1 Recovery Action Plan Guidelines July 2011

2 TABLE OF CONTENTS Section 1: Introduction... 3 Audience... 3 Background... 3 Purpose... 3 Section 2: Development of a Recovery Action Plan... 4 Information Sources... 4 Recovery Committee Meetings... 4 Impact Assessment... 5 Recovery Assessment... 5 Community Consultation Groups... 5 Recovery Task Groups... 6 Other Information Sources... 6 Monitoring... 6 Section 3: Components of the Recovery Action Plan... 7 Introduction... 7 Risks... 7 Recovery Issues and Actions Register... 7 Exit Strategy... 8 Information Sources... 8 Annexure... 9 Recovery Action Plan Example... 9 Definitions July 2011 Recovery Action Plan Guidelines 2

3 Section 1: Introduction Audience 1. These guidelines are written to assist recovery committees in the development of a recovery action plan. These guidelines and the associated template may also assist recovery task groups and community consultation groups in the preparation of their recovery action plan. Background 2. The NSW State Disaster Plan states that recovery operations in NSW are supported by the development of a recovery action plan that will be developed for all events requiring a formal recovery process. 3. The NSW Recovery Plan specifies that the first action for recovery committees is to develop a recovery action plan that details priorities, resource allocation and management. 4. Where a formal recovery committee is not established, a recovery action plan may still be developed by the local council or the Local Emergency Management Committee (LEMC). This will assist in guiding decisions and activities to ensure a successful recovery. Purpose 5. The Recovery Action Plan Guidelines are written as a supporting document to the NSW Recovery Plan. These guidelines should be read in conjunction with the NSW Recovery Plan and the suite of guidelines written in support of the Plan. These documents are available at 6. This document is written as a guide only and is non-prescriptive. A recovery action plan is unique to each event and guided by the needs of the community and the capacity to respond to these needs. An example is provided as an annexure and may be adapted as required for each disaster or emergency. July 2011 Recovery Action Plan Guidelines 3

4 Section 2: Development of a Recovery Action Plan 7. A recovery action plan provides the strategic direction and operational actions required to facilitate a successful recovery at local, district or state level. 8. One of the first actions for recovery committees is to develop a recovery action plan. A recovery action plan is an ongoing process that may need to be updated as the recovery unfolds or as further information becomes available in order to meet the needs of the community. Recovery Planning Pre event planning for recovery "Event" A natural disaster or other emergency Recovery Action Plan Responding to community needs after an event Figure 1: Timeline for the development of recovery plans Information Sources 9. Recovery activities may be derived from a number of key information sources including recovery committee minutes, impact assessments, recovery assessments, nongovernment organisations, community, businesses, organisations and industries, media, emergency services and government departments. 10. These actions, once agreed upon by the committee, should be incorporated into the recovery committee s overall recovery action plan for the event. Recovery Committee Meetings 11. Key actions for the recovery action plan may come from the decisions and actions of recovery committee meetings. July 2011 Recovery Action Plan Guidelines 4

5 Impact Assessment 12. An impact assessment is completed as soon as possible following a disaster or emergency by the Local Emergency Operations Controller (LEOCON). The impact assessment provides key information on the impact of the disaster on the community. 13. The impact assessment may also provide valuable information for forming the basis of the recovery action plan including potential risks and recovery requirements. Recovery Assessment 14. A recovery assessment may be completed for all events requiring a formal recovery process. It assesses the damage, loss and needs of an affected community across the four environments (social, built, economic and natural) following a major event. A recovery assessment builds on the information provided in the impact assessment completed during the response phase. 15. A recovery assessment process may be repeated throughout the recovery, to identify the changing needs of the community in short, medium and long term and may inform the development of a recovery action plan. Community Consultation Groups 16. The recovery committee may task community consultation groups to develop a recovery action plan on behalf of the community. The community consultation group should liaise with the community to develop and prioritise action items, assist with the implementation and provide feedback to the recovery committee. 17. Community involvement in the recovery action plan process promotes community ownership of recovery and future resilience. A number of strategies can be used to engage the community including workshops and community meetings. July 2011 Recovery Action Plan Guidelines 5

6 Recovery Committee recovery action plan Recovery Task Groups 18. The recovery committee may request that recovery task groups develop a recovery action plan with a specific focus on a particular recovery environment, for example social, built, economic or natural. Other Information Sources 19. Additional key information sources include non-government organisations, community, businesses, organisations and industries, media, emergency services and government departments. Community Consultation Group Recovery Action Plan Recovery Task Group Recovery Action Plan Recovery Committee Minutes Impact & Recovery Assessments Non-Government Organisations Businesses Media Government Departments Community Emergency Services Figure 2: Information sources for recovery actions for a recovery committee Monitoring 20. It is essential that each of the actions are monitored by the recovery committee and reported against by the responsible agency. 21. The development of a recovery plan is an ongoing process. New issues and actions will need to be added to the plan as the recovery progresses. 22. The recovery action plan should be updated at each recovery meeting. July 2011 Recovery Action Plan Guidelines 6

7 Section 3: Components of the Recovery Action Plan Introduction 23. The introduction should include an overview of the disaster or emergency. Types of information that should be documented includes: type of emergency (e.g. flood, bushfire, earthquake) location (including Local Government Areas, towns, villages and communities impacted) Major impacts on the community including disruptions to essential services. Impacts should be broken up into the four recovery environments: social, built, economic and natural. Risks 24. Consider the following: What risks are present including the potential for further events? How severe are the risks? If the risks eventuate, how are they likely to impact recovery operations? 25. Existing emergency risk management processes should be used when identifying, analysing, evaluating and treating the risks. Recovery Issues and Actions Register 26. Details the: issues or needs in each of the four environments: social, infrastructure, economic and natural issues that have not been considered or for which further information is required specific recovery activity or task required to address the issue agency(s) responsible for completing the task priority of the activity e.g. high, medium and low duration e.g. short, medium and long term activity date the action is due to be completed status e.g. completed, in progress, outstanding July 2011 Recovery Action Plan Guidelines 7

8 27. Any outstanding issues from the response phase should also be included. These may be detailed in the combat agency or supporting functional area reports, advised by agency or functional area representatives on the recovery committee or detailed in the Impact Assessment. 28. For large scale events each of the tables may need to be split into further tables detailing short, medium and long term priorities. Exit Strategy 29. An exit strategy is a systematic plan for the withdrawal of formal recovery structures once there is no longer a need for regular multi-agency co-ordination and any remaining issues can be dealt with by individual agencies as a part of their normal business. 30. The exit strategy should detail the: outstanding or ongoing task and associated activities handover of responsibilities to the agency or service that usually have responsibility for those activities, under normal circumstances Information Sources NSW State Disaster Plan NSW Recovery Plan Community Capacity Building in Disaster Recovery: leaving the community in a better place Albany Community Recovery Management Whittlesea Community Recovery Plan NSW Guidelines on Funding July 2011 Recovery Action Plan Guidelines 8

9 Annexure Recovery Action Plan Example Event Name Borta Coast Flood 2011 Date of Event 14 March 2011 Prepared By Borta Coast Local Recovery Committee Date Prepared 16 March 2011 Review Date Introduction On 14 March 2011, Borta Coast experienced strong winds and heavy rain resulting in widespread flooding across the local government area. The Ballooochi River flooded to major levels impacting on surrounding residences and the caravan park. The SES is the combat agency and continuing operations. The Borta Coast Recovery Committee was established to oversee recovery operations. A Recovery Coordinator, Mr Green, has been appointed. Key Statistics (as at 23/03/11) 3,522 animal losses; 30 caravans inundated; 2,000 homes inundated; 160 businesses inundated Impacts Social: Built: Economic: Natural: Immediate welfare assistance, displaced residents, public health risks from sewerage, contaminated household goods, carcasses and mosquito borne diseases, mental health issues, loss of social activities Building inundation, public school building damaged, power outages, significant road, culvert and bridge damage, land slips, water supply pump damaged, community facilities damaged and closed (library, community hall, parks and museum), nursing home damaged Inadequate and declined insurance, local business loss of income, tourism decline, loss of wages, loss of stock and machinery Decline in water quality of the drinking water, undercutting, slumping and erosion of banks, beach erosion, debris build up in creeks and rivers, large quantity of waste and debris

10 Risks Potential Risk Severity Impact Further rain causing flash flooding High rainfalls (up to 200ml) are expected in the next couple of days Further flooding and inundation Sewerage loss due to inundation High 600 homes without sewerage for up to 3 weeks if current systems fail Recovery Issues & Actions Priority: High Issue/Need Action/Task Agency responsible Some residents have lost everything. No Food, clothing and temporary housing Community access to money, clothing. Unable to stay required Services in home Main building of nursing home damaged and uninhabitable. Unable to temporarily house within own facility Main access road into town closed due to damage Electricity outage at hospital, backup generator in use additional supplies requested Several businesses now closed staff unemployed, no income Tap water contaminated, sewerage system damaged Alternate temporary housing for residents to be sought Temporary repairs to allow road to be opened ASAP Additional supplies of diesel to be delivered to the hospital Health, ADHC Environment Social Social Duration (Term) Short to medium Medium to Long Council Built Short SES Built Immediate financial assistance required Centrelink Economic Short Health messages distributed Health / Natural / Short Council Built Date to be completed Status July 2011 Recovery Action Plan Guidelines 10

11 Priority: Medium Issue/Need Action/Task Agency responsible Environment Duration (Term) Reports of mental health issues for Mental Health to establish a 1300 Health Social Long community members and recovery staff helpline for assistance affected by the flood Evacuation Centre to close on 17/03/11. Need central point for information and services for the community Many local roads damaged a number of residents are isolated Local public school main building and 2 classrooms damaged. Students cannot return. A large number of livestock, fodder and farming machinery damaged Disposal of households good damaged by the flood water Large numbers of animal carcasses on roads and private property Establish a recovery centre for the community Resupply continuing. Temporary repairs to be carried out ASAP Students to be sent to neighbouring schools. Temporary classrooms to be sought RAA to distribute information on grants available to farmers Arrange for the community to get free access to the tip for the next 2 weeks Arrange assistance for removal and disposal Recovery Committee, Public Works, Council SES, Council, RTA Education & Training, Transport Rural Assistance Authority Social Built Built Economic Short to Medium Medium Medium Council Natural Short Primary Industries Natural Medium Date to be completed Status July 2011 Recovery Action Plan Guidelines 11

12 Priority: Low Issue/Need Action/Task Agency responsible Agency information and available grants Council to develop a recovery Council, needs to be communicated to the newsletter for the community. Agencies community Agencies to supply information to Potential angst in the community Damage to fire trails Community Hall damaged permanently. Needs to be demolished. Significant impact on tourism Debris build up in creeks potentially causing further erosion and flooding Fish kill in Ballooochi River Council Community meeting and bbq to be held on 22 March. Agency representation required Discussions to be held with the Rural Fire Service in relation to restoration Alternate hall to be sourced for ongoing community social activities. Long term planning needed. Examine marketing campaign to regain tourism number prior to Easter Further discussions and examination required - potential removal Investigation required. Water and fish samples to be collected for analysis. No fishing signs to be placed at river Council, Agencies Environment Social Social Duration (Term) Medium to Long Medium Recovery Built Medium Coordinator Council Built Long Tourism Economic Long NSW CMA Natural Long Industry & Investment Natural Long Date to be completed Status Exit Strategy Outstanding Task Activities Agency Responsible Tasks from table above to be listed here once recovery committee winds down July 2011 Recovery Action Plan Guidelines 12

13 Definitions Community Consultation Group A group of local community members, including people affected by an event and representatives of local organisations, who meet and provide input and guidance to recovery committees. Disaster An occurrence, whether or not due to natural causes, that causes loss of life, injury, distress or danger to persons, or loss of, or damage to, property (Source: NSW Displan). Disaster Recovery The coordinated process of supporting disaster affected communities in the reconstruction of the physical infrastructure and the restoration of emotional, social, economic and physical wellbeing (Source: Australian Emergency Manual, Disaster Recovery EMA 2004). Emergency An emergency due to an actual or imminent occurrence (such as fire, flood, storm, earthquake, explosion, terrorist act, accident, epidemic or warlike action) which: (a) endangers, or threatens to endanger, the safety or health of persons or animals in the State; or (b) destroys or damages, or threatens to destroy or damage, any property in the State, being an emergency which requires a significant and co-ordinated response. For the purposes of the definition of emergency, property in the State includes any part of the environment of the State. Accordingly, a reference in the Act to: (a) threats or danger to property includes a reference to threats or danger to the environment, and (b) the protection of property includes a reference to the protection of the environment (Source: SERM Act). Essential Services For the purposes of the Essential Services Act, 1988, a service is an essential service if it consists of any of the following: a. the production, supply or distribution of any form of energy, power or fuel or of energy, power or fuel resources; b. the public transportation of persons or freight: c. the provision of fire-fighting services; d. the provision of health services (including hospital or medical services);

14 e. the provision of ambulance services; f. the production, supply or distribution of pharmaceutical products; g. the provision of garbage, sanitary cleaning or sewerage services; h. the supply or distribution of water; i. the conduct of a welfare institution; j. the conduct of a prison; k. a service declared to be an essential service under subsection (2); l. a service comprising the supply of goods or services necessary for providing any service referred to in paragraphs (a) - (k) (Source: NSW Displan). Hazard A potential or existing condition that may cause harm to people or damage to property or the environment (Source: NSW Displan). Impact Assessment A continuous and dynamic process of ongoing information assessments. It involves the collection, interpretation, analysis and treatment of social, built, economic and natural impacts to a community or communities. Local Emergency Management Committee (LEMC) The committee constituted under the State Emergency and Rescue Management Act 1989 (as amended), for each local government area, and is responsible for the preparation of plans in relation to the prevention of, preparation for, response to and recovery from emergencies in the local government area (Local DISPLAN) for which it is constituted. Local Emergency Operations Controller (LEOCON) A Police Officer appointed by the District Emergency Operations Controller as the Local Emergency Operations Controller for the Local Government Area (Source: NSW Displan). Natural Disaster A serious disruption to a community or region caused by the impact of a naturally occurring rapid onset event that threatens or causes death, injury or damage to property or the environment and which requires significant and coordinated multi-agency and community response. Such serious disruption can be caused by any one, or a combination, of the following natural hazards: bushfire; earthquake; flood; storm; cyclone; storm surge; landslide; tsunami; meteorite strike; or tornado (Source: NSW Displan). July 2011 Recovery Action Plan Guidelines 14

15 NSW Recovery Plan The plan outlining the strategic intent, responsibilities, authorities and mechanisms for disaster recovery in NSW. NSW State Disaster Plan Details emergency preparedness, response and recovery arrangements for NSW to ensure the coordinated response to emergencies by all agencies having responsibilities and functions in emergencies. Recovery In relation to an emergency includes the process of returning an affected community to its proper level of functioning after an emergency (Source: NSW Displan). Recovery Action Plan A plan developed to provide the strategic direction and operational actions required to facilitate a successful recovery at local, district and/or state level. Recovery Assessment A formalised process for assessing the damage, loss and needs of an affected community following a major emergency. Recovery Committee The strategic decision making body for recovery providing visible and strong leadership with a key role in restoring confidence to the community through assessing the consequences of the emergency and coordinating activities to rebuilding, restoring and rehabilitating the affected community. Recovery Coordinator The public face of the recovery operation, providing leadership to the recovery committee and coordinating the recovery effort in accordance with agreed recovery plans. Recovery Task Group A coordinated group of agencies with significant expertise in a particular recovery environment (social, built, economic, natural). Risk A concept used to describe the likelihood of harmful consequences arising from the interaction of hazards, communities and the environment (Source: NSW Displan). July 2011 Recovery Action Plan Guidelines 15

16 Risk Assessment The process used to determine risk management priorities by evaluating and comparing the level of risk against predetermined standards, target risk levels or other criteria (Source: NSW Displan). Risk Management The systematic application of management policies, procedures and practices to the tasks of identifying, analysing, evaluating, treating and monitoring risk (Source: NSW Displan). State Emergency and Rescue Management Act 1989 (SERM Act) as amended The underlying act for emergency management in NSW. It specifies responsibilities of the Minister and requirements of the Displan. Supporting Plan A plan prepared by an agency, organisation or functional area, which describes the support which is to be provided to the controlling or coordinating authority during emergency operations. It is an action plan which describes how the agency / organisation or functional area is to be coordinated in order to fulfil the roles and responsibilities allocated (Source: NSW Displan). July 2011 Recovery Action Plan Guidelines 16

Community Emergency Planning Guide

Community Emergency Planning Guide Community Emergency Planning Guide Our district has experienced numerous events over past years. Evidence from previous emergencies has shown that communities that plan and manage their own needs before,

More information

BRYN MAWR COLLEGE EMERGENCY RESPONSE PLAN Revised 3/17/08 (abridged)

BRYN MAWR COLLEGE EMERGENCY RESPONSE PLAN Revised 3/17/08 (abridged) BRYN MAWR COLLEGE EMERGENCY RESPONSE PLAN Revised 3/17/08 (abridged) This document is a synopsis of the planning and preparation the College has undertaken to handle emergencies in a professional, efficient,

More information

EMERGENCY PROGRAM MANAGEMENT REGULATION 477/94

EMERGENCY PROGRAM MANAGEMENT REGULATION 477/94 PDF Version [Printer-friendly - ideal for printing entire document] EMERGENCY PROGRAM MANAGEMENT REGULATION 477/94 Published by Quickscribe Services Ltd. Updated To: [includes B.C. Reg. 200/98 amendments]

More information

Bridge Parish Council Community Emergency Plan

Bridge Parish Council Community Emergency Plan BRIDGE Parish Council Caring for the village Bridge Parish Council Community Emergency Plan IF YOU ARE IN IMMEDIATE DANGER CALL 999 October 2014 All enquiries relating to this document should be sent to:

More information

The University of British Columbia Board of Governors

The University of British Columbia Board of Governors The University of British Columbia Board of Governors Policy No.: 8 Approval Date: May 2000 Last Revision: June 2005 Responsible Executive: Vice-President, Finance, Resources and Operations Title: Disaster

More information

Flood warnings. What they are and what they do. A guide to the Environment Agency s flood warning codes

Flood warnings. What they are and what they do. A guide to the Environment Agency s flood warning codes Flood warnings What they are and what they do A guide to the Environment Agency s flood warning codes We are the Environment Agency. It s our job to look after your environment and make it a better place

More information

Animals in Disasters

Animals in Disasters MODULE B UNIT 6 Animals in Disasters Recovering from a Disaster Overview Federal, State, and local governments work together in any major emergency. Emergency assistance funding is based on the concept

More information

Emergency Management Audit For Businesses

Emergency Management Audit For Businesses Emergency Management Audit For Businesses Sponsor Acknowledgement: This manual is sponsored by NZ Safety Limited and produced for the Ministry of Civil Defence Public Education Advisory Committee by Auckland

More information

Draft Dapto Flood Management Plan

Draft Dapto Flood Management Plan NATURE OF HAZARD Draft Dapto Flood Management Plan Since Dapto school has been established on the current site there have been two floods. The SES is responsible for responding to floods in NSW. During

More information

Good Security. Good Business

Good Security. Good Business Good Security Good Business Good Security Good Business Attorney-General s foreword Small business plays a crucial role, not only in our nation s economy but in Australian society. We often make decisions

More information

Flood Information Update No. 4 20 January 2011

Flood Information Update No. 4 20 January 2011 Flood Information Update No. 4 20 January 2011 This Flood Information Update contains information about services available to the community to assist in dealing with the impact of the recent flood event

More information

Preparation. Preparation. Step 2 Prepare an emergency kit. Step 1 Prepare your emergency plan. Step 4 Tune into warnings

Preparation. Preparation. Step 2 Prepare an emergency kit. Step 1 Prepare your emergency plan. Step 4 Tune into warnings This emergency toolkit provides you with steps to take before and during emergencies to protect you and your property. The Victoria State Emergency Service (SES) is a volunteer organisation dedicated to

More information

Emergency Management is responsible for coordinating the City of Houston s preparation for and response to emergency situations.

Emergency Management is responsible for coordinating the City of Houston s preparation for and response to emergency situations. CITY OF HOUSTON Office of Emergency Management October 2004 Emergency Management is responsible for coordinating the City of Houston s preparation for and response to emergency situations. Houston is exposed

More information

Assessing Resilience and Vulnerability in the Context of Emergencies: Guidelines

Assessing Resilience and Vulnerability in the Context of Emergencies: Guidelines Assessing Resilience and Vulnerability in the Context of Emergencies: Guidelines Acknowledgements Assessing Resilience and Vulnerability in the Context of Emergencies: Guidelines This work is copyright

More information

STATE EMERGENCY MANAGEMENT PLAN FOR FLOOD SEPTEMBER 2010 (WESTPLAN - FLOOD)

STATE EMERGENCY MANAGEMENT PLAN FOR FLOOD SEPTEMBER 2010 (WESTPLAN - FLOOD) STATE EMERGENCY MANAGEMENT PLAN FOR FLOOD SEPTEMBER 2010 (WESTPLAN - FLOOD) Prepared by APPROVED AT SEMC MEETING RESOLUTION NO: 91/2010 DATE OF APPROVAL: 21 September 2010 REVIEW DATE: September 2015 Contact

More information

Basic system of measures for flood damage mitigation in Japan. Preparedness for major floods

Basic system of measures for flood damage mitigation in Japan. Preparedness for major floods Basic system of measures for flood damage mitigation in Japan Preparedness for major floods Past major floods and state-level efforts Role of the 2 MLIT's disaster prevention efforts Disaster prevention

More information

Bus incident management planning: Guidelines

Bus incident management planning: Guidelines Bus incident management planning: Guidelines What is incident management planning? Incident management planning is everything your business does to prepare for potential disruptive or damaging incidents.

More information

Disaster Preparedness for Persons with Mental Health Needs

Disaster Preparedness for Persons with Mental Health Needs Disaster Preparedness: The impact of hurricanes, tornadoes, acts of terrorism, and floods are all clear in the minds of everyone today. But, even though we all know what CAN happen, are we prepared? Can

More information

11. Health and disability services

11. Health and disability services 11. Health and disability services Summary The Ministry of Health and all other health sector agencies undertake the planning necessary to provide health and disability services in the event of any emergency.

More information

Sample Emergency and Critical Incident Policy and Procedure

Sample Emergency and Critical Incident Policy and Procedure Sample Emergency and Critical Incident Policy and Procedure 1. Purpose and Scope Emergencies and critical incidents in the workplace can affect people physically and psychologically, and affect program

More information

PRESENTERS: BACHELOR OF ARTS- PSYCHOLOGY

PRESENTERS: BACHELOR OF ARTS- PSYCHOLOGY KIBET J. NELLY PRESENTERS: MAGAI N. DORCAS BACHELOR OF ARTS- PSYCHOLOGY DISASTER? A serious disruption of the functioning of a community or society causing widespread human, material, economic or environmental

More information

Anchorage All-Hazard Mitigation Plan October 2004

Anchorage All-Hazard Mitigation Plan October 2004 EXECUTIVE SUMMARY The Municipality of Anchorage (MOA) is vulnerable to a wide range of natural, technological, and human/societal hazards including earthquakes, avalanches, and hazardous material accidents.

More information

Assisted Living Facilities & Adult Care Comprehensive Emergency Management Plans

Assisted Living Facilities & Adult Care Comprehensive Emergency Management Plans Assisted Living Facilities & Adult Care Comprehensive Emergency Management Plans STATUTORY REFERENCE GUIDANCE CRITERIA The Henrico County Division of Fire s Office of Emergency Management provides this

More information

Maryland Emergency Operations Plan

Maryland Emergency Operations Plan Maryland Emergency Operations Plan Purpose The purpose of the Maryland Emergency Operations Plan (EOP) is to outline an approach and designate responsibilities intended to minimize the consequences of

More information

Emergency Management Certification and Training (EMC & T) Refresher Terry Hastings, DHSES Senior Policy Advisor

Emergency Management Certification and Training (EMC & T) Refresher Terry Hastings, DHSES Senior Policy Advisor Emergency Management Certification and Training (EMC & T) Refresher Terry Hastings, DHSES Senior Policy Advisor 2015 NYSEMA Conference 2 Please sign in to ensure that you receive credit for the refresher

More information

DISASTER MANAGEMENT. Goals To instill an understanding of the disaster management process

DISASTER MANAGEMENT. Goals To instill an understanding of the disaster management process DISASTER MANAGEMENT Goals To instill an understanding of the disaster management process Learning outcomes After completing this session, you will be able to Affirm the usefulness of integrating management

More information

Table of Contents ESF-3-1 034-00-13

Table of Contents ESF-3-1 034-00-13 Table of Contents Primary Coordinating Agency... 2 Local Supporting Agencies... 2 State, Regional, and Federal Agencies and Organizations... 3 Purpose... 3 Situations and Assumptions... 4 Direction and

More information

Local Flood Guide. Safe. Warragul. Flood information for Warragul. Warragul

Local Flood Guide. Safe. Warragul. Flood information for Warragul. Warragul Warragul Safe Flood information for Warragul Warragul Local Flood Information The Warragul local area Your local emergency broadcasters are: Warragul is located east of Melbourne. The town s major waterways

More information

Flooding Fast Facts. flooding), seismic events (tsunami) or large landslides (sometime also called tsunami).

Flooding Fast Facts. flooding), seismic events (tsunami) or large landslides (sometime also called tsunami). Flooding Fast Facts What is a flood? Flooding is the unusual presence of water on land to a depth which affects normal activities. Flooding can arise from: Overflowing rivers (river flooding), Heavy rainfall

More information

INTERIM STATE EMERGENCY MANAGEMENT PLAN FOR STATE LEVEL RECOVERY COORDINATION WESTPLAN RECOVERY COORDINATION

INTERIM STATE EMERGENCY MANAGEMENT PLAN FOR STATE LEVEL RECOVERY COORDINATION WESTPLAN RECOVERY COORDINATION INTERIM STATE EMERGENCY MANAGEMENT PLAN FOR STATE LEVEL RECOVERY COORDINATION December 2013 WESTPLAN RECOVERY COORDINATION Approved by the State Emergency Management Committee Resolution No: 106/2013 Review

More information

PART C EMERGENCY MANAGEMENT ARRANGEMENTS

PART C EMERGENCY MANAGEMENT ARRANGEMENTS PART C EMERGENCY MANAGEMENT ARRANGEMENTS Photo courtesy of Barry Davies Importance to the Community Protecting and reassuring the community in circumstances of an emergency that threatens the peace, stability

More information

Municipal Emergency Management Planning Arrangements Guidelines for Committees Part 6: Emergency Management Manual Victoria

Municipal Emergency Management Planning Arrangements Guidelines for Committees Part 6: Emergency Management Manual Victoria Municipal Emergency Management Planning Arrangements Guidelines for Committees Part 6: Emergency Management Manual Victoria Part 6 - Municipal Emergency Management Planning Arrangements Contents 6.1 Introduction

More information

Emergency Procedures Plan

Emergency Procedures Plan Page 1 of 62 Emergency Procedures Plan Facilities Management and Services (FM+S) Page 2 of 62 1. PRELIMINARIES 1.1 AMENDMENT APPROVAL SHEET Amendment No. Date Version A May 2005 Page No. Amended By Approved

More information

Flood Management and Reconstruction: the Recent Queensland Experience

Flood Management and Reconstruction: the Recent Queensland Experience Flood Management and Reconstruction: the Recent Queensland Experience Chair, Queensland Reconstruction Authority Major General Richard Wilson January 2012 Scale and Scope - Timeline Dec 23: Rainfall central

More information

PART 2 LOCAL RECOVERY ARRANGEMENTS

PART 2 LOCAL RECOVERY ARRANGEMENTS CONTENTS Distribution List 2 Amendment Record 4 PART 1 MANAGEMENT 1. Authority for the Arrangements 5 2. Geographical area covered 5 3. Aim 5 4. Objectives 5 5. Scope 6 6. Title 6 7. Related Documents

More information

Business Continuity Plan Template

Business Continuity Plan Template Business Continuity Plan Template Disclaimer This publication has been produced to provide a guide for people anticipating going into business and for business owners. It should not be regarded as an

More information

Promote Business Continuity Planning for Disaster Resiliency in Vietnamese economy

Promote Business Continuity Planning for Disaster Resiliency in Vietnamese economy Promote Business Continuity Planning for Disaster Resiliency in Vietnamese economy Presented by: Nguyen Thị Thu Ha Disaster Management Center, Viet Nam Email: nguyenhadmc@gmail.com Tel: (+84) 966.175.688

More information

PROPOSAL FOR CONTRACTORS ALL RISKS

PROPOSAL FOR CONTRACTORS ALL RISKS PROPOSAL FOR CONTRACTORS ALL RISKS 1. Title of contract (If project consist of several sections, specify section(s) to be insured) 2. Location of site Country/Province/district City/town/village 3. Name

More information

Glossary. ambulance: a vehicle equipped for transportation of sick and injured persons. believe: to accept as true or real

Glossary. ambulance: a vehicle equipped for transportation of sick and injured persons. believe: to accept as true or real act: the process of doing or performing something ambulance: a vehicle equipped for transportation of sick and injured persons believe: to accept as true or real cascading disaster: the effects of one

More information

Otago Civil Defence Emergency Management

Otago Civil Defence Emergency Management Otago Civil Defence Emergency Management Group Plan 2012-2017 PLAN STRUCTURE Glossary The Glossary provides definitions or interpretations of terminology, acronyms and abbreviations. Introduction Risk

More information

disaster recovery and contingency plan RISK MANAGEMENT MADE TO MEASURE

disaster recovery and contingency plan RISK MANAGEMENT MADE TO MEASURE disaster recovery and contingency plan RISK MANAGEMENT MADE TO MEASURE INTRODUCTION Contingency planning for business continuity (business continuity management) is defined by the Institute of Business

More information

Disaster & Disability: The Role of the local government to minimize the community risk during the disaster.

Disaster & Disability: The Role of the local government to minimize the community risk during the disaster. Disaster & Disability: The Role of the local government to minimize the community risk during the disaster. Shahidul Haque Chief Executive Social Assistance and Rehabilitation for the Physically Vulnerable

More information

Natural Disasters & Assessing Hazards and Risk. Natural Hazards and Natural Disasters

Natural Disasters & Assessing Hazards and Risk. Natural Hazards and Natural Disasters Page 1 of 9 EENS 3050 Tulane University Natural Disasters Prof. Stephen A. Nelson Natural Disasters & Assessing Hazards and Risk This page last updated on 19-Aug-2014 Natural Hazards and Natural Disasters

More information

Don t let your business g o u n der

Don t let your business g o u n der Business FloodSafe Toolkit and Plan Don t let your business go under Never drive, ride or walk through floodwater If you need assistance during a fl od, call the SES on 132 500 If an emergency is life

More information

Local flood and landslide guide. Halls Gap HALLS GAP

Local flood and landslide guide. Halls Gap HALLS GAP Local flood and landslide guide Halls Gap HALLS GAP Local Flood Information The Halls Gap local area Halls Gap is located in the heart of the Grampians National Park surrounded by the Grampians mountain

More information

Graduate School of Disaster Prevention Kangwon National University. http://college.kangwon.ac.kr/prevention/main.jsp

Graduate School of Disaster Prevention Kangwon National University. http://college.kangwon.ac.kr/prevention/main.jsp Graduate School of Disaster Prevention Kangwon National University 1joongang-Ro Samcheok-city, Gangwon-Do, Republic of Korea http://college.kangwon.ac.kr/prevention/main.jsp Outline Natural disasters such

More information

How To Write A Business Floodsafe Plan

How To Write A Business Floodsafe Plan Business FloodSafe Toolkit and Plan Don t let your business go under Never drive, ride or walk through floodwater If you need assistance during a fl od, call the SES on 132 500 If an emergency is life

More information

Business continuity plan

Business continuity plan Business continuity plan CONTENTS INTRODUCTION 2 - Scope - Components BUSINESS IMPACT ANALYSIS 3 - Business Affairs - Information Technology RISK ASSESSMENT 5 - Broad Categories of Hazards - Hazard Table

More information

EMERGENCY COMMUNICATION PLAN

EMERGENCY COMMUNICATION PLAN EMERGENCY COMMUNICATION PLAN 2 Document Control Revision: 1 Date: 4 February 2014 Status: Document change control: Approved by EPC Revision # Change Description Date Author 1 Initial document release as

More information

UNITED CHURCH OF CHRIST LOCAL CHURCH DISASTER PREPAREDNESS AND RESPONSE PLANNING GUIDELINES

UNITED CHURCH OF CHRIST LOCAL CHURCH DISASTER PREPAREDNESS AND RESPONSE PLANNING GUIDELINES UNITED CHURCH OF CHRIST LOCAL CHURCH DISASTER PREPAREDNESS AND RESPONSE PLANNING GUIDELINES The United Church of Christ local churches may use this plan as a guide when preparing their own disaster plans

More information

CERT Damage Assessment Operations

CERT Damage Assessment Operations CERT DAMAGE ASSESSMENT OPERATIONS CERT Damage Assessment Operations Residential Assessments Individual Assistance Program CERT DAMAGE ASSESSMENT OPERATIONS AGENDA Requirements Pre-Official Damage Assessment

More information

Policy Clarifications on the Eligibility of Water and Wastewater Utility Projects for FEMA s Public Assistance and Hazard Mitigation Assistance Grants

Policy Clarifications on the Eligibility of Water and Wastewater Utility Projects for FEMA s Public Assistance and Hazard Mitigation Assistance Grants Policy Clarifications on the Eligibility of Water and Wastewater Utility Projects for FEMA s Public Assistance and Hazard Mitigation Assistance Grants I. Introduction and Purpose This document provides

More information

Chatham County Disaster Recovery Plan Recovery Planning Update. Mark Misczak, Brock Long, & Corey Reynolds Hagerty Consulting April 7, 2015

Chatham County Disaster Recovery Plan Recovery Planning Update. Mark Misczak, Brock Long, & Corey Reynolds Hagerty Consulting April 7, 2015 Chatham County Disaster Recovery Plan Recovery Planning Update Mark Misczak, Brock Long, & Corey Reynolds Hagerty Consulting April 7, 2015 Welcome Introduction to Recovery Planning Recovery Planning Process

More information

A Comprehensive Summary

A Comprehensive Summary Minnesota Department of Public Safety Division of Homeland Security and Emergency Management Minnesota Recovers Task Force Fact Sheet 2015 A Comprehensive Summary Purpose This document will review the

More information

Standard Operating Procedures for Flood Preparation and Response

Standard Operating Procedures for Flood Preparation and Response Standard Operating Procedures for Flood Preparation and Response General Discussion Hurricanes, tropical storms and intense thunderstorms support a conclusion that more severe flooding conditions than

More information

Critical Incident Policy. Document Sponsor: Dr Stephen Weller Deputy Vice-Chancellor, University Services and Head of Campus, Cairns

Critical Incident Policy. Document Sponsor: Dr Stephen Weller Deputy Vice-Chancellor, University Services and Head of Campus, Cairns Critical Incident Policy Document Sponsor: Dr Stephen Weller Deputy Vice-Chancellor, University Services and Head of Campus, Cairns Document Date: 14 September 2011 Contents Intent... 1 Scope... 1 Definitions...

More information

Australian Capital Territory ACT Community Recovery Sub-Plan

Australian Capital Territory ACT Community Recovery Sub-Plan Australian Capital Territory ACT Community Recovery Sub-Plan A supporting plan of the ACT Recovery Plan that details the arrangements for the provision of services targeted towards social recovery within

More information

Date plan was updated: Household name: Address: Phone:

Date plan was updated: Household name: Address: Phone: Home Emergency Plan. Date plan was updated: Household name: Address: Phone: Storms and other emergencies can happen anywhere and at any time. They can strike without warning and have a significant impact

More information

REPUBLIC OF SOUTH AFRICA DISASTER MANAGEMENT AMENDMENT BILL

REPUBLIC OF SOUTH AFRICA DISASTER MANAGEMENT AMENDMENT BILL REPUBLIC OF SOUTH AFRICA DISASTER MANAGEMENT AMENDMENT BILL -------------------------------- (As introduced in the National Assembly (proposed section 76; explanatory summary of Bill published in Government

More information

CRISIS MANAGEMENT PLAN FOR THE DSK

CRISIS MANAGEMENT PLAN FOR THE DSK CRISIS MANAGEMENT PLAN FOR THE DSK March, 2009 By Christa Dietterle Index: 1. Executive Summary page 2 2. Introduction page 3 3. Prevention and Mitigation page 6 4. Preparedness page 7 5. Response page

More information

Pike County General Health District. Emergency Response Plan

Pike County General Health District. Emergency Response Plan Pike County General Health District Emergency Response Plan Updated October 2014 Basic Plan Primary Agency Support Agencies Introduction Purpose Scope Phases of Emergency Management Situations Assumptions

More information

Landslides. Landslides-1. March 2007

Landslides. Landslides-1. March 2007 Landslides Learn if landslides, including debris flows, could occur in your area by contacting local officials, your state geological survey or department of natural resources, or the geology department

More information

The Role of Government in a Disaster

The Role of Government in a Disaster Chapter 3: During the Disaster The Role of Government in a Disaster Government agencies play a critical role during times of disaster, but the exact role of government is often unclear to disaster victims.

More information

KAWERAU DISTRICT COUNCIL BUSINESS DISASTER RECOVERY PLAN 2011

KAWERAU DISTRICT COUNCIL BUSINESS DISASTER RECOVERY PLAN 2011 KAWERAU DISTRICT COUNCIL BUSINESS DISASTER RECOVERY PLAN 2011 Kawerau District Council Private Bag 1004 Ranfurly Court KAWERAU 3169 Tel (07) 306 9009 Fax (07) 323 8072 Email kaweraudc@kaweraudc.govt.nz

More information

Your responsibilities...

Your responsibilities... Your responsibilities... Identify if you are living in a flood risk area: visit www.environment-agency.gov.uk/floodline or call Floodline on 0845 9881188. Protect your home or property. Provide your own

More information

Preparedness in the Southwest

Preparedness in the Southwest Preparedness in the Southwest Risk Assessment and Hazard Vulnerability Developed by The Arizona Center for Public Health Preparedness Cover Art www.azcphp.publichealth.arizona.edu Chapter 1 Importance

More information

Draft 8/1/05 SYSTEM First Rev. 8/9/05 2 nd Rev. 8/30/05 EMERGENCY OPERATIONS PLAN

Draft 8/1/05 SYSTEM First Rev. 8/9/05 2 nd Rev. 8/30/05 EMERGENCY OPERATIONS PLAN Draft 8/1/05 SYSTEM First Rev. 8/9/05 2 nd Rev. 8/30/05 EMERGENCY OPERATIONS PLAN I. INTRODUCTION A. PURPOSE - The University of Hawaii System Emergency Operations Plan (EOP) provides procedures for managing

More information

A Guide to the Role of Community Flood Wardens

A Guide to the Role of Community Flood Wardens A Guide to the Role of Community Flood Wardens What is a Community Flood Warden Scheme? Community Flood Warden schemes are completely voluntary, and can consist of a single person or several people acting

More information

Local Government and Recovery in WA

Local Government and Recovery in WA Local Recovery Guidelines VERSION Local Recovery Guidelines V4 December 2014 TABLE OF CONTENTS CONTENTS PART 1: INTRODUCTION TO RECOVERY MANAGEMENT... 4 HOW TO USE THE GUIDELINES... 4 WHAT IS RECOVERY

More information

NEW SOUTH WALES STATE FLOOD SUB PLAN A SUB PLAN OF THE NEW SOUTH WALES DISASTER PLAN (DISPLAN)

NEW SOUTH WALES STATE FLOOD SUB PLAN A SUB PLAN OF THE NEW SOUTH WALES DISASTER PLAN (DISPLAN) NEW SOUTH WALES STATE FLOOD SUB PLAN A SUB PLAN OF THE NEW SOUTH WALES DISASTER PLAN (DISPLAN) AUTHORISATION This New South Wales State Flood Sub Plan is a sub-plan of the State Disaster Plan (DISPLAN).

More information

ACT COMMUNITY RECOVERY PLAN. A Functional Plan of the ACT Emergency Plan

ACT COMMUNITY RECOVERY PLAN. A Functional Plan of the ACT Emergency Plan ACT COMMUNITY RECOVERY PLAN A Functional Plan of the ACT Emergency Plan Prepared by Community Recovery ACT Department of Disability, Housing and Community Services August 2007 Authorisation The Australian

More information

HEALTH INFORMATION MANAGEMENT In Emergency

HEALTH INFORMATION MANAGEMENT In Emergency HEALTH INFORMATION MANAGEMENT In Emergency Regional training course on emergency response operation, Hue, Viet Nam, 23-27 Feb, 2009 Learning Objectives By the end of this session, the participant should

More information

South West Lincolnshire NHS Clinical Commissioning Group Business Continuity Policy

South West Lincolnshire NHS Clinical Commissioning Group Business Continuity Policy South West Lincolnshire NHS Clinical Commissioning Group Business Continuity Policy Reference No: CG 01 Version: Version 1 Approval date 18 December 2013 Date ratified: 18 December 2013 Name of Author

More information

Long Term Recovery and Rehabilitation. Issues for discussion. Recovery

Long Term Recovery and Rehabilitation. Issues for discussion. Recovery Long Term Recovery and Rehabilitation Issues for discussion Recovery The restoration, and improvement where appropriate, of facilities, livelihoods and living conditions of disaster-affected communities,

More information

El Nino in the OC. Orange County Sheriff s Department Emergency Management Division

El Nino in the OC. Orange County Sheriff s Department Emergency Management Division El Nino in the OC Orange County Sheriff s Department Emergency Management Division The mission of the Orange County Sheriff s Department s Emergency Management Division is to promote, facilitate, and support

More information

2010-11. Recovery Progress Report

2010-11. Recovery Progress Report Victorian Floods 2010-11 Recovery Progress Report SUMMARY FOREWORD Floods can wreak havoc on everything in their path and the numerous flooding events that hit more than two-thirds of Victoria from late

More information

CHAPTER 37 DISASTER RECOVERY AND RECONSTRUCTION

CHAPTER 37 DISASTER RECOVERY AND RECONSTRUCTION CHAPTER 37 DISASTER RECOVERY AND RECONSTRUCTION 37.01 Authority 37.07 Temporary Regulations 37.02 Purposes 37.08 Demolition of Damaged Buildings 37.03 Definitions 37.09 Temporary and Permanent Housing

More information

Natural Hazards 1.1. Natural Hazards. Objective: Natural Hazards in Western Australia Are we at risk? Page 1. Natural Hazards Years 5-7

Natural Hazards 1.1. Natural Hazards. Objective: Natural Hazards in Western Australia Are we at risk? Page 1. Natural Hazards Years 5-7 Natural Hazards 1.1 Engage Natural Hazards To introduce students to the natural hazards which occur in Western Australia and their risk. Western Australia experiences a range of natural hazards each year,

More information

ALBUQUERQUE EMERGENCY OPERATIONS PLAN ANNEX 8 DAMAGE ASSESSMENT AND REPORTING

ALBUQUERQUE EMERGENCY OPERATIONS PLAN ANNEX 8 DAMAGE ASSESSMENT AND REPORTING ALBUQUERQUE EMERGENCY OPERATIONS PLAN ANNEX 8 DAMAGE ASSESSMENT AND REPORTING PRIMARY RESPONSIBILITY Albuquerque City and Bernalillo County Government SECONDARY RESPONSIBILITY Department of Public Safety,

More information

February 2011 Records disaster preparedness and

February 2011 Records disaster preparedness and February 2011 Records disaster preparedness and recovery It will never happen... Disasters are unexpected events with destructive consequences which can be measured by the scale of damage as well as the

More information

CRITICAL/NON CRITICAL INCIDENT MANAGEMENT AND REPORTING PROCEDURE

CRITICAL/NON CRITICAL INCIDENT MANAGEMENT AND REPORTING PROCEDURE CRITICAL/NON CRITICAL INCIDENT MANAGEMENT AND REPORTING PROCEDURE This procedure must be read in conjunction and interpreted in line with the Critical/Non Critical Incident Management and Reporting policy.

More information

City of Salinas Flood Response Preparations

City of Salinas Flood Response Preparations City of Salinas Flood Response Preparations Winter Preparations Goals for 2015/2016 Community Preparedness in the event of flooding Media cooperation on safety and preparedness, public information sharing

More information

Emergency Plan Starter Kit

Emergency Plan Starter Kit ARDA-HOA Outreach Emergency Plan Starter Kit Advanced planning is the key to any type of natural disaster. A. Is your property at risk for any type of natural disaster hurricane, tornado, wild fire, floods,

More information

CONTRACTORS ALL RISKS INSURANCE PROPOSAL FORM CONTRACTORS ALL RISKS INSURANCE PROPOSAL FORM

CONTRACTORS ALL RISKS INSURANCE PROPOSAL FORM CONTRACTORS ALL RISKS INSURANCE PROPOSAL FORM Allied Cooperative Insurance Group (ACIG) شركة املجموعة املتحدة للتاأمني التعاوين ) أ سيج( CONTRACTORS ALL RISKS INSURANCE Call us: 920012331 www.acig.com.sa CONTRACTORS ALL RISKS INSURANCE UCONTRACTORS

More information

Floods as a One Health Problem

Floods as a One Health Problem Floods as a One Health Problem Learning Objec7ves At the end of the session par7cipants will be able to: Understand how floods (and other disasters) can be viewed as a One Health problem Describe how climate

More information

Pinkenba emergency evacuation

Pinkenba emergency evacuation Pinkenba Community E ContEnts 1. Amendments 4 2. IntroductIon 5 2.1 overview 5 2.2 Authority 5 2.3 Purpose 5 2.4 scope 5 2.5 Pinkenba residential area 5 2.6 review process 6 2.7 emergency management methodology

More information

TIPS ON GENERAL INSURANCE: PREPAREDNESS AND RECOVERY

TIPS ON GENERAL INSURANCE: PREPAREDNESS AND RECOVERY TIPS ON GENERAL INSURANCE: PREPAREDNESS AND RECOVERY MARCH 2007 THE IMPORTANCE OF HAVING GENERAL INSURANCE Insurance is an important component of an individuals and businesses risk management program.

More information

Flood Facts 2F.1. Flood Facts

Flood Facts 2F.1. Flood Facts Flood Facts 2F.1 Engage Flood Facts To introduce students to the causes and effects of flooding in Western Australia. Flooding occurs in the Australian environment as part of the natural water or hydrologic

More information

Water Quality Contingency Planning Standard EPB 540B

Water Quality Contingency Planning Standard EPB 540B Water Quality Contingency Planning Standard EPB 540B November 15, 2012 Water Quality Contingency Planning Standard The Water Quality Contingency Plan Standard is provided to aid waterworks owners and operators

More information

BUSINESS CONTINUITY PLAN

BUSINESS CONTINUITY PLAN Business Logo or Name here BUSINESS CONTINUITY PLAN FOR PERSONAL CARE PROVIDERS TEMPLATE PREPARED BY DEVON COUNTY COUNCIL EMERGENCY PLANNING SERVICE BUSINESS CONTINUITY PLAN LIST OF CONTENTS 1. DISCLAIMER...

More information

9.8 APPENDIX H Proclamations/Declarations-Frequently Asked Questions

9.8 APPENDIX H Proclamations/Declarations-Frequently Asked Questions 9.8 APPENDIX H Proclamations/Declarations-Frequently Asked Questions Frequently Asked Questions Local Emergency (City/County) What is a local emergency? Conditions of disaster or extreme peril (air pollution,

More information

Disaster Recovery Financial Assistance

Disaster Recovery Financial Assistance Disaster Recovery Financial Assistance Recovering from a disaster is a partnership effort among local, state and federal government agencies in conjunction with private and non-profit organizations. Rebuilding

More information

OURIMBAH FLOOD RESPONSE PLAN

OURIMBAH FLOOD RESPONSE PLAN OURIMBAH FLOOD RESPONSE PLAN February 2014 2 EMERGENCY CONTACT DETAILS Security Services for all Emergencies (24 Hours) Ourimbah 4348 4222 If not able to be reached please call Newcastle on Newcastle 4921

More information

Operations Directives

Operations Directives Queensland Operations Doctrine Operations Directives Incident Management System Hierarchy of Command and Control Version: 1.0 Valid from: 22/12/2008 ODI 2.0 1. PURPOSE To detail the command and control

More information

Emergency Response and Business Continuity Management Policy

Emergency Response and Business Continuity Management Policy Emergency Response and Business Continuity Management Policy Owner: John Duffy, Registrar & Secretary Last updated: September 2012 Version: 04 Document control Date Version Author Changes To be populated

More information

Jefferson Parish Department of Water Emergency Plan

Jefferson Parish Department of Water Emergency Plan 1. Overview Jefferson Parish Department of Water Emergency Plan 1.1. Purpose The purpose of this document is to establish procedures for the Department of Water during natural disasters or terrorist acts.

More information

RISD Hurricane Preparedness

RISD Hurricane Preparedness RISD Hurricane Preparedness Hurricane It is the policy of RISD to view each hurricane threat as an extremely hazardous condition. As such, our goal is to minimize the risk to personnel consistent with

More information

PUBLIC ASSISTANCE DAMAGE ASSESSMENT

PUBLIC ASSISTANCE DAMAGE ASSESSMENT PUBLIC ASSISTANCE DAMAGE ASSESSMENT Who does it? Political Subdivisions, Special Districts, Local/Regional Authorities, Public Schools/Colleges/Universities, Certain Private Non-Profit Organizations (PNP)

More information

Don t gamble with your business prepare for survival

Don t gamble with your business prepare for survival Don t gamble with your business prepare for survival Businesslike, efficient and customer aware This guide will help you to identify potential risks, make preparations for emergencies and test how your

More information

UNOPS Risk-Sensitive Planning for Resilient Infrastructure Development

UNOPS Risk-Sensitive Planning for Resilient Infrastructure Development UNOPS Risk-Sensitive Planning for Resilient Infrastructure Development 5 th Africa Regional Platform for Disaster Risk Reduction Abuja, Nigeria by Jeffrey Crawford, UNOPS 14 May 2014 What is Resilient

More information