1 SECTION 1 - GENERAL PROCEDURES TABLE OF CONTENTS 1.1 Preface Formal Quotation Requirements General Parameters of Quote for Machinery and Equipment Itemized Prices Proposal Description Project Completion Order and Alterations Work at Buyer s Facility Payment Schedule Page General Procedures - 1-1
2 SECTION 1 - GENERAL PROCEDURES 1.1 Preface This specification has been written to present Robert Bosch Corporation/Affiliate s (hereinafter referred to as Bosch ) requirements for industrial equipment in an orderly manner. Supplier and any subsequent suppliers shall comply with this specification and with "General Terms and Conditions for the Purchase of Capital Equipment" (see Appendix 1.1). It is not intended to limit or inhibit development in industrial equipment design. Functional design of equipment shall be the equipment supplier s responsibility. The application of "Lean Equipment Design" principles is required. If the supplier interprets the requirements of this document or any Bosch specification to be in conflict with Federal or State regulations, it is the supplier s responsibility to get clarification from Bosch s Project Engineer. Deviations to specifications provided herein may be allowed when necessary, and agreed upon in writing by Project Engineer. Copy to Purchasing. Individual locations may have plant specific requirements which can be found in Section Formal Quotation Requirements General Request for Quotations (RFQ) are originated by the Project Engineer and transmitted through the Purchasing Department to the equipment supplier. The Project Engineer shall provide process and equipment specifications adequate to define Bosch's requirements for the particular equipment under consideration. Quotes must be returned to Purchasing Department and must have Bosch RFQ number. All paper quotations must be submitted in triplicate. Electronically submitted quotes need buyer's permission. General Procedures - 1-2
3 1.2.2 Parameters of Quote for Machinery & Equipment a) All production machinery must comply with General Delivery Specifications. The quotation must include this statement: We agree to conform to Bosch s General Delivery Specifications - for machinery and equipment. If this is not possible, a request for specific deviations must be included in the quotation and written approval of the deviations requested must be obtained from the Project Engineer or his/her immediate supervisor before an order can be accepted. b) The following information to be included: Bosch RFQ Number Part name(s), number(s), and/or identification number. Name of Project Engineer requesting the quote. Machine tool equipment supplier s quotation number and date. c) The quotation shall include firm delivery dated from the date of purchase order. d) Document requirements: All drawings, documentation, etc., as per Section 8 shall be supplied in English. e) Must provide special foundation or other site requirements in quote. f) A basic timeline containing critical milestones is to be provided with the quote. General Procedures - 1-3
4 1.2.3 Itemized Prices The following shall be itemized and separately priced on the quote: a) Basic machine b) Special Machine Options c) Fixtures/Workholding d) Perishable Tools (if requested). e) Charges, if any, for engineering, source code, drawings, or service information. f) Auxiliary equipment of a separable nature, such as: Hydraulics, Air Handling, Coolant Filtration, Conveyors, etc. g) Environmental and health control devices. This would include but not be limited to chip removal, mist, and vacuum equipment. h) Electrical and electronic controls. i) Automatic gaging and size control (if requested). j) Spare parts package. k) Machine run-off costs. l) Service and installation charges (if required). m) Cost of training. n) Warranty Information. General Procedures - 1-4
5 1.2.4 Proposal Description The items quoted shall be accurately described by proposal drawings and/or text. Data on obtainable production rates, (in 85% utilization), estimated power consumption, maximum change-over times, buffer capacity between stations, and process and gage capabilities shall be included where applicable. Complete cycle detail is required on each station. Estimated coolant, water, steam, compressed air, gas, etc., consumption and/or flow rates required at machine must be included Number of pieces that will be run-off for each part number is defined in Appendix 6.1. These are the quantity of parts that will be run at no charge as part of the quote package, and are expected to be good parts per Bosch s requirements. Pieces required for set-up, tryout, or to qualify equipment shall be supplied by Bosch Information required for Control System Overview (Appendix 5.1) should be included in proposal as much as possible. Information not available at time of proposal must be submitted along with concept approval drawings The supplier shall inform the Project Engineer of any known or suspected by-products of machine fluids used which may be hazardous to health Project Completion At the completion of each project, parts, drawings and support documentation belonging to Bosch to be entirely returned. General Procedures - 1-5
6 1.3 Order and Alterations Purchase orders and amendments to purchase orders are issued by Bosch through the Purchasing Department only. No statement of intent to purchase or to amend an existing order is a commitment by Bosch until issued by the Purchasing Department When the product design is changed, new prints will be submitted to the equipment supplier by the Project Engineer, with a written request to quote modification of the equipment under construction required to comply with the revised product design; including changes to price and delivery. After approval of the proposed modification by Bosch, an amendment will be issued by the Purchasing Department to cover the additional costs Acknowledgment of the order acceptance and confirmation of delivery or price shall be received by the Bosch Purchasing Department and the Project Engineer responsible as soon as possible, but not later than three weeks after receipt of purchase order by the equipment manufacturer. 1.4 Work at Buyer s Facility (See also Section 9: General Terms and Conditions for the Purchase of Capital Equipment (Appendix 1.1)) Equipment supplier to provide installation supervision or instruction to assure that equipment is installed properly and fulfills requirements of the warranty All equipment suppliers must sign and adhere to each facilities Contractor Safety Declaration. This requires the supplier to follow plant-specific lock out, tag out requirement, confined space entry, etc Welding, cutting, soldering jobs, heating and thawing with welding torches, gasoline or gas burners, etc., are forbidden unless specific permits are obtained from Bosch Bosch draws particular attention to the fact that smoking may be restricted or forbidden in certain areas of our plants. Safety glasses and appropriate working attire and footwear are required within all Bosch facilities. Other safety equipment is as required by OSHA regulations. General Procedures - 1-6
7 1.5 Payment Schedule (See also Section 5 and 7.3 of General Terms and Conditions for the Purchase of Capital Equipment (Appendix 1.1)) Robert Bosch Corporation payment schedule for the Purchase of Capital Equipment is as follows: 80% Net 30 of complete purchase price upon Delivery of equipment to specified Bosch Facility. 20% Net 30 of complete purchase price upon Final Acceptance at specified Bosch Facility. (See Section 7 for Pre-Final Acceptance Checklist.) General Procedures - 1-7
ALVERNIA UNIVERSITY OSHA REGULATION: 29 CFR 1910.147 THE CONTROL OF HAZARDOUS ENERGY (LOCKOUT / TAGOUT) SECTION: 2400
OSHA REGULATION: 29 CFR 90.7 THE CONTROL OF HAZARDOUS ENERGY (LOCKOUT / TAGOUT) DATE: 0/5/2008 DATE: /2/202 A. POLICY. This procedure follows requirements set forth in 29 CFR 90.7. 2. It is the policy
More informationREQUEST FOR QUOTATIONS
Metropolitan Washington Airports Authority Materials Management, MA-133 Terminal A, Room 278 Washington, DC 20001-4901 REQUEST FOR QUOTATIONS 1. FOR INFORMATION CONTACT NAME: Regina Leigh 2. REQUEST FOR
More informationLockout / Tagout Program
Lockout / Tagout Program Table of Contents Page Scope... 2 Definitions... 2 Authorization... 3 Responsibilities... 4 Compliance and Enforcement... 4 When to Lockout/Tagout (LOTO)... 5 Lockout Procedure...
More informationForm P ITEM DESCRIPTION UNIT ESTIMATED 12 MONTH QUANTITY
REQUEST FOR QUOTATION **THIS IS NOT AN ORDER** BOARD OF COUNTY COMMISSIONERS, PALM BEACH COUNTY PURCHASING DEPARTMENT 50 S. MILITARY TRAIL, SUITE 110, WEST PALM BEACH, FL 33415-3199 PHONE (561) 616-6823
More informationHOUSTON COUNTY BOARD OF COMMISSIONERS PURCHASING DEPARTMENT
August 5, 2015 Dear Vendor: The Houston County Board of Commissioners is soliciting sealed bids for the provision of one (1) new 2015 or 2016 year model Ford Explorer SUV for use by the Houston County
More informationBWC Division of Safety and Hygiene
BWC Division of Safety and Hygiene A SAMPLE LOCKOUT/TAGOUT PROCEDURE A good Lockout/Tagout Procedure, at a minimum, should contain the following elements: 1. All maintenance personnel shall be provided
More informationPage85. Lock-out Tag-out Plan
Page85 Lock-out Tag-out Plan Page86 Lock-out / Tag-Out Plan Table of Contents 1. Policy 2. Purpose 3. Scope 4. General Procedures 5. Application of Control Procedure 6. Release from Control Procedure 7.
More informationSafe and Efficient Hydraulic Systems Review of ISO 4413 Hydraulic Fluid Power General Rules and Safety Requirements for Systems and Their Components
Safe and Efficient Hydraulic Systems Review of ISO 4413 Hydraulic Fluid Power General Rules and Safety Requirements for Systems and Their Components Jerry Carlin Eaton Hydraulics November 20, 2013 Evolution
More informationMANAGEMENT AND USE OF WORK EQUIPMENT: PRESSURE SYSTEMS
Health & Safety Services Unit name goes here Safety Code of Practice 46, Part 2 1st Edition, November 2009 MANAGEMENT AND USE OF WORK EQUIPMENT: PRESSURE SYSTEMS University of Reading 2015 Page 1 Contents
More informationHealthandSafetyOntario.ca. What is a work permit? Why use a work permit? Types of work permits. When is a work permit needed?
work permits What is a work permit? A work permit is a written form used to authorize jobs that expose workers to serious hazards. It identifies the work to be done, the hazards involved, and the necessary
More informationQuality Management System
LH Sleightholme Ltd, Westfield Works, Helperthorpe, Malton, North Yorkshire YO17 8TQ Quality Management System MANUAL ISO 9001:2008 This Quality Management System Manual has been issued on the authority
More informationRequest for Quotation (RFQ) for Adjustable Sit to Stand Desk Reference No.: UNWHQRFQ31. [Insert Title of Goods]
Request for Quotation (RFQ) for Adjustable Sit to Stand Desk Reference No.: UNWHQRFQ31 [Insert Title of Goods] 01 September, 2015 Dear Sir/Madam, Subject: Request for Quotation (RFQ) for the provision
More informationABTREX INDUSTRIES, INC. QUALITY MANAGEMENT SYSTEM MANUAL
ABTREX INDUSTRIES, INC. QUALITY MANAGEMENT SYSTEM MANUAL Project Quality Management System Status APPROVED Approved by KB Keith Byars, Vice President Owner KC Kevin Couvillion, Operations Manager Author
More informationProcess Plant Construction: A Handbook for Quality Management
Process Plant Construction: A Handbook for Quality Management Process Plant Construction: A Handbook for Quality Management Patrick Noble ISBN: 978-1-4051-8725-1 Hardcover 232 pages January 2009, Wiley-Blackwell
More informationEUROPEAN INDUSTRIAL GASES ASSOCIATION
WORK PERMIT SYSTEMS IGC Doc 40/02/E EUROPEAN INDUSTRIAL GASES ASSOCIATION AVENUE DES ARTS 3-5 B 1210 BRUSSELS Tel : +32 2 217 70 98 Fax : +32 2 219 85 14 E-mail : info@eiga.org Internet : http://www.eiga.org
More informationIntroduction. Engineering Skills Development
Fossil Operations Introduction The Engineer Development Program provides college graduate engineers with a broad view of the company through opportunities in various power plants, engineering facilities
More informationRMM 306 Lockout/Tagout (LOTO) Program for the Control of Hazardous Energy Page 2 June 2016
RMM 306 Lockout/Tagout (LOTO) Program for the Control of Hazardous Energy Page 2 3 Related Documents 3.1 Occupational Health and Safety Act, R.S.O. 1990 3.2 Regulations for Industrial Establishments, R.R.O.
More informationIV. Orders, Quotations, Bids and Request for Proposal (RFP) Requirements
Policy 707 Noninstructional Operations and Business Services Purchasing I. Purpose This policy defines the process for purchasing supplies, equipment, materials and services that will be used to meet the
More informationIndependent Contractor Policy
Independent Contractor Policy This Policy has been implemented to prevent accidents and personal injuries. It is not intended to be entirely inclusive. It is the responsibility of the Independent Contractor
More informationLockout - Tagout. Control of Hazardous Energy OSHA Standard 1910.147
Lockout - Tagout Control of Hazardous Energy OSHA Standard 1910.147 You will learn Purpose of Lockout-Tagout Requirements for LOTO Types of Hazardous Energy Procedures for LOTO Types of Energy Electrical
More informationALVERNIA UNIVERSITY OSHA REGULATION: 29 CFR 1910.252 WELDING, CUTTING, AND BRAZING ( HOT WORK ) SECTION: 3600
OSHA REGULATION: 9 CFR 90.5 WELDING, CUTTING, AND BRAZING ( HOT WORK ) A. POLICY. This procedure follows requirements set forth in 9 CFR 90.5.. This policy applies to all Hot Work operations being done
More informationGE Power Electronics Business Total Quality Management for Suppliers
GE Power Electronics Business Total Quality Author: Reviewers: Contributors: Alessandro A. Cervone Technical Manager Component & Reliability Engineering Alicia Scott Title Erika Nannis Title Robert Roessler
More informationWEEKLY SAFETY MEETING All Euramax Subsidiaries LOCKOUT / TAGOUT. Safety Meeting Contents. Meeting Notice. Leaders Guide.
Safety Meeting Contents Meeting Notice Leaders Guide Employee Handout Employee Quiz Meeting Sign-In Sheet Employee Puzzle PRIOR TO THE WEEKLY MEETING: - Post the meeting notice by the timeclock - Read
More informationCORPORATE QUALITY MANUAL
Corporate Quality Manual Preface The following Corporate Quality Manual is written within the framework of ISO 9001:2008 Quality System by the employees of CyberOptics. CyberOptics recognizes the importance
More informationINTRODUCTION... 3. 1.0 Purpose... 4. 2.0 Policy... 4. Exception for Short-Term Workplace Visits... 4. Relevant Legislation and Regulations...
March 2006 INTRODUCTION... 3 1.0 Purpose... 4 2.0 Policy... 4 Exception for Short-Term Workplace Visits... 4 Relevant Legislation and Regulations... 5 Definitions... 5 Contractor Safety Coordination Overview...
More informationUniversity of Nevada, Reno
University of Nevada, Reno THE CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAGOUT) PROGRAM Program Contact Person: John A. Braun, CSP Environmental Health and Safety University of Nevada, Reno Phone: 775-784-6478
More informationWelding, Brazing & Cutting Guidelines
FIRENET FIRE PREVENTION DEPARTMENT November 2010 Welding, Brazing & Cutting Guidelines Hot Work is any work activity that generates a flame, heat or sparks such as soldering, brazing, welding, torch cutting
More informationHealthandSafetyOntario.ca. Introduction. Responsibilities. Health and Safety Policy
starting your Health and safety program Introduction Workplace injuries and illnesses can be prevented. The key to achieving safe production is to identify and control all workplace health and safety hazards.
More informationThe Procurement Guidelines of. the Japanese Grant Aid. (Type I-G)
The Procurement Guidelines of the Japanese Grant Aid JAPAN INTERNATIONAL COOPERATION AGENCY (JICA) 1 Table of Contents PART I Basic Principles... 4 I-1 Introduction... 4 I-2 Parties Concerned... 4 I-3
More informationNew Program Quality Requirements for Suppliers (NPQR) For Limited Manufacturing of Components and/or Processes for Engineering Certification
New Program Quality Requirements for Suppliers (NPQR) For Limited Manufacturing of Components and/or Processes for Engineering Certification Revision A New Program Quality Requirements for Suppliers Rev.
More informationContract for Capital Purchase N [reference of the COMPANY]
Contract for Capital Purchase N [reference of the COMPANY] Between [ ].... represented by the duly authorized persons designated on the signature page of the present CONTRACT, hereinafter referred to in
More informationHOUSTON COUNTY BOARD OF COMMISSIONERS PURCHASING DEPARTMENT
2020 KINGS CHAPEL ROAD (478) 218-4800 PERRY, GEORGIA 31069-2828 FACSIMILE (478) 218-4805 October 6, 2015 Dear Vendor: RE: Bid #16-17 One New Excavator The Houston County Board of Commissioners is soliciting
More informationSolicitation 1210-014. Web Hosting Services for the Disaster Volunteer Network. State of California
Solicitation 1210-014 Web Hosting Services for the Disaster Volunteer Network State of California Oct 12, 2012 4:28:36 PM PDT p. 1 Bid 1210-014 Web Hosting Services for the Disaster Volunteer Network Bid
More informationControl of Hazardous Energy (Lockout / Tagout)
WAUKESHA COUNTY TECHNICAL COLLEGE Control of Hazardous Energy (Lockout / Tagout) Release Date: March 26, 2012 Revision Date: March 26, 2012 Revision Level: 1 TABLE OF CONTENTS Purpose... 1 Scope... 1 Responsibilities...
More information6-19-87 WASTEWATER TREATMENT MECHANIC, 5614 WASTEWATER TREATMENT MECHANIC SUPERVISOR, 5617
6-19-87 WASTEWATER TREATMENT MECHANIC, 5614 WASTEWATER TREATMENT MECHANIC SUPERVISOR, 5617 Summary of Duties: Performs a variety of skilled tasks in maintaining, overhauling and assembling mechanical equipment
More informationWork Permits. A Health and Safety Guideline for Your Workplace. When is a Work Permit Needed? What is a Work Permit? Why use a Work Permit?
A Health and Safety Guideline for Your Workplace What is a Work Permit? A work permit is a written form used to authorize jobs that expose workers to serious hazards. It identifies the work to be done,
More informationLOCKOUT/TAGOUT PROGRAM. Table of Contents
Western University of Health Sciences IIPP SUB-PROGRAM LOCKOUT/TAGOUT PROGRAM Table of Contents 1.0 INTRODUCTION 1 2.0 PURPOSE 1 3.0 RESPONSIBILITIES 1 Supervisors 1 Employees 1 4.0 TRAINING 2 5.0 WRITTEN
More informationStudent Shop Safety Policy GS92 Page 1
Policy Subject: Student Shop Safety Effective: 8/1/2012 Affected Area: Machine Shops on Campus Reviewed/Revised: 8/1/2012 1.0 Purpose, Applicability, and Scope 1.1 Purpose- This policy identifies the requirements
More informationIn Vehicle Electronics Policy Cell Phones and Mobile Computers
In Vehicle Electronics Policy Cell Phones and Mobile Computers 1 Cell Phones and Mobile Computers Human Resource Policy TABLE OF CONTENTS 1. Purpose...3 2. Introduction...3 3. Responsibility...3 4. Policy...4
More informationREQUEST FOR QUOTATION **THIS IS NOT AN ORDER**
REQUEST FOR QUOTATION **THIS IS NOT AN ORDER** Form P BOARD OF COUNTY COMMISSIONERS, PALM BEACH COUNTY PURCHASING DEPARTMENT 50 S. MILITARY TRAIL, SUITE 110, WEST PALM BEACH, FL 33415-3199 PHONE (561)
More informationBuilding Commissioning 17900-1
SECTION 17900 BUILDING COMMISSIONING PART 1 - GENERAL 1.01 WORK DESCRIPTION: A. General: 1. The Commissioning process is a joint team effort to ensure that all mechanical equipment, controls, and systems
More informationDonaldson Buys Value SBOSS. Donaldson Supplier Business Operating System Standard (SBOSS)
Donaldson Supplier Business Operating System Standard () Supplier Business Operating System Standard () INTRODUCTION DCI is a multi-plant manufacturing company serving several different markets. These
More informationConducting a Job Hazard Assessment. Environmental, Health and Safety 275-3241
Conducting a Job Hazard Assessment Environmental, Health and Safety 275-3241 EH&S Programs: Fire Safety Blood Borne Pathogens Hazard Communication Personal Protective Equipment Emergency Preparedness General
More informationMarketing Director, Finishing Store and Despatch, Workshop Supervisor
Managing Director ACCOUNTABLE TO: Board of Directors Marketing Director, Finishing Store and Despatch, Workshop Supervisor To ensure the company operates profitably and in an ethical manner in order to
More informationHOT WORK PERMIT PROGRAM TRAINING. John Braun
HOT WORK PERMIT PROGRAM TRAINING John Braun 1.0 INTRODUCTION 1.2 Purpose The Hot Work Permit Program has been developed for University employees that work on or around hot work activities. This program
More informationIntroduction to Manufacturing Process
Introduction to Manufacturing Process What is Manufacturing? The English word manufacture is several centuries old. The term manufacture comes from two Latin words, manus (hand) and factus (make). As per
More informationAsbestos Management & Abatement
Asbestos Management & Abatement Latest revised date: October 29, 2012 Page 1 of 18 1.0 LEGAL & LEGISLATIVE REQUIREMENTS This standard provides guidance to meeting the minimum requirements of the Act &
More informationDivision of Public Health Administrative Manual
PURPOSE To establish a protocol for the development of a written Division of Public Health Hazard Communications Program at each applicable office or laboratory workplace and to assure that employees are
More informationControl of Hazardous Energy LOCKOUT/TAGOUT 29 CFR 1910.147
Control of Hazardous Energy LOCKOUT/TAGOUT 29 CFR 1910.147 Contents I. Introduction II. Scope and Application III. Definitions IV. Lockout/Tagout Manual V. Energy Control Procedures 1. Applying Energy
More informationSupplier Change Notification Process
Horton Supplier Change tification Process Supplier Change tification Process Page 1 of 5 Horton Supplliier Change tiiffiicatiion Process The purpose of this process is to define the procedure suppliers
More informationCompany Quality Manual Document No. QM Rev 0. 0 John Rickey Initial Release. Controlled Copy Stamp. authorized signature
Far West Technology, Inc. ISO 9001 Quality Manual Document No.: QM Revision: 0 Issue Date: 27 August 1997 Approval Signatures President/CEO Executive Vice President Vice President/CFO Change Record Rev
More informationMANAGEMENT SYSTEM MANUAL
MANAGEMENT SYSTEM MANUAL Scope of the management system: Oil-, chemistry-, gas and energy industry equipment development, production and sales Valukoja Street 7/2 Bank: Nordea Bank Finland Plc 11415 Tallinn,
More informationTEMPORARY EMPLOYEES SAFETY PROCEDURES
TEMPORARY EMPLOYEES SAFETY PROCEDURES Temporary Agencies will ensure that any temporary employee sent to work at Modern will have received and understand the General Safety Rules. GENERAL SAFETY RULES
More informationTERMS AND CONDITIONS OF SALE. Quotations, Purchase Orders, Acknowledgements, Packing Lists/Slips, Invoices & Credits
Quotations, Purchase Orders, Acknowledgements, Packing Lists/Slips, Invoices & Credits All quotations of Seller ( Quotations ) and purchase orders of Buyer ( Purchase Orders ) shall be subject to these
More informationLiverpool City Region Local Enterprise Partnership Request for Written Quotation. for. Mobile telephone contract. July 2015
Liverpool City Region Local Enterprise Partnership Request for Written Quotation for Mobile telephone contract July 2015 Contents Section 1. INTRODUCTION Background and summary/overview of requirements
More informationLockout/Tagout Compliance Guide and Checklist
Lockout/Tagout Compliance Guide and Checklist Scope: The OSHA Control of Hazardous Energy (Lockout/Tagout) standard (29 CFR 1910.147) covers the servicing and maintenance of machines and equipment in which
More informationLOCK-OUT/TAG-OUT PROGRAM I. Purpose
LOCK-OUT/TAG-OUT PROGRAM I. Purpose This procedure establishes requirements for the lockout of energy isolating devices. It should be used to ensure that the machine or piece of equipment is isolated from
More informationConstruction Contract
Construction Contract Case Number: Date: Borrower Name(s): Phone #: Phone #: THIS IS A MODEL DOCUMENT FOR USE IN RENOVATION OR CONSTRUCTION LOAN TRANSACTIONS. THIS FORM IS PROVIDED AS AN EXAMPLE AND IS
More informationPurchase Order Clauses and Conditions
Purchase Order Clauses and Conditions All purchase orders for materials, special processes, machining and fabrication services and end items are subject to the following requirements: General Requirements:
More informationSpecialties Manufacturing. Talladega Castings & Machine Co., Inc. ISO 9001:2008. Quality Manual
Specialties Manufacturing Talladega Castings & Machine Co., Inc. ISO 9001:2008 This document is the property of TMS and may not be reproduced, wholly, or in part, without the express consent of TMS. Rev.
More informationRFQ No. 4856B-0-2016/MD. REQUEST FOR QUOTATION City of Norfolk. Vendor: Issued: 11/06/2015 Due: 11/11/2015@ 2:00 PM
REQUEST FOR QUOTATION City of Norfolk (Please include your company name and address below) Vendor: Issued: 11/06/2015 Due: 11/11/2015@ 2:00 PM Mail or fax reply to: Office of the Purchasing Agent Attn:
More informationBASE CONSTRUCTION INC
BASE CONSTRUCTION INC 14252 CULVER DRIVE A-630 IRVINE,CA 92604-0326 OFFICE:949 387-3471 Shop 714 994 9563 CELL:949 735-5292 FAX:949 786-8753 QUALITY ASSURANCE and QUALITY CONTROL MANUAL 1 TABLE OF CONTENTS
More informationMACHINE QUOTATION. Show Machine Special Clearance Sale Price
Cyber CNC Machinery Sales, Inc. S86 W22400 Edgewood Avenue Big Bend, WI 53103 e-mail:sales@cybercnc.com Phone (262) 662-1100 Fax (262) 662-1104 MACHINE QUOTATION Show Machine Special Clearance Sale Price
More informationOH&S Management Systems Audit Checklist (NAT, E3)
3.1.2 3.1.1 Introduction OH&S Management Systems Audit Checklist (NAT, E3) This audit checklist is based on Element 3 (Implementation) of the National Self-Insurers OHS Audit Tool. For a full copy of the
More informationSafety and Environmental Information for External Companies Koehler Oberkirch
and al and at Work 1. Delivery, Notice, Signature After receiving the following information sheets, the team leader from every external company is required to read through them, explain them to their employees,
More informationSolicitation 420-1614/1621. Kofax Software Transfer, Upgrade, & Maintenance. Bid designation: Public. State of California
5 Solicitation 420-1614/1621 Kofax Software Transfer, Upgrade, & Maintenance Bid designation: Public State of California 2/12/2015 4:50 PM p. 1 6 Kofax Software Transfer, Upgrade, & Maintenance 5 Bid Number
More informationPROCEDURES: Purchasing Policy
AUTHORITY: University Administration POLICY: A:VPFA # / RESPONSIBILITY: Vice President Finance and Administration Effective Date: April 1, 2013 Purpose To implement the, the following specific actions
More informationLockout/Tagout Training Program
Lockout/Tagout Training Program (Student Handouts) Name Date This page intentionally left blank. Notes page: 2 Notes page: 3 Sample Written Program for Control of Hazardous Energy (Lockout/Tagout) 4 1910.147
More informationTECHNICAL GUIDE APPENDIX: GLOSSARY
TECHNICAL GUIDE APPENDIX: GLOSSARY A ACTION TEAM - a team of people contracted to implement the disaster recovery housing plan post-disaster; action teams work in the areas of navigation, eligibility/
More informationIntroduction. Cooper Standard Global Supplier Quality Manual Page 2 of 11
Global Supplier Quality Manual Revision 3 Introduction 1. Purpose: This manual has been created for Cooper Standard s (CS) Production, Prototype and Service Suppliers. The manual includes all CS locations
More informationTOOLING DEFINITIONS, COST AND AUDIT GUIDELINES
INTRODUCTION AND SCOPE This document sets forth the rights of Lear Corporation or its subsidiaries or affiliates (Lear) with regard to the auditing of 1) tooling paid for by Lear and used either (a) by
More informationAsset Management Policy
Asset Management Policy Issue Date: August 2011 Author: Head of Finance Approval Body: Senior Leadership Team CONTENTS Page 1. Policy Statement 3 2. Scope 3 3. Definitions 3 4. Accountabilities and Responsibilities
More informationREQUEST FOR QUOTATIONS 13-57. 2013 or Newer Unused Police Sedans
NOTICE IF RECEIVING THIS RFQ BY INTERNET, CALL (707) 543-3700 TO REGISTER AS A BIDDER. FAILURE TO REGISTER AS A BIDDER MAY RESULT IN YOUR FIRM NOT RECEIVING BID ADDENDUMS. FAILURE TO SUBMIT BID ADDENDUMS
More informationRDTL Procurement Best Practice Guide 7: Managing Contracts. RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS
RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS 1 RDTL Procurement Guidelines The Procurement Legal Regime Decree Law sets out new procurement processes which must
More informationENGINEERING SPECIFICATION. Engineering Specification SAPPHIRE 42 Bar
Engineering Specification SAPPHIRE 42 Bar PART 1 GENERAL 1.1 DESCRIPTION OF WORK This specification outlines the requirements for a "Total Flood" SAPPHIRE Clean Agent Fire Suppression System. The work
More informationQUALITY ASSURANCE MANUAL JPM OF MISSISSIPPI, INC.
QUALITY ASSURANCE MANUAL JPM OF MISSISSIPPI, INC. Hattiesburg, MS Revision E 01/19/11 Revised to ISO 9001:2008 on July 9, 2009 JPM OF MISSISSIPPI, INC. MANAGEMENT QUALITY POLICY It is the goal of JPM of
More informationEnviro Safety Products Resource Center. OSHA Checklist for General Industry
Enviro Safety Products Resource Center OSHA Checklist for General Industry The Occupational Safety and Health Administration (OSHA) require many standards to be met by businesses and industries. OSHA sets
More informationINFORMATION SHEET 2015 Ontario Renovates Program for Homeowners
INFORMATION SHEET 2015 Ontario Renovates Program for Homeowners Ontario Renovates Program Development Officer (PDO) 519-255-5200 Ext. 5349 or Ext. 5470 Disclaimer: Details contained herein are for informational
More informationSubvented Social Welfare Non-Governmental Organisations Procurement Procedures
Subvented Social Welfare Non-Governmental Organisations Procurement Procedures Corruption Prevention Department Independent Commission Against Corruption March 2001 CONTENTS Pages Introduction 1 The Basic
More informationKennebecasis Valley Fire Department Inc.
Inc. Chief Bill Ireland Deputy Chief Dan McCoy 7 Campbell Drive, Rothesay, NB E2E 5B6 Phone (506 848-6604 Fax (506 848-6608 Email: admin.kvfd@nb.aibn.com REQUEST FOR QUOTATION RFQ No. 15-1030 Winter Maintenance
More informationANGUS COUNCIL SUPPLEMENTARY CONDITIONS OF CONTRACT. SC 01 - Contract Performance Guarantee Insurance
SC 01 - Contract Performance Guarantee Insurance For contracts equal to or exceeding 750,000 in value the Contractor shall, within 28 days of the date of the award of the Contract, obtain and provide to
More informationPRECISION MICRODYNAMICS QUOTE / CONTRACT TERMS & CONDITIONS
1. General. All quotations furnished by Precision MicroDynamics Inc., ( PMDi ) or its authorized agents are solely for information of the party to whom the Quotation is addressed ( Buyer ). Any order resulting
More informationTitle: Complying with US Customs Product Documentation and Marking Requirements (CFR, Title 19,U.S.C. 19, HTS US)
Title: Complying with US Customs Product Documentation and Marking Requirements (CFR, Title 19,U.S.C. 19, HTS US) Document Number: 609030 Document Level: II Process Owner: Traffic Revision: Rev - C Page:
More informationLOCKOUT/TAGOUT (LOTO) SAFETY PROGRAM
1 UNIVERSITY OF WEST FLORIDA LOCKOUT/TAGOUT (LOTO) SAFETY PROGRAM (EQUIPMENT HAZARD DE-ENERGIZING AND ISOLATION) DEPARTMENT OF ENVIRONMENTAL HEALTH AND SAFETY 11000University Parkway Pensacola, FL 32514
More informationProcedures for Tenders and Contracts. October 2014. Huon Valley Council Procedures for Tenders and Contracts October 2014 Page 1 of 14
Procedures for Tenders and Contracts October 2014 Huon Valley Council Procedures for Tenders and Contracts October 2014 Page 1 of 14 Huon Valley Council Procedures for Tenders and Contracts October 2014
More informationPURCHASE ORDER ATTACHMENT Q-202 SOFTWARE QUALITY SUBCONTRACTOR REQUIREMENTS TASK DESCRIPTIONS - PURCHASE CATEGORY "B"
PURCHASE ORDER ATTACHMENT Q-202 SOFTWARE QUALITY SUBCONTRACTOR REQUIREMENTS TASK DESCRIPTIONS - PURCHASE CATEGORY "B" 1 SOFTWARE QUALITY PROGRAM. This attachment establishes the software quality requirements
More informationTABLETTING BUYER S GUIDE
TABLETTING BUYER S GUIDE THE KEY QUESTIONS YOU NEED TO ASK BEFORE BUYING A TABLET PRESS TABLETTING BUYER S GUIDE THE KEY QUESTIONS YOU NEED TO ASK BEFORE BUYING A TABLET PRESS Buying a tablet press is
More informationWORKING IN CONFINED SPACES GUIDELINES
WORKING IN CONFINED SPACES GUIDELINES Contents 1 Introduction... 2 2 Scope... 2 3 Definitions... 2 4 Responsibilities... 3 4.1 Permit Authoriser... 3 4.2 Permit Receiver... 3 4.3 Responsible UOW Officer...
More informationREQUEST FOR EXPRESSIONS OF INTEREST 4887 EOI NETWORK BACKUP/EMAIL ARCHIVING
4887 EOI REQUEST FOR EXPRESSIONS OF INTEREST 4887 EOI NETWORK BACKUP/EMAIL ARCHIVING Expressions of Interest will be received at the Information Counter, Main Floor, Richmond City Hall, addressed to the
More informationT146 Electro Mechanical Engineering Technician MTCU Code 51021 Program Learning Outcomes
T146 Electro Mechanical Engineering Technician MTCU Code 51021 Program Learning Outcomes Synopsis of the Vocational Learning Outcomes* The graduate has reliably demonstrated the ability to: 1. fabricate
More informationAn inventory of hazardous materials used in your workplace will prove useful.
Introduction Fire Protection is an organized approach designed to prevent fires. In the event of a fire, a fire protection program will help prevent or minimize personal injuries, losses, and harm to the
More informationCUMMINS FILTRATION SUPPLIER S HANDBOOK TO SUPPLIER COLLABORATIVE PLANNING
CUMMINS FILTRATION SUPPLIER S HANDBOOK TO SUPPLIER COLLABORATIVE PLANNING SUPPLIER COLLABORATIVE PLANNING SUPPLIER EXCEPTION MANAGEMENT PROCESS The following processes and procedures will assist Supplier
More informationDocument Management System Request for Proposal
Request for Proposal W240 N3065 Pewaukee Rd Pewaukee, WI 53072 Contact: Robert Kewan Director of Information Technology 262-691-6001 kewan@pewaukee.wi.us PROPOSALS DUE Friday May 13, 2016 NO LATER THAN
More informationHelical Products Co., Inc.
Q01 GENERAL REQUIREMENTS 1. Supplier Responsibilities 1.1. Delivery Certification By delivering products or services on the Contract, the Supplier certifies that such products or services are in compliance
More informationGeneral Conditions of Purchase (as of March 2002) Abbr.: AEB 03-2002 of the Salzgitter Bauelemente GmbH, Salzgitter
General Conditions of Purchase (as of March 2002) Abbr.: AEB 03-2002 of the Salzgitter Bauelemente GmbH, Salzgitter 1. Area of validity (1) The present conditions shall apply to all supplies and services
More informationCOUNTY OF DUTCHESS OFFICE OF CENTRAL AND INFORMATION SERVICES DIVISION OF CENTRAL SERVICES 27 HIGH STREET POUGHKEEPSIE, NEW YORK 12601 (845) 486-3670
COUNTY OF DUTCHESS OFFICE OF CENTRAL AND INFORMATION SERVICES DIVISION OF CENTRAL SERVICES 27 HIGH STREET POUGHKEEPSIE, NEW YORK 12601 (845) 486-3670 The Division of Central Services has developed this
More informationCEG/GP/1534/257/RFQ27016/ [01] Technical specification for NB 350 CB pipe :
[01] Technical specification for NB 350 CB pipe : Size :- NB 350 Plain End, ID 336 MM, OD 406 mm, Length - 5.3 meters +/- 25 mm Outer shell : Rolled and welded from 5 mm thick carbon steel coil / plates
More informationEXHIBIT A SCOPE OF WORK
EXHIBIT A SCOPE OF WORK 1. (Contractor) shall provide fire alarm system maintenance/repair/testing services as described herein to the California Department of Veterans Affairs (hereinafter CDVA, CalVet,
More informationBusiness Unit/Area: N/A. Protocol No.: COR-3S3-PR
Page 1 Overview Purpose This Devon Energy EHS Protocol establishes minimum requirements for securing, locking and tagging out energyisolating devices, and for the protection of workers from the unexpected
More informationThe Pennsylvania State University ------------- Physical Security Office. Intrusion Alarm. Performance Specification
The Pennsylvania State University ------------- Physical Security Office Intrusion Alarm Performance Specification By PHYSICAL SECURITY OFFICE Group (Access Controls & Electronic Security Programs) and
More information