RESTORE / OFFSET End Abandonment/Reclamation and Closure Conduct safe and effective cessation of activities. Achieve NNL/NPI Ensure gains last as long as impacts and preferably in perpetuity Compliance monitoring Until end of lender involvement. Planning and management of long-term liabilities. AVOID / MINIMISE / RESTORE / OFFSET 8
9 APPENDIX 1. CRITICAL HABITAT The concept of Critical Habitat is used by the IFC to define those ecosystems which are most valuable for Biodiversity. Critical habitats are areas with high biodiversity value, including (i) habitat of significant importance to Critically Endangered and/or Endangered species; (ii) habitat of significant importance to endemic and/or restricted-range species; (iii) habitat supporting globally significant concentrations of migratory species and/or congregatory species; (iv) highly threatened and/or unique ecosystems; and/or (v) areas associated with key evolutionary processes¹. This critical habitat definition is in line with criteria captured from a wide range of definitions of priority habitat for biodiversity conservation in use by the conservation community and incorporated in related governmental legislation and regulations. Critical habitats are areas of high biodiversity value that may include at least one or more of the five values above and/or other recognized high biodiversity values. Critical habitat is identified irrespective of the type or scale of the development or impact. This means that its definition is based on biodiversity of the area, not the impacts from a project. Critical habitat is an inherent property of an area. Guidance Note 6 of IFC provides more detailed guidance on the definition and the process to determine whether an area qualifies as Critical Habitat. Access IFC Guidance Note 6: ¹ Source: IFC Performance Standard 6,
10 APPENDIX 2. UNCERTAINTIES IN MANAGING BIODIVERSITY RISKS The following are examples of uncertainties in managing biodiversity risks that may require additional or earlier timing of activities. Data deficiencies related to assessing biodiversity value (e.g. insufficient or absent baseline data; lack of data on seasonality, species/habitat distribution, or population size; new-to-science species) Data deficiencies related to biodiversity trends and pressures (i.e. background rate of increase/decrease and causal factors) Data deficiencies related to identification of mitigation options, including availability of offset sites Technical uncertainties related to mitigation options (e.g. untested methodology or approach) Climate change effects and unforeseen natural disasters Political uncertainties, including legal mechanisms for securing offsets, land tenure, etc. Financial uncertainties, including costs of mitigation to achieve no net loss of biodiversity Uncertainties can be determined using a mitigation feasibility analysis. Biodiversity mitigation options can be filtered in three ways: theoretical, technical, and political feasibility. The number of options for actions will decrease as they are assessed for theoretical, technical, and political feasibility. The level of uncertainty will also decrease as each type of feasibility is determined. Adapted from The Biodiversity Consultancy, 2012 As indicated in the timeline illustration and the table, offset selection, design and implementation can take a long time and will usually not be completed before start of construction. The objective should be to minimize uncertainty about the offset outcomes by selecting options that are at least technically and politically feasible as agreed with relevant stakeholders and includes a fall-back option as appropriate. If that is not possible in the timeframe of the project, the associated uncertainty needs to be assessed. 10
11 APPENDIX 3. FINANCIAL PROCESS ENGAGE FINANCIAL ADVISOR The finance process often begins early with the hiring of a financial advisor to evaluate and structure optimal financing solutions for the project. The financial structure may include a combination of commercial bank debt, multilateral and bilateral institutional support, equity financing, and/or credit enhancement. Many Equator Principles (EP) Financial Institutions now differentiate themselves as financial advisors with the capacity to ensure companies structure their projects so that they can successfully access the EP-covered financial market. Financial advisory services may include assistance with developing the Terms of Reference for a bankable ESHIA, hiring consultants with experience applying international standards, and advising on lender expectations related to biodiversity issues that may require long lead times to address before the project is bankable. SELECT MANDATED LEAD ARRANGERS (MLAS) Once the financial structure is decided, the financial advisor will assist the project sponsors in developing a Request for Proposal (RfP) for Mandated Lead Arrangers. MLAs lead the financing by committing to raise the complete commercial debt amount in the financial markets. MLAs will typically provide a portion of the debt themselves, and then pass along the rest of the debt, and hence the risk, to other lenders (called Participants). The process of selling the debt to other banks is called syndication. MLAs enter the project cycle at a later stage than the financial advisor (typically after the ESHIA is prepared), and therefore, may not have the same opportunity to influence biodiversity planning early on. However, MLAs play a leading role in the financing process, and as part of their due diligence process, they may require project sponsors to address gaps in biodiversity assessment and planning prior to financial close. This can and often does lead to delays in financing if long lead times are required. In some extreme cases, financial institutions approached on a project (to participate either as MLA or as Participant) can decline the offer because of key risks and impacts (e.g. on biodiversity) not being appropriately taken into account, with no clear prospect for improvement. This can also be a financial risk for the project sponsors. ENVIRONMENTAL AND SOCIAL DUE DILIGENCE/ EQUATOR PRINCIPLES REVIEW Once MLAs are appointed, the environmental and social due diligence begins, including the EP review, if applicable. When there is a group of banks, one will coordinate the due diligence process on behalf of the whole lender group. This coordination role can be assumed by a bank already bearing a coordination role such as the arranger or the technical bank or agent. In some cases, where the environmental and social impacts are significant, a separate role will be created called the Environment bank or agent. From 2014 onwards the application of EP will prompt the appointment of an EP bank or agent where the scale of environmental and social impacts requires it and EP banks feel a need to discuss problematic issues. The agent or bank in charge of coordinating the process will prepare a scope of work for the due 11
12 diligence and manage the RfP process for selecting an independent engineer or Lenders Independent Environmental and Social Consultant (IESC) sometimes with qualified biodiversity experts (if one has not already been appointed, by the financial advisor for example). In some cases, specialized biodiversity expertise, potentially with knowledge and experience on biodiversity offsets, may need to be contracted separately. It is therefore very important to identify the project s risks and potential impacts as early as possible, in order to plan accordingly. The due diligence process concludes with a due diligence report prepared by the Independent Engineer or the IESC that assesses the project plans against the IFC Performance Standards, and outlines actions that need to be taken to ensure compliance is achieved over time. For projects impacting natural or critical habitat, the IFC Performance Standard 6 requires project sponsors to develop mitigation measures to achieve no net loss (where feasible) or net positive gain of biodiversity, respectively. FINALIZE TERMS AND CONDITIONS WITHIN LOAN DOCUMENTATION Under the Equator Principles, project loan agreements must include a covenant to comply with the Environmental, Social, and Health Management Plan (ESHMP) and the Equator Principles Action Plan (EPAP, where applicable). An EPAP is usually prepared when any gaps or non-compliances with the IFC Performance Standards have been identified. The EPAP outlines time-bound actions to achieve compliance with the IFC Performance Standards, and the deadlines for completing each action may be specified as a date or prior to financing milestones such as project completion or first disbursement. With the inclusion of a positive covenant in the loan agreement, the EPAP becomes a contractually binding document. MONITORING AFTER FINANCIAL CLOSE Lenders will usually require on-site monitoring and reporting of compliance with the environmental terms and conditions outlined in the loan agreement, and for sensitive projects subject to the Equator Principles such monitoring is systematically required. The monitoring frequency depends on the complexity of the project but is typically quarterly during the construction phase and annually during operations through the life of the loan. When restoration and/or offset implementation is required to achieve no net loss or net positive gain of biodiversity, compliance with the IFC Performance Standard 6 may take significantly more time than lender (or even project sponsor) involvement. In these cases, lenders and project sponsors should consider long-term funding mechanisms and governance structures for oversight and management of restoration and/or offset measures. 12
13 APPENDIX 4. GLOSSARY Biodiversity Action Plan (BAP): A plan to manage potential risks to changes in biodiversity or ecosystems services arising from environmental aspects of assets and activities; it lists the actions to take to conserve or enhance biodiversity. Covenant: the promises made by the Borrower to undertake certain actions (positive covenant) or to refrain from taking certain actions (negative covenant). Condition precedents: a set of pre-conditions that must be satisfied before the borrower can request drawdown, or before other credit facilities can be made available under a loan agreement. Conditions Precedent can be used to require borrowers to make certain progress on environmental and social issues before disbursement. Environmental, Social & Health Impact Assessment (ESHIA): A methodology to identify and assess the environmental, social and health impacts of a proposed project. It involves evaluating alternatives and identifying measures for mitigation, or enhancement, management and monitoring environmental (including biodiversity), social, socio-economic, public and community health impacts. Environmental, Social & Health Management Plan (ESHMP): In the context of ESHIA a list of the commitments made by a project to mitigate, manage and monitor identified environmental, social and health issues for the project and the proposed means of achieving them. Equator Principles Review: Process of due diligence review, whereby an independent consultant assesses a project s compliance with the Equator Principles and IFC Performance Standards on behalf of a group of lenders. Front-end loading: Front-end loading includes robust planning and design early in a project's lifecycle (i.e., the front end of a project), at a time when the ability to influence changes in design is relatively high and the cost to make those changes is relatively low. Mitigation Hierarchy: Actions to anticipate and avoid, or where avoidance is not possible, minimize, and, where residual impacts remain, compensate/offset for risks and impacts to the environment (IFC 2012) No Net Loss (NNL): No net loss is defined as the point at which project-related impacts on biodiversity are balanced by measures taken to avoid and minimize the project s impacts, to undertake on-site restoration and finally to offset significant residual impacts, if any, on an appropriate geographic scale (e.g., local, landscape-level, national, regional). (IFC 2012) Net Positive Impact (NPI): NPI or net gains are additional conservation outcomes that can be achieved for the biodiversity values for which the critical habitat was designated. Net gains may be achieved through the development of a biodiversity offset and/or, in instances where the client could meet the requirements of this Performance Standard 6 without a biodiversity offset, the client should achieve net gains through the implementation of programs that could be implemented in situ (on-the-ground) to enhance habitat, and protect and conserve biodiversity. (IFC 2012) Offset: Offsets are measurable conservation outcomes resulting from actions designed to compensate for significant residual adverse biodiversity impacts arising from project development and persisting after appropriate avoidance, minimization and restoration measures have been taken. 13
1. What is a biodiversity offset?
How can BBOP help companies? This document is intended for developers who are considering undertaking a biodiversity offset and may welcome help from the Business and Biodiversity Offsets Programme (BBOP).
REPORTING ON EQUATOR PRINCIPLES IMPLEMENTATION
REPORTING ON EQUATOR PRINCIPLES IMPLEMENTATION YEAR 2014 INTRODUCTION The Equator Principles 1 (EPs) have become the leading financial industry benchmark for determining, assessing and managing environmental
PPP Basics and Principles of a PPP Framework
Note 1 May 2012 PPP Basics and Principles of a PPP Framework This note is the first in a series of notes on developing a comprehensive policy, legal, and institution framework for public-private partnership
13 ENVIRONMENTAL AND SOCIAL MANAGEMENT SYSTEM
13 ENVIRONMENTAL AND SOCIAL MANAGEMENT SYSTEM This ESIA has identified impacts (both positive and negative) to the physical, natural and socio-economic environments, as well as to community and worker
MORGAN STANLEY ENVIRONMENTAL POLICY STATEMENT
MORGAN STANLEY ENVIRONMENTAL POLICY STATEMENT Morgan Stanley recognizes the critical importance of a healthy environment to our global society, our economy, our business and our people. We also realize
PROJECT MANAGEMENT FRAMEWORK
PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to
Agreements, bonds and guarantees
Agreements, bonds and guarantees SPV Formation The Special Project Vehicle (SPV) may take a variety of forms, including a corporation, limited liability company, general partnership, limited partnership,
Risk Management of Outsourced Technology Services. November 28, 2000
Risk Management of Outsourced Technology Services November 28, 2000 Purpose and Background This statement focuses on the risk management process of identifying, measuring, monitoring, and controlling the
Audit summary. 1.1 Introduction
1 Audit summary 1.1 Introduction 1.1.1 Background In November 2007 the Government announced that it had selected a private partner to construct a new Royal Children s Hospital (RCH), on a site immediately
ENVIRONMENTAL AND SOCIAL RISK ASSESSMENT IN LENDING
ENVIRONMENTAL AND SOCIAL RISK ASSESSMENT IN LENDING Barclays has a strong and longstanding commitment to managing the environmental and social risks associated with commercial lending. We recognise that
Goldman Sachs Environmental Policy Framework
Goldman Sachs Environmental Policy Framework Goldman Sachs believes that a healthy environment is necessary for the well-being of society, our people and our business, and is the foundation for a sustainable
The Role of the Lender Common Infrastructure Design and Scoping Issues ESIA: The Management Planning Process Case Study Cross Cutting Themes:
Infrastructure Development, Ecosystem Services and the need for Adaptive Management: An EPFI s Perspective Chris Pullen Export Development Canada IAIA Biodiversity Symposium February 7, 2013 Presentation
Guideline. Records Management Strategy. Public Record Office Victoria PROS 10/10 Strategic Management. Version Number: 1.0. Issue Date: 19/07/2010
Public Record Office Victoria PROS 10/10 Strategic Management Guideline 5 Records Management Strategy Version Number: 1.0 Issue Date: 19/07/2010 Expiry Date: 19/07/2015 State of Victoria 2010 Version 1.0
COMMERCIAL LENDING POLICY DEVELOPMENT GUIDE Minimum Considerations
DRAFT FOR COMMENT Additional Tools: COMMERCIAL LENDING POLICY DEVELOPMENT GUIDE Minimum Considerations Class 2 Institutions April 2013 This document is also available in French. COMMERCIAL CREDIT POLICY
Good Practice Checklist
Investment Governance Good Practice Checklist Governance Structure 1. Existence of critical decision-making bodies e.g. Board of Directors, Investment Committee, In-House Investment Team, External Investment
TO: Chief Executive Officers of National Banks, Federal Branches and Data-Processing Centers, Department and Division Heads, and Examining Personnel
AL 2000 12 O OCC ADVISORY LETTER Comptroller of the Currency Administrator of National Banks Subject: Risk Management of Outsourcing Technology Services TO: Chief Executive Officers of National Banks,
Project Management Guidebook
METHOD 12 3 empowering managers to succeed Project Management Guidebook ISBN 0-473-10445-8 A bout this e-book This e-book was created by Method123 (see www.method123.com) to help provide you with a simple
IBAT (Integrated Biodiversity Assessment Tool)
IBAT (Integrated Biodiversity Assessment Tool) Martin Sneary, Manager Biodiversity Risk Assessment & Corporate Decision Support (based in Washington DC) Format of session Key sources of biodiversity information
COMMERCIAL LENDING POLICY DEVELOPMENT GUIDE Minimum Expectations
Additional Tools: COMMERCIAL LENDING POLICY DEVELOPMENT GUIDE Minimum Expectations Class 2 Institutions February 2014 Ce document est également disponible en français. COMMERCIAL LENDING POLICY DEVELOPMENT
ARCH CAPITAL ADVISORS
ARCH CAPITAL ADVISORS TERM SHEET Mezzanine Debt This term sheet does not constitute an offer and is solely for discussion purposes. This term sheet shall not be construed as creating any obligations on
BEST PRACTICE GUIDE 6: ESTABLISHING CONTRACTS. RDTL MINISTRY OF FINANCE Procurement Service
RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 6: ESTABLISHING CONTRACTS 1 RDTL Procurement Guidelines The Procurement Legal Regime Decree Law sets out new procurement processes which
PROCEDURES FOR ENVIRONMENTAL AND SOCIAL APPRAISAL AND MONITORING OF INVESTMENT PROJECTS
PROCEDURES FOR ENVIRONMENTAL AND SOCIAL APPRAISAL AND MONITORING OF INVESTMENT PROJECTS Approved 10 July 2015 CONTENTS 1. INTRODUCTION 1 2. OVERVIEW OF THE ENVIRONMENTAL AND SOCIAL APPRAISAL AND MONITORING
The Gateway Review Process
The Gateway Review Process The Gateway Review Process examines programs and projects at key decision points. It aims to provide timely advice to the Senior Responsible Owner (SRO) as the person responsible
Development, Acquisition, Implementation, and Maintenance of Application Systems
Development, Acquisition, Implementation, and Maintenance of Application Systems Part of a series of notes to help Centers review their own Center internal management processes from the point of view of
CHAPTER 24: ENVIRONMENTAL MANAGEMENT
Central Eyre Iron Project Environmental Impact Statement CHAPTER 24: ENVIRONMENTAL MANAGEMENT CHAPTER 24 ENVIRONMENTAL MANAGEMENT COPYRIGHT Copyright Iron Road Limited, 2015 All rights reserved This document
Meet challenges head on
Meet challenges head on Deal Advisory / Global We can help you master Financial Restructuring. Enhancing value through financial restructuring. / 1 Your vision. Our proven capabilities. Despite its challenges,
Principal risks and uncertainties
Principal risks and uncertainties Our risk management approach We have a well-established risk management methodology which we use throughout the business to allow us to identify and manage the principal
Central Bank of Ireland Guidelines on Preparing for Solvency II Pre-application for Internal Models
2013 Central Bank of Ireland Guidelines on Preparing for Solvency II Pre-application for Internal Models 1 Contents 1 Context... 1 2 General... 2 3 Guidelines on Pre-application for Internal Models...
Social impact assessment. Guideline to preparing a social impact management plan
Social impact assessment Guideline to preparing a social impact management plan September 2010 Looking forward. Delivering now. The Department of Infrastructure and Planning leads a coordinated Queensland
Department of the Interior. Departmental Manual
Page 1 of 10 Department of the Interior Departmental Manual Effective Date: 10/23/2015 Series: Public Lands Part 600: Public Land Policy Chapter 6: Implementing Mitigation at the Landscape-scale Originating
Skatteudvalget 2014-15 (2. samling) SAU Alm.del Bilag 48 Offentligt. Programme, Project & Service Management Analysis
Skatteudvalget 2014-15 (2. samling) SAU Alm.del Bilag 48 Offentligt Programme, Project & Service Management Analysis Table of Content 1 Executive Summary... 3 1.1 Scope of Work... 3 1.2 Methodology for
USAID-Funded Economic Governance II Project Credit Risk Workshop - Intermediate March 2006. The Credit Process. Funded by: 2006 BearingPoint, Inc.
USAID-Funded Economic Governance II Project Credit Risk Workshop - Intermediate March 2006 The Credit Process Funded by: 2006 BearingPoint, Inc. Table of Contents MODULE 2: THE CREDIT PROCESS OVERVIEW...1
CONTRACT MANAGEMENT FRAMEWORK
CONTRACT MANAGEMENT FRAMEWORK August 2010 Page 1 of 20 Table of contents 1 Introduction to the CMF... 3 1.1 Purpose and scope of the CMF... 3 1.2 Importance of contract management... 4 1.3 Managing contracts...
Guidelines for Minimum Standards Property Management Planning. Financial Management Module
Guidelines for Minimum Standards Property Management Planning Financial Management Module June 2011 June 2011 Acknowledgements All stakeholders who contributed to the development of the Financial Management
Audit issues when financial market conditions are difficult and credit facilities may be restricted
Bulletin 2008/01 Audit issues when financial market conditions are difficult and credit facilities may be restricted THE AUDITING PRACTICES BOARD The Auditing Practices Board Limited, which is part of
4 Project Implementation and Monitoring
4 Project Implementation and Monitoring Version 3, 29 July 2014 Contents 4. Implementation and Monitoring... 2 4.1 Project Implementation... 3 4.1.1 Setting up project implementation... 3 4.1.2 Development
Adaptive Management Measures under the Canadian Environmental Assessment Act
Operational Policy Statement Adaptive Management Measures under the Canadian Environmental Assessment Act Purpose This operational policy statement (OPS) provides best practice guidance on the use of adaptive
Project Services. How do we do it?
Project Services Many organisations struggle with inconsistent or poor project management performance across their business. Sometimes the failure to deliver on time and on budget (or at all!) is simply
private finance initiative
private finance initiative Lessons Learned We recently held a series of PFI Roundtable Discussions in collaboration with Trowers & Hamlins LLP. Finance managers from throughout the UK were invited to share
Audit of the Test of Design of Entity-Level Controls
Audit of the Test of Design of Entity-Level Controls Canadian Grain Commission Audit & Evaluation Services Final Report March 2012 Canadian Grain Commission 0 Entity Level Controls 2011 Table of Contents
Unofficial Consolidation
CENTRAL BANK (SUPERVISION AND ENFORCEMENT) ACT 2013 (SECTION 48) (LENDING TO SMALL AND MEDIUM-SIZED ENTERPRISES) REGULATIONS 2015 (S.I. No. 585 of 2015) Unofficial Consolidation This document is an unofficial
https://www.ofgem.gov.uk/publications-and-updates/ofto-build-providing-additional-flexibility-through-extendedframework
All interested parties Direct Dial: 020 7901 1849 Email: [email protected] Date: 17 November 2015 Dear Colleague EPC Contract Principles for OFTO Build Tenders This letter provides guidance
Conceptual Framework for Financial Reporting
Conceptual Framework for Financial Reporting Chapter 1: The Objective of Financial Reporting INTRODUCTION OB1. The first chapter of the conceptual framework establishes the objective of general purpose
Asset Management Policy March 2014
Asset Management Policy March 2014 In February 2011, we published our current Asset Management Policy. This is the first update incorporating further developments in our thinking on capacity planning and
OBLIGATION MANAGEMENT
OBLIGATION MANAGEMENT TRACK & TRACE: CONTRACTUAL OBLIGATIONS Better Visibility. Better Outcomes RAMESH SOMASUNDARAM DIRECTOR, IT VENDOR MANAGEMENT SERVICES MARCH 2012 E N E R G I C A Governance Matter
Developing Your Strategic Plan
Training Module: Developing Your Strategic Plan This training contains general information only and Deloitte is not, by means of this training session, rendering accounting, business, financial, investment,
Financing PPPs: Project Finance June 2006
Financing PPPs: Project Finance June 2006 Index Section I. Section II. Section III. Project Finance Spanish Market Advantages Risk Matrix P. 2 Section I Project Finance Project Finance Definition Definition:
5 Year Strategic Plan
Mid Atlantic Fishery Management Council 5 Year Strategic Plan 2014 2018 DRAFT 5/31/2013 Table of Contents Table of Contents... 1 Introduction... 2 The Mid Atlantic Fishery Management Council... 2 Rationale
Role of Civil Society Organisations in REDD Projects
Role of Civil Society Organisations in REDD Projects A joint study by the Conservation Finance Alliance and PricewaterhouseCoopers Sergio Salas pwc Agenda/Contents Our work in ecosystems and biodiversity
Electricity Settlements Company Ltd Framework Document
Electricity Settlements Company Ltd Framework Document This framework document has been drawn up by the Department of Energy and Climate Change in consultation with the Electricity Settlements Company.
OMS in practice. A supplement to Report No. 510, Operating Management System Framework. OGP Report No. 511 June 2014
International Association of Oil & Gas Producers OMS in practice OGP Report No. 511 June 2014 A supplement to Report No. 510, Operating Management System Framework Disclaimer Whilst every effort has been
UNITED STATES DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL
UNITED STATES DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL AUDIT SERVICES August 24, 2015 Control Number ED-OIG/A04N0004 James W. Runcie Chief Operating Officer U.S. Department of Education Federal
Project Management Plan for
Project Management Plan for [Project ID] Prepared by: Date: [Name], Project Manager Approved by: Date: [Name], Project Sponsor Approved by: Date: [Name], Executive Manager Table of Contents Project Summary...
6.0 Procurement procedure 1 Infrastructure
Page 6-1 6.0 Procurement procedure 1 Infrastructure 6.1 Overview Introduction Procurement procedure 1 Infrastructure consists of four parts: guidelines for understanding the strategic context for the procurement
REPUBLIC OF KENYA COUNTY GOVERNMENT OF LAIKIPIA MEDIUM TERM DEBT MANAGEMENT STRATEGY 2013/14-2017/18
REPUBLIC OF KENYA COUNTY GOVERNMENT OF LAIKIPIA MEDIUM TERM DEBT MANAGEMENT STRATEGY 2013/14-2017/18 COUNTY EXECUTIVE MEMBER, FINANCE, PLANNING AND COUNTY DEVELOPMENT LAIKIPIA COUNTY February 2014 i EXECUTIVE
THE EQUATOR PRINCIPLES JUNE 2013
THE EQUATOR PRINCIPLES JUNE 2013 A financial industry benchmark for determining, assessing and managing environmental and social risk in projects www.equator-principles.com CONTENTS PREAMBLE... 2 SCOPE...
Green Credit Guidelines
Notice of the China Banking Regulatory Commission CBRC on Issuing the Green Credit Guidelines CBRC local offices, policy banks, state-owned commercial banks, jointstock commercial banks, financial assets
Oil Sands Environmental Coalition
Oil Sands Environmental Coalition 2 December 2013 Canadian Environmental Assessment Agency Attention: David Haddon Panel Manager 160 Elgin Street, 22nd Floor Ottawa ON K1A 0H3 [email protected]
ENTERPRISE RISK MANAGEMENT FRAMEWORK
ENTERPRISE RISK MANAGEMENT FRAMEWORK COVENANT HEALTH LEGAL & RISK MANAGEMENT CONTENTS 1.0 PURPOSE OF THE DOCUMENT... 3 2.0 INTRODUCTION AND OVERVIEW... 4 3.0 GOVERNANCE STRUCTURE AND ACCOUNTABILITY...
pm4dev, 2007 management for development series The Project Management Processes PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2007 management for development series The Project Management Processes PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage
Long Term Financial Planning
Long Term Financial Planning Framework and Guidelines Long Term Financial Planning Framework and Guidelines for Western Australian Local Governments p1. Contents Foreword 4 1. Introduction 7 2. Purpose
Governments implement PPP programmes in the healthcare sector for one or more of a number of reasons:
UNECE Healthcare PPP Project Team Project Brief Introduction This is a very active time globally for the healthcare sector as demand for services continues to grow exponentially, driven by rising life
Outsourcing: key legal issues and contractual protections
Page 1 Outsourcing: key legal issues and contractual protections Paul Jones May 2009 Introduction As the economic climate becomes more challenging, organisations in all sectors are looking to drive efficiencies
Risk Management Policy and Process Guide
Risk Management Policy and Process Guide Status: pending Next review date: December 2015 Page 1 Information Reader Box Directorate Medical Nursing Patients & Information Commissioning Operations (including
State of Minnesota. Enterprise Security Strategic Plan. Fiscal Years 2009 2013
State of Minnesota Enterprise Security Strategic Plan Fiscal Years 2009 2013 Jointly Prepared By: Office of Enterprise Technology - Enterprise Security Office Members of the Information Security Council
More simply, a Bank Bill is a promise by the borrower
Contents 1 What are Bank Bills? 2 Features of Bank Bills 3 Borrowing via Bank Bills 4 Investing in Bank Bills 5 Managing Your Interest Rate Exposure 6 Interest Rate Risk Management Instruments 7 Bank Bill
Risk Management. Group Standard
Group Standard Risk Management Effective risk management allows Serco to improve customer service, maximize opportunities and reduce business loss from overruns and cost from risks that materialise SMS
Financial Services FINANCIAL SERVICES UTILITIES 57 FINANCIAL SERVICES AND UTILITIES 2016-2018 BUSINESS PLAN. CR_2215 Attachment 1
CR_2215 Attachment 1 Financial Services FINANCIAL SERVICES & UTILITIES 57 FINANCIAL SERVICES AND UTILITIES 2016-2018 BUSINESS PLAN Acting Branch Manager: Stacey Padbury Table of Contents INTRODUCTION Our
1.1 An initial request to enter into a contractual arrangement may be initiated by either Massey University or another party (Other Party).
CONTRACT MANAGEMENT PROCEDURE Section Risk Management Contact Risk Manager Last Review February 2013 Next Review February 2016 Approval Not required Procedures Contract Initiation Request Mandatory Guidance
Key issues in bank lending
Key issues in bank lending Introduction Welcome to Keynotes. Keynotes is a monthly event and publication to help early stage businesses get to grips with key legal issues. A bit about us Keynotes is brought
PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:
PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: Project Name Project Management Plan Document Information Document Title Version Author Owner Project Management Plan Amendment History
Insurance management policy and guidelines. for general government sector, September 2007
Insurance management policy and guidelines for general government sector September 2007 i Contents 1. Introduction... 2 2. Identifying risk is the first step... 2 3. What is risk?... 2 4. Insurance is
Managing Interest Rate Exposure
Managing Interest Rate Exposure Global Markets Contents Products to manage Interest Rate Exposure...1 Interest Rate Swap Product Overview...2 Interest Rate Cap Product Overview...8 Interest Rate Collar
Insurer audit manual
Insurer audit manual Disclaimer This publication may contain work health and safety and workers compensation information. It may include some of your obligations under the various legislations that WorkCover
Objective of General Purpose Financial Reporting
Statement of Accounting Concepts SAC 2 (8/90) Objective of General Purpose Financial Reporting Prepared by the Public Sector Accounting Standards Board of the Australian Accounting Research Foundation
2 COMMENCEMENT DATE 5 3 DEFINITIONS 5 4 MATERIALITY 8. 5 DOCUMENTATION 9 5.1 Requirement for a Report 9 5.2 Content of a Report 9
PROFESSIONAL STANDARD 300 VALUATIONS OF GENERAL INSURANCE CLAIMS INDEX 1 INTRODUCTION 3 1.1 Application 3 1.2 Classification 3 1.3 Background 3 1.4 Purpose 4 1.5 Previous versions 4 1.6 Legislation and
APES 320 Quality Control for Firms
APES 320 Quality Control for Firms APES 320 Quality Control for Firms is based on International Standard on Quality Control (ISQC 1) (as published in the Handbook of International Auditing, Assurance,
Business-critical Insurance
Business-critical Insurance Identifying those insurances that support the business and its strategy Guide 2015 Contents Introduction... 4 Categories of insurance... 5 Determining which insurance covers
Project Governance a board responsibility. Corporate Governance Network
Project Governance a board responsibility Corporate Governance Network November 2015 1 Contents Page Introduction 3 Board responsibilities 3 What is project governance? 4 The boards duties in respect of
RDTL Procurement Best Practice Guide 7: Managing Contracts. RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS
RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS 1 RDTL Procurement Guidelines The Procurement Legal Regime Decree Law sets out new procurement processes which must
DCU BULLETIN Division of Credit Unions Washington State Department of Financial Institutions Phone: (360) 902-8701 FAX: (360) 704-6901
DCU BULLETIN Division of Credit Unions Washington State Department of Financial Institutions Phone: (360) 902-8701 FAX: (360) 704-6901 December 19, 2007 No. B-07-13 Structuring a Member Business Lending
Business Plan Helpsheet
NORTHERN IRELAND Business Plan Helpsheet Published by Chartered Accountants Ulster Society with content from CCAB-I and the Irish Banking Federation Business Plan Helpsheet 01 Contents This helpsheet has
London Green Fund Selection of Waste Urban Development Funds IR-893. Questions and Answers
London Green Fund Selection of Waste Urban Development Funds IR-893 Questions and s Question 1. What restriction, if any, will be placed on the waste UDF s ability to re-invest the initial commitment of
Operating Management System Framework
International Association of Oil & Gas Producers Operating Management System Framework OGP Report No. 510 June 2014 for controlling risk and delivering high performance in the oil and gas industry Disclaimer
Procurement Transformation Division. Procurement guidance. Engaging and managing consultants. Includes definitions for consultants and contractors
Procurement guidance Engaging and managing consultants Includes definitions for consultants and contractors Procurement guidance: Engaging and managing consultants Page 2 of 17 Table of contents Table
Overcoming financing challenges for Hydro Power Projects Francois Viljoen, Director, Cresco Project Finance, South Africa
Overcoming financing challenges for Hydro Power Projects Francois Viljoen, Director, Cresco Project Finance, South Africa Contents Features of Project Finance Challenges posed by Project Finance Risk assessment
Risks and uncertainties
Risks and uncertainties Our risk management approach We have a well-established risk management methodology which we use throughout the business to allow us to identify and manage the principal risks that
Terms of Reference. Project Management Advisor for the Development of a Public Debt Management System (PDMS)
Terms of Reference Project Management Advisor for the Development of a Public Debt Management System (PDMS) (A) Background The Commonwealth is a voluntary association of 53 countries that support each
Gateway review guidebook. for project owners and review teams
Gateway review guidebook for project owners and review teams The State of Queensland (Queensland Treasury and Trade) 2013. First published by the Queensland Government, Department of Infrastructure and
Part One: Introduction to Partnerships Victoria contract management... 1
June 2003 The diverse nature of Partnerships Victoria projects requires a diverse range of contract management strategies to manage a wide variety of risks that differ in likelihood and severity from one
THE EQUATOR PRINCIPLES ASSOCIATION GOVERNANCE RULES
THE EQUATOR PRINCIPLES ASSOCIATION GOVERNANCE RULES 1) Introduction This governance document sets out the Rules of the unincorporated association of Equator Principles Financial Institutions and provides
PROJECT FINANCE & LOAN SYNDICATIONS. Theories, Procedures & Techniques
PROJECT FINANCE & LOAN SYNDICATIONS Theories, Procedures & Techniques What is Project Finance? A Project Finance transaction involves the mobilization of debt, equity, contingent equity, hedges and a variety
Please send your responses via email, to: [email protected]. Respondent details. Mark Redhead. Head of Policy
REFORM OF THE PRIVATE FINANCE INITIATIVE RESPONSE Please send your responses via email, to: [email protected] The deadline for responses is Friday 10 February 2012. Respondent details Your